Fabricated reinforced concrete primary and secondary beam rigid connection structure

Through the rigid joint structure of the main and secondary beams of prefabricated reinforced concrete without supporting, the combination of prefabricated main beams, secondary beams, gaskets, stirrups and high-strength concrete, the rigid joint connection of the main and secondary beams in the existing technology is solved to affect the construction progress. The problem of this achieves the effect of reducing the risk of negative bending moment cracks and improving seismic resistance.

CN222044451UActive Publication Date: 2024-11-22HUNAN KEXIN ELECTRIC POWER DESIGN CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420594733.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-26
Publication Date
2024-11-22
Estimated Expiration
2034-03-26

AI Technical Summary

Technical Problem

The existing prefabricated reinforced concrete main and secondary beams need to be connected to the rigid connection of existing prefabricated reinforced concrete main beams and secondary beams, which affects the construction progress of prefabricated concrete buildings.

Method used

Adopt the rigid joint structure of the main and secondary beams of prefabricated reinforced concrete without supporting. The prefabricated main beams, prefabricated secondary beams, gaskets, stirrups, formwork and high-strength concrete are used to pour high-strength concrete into the prefabricated main beams, secondary beams, and high-strength concrete. The gaskets, stirrups, support fixtures, etc. solidify together to form a rigid joint structure of the prefabricated reinforced concrete main and secondary beams.

Benefits of technology

Avoid negative bending moment cracks at the end of the secondary beam, reduce the span bending moment and cross-sectional size of the articulated connection, reduce the risk of falling secondary beams in earthquake conditions, improve the seismic performance of the building, and reduce the prefabricated secondary beams. Weight and project volume reduce engineering construction costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222044451U_ABST
    Figure CN222044451U_ABST
Patent Text Reader

Abstract

An assembly type reinforced concrete primary and secondary beam rigid connection structure comprises a prefabricated primary beam, a prefabricated secondary beam, a gasket, a stirrup, a formwork, a supporting and fixing piece and post-cast high-strength concrete. The prefabricated main beams, the prefabricated secondary beams, the gaskets, the stirrups, the supporting fixing pieces and the like are solidified together through post-pouring high-strength concrete between the prefabricated main beams, the prefabricated secondary beams and the formwork to form the assembly type reinforced concrete primary and secondary beam rigid connection structure. Hogging moment cracks are prevented from being generated at the ends of the assembly type reinforced concrete primary and secondary beam hinged connection secondary beam, meanwhile, the mid-span bending moment of the assembly type reinforced concrete primary and secondary beam hinged connection secondary beam and the section size of the secondary beam are reduced through rigid connection of the assembly type reinforced concrete primary and secondary beam, and the risk that the secondary beam falls under the earthquake working condition is reduced. The anti-seismic property of the building is enhanced, the weight and the engineering quantity of the prefabricated secondary beam are reduced, and the engineering construction cost is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to a prefabricated reinforced concrete primary and secondary beam connection, in particular to a prefabricated reinforced concrete primary and secondary beam rigid connection structure. Background Art

[0002] my country is promoting the construction of prefabricated concrete buildings. At present, the Technical Standard for Prefabricated Concrete Buildings in my country does not have a schematic diagram of the rigid connection of prefabricated reinforced concrete main and secondary beams, but only a schematic diagram of the hinged connection of the main and secondary beams. At the same time, the clause description indicates that considering the actual structural characteristics of the connection node between the concrete secondary beam and the main beam, it is difficult to fully realize the ideal hinged connection node in actual engineering. The end of the secondary beam is actually partially constrained and there is a certain negative bending moment. In order to avoid negative bending moment cracks at the end of the secondary beam, sufficient upper longitudinal steel bars must be arranged at the end of the secondary beam.

[0003] The rigid connection and construction method of prefabricated reinforced concrete primary and secondary beams is one of the important technologies in the construction of prefabricated concrete buildings. Not long ago, a survey was conducted on pilot projects of rigid connection of prefabricated reinforced concrete primary and secondary beams in developed areas such as Shanghai. The existing technology requires scaffolding to be set up under the prefabricated main beams and secondary beams to support the prefabricated main beams and secondary beams, and a construction method of cast-in-place reinforced concrete with formwork is added at the rigid connection of the primary and secondary beams. This rigid connection and construction method of the primary and secondary beams seriously affects the construction progress of prefabricated concrete buildings. Utility Model Content

[0004] The technical problem to be solved by the utility model is to overcome the defect of the prior art that a support frame needs to be set up under the prefabricated main beam and secondary beam before the cast-in-place reinforced concrete and formwork are added at the rigid connection of the main and secondary beams, which seriously affects the construction progress of the prefabricated concrete building, and to provide a prefabricated reinforced concrete main and secondary beam rigid connection structure that does not require the setting up of supporting prefabricated main beams and secondary beams.

[0005] The technical solution adopted by the utility model to solve its technical problems is a prefabricated reinforced concrete main and secondary beam rigid connection structure, which includes a prefabricated main beam, a prefabricated secondary beam, a gasket, stirrups, a template, support fixings, and high-strength concrete. The prefabricated main beam, prefabricated secondary beam, a gasket, stirrups, support fixings, etc. are solidified together by pouring the high-strength concrete to form an prefabricated reinforced concrete main and secondary beam rigid connection structure.

[0006] Furthermore, the prefabricated main beam includes a pre-embedded cantilever steel frame, pre-embedded secondary beam longitudinal lap steel bars and pre-cast reinforced concrete, and the pre-cast reinforced concrete has a keyway A, etc.; the pre-embedded cantilever steel frame is composed of a connecting piece A and two L-shaped main steel frames, and the L-shaped main steel frame has pre-openings and is fixedly connected with a sleeve; the pre-embedded cantilever steel frame and the pre-embedded secondary beam longitudinal lap steel bars, the main beam steel bars, etc. are positioned, installed with formwork, and then poured with concrete to form a prefabricated main beam.

[0007] Furthermore, the prefabricated secondary beam includes reserved longitudinal lap steel bars extending out of the secondary beam, embedded double-bearing plates and prefabricated reinforced concrete, and the prefabricated reinforced concrete has a keyway B; the embedded double-bearing plates are composed of connecting parts B and two main steel plates; the embedded double-bearing plates, reserved longitudinal lap steel bars extending out of the secondary beam, secondary beam steel bars, etc. are positioned, installed with formwork, and then poured with concrete to form the prefabricated secondary beam.

[0008] Furthermore, the gasket is located on the foot of the L-shaped main steel frame of the embedded cantilever steel frame and between the embedded double support plates.

[0009] Furthermore, the stirrups are located outside the embedded secondary beam longitudinal lap steel bars and the reserved longitudinal lap steel bars extending out of the secondary beam to wrap them together.

[0010] Furthermore, the supporting fixing member includes a bolt, a bolt with a sleeve, a nut, and a gasket; the supporting fixing member is used to support and fix the template.

[0011] Furthermore, the template is a common template that needs to be disassembled or a template that does not require disassembly; the template has prefabricated fixed openings.

[0012] Furthermore, the embedded cantilever steel frame and the embedded secondary beam longitudinal lap steel bars are simultaneously picked out on both sides and connected to the prefabricated secondary beams on both sides.

[0013] The utility model has the following beneficial technical effects:

[0014] Avoid negative bending moment cracks at the ends of secondary beams where prefabricated reinforced concrete main and secondary beams are hingedly connected. At the same time, the rigid connection structure of prefabricated reinforced concrete main and secondary beams reduces the mid-span bending moment of secondary beams where prefabricated reinforced concrete main and secondary beams are hingedly connected and the cross-sectional size of secondary beams, reduces the risk of beams falling under earthquake conditions, enhances the seismic performance of the building, reduces the weight of prefabricated secondary beams and their engineering volume, and reduces the cost of engineering construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 It is a schematic diagram of the plan layout of an embodiment of an assembled reinforced concrete primary and secondary beam rigid connection structure of the utility model;

[0016] Figure 2 yes Figure 1 Schematic diagram of the AA section;

[0017] Figure 3 yes Figure 2 Schematic diagram of the prefabricated main beam 2;

[0018] Figure 4 yes Figure 3 Schematic diagram of the embedded cantilever steel skeleton 6;

[0019] Figure 5 yes Figure 2 Schematic diagram of the middle precast secondary beam 3;

[0020] Figure 6 yes Figure 5 Schematic diagram of the middle double-loaded plate 15;

[0021] Figure 7 yes Figure 2 Schematic diagram of the middle BB section;

[0022] Figure 8 yes Figure 7 Schematic diagram of the embedded cantilever steel skeleton 6;

[0023] Fig. 9 yes Figure 7 Schematic diagram of the middle double-loaded plate 15;

[0024] Fig.10 yes Figure 2 Schematic diagram of the CC section.

[0025] Description of reference numerals:

[0026] 1. Rigid connection structure of main and secondary beams; 2. Prefabricated main beams; 3. Prefabricated secondary beams; 4. Stirrups; 5. Formwork; 6. Embedded cantilever steel skeleton; 7. Embedded longitudinal lap steel bars of secondary beams; 8. Keyway A; 9. L-shaped main steel skeleton; 10. Connector A; 11. Opening; 12. Sleeve; 13. Reserved longitudinal lap steel bars extending out of secondary beams; 14. Keyway B; 15. Double support plate; 16. Main steel plate; 17. Connector B; 18. Prefabricated fixed openings; 19. Disassembly-free formwork of calcium silicate board; 20. Support fixings; 21. Gasket. DETAILED DESCRIPTION

[0027] The structure of the rigid connection of the continuous secondary beams on both sides of the main beam of the utility model is further described in detail below in conjunction with the accompanying drawings and embodiments.

[0028] Reference Figures 1 to 10 This embodiment includes a precast main beam 2, a precast secondary beam 3, a gasket 21, stirrups 4, a template 5, a support fixing member 20, and high-strength concrete. The precast main beam 2, the precast secondary beam 3, the gasket 21, stirrups 4, the template 5, and the support fixing member 20 are solidified together by pouring the high-strength concrete to form an assembled reinforced concrete main and secondary beam rigid connection structure 1.

[0029] The prefabricated main beam 2 includes a pre-embedded cantilever steel frame 6, a pre-embedded secondary beam longitudinal lap steel bar 7 and prefabricated reinforced concrete, and the prefabricated reinforced concrete has a prefabricated keyway A8; the pre-embedded cantilever steel frame 6 is composed of two L-shaped main steel frames 9 and a connecting piece A10, and the L-shaped main steel frame 9 is pre-opened with a hole 11 and welded with a sleeve 12; after the two L-shaped main steel frames are pre-opened with a hole 11 and welded with a sleeve 12 as required, they are respectively welded with the connecting piece A10 to form a steel structure as a whole, that is, the pre-embedded cantilever steel frame 6; the pre-embedded cantilever steel frame 6 and the pre-embedded secondary beam longitudinal lap steel bar 7, and the main beam steel bar are positioned, the template 5 is installed, and the keyway A8 is reserved, and then poured with concrete to form the prefabricated main beam 2.

[0030] The prefabricated secondary beam 3 includes reserved longitudinal lap steel bars 13 extending out of the secondary beam, pre-buried double-bearing plate 15 and prefabricated reinforced concrete, and the prefabricated reinforced concrete has a prefabricated keyway B14; the double-bearing plate 15 is composed of two main steel plates 16 and a connecting piece B17; the connecting piece B17 is welded to the two main steel plates 16 to form a steel structure as a whole, namely, the double-bearing plate 15. The pre-buried double-bearing plate 15, the reserved longitudinal lap steel bars 13 extending out of the secondary beam, and the secondary beam steel bars are positioned, installed with a formwork 5 and a reserved keyway B14, and connected together by concrete pouring to form the prefabricated secondary beam 3.

[0031] The gasket 21 is located between the foot of the L-shaped main steel frame of the embedded cantilever steel frame 6 of the beam and the embedded double support plate 15 of the secondary beam. It is used to fine-tune the upper and lower elevations of the embedded double support plate 15 of the secondary beam and the secondary beam, and at the same time bear the pressure transmitted from the embedded double support plate 15 of the secondary beam to the foot of the L-shaped main steel frame on the embedded cantilever steel frame 6.

[0032] The stirrups 4 are located outside the embedded secondary beam longitudinal lap steel bars 7 and the reserved longitudinal lap steel bars 13 extending out of the secondary beam and wrap them together.

[0033] The template 5 is a calcium silicate board non-disassembly template 19 with a prefabricated fixed opening 18 and a dovetail groove on one side. The calcium silicate board non-disassembly template 19 with the dovetail groove faces the inner side of the rigid joint to facilitate pouring with concrete to form a whole; the supporting fixing part 20 includes bolts, sleeve bolts, nuts, and washers;

[0034] The formwork 5 is installed and fixed on the embedded cantilever steel frame 6 and the two sides and bottom of the main and secondary beam rigid connection structure 1 through the supporting fixing parts 20; the high-strength concrete main and secondary beam rigid connection structure 1 is cast between the formwork 5 and the prefabricated main beam 2 and the prefabricated secondary beam 3.

[0035] The two sides of a prefabricated main beam 2 are respectively connected to the prefabricated secondary beams 3 on both sides, that is, the prefabricated main beam 2 is connected to the two prefabricated secondary beams 3, and the embedded cantilever steel frame 6 and the embedded secondary beam longitudinal lap steel bars 7 of a prefabricated main beam 2 are simultaneously picked out and rigidly connected to the two prefabricated secondary beams 3 on both sides, thus forming a structure in which the main beam is rigidly connected to the continuous secondary beams on both sides.

[0036] The utility model avoids the generation of negative bending moment cracks at the ends of the secondary beams where the assembled reinforced concrete main and secondary beams are hingedly connected. At the same time, the rigid connection structure of the assembled reinforced concrete main and secondary beams reduces the mid-span bending moment of the secondary beams where the assembled reinforced concrete main and secondary beams are hingedly connected and the cross-sectional size of the secondary beams, reduces the risk of beams falling under earthquake conditions, enhances the seismic performance of the building, reduces the weight of the prefabricated secondary beams and the engineering quantity, and reduces the construction cost of the project.

[0037] The above are all preferred embodiments of the present utility model, and the protection scope of the present utility model is not limited thereto. Among them, the same parts are represented by the same figure marks. It should be noted that the words "front", "rear", "left", "right", "up" and "down" used in the following description refer to the directions in the drawings, and the words "inside" and "outside" refer to the directions toward or away from the geometric center of a specific component, respectively. Therefore: All equivalent changes made according to the structure, shape, and principle of the present utility model should be covered within the protection scope of the present utility model.

Claims

1. An assembled reinforced concrete primary and secondary beam rigid connection structure, characterized in that: The invention comprises a prefabricated main beam (2), a prefabricated secondary beam (3), a gasket (21), stirrups (4), a template (5), a supporting fixture (20), and high-strength concrete. The prefabricated main beam (2), the prefabricated secondary beam (3), the gasket (21), stirrups (4), the template (5), and the supporting fixture (20) are solidified together by pouring the high-strength concrete to form an assembled reinforced concrete main and secondary beam rigid connection structure (1); the prefabricated main beam (2) comprises a pre-buried cantilever steel frame (6), pre-buried secondary beam longitudinal lap steel bars (7), and pre-buried reinforced concrete, and the pre-buried reinforced concrete has a keyway A (8); the pre-buried cantilever steel frame (6) is composed of a connecting piece A (10) and two L-shaped main steel frames (9), and the L-shaped main steel frames (9) has a pre-opened hole (11) and is fixedly connected with a sleeve (12); the pre-buried cantilever steel frame (6) and the pre-buried secondary beam longitudinal lap steel bars (7), the main beam steel bars are positioned, a template (5) is installed, and then concrete is poured to form a prefabricated main beam (2); the prefabricated secondary beam (3) includes reserved longitudinal lap steel bars (13) extending out of the secondary beam, a pre-buried double support plate (15) and prefabricated reinforced concrete, and the prefabricated reinforced concrete has a keyway B (14); the pre-buried double support plate (15) is composed of a connecting piece B (17) and two main steel plates (16); the pre-buried double support plate (15), the reserved longitudinal lap steel bars (13) extending out of the secondary beam, the secondary beam steel bars are positioned, a template (5) is installed, and then concrete is poured to form a prefabricated secondary beam (3).

2. The assembled reinforced concrete primary and secondary beam rigid connection structure according to claim 1, characterized in that: The gasket (21) is located on the foot of the L-shaped main steel frame (9) of the embedded cantilever steel frame (6) and between the embedded double support plate (15).

3. The assembled reinforced concrete primary and secondary beam rigid connection structure according to claim 1, characterized in that: The stirrups (4) are located outside the embedded secondary beam longitudinal lap steel bars (7) and the reserved secondary beam longitudinal lap steel bars (13) to wrap them together.

4. The assembled reinforced concrete primary and secondary beam rigid connection structure according to claim 1, characterized in that: The supporting fixing member (20) comprises a bolt, a bolt with a sleeve, a nut, and a gasket; the supporting fixing member (20) is used to support and fix the template (5).

5. The assembled reinforced concrete primary and secondary beam rigid connection structure according to claim 1, characterized in that: The template (5) is a common template that needs to be disassembled or a template that does not require disassembly, and the template (5) has a prefabricated fixed opening (18).