Multifunctional pilot tunnel structure suitable for extra-long highway tunnel portal

By designing a multi-functional guide hole structure at the entrance of a special highway tunnel, including the first guide hole and the second guide hole, the construction difficulties in steep terrain are solved, the convenience and safety of construction are achieved, and the slewing lanes are provided during the operation period. , easy to pass through.

CN222045777UActive Publication Date: 2024-11-22HUNAN PROVINCIAL COMM PLANNING SURVEY & DESIGN INST CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420547444.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-20
Publication Date
2024-11-22
Estimated Expiration
2034-03-20

AI Technical Summary

Technical Problem

The terrain of the extra-long tunnel opening section in mountainous and hilly areas is steep, making it difficult to reach construction machinery, lack of construction work platforms, and it is difficult to drain and slag output during construction, which is not conducive to rapid evacuation and emergency rescue.

Method used

A multifunctional guide hole structure is designed, including the first guide hole and the second guide hole. The first guide hole connects from outside the mountain to the main hole of the tunnel to be constructed, and the drainage problem is solved through the guide hole ditch and water diversion device. The second guide hole provides a slewing lane to ensure safety and convenience of construction.

Benefits of technology

It realizes tunnel construction without building a platform in steep terrain, solves the difficulties in drainage and slag discharge during construction, improves emergency evacuation capabilities, and provides slewing lanes during the operation period to facilitate vehicle access.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222045777U_ABST
    Figure CN222045777U_ABST
Patent Text Reader

Abstract

The utility model provides a multifunctional pilot tunnel structure suitable for an extra-long highway tunnel portal. The multifunctional pilot tunnel structure comprises a first pilot tunnel and a second pilot tunnel, wherein the first pilot tunnel is used for being communicated with a to-be-constructed tunnel main tunnel located on the outermost side, and the second pilot tunnel is used for being communicated with two adjacent to-be-constructed tunnel main tunnels. The first end of the first pilot tunnel penetrates out of the mountain to be communicated with the outside to form a tunnel opening, the second end of the first pilot tunnel is used for being communicated with the outermost main tunnel to be constructed, the tunnel opening section and the tunnel body section of the outermost main tunnel to be constructed are distributed on the two sides of the second end respectively, and the elevation is gradually reduced from the second end to the first end to form a slope beta; and the second pilot tunnel is communicated with the first pilot tunnel. According to the multifunctional pilot tunnel structure suitable for the extra-long highway tunnel portal, water and slag in the tunnel main hole can be discharged in time through the first pilot tunnel; the problems that a construction working face of an existing steep terrain extra-long highway tunnel portal is difficult to develop, drainage is difficult during construction and operation, and rescue and disaster prevention are difficult during operation are effectively solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of tunnel engineering, and in particular relates to a multifunctional guide tunnel structure at an extra-long highway tunnel entrance. Background Art

[0002] At present, my country's transportation has been rapidly developed, the transportation network has been continuously improved, and the focus of transportation construction has shifted from the developed coastal areas to the west and north, and from the plains to the mountainous and hilly areas. This means that the intensity of highway construction has increased, and more and more long tunnels have appeared. However, for mountainous and hilly areas, the entrances of long tunnels are often steep, and generally use a bridge-tunnel connection method. It is difficult for construction machinery to reach the entrance section, and there is no construction platform for tunnel construction. In addition, if there is no construction platform at the entrance section of the long tunnel, and a one-way excavation method is used, it is not conducive to drainage and slag discharge during the construction stage, and it greatly increases the construction period. At the same time, for mountainous and hilly areas, bridges or tunnels are often used to pass through, and it is often not convenient to set up a turning lane, which is not conducive to driving convenience. In particular, when a dangerous situation occurs in the tunnel, it is impossible to quickly evacuate vehicles and personnel, and carry out emergency rescue. Therefore, for the entrance section of the long tunnel connected by the bridge and tunnel with a relatively steep terrain, how to solve the problems of difficulty in carrying out construction operations, drainage, and slag discharge in the tunnel is a difficult problem that urgently needs to be studied and solved.

[0003] In summary, there is an urgent need for a multifunctional guide tunnel structure suitable for the portal of an extra-long highway tunnel to solve the problems existing in the prior art. Utility Model Content

[0004] The utility model aims to provide a multifunctional guide tunnel structure suitable for the entrance of a super-long highway tunnel, aiming to solve the problems of difficulty in carrying out construction work on the entrance of a super-long highway tunnel with steep terrain, difficulty in drainage during construction and operation, and difficulty in rescue and disaster prevention during operation. The specific technical scheme is as follows:

[0005] A multifunctional guide tunnel structure suitable for the portal of an extra-long highway tunnel comprises a first guide tunnel for connecting the outermost main tunnel to be constructed and a second guide tunnel for connecting two adjacent main tunnels to be constructed; the first end of the first guide tunnel passes through the mountain and is connected to the outside to form a portal, and the second end of the first guide tunnel is used to connect with the outermost main tunnel to be constructed, wherein the portal section and the tunnel body section of the outermost main tunnel to be constructed are respectively distributed on both sides of the second end, and the elevation gradually decreases from the second end to the first end to form a slope β; the second guide tunnel is connected to the first guide tunnel.

[0006] Furthermore, a pilot tunnel ditch is provided at the bottom of the first pilot tunnel, and the pilot tunnel ditch is used to connect with the main tunnel ditch at the bottom of the main tunnel of the tunnel after construction is completed. The elevation of the pilot tunnel ditch is lower than the elevation of the main tunnel ditch. A water diversion device is provided between the main tunnel ditch and the pilot tunnel ditch to transfer part or all of the water in the main tunnel ditch to the pilot tunnel ditch.

[0007] Furthermore, the water diversion device includes a drainage ditch and a water diversion pipe. The drainage ditch is arranged along the length direction of the main tunnel of the tunnel. The water diversion pipe is installed between the main tunnel ditch and the drainage ditch. One end of the water diversion pipe is connected to the main tunnel ditch, and the other end of the water diversion pipe is connected to the drainage ditch. Along the direction from the main tunnel ditch to the drainage ditch, the elevation of the water diversion pipe gradually decreases and forms a slope α.

[0008] Furthermore, the slope rate of the slope α is controlled between 2% and 4%.

[0009] Furthermore, a plurality of water diversion pipes are arranged along the length direction of the drainage ditch, the cross section of the drainage ditch along its length direction is V-shaped, and the guide tunnel ditch is connected to the V-shaped bottom of the drainage ditch.

[0010] Furthermore, an invert lining is provided at the bottom of the second pilot tunnel.

[0011] Furthermore, the width of the second guide tunnel is not less than 6 meters, and the height is not less than 5 meters.

[0012] Furthermore, the first end of the first guide tunnel is connected to the existing road.

[0013] Furthermore, the distance between the intersection of the first pilot tunnel and the main tunnel and the entrance of the main tunnel is between 400 meters and 500 meters.

[0014] Furthermore, the slope of the pilot tunnel ditch is consistent with the slope β of the first pilot tunnel.

[0015] The application of the technical solution of the utility model has the following beneficial effects:

[0016] The utility model excavates the first pilot tunnel at a location lower than the tunnel entrance and with a relatively flat terrain before constructing the main tunnel. When excavating at a relatively flat terrain, construction can be smoothly carried out without building a construction platform, thereby solving the problem that the main tunnel has no construction working surface at a steep location. During the construction of the first pilot tunnel, the elevation of the first pilot tunnel is gradually raised, and it is approached to the location of the main tunnel to be constructed, until the first pilot tunnel is excavated to the main tunnel to be constructed. After the construction of the first pilot tunnel is completed, the construction of the second pilot tunnel is carried out; by constructing the main tunnel of the tunnel in two directions from the intersection of the first pilot tunnel, the second pilot tunnel and the main tunnel to be constructed, during the construction of the main tunnel, the groundwater gushing out of the main tunnel can flow out through the first pilot tunnel, and the slag generated by the construction of the main tunnel can be transported out through the first pilot tunnel by a slag truck, thereby solving the problem of difficulty in drainage and slag removal during tunnel construction; during operation, the second pilot tunnel can solve the problem that a main tunnel revolving lane cannot be set.

[0017] In addition to the above-described purposes, features and advantages, the present invention has other purposes, features and advantages. The present invention will be further described in detail below with reference to the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] The drawings constituting a part of this application are used to provide a further understanding of the present invention. The illustrative embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation on the present invention. In the drawings:

[0019] Figure 1 The utility model is applicable to the overall structure of the embodiment 1 of the multifunctional guide tunnel structure of the extra-long highway tunnel. Figure 1 ;

[0020] Figure 2 It is a schematic diagram of the cross-sectional structure of Embodiment 1 of the utility model applicable to the multifunctional guide tunnel structure of the portal of a super-long highway tunnel;

[0021] Figure 3 This is a schematic diagram of the cross-sectional structure of the first guide tunnel of the utility model, which is applicable to the embodiment 1 of the multifunctional guide tunnel structure for the entrance of a super-long highway tunnel;

[0022] Figure 4 The utility model is applicable to the overall structure of the embodiment 1 of the multifunctional guide tunnel structure of the extra-long highway tunnel. Figure 2 ;

[0023] Figure 5 It is a cross-sectional view of the water collection trough of the embodiment 1 of the multifunctional guide tunnel structure applicable to the entrance of a super-long highway tunnel of the utility model along the direction of the main tunnel of the tunnel;

[0024] Figure 6It is a top view of a water diversion device of Embodiment 1 of the utility model which is applicable to a multifunctional guide tunnel structure at an entrance of a super-long highway tunnel;

[0025] Figure 7 It is a schematic diagram of the cross-sectional structure of the second guide tunnel of Embodiment 1 of the utility model which is applicable to the multifunctional guide tunnel structure of the portal of a super-long highway tunnel.

[0026] Figure 8 It is a schematic diagram of the overall structure of Embodiment 2 of the multifunctional guide tunnel structure applicable to an extra-long highway tunnel portal of the utility model.

[0027] Fig. 9 It is a schematic diagram of the overall structure of Embodiment 3 of the multifunctional guide tunnel structure applicable to the portal of an extra-long highway tunnel of the utility model.

[0028] Among them, 10, main tunnel; 11, main tunnel ditch; 12, tunnel entrance section; 13, tunnel body section; 20, first pilot tunnel; 21, second end; 22, first end; 23, slope β; 24, pilot tunnel ditch; 30, water diversion device; 31, drainage ditch; 32, water diversion pipe; 33, slope α; 40, second pilot tunnel; 41, invert lining; 50, existing road. DETAILED DESCRIPTION

[0029] In order to facilitate the understanding of the present invention, the present invention will be described more comprehensively below, and preferred embodiments of the present invention are given. However, the present invention can be implemented in many different forms and is not limited to the embodiments described herein. On the contrary, the purpose of providing these embodiments is to make the understanding of the disclosure of the present invention more thorough and comprehensive.

[0030] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art of the present invention. The terms used herein in the specification of the present invention are only for the purpose of describing specific embodiments and are not intended to limit the present invention.

[0031] Embodiment 1:

[0032] See also Figure 1The present embodiment provides a multifunctional guide tunnel structure suitable for the portal of an extra-long highway tunnel, including a first guide tunnel 20 for connecting the outermost main tunnel 10 to be constructed and a second guide tunnel 40 for connecting two adjacent main tunnels 10 to be constructed; the first end 22 of the first guide tunnel 20 passes through the mountain and is connected to the outside to form a portal, and the second end 21 of the first guide tunnel 20 is used to communicate with the outermost main tunnel 10 to be constructed, wherein the portal section 12 and the tunnel body section 13 of the outermost main tunnel 10 to be constructed are respectively distributed on both sides of the second end 21, and the elevation gradually decreases from the second end 21 to the first end 22 and forms a slope β23; the second guide tunnel 40 is connected to the first guide tunnel 20.

[0033] It can be understood that during construction, the first pilot tunnel 20 on the side of the outermost tunnel main tunnel 10 to be constructed is first excavated. In this embodiment, there are two tunnel main tunnels 10, namely the left tunnel main tunnel 10 and the right tunnel main tunnel 10 (that is, the two tunnel main tunnels 10 are the outermost tunnel main tunnels 10 to be constructed). The excavation position of the first pilot tunnel 20 is selected at a location with a gentle slope, which is convenient for excavation construction when no construction platform is built. Excavation is carried out without building a construction platform. On the one hand, it is convenient for construction personnel to construct the first pilot tunnel 20, and on the other hand, it saves time for excavation construction. After the construction of the first pilot tunnel 20 is completed, the second pilot tunnel 40 is constructed so that the first pilot tunnel 20 and the second pilot tunnel 40 are connected, and then the main tunnels 10 on the left and right sides are constructed. In the process of constructing the main tunnel 10, the main tunnel 10 is firstly reversely excavated to obtain the tunnel entrance section 12 of the main tunnel 10, so that the main tunnel 10 and the bridge are connected, and then the main tunnel 10 is forwardly excavated to obtain the tunnel body section 13 of the main tunnel 10. In the process of forward excavation of the main tunnel 10, the water gushing out of the main tunnel can be discharged through the first pilot tunnel 20, and the slag generated during the construction of the main tunnel 10 can be transported out through the first pilot tunnel 20. When the main tunnel 10 encounters a dangerous situation during the construction process, the construction personnel can quickly escape through the first pilot tunnel 20 and carry out emergency rescue, which increases the escape probability of the construction personnel when a dangerous accident occurs. The second pilot tunnel 40 is connected with the first pilot tunnel 20, so that the second pilot tunnel 40 is horizontally connected to the two main tunnels 10 to be constructed. During operation, the second guide tunnel 40 solves the problem that the conventional tunnel main tunnel 10 cannot be provided with a turnaround lane, and facilitates the vehicle to turn around through the second guide tunnel 40 during operation of the tunnel main tunnel 10. In this embodiment, the first guide tunnel 20 is a type I guide tunnel, and the second guide tunnel 40 is a type II guide tunnel.

[0034] Further, refer to Figure 1 and Figure 2The distance between the intersection of the first pilot tunnel 20 and the main tunnel 10 and the entrance of the main tunnel 10 is between 400 meters and 500 meters. If the distance is too short, it is not easy to avoid steep terrain, and if the distance is too long, the construction volume is large, which is not conducive to construction. Preferably, the elevation of the second end 21 is higher than the first end 22, that is, the end at the entrance of the first pilot tunnel 20 is the low end, wherein the slope β23 is controlled between 2% and 6%, so as to facilitate the drainage and slag discharge functions through the first pilot tunnel 20.

[0035] Further, refer to Figure 2 and Figure 3 A guide tunnel ditch 24 is provided at the bottom of the first guide tunnel 20. The guide tunnel ditch 24 is used to communicate with the main tunnel ditch 11 at the bottom of the main tunnel 10 after construction. The elevation of the guide tunnel ditch 24 is lower than that of the main tunnel ditch 11. A water diversion device 30 is provided between the main tunnel ditch 11 and the guide tunnel ditch 24 to transfer part or all of the water in the main tunnel ditch 11 to the guide tunnel ditch 24. The water diversion device 30 transfers the water in the main tunnel ditch 11 to the guide tunnel ditch 24 to play a diversion role, which can solve the problem of large water volume in the center ditch of the main tunnel and untimely drainage in the case of heavy rain or continuous rainfall.

[0036] Understandably, referring to Figure 2 , Figure 4 , Figure 5 and Figure 6 The water diversion device 30 includes a drainage ditch 31 and a water diversion pipe 32. The drainage ditch 31 is arranged along the length direction of the main tunnel 10 of the tunnel. The water diversion pipe 32 is installed between the main tunnel ditch 11 and the drainage ditch 31. One end of the water diversion pipe 32 is connected to the main tunnel ditch 11, and the other end of the water diversion pipe 32 is connected to the drainage ditch 31. Along the direction from the main tunnel ditch 11 to the drainage ditch 31, the elevation of the water diversion pipe 32 gradually decreases to form a slope α33.

[0037] Preferably, the slope α33 is controlled between 2% and 4%, so that the water in the main tunnel ditch 11 flows to the sink ditch 31 through the water diversion pipe 32 under the action of gravity. The slope of the pilot tunnel ditch 24 is consistent with the slope β23 of the first pilot tunnel 20, so that the depth of the pilot tunnel ditch 24 is consistent at all locations, so that the water in the pilot tunnel ditch 24 can smoothly flow out of the hole of the first pilot tunnel 20 along the pilot tunnel ditch 24.

[0038] Further, refer to Figure 4 , Figure 5 and Figure 6, multiple water diversion pipes 32 are arranged along the length direction of the water collection ditch 31. In the present embodiment, 6 water diversion pipes 32 are arranged, and two adjacent water diversion pipes 32 are arranged with an interval of 1 meter between them. The cross-section of the water collection ditch 31 along its length direction is V-shaped. When water enters the water collection ditch 31 from the main tunnel ditch 11 along the water diversion pipes 32, the water will gather at the bottom of the V-shape of the water collection ditch 31, that is, the middle position of the water collection ditch 31. The guide tunnel ditch 24 is connected to the V-shaped bottom of the water collection ditch 31, so that all the water in the water collection ditch 31 can enter the guide tunnel ditch 24 and be discharged through the guide tunnel ditch 24.

[0039] Further, refer to Figure 2 and Figure 4 In this embodiment, the outer sides of the two main tunnels 10 to be constructed are both connected with the first guide tunnels 20, and the second guide tunnel 40 and the two first guide tunnels 20 form a U-shaped structure. The width of the second guide tunnel 40 is not less than 6 meters, and the height is not less than 5 meters, so that vehicles can pass smoothly through the second guide tunnel 40 during the operation of the main tunnel 10.

[0040] Further, refer to Figure 7 An inverted arch lining 41 is arranged at the bottom of the second guide tunnel 40, and the inverted arch lining 41 can resist the upward force of the bottom, prevent the bottom drum from bulging and deforming, reduce the ground subsidence, increase the stability of the second guide tunnel 40, and prevent the second guide tunnel 40 from becoming unstable and causing safety accidents.

[0041] The utility model is applicable to the construction steps and principles of the multifunctional guide tunnel structure of the portal of a super-long highway tunnel as follows: firstly, according to the terrain, the portal positions of two first guide tunnels 20 are selected on both sides of the left and right main tunnels 10 to be constructed, the portal positions of the first guide tunnels 20 are lower than the intersection position of the tunnel main tunnel 10 and the first guide tunnels 20, the two first guide tunnels 20 are excavated in sequence, and during the excavation process, a guide tunnel ditch 24 is dug at the middle position of the bottom of the first guide tunnel 20 until the first guide tunnel 20 is excavated to the intersection position with the left tunnel main tunnel 10, and the other guide tunnel is excavated to the intersection position with the right tunnel main tunnel 10, and a second guide tunnel 40 is excavated between the left tunnel main tunnel 10 and the right tunnel main tunnel 10, so that the second guide tunnel 40 is connected with the two first guide tunnels 20, and an invert lining 41 is constructed at the bottom of the second guide tunnel 40 to improve the stability of the second guide tunnel 40. After the construction of the first pilot tunnel 20 and the second pilot tunnel 40 is completed, the entrance section 12 of the left tunnel main tunnel 10 and the entrance section 12 of the right tunnel main tunnel 10 are excavated in reverse order, and the body section 13 of the left tunnel main tunnel 10 and the body section 13 of the right tunnel main tunnel 10 are excavated in the forward direction. During the excavation process, the transport vehicle can use the intersection of the second pilot tunnel 40 and the left tunnel main tunnel 10 and the intersection of the second pilot tunnel 40 and the right tunnel main tunnel 10 to turn around, which is convenient for the vehicle to transport the slag. A V-shaped drainage ditch 31 is dug at one end of the two first pilot tunnels 20 close to the tunnel main tunnel 10, and a water diversion pipe 32 is laid, so that the water in the ditch of the tunnel main tunnel 10 can be smoothly discharged into the drainage ditch 31 through the water diversion pipe 32 under the action of gravity, and discharged through the pilot tunnel ditch 24. While excavating in the forward direction, the main tunnel ditch 11 is excavated in the middle of the bottom of the left tunnel main tunnel 10 and the middle of the bottom of the right tunnel main tunnel 10.

[0042] Embodiment 2:

[0043] Compared with Example 1, the difference of this embodiment is: Figure 8 The first end 22 of the first guide tunnel 20 is connected to the existing road 50. When an emergency occurs in the main tunnel 10 during operation, vehicles in the main tunnel 10 can escape through the first guide tunnel 20 via the existing road 50, or rescue vehicles can enter the main tunnel 10 via the existing road 50 via the first guide tunnel 20 to carry out rescue.

[0044] The remaining details are basically the same as those in Example 1 and will not be described in detail here.

[0045] Embodiment 3:

[0046] Compared with Example 1, the difference of this embodiment is: Fig. 9This embodiment is aimed at the construction situation with three tunnel main holes 10, which are respectively the left tunnel main hole 10, the middle tunnel main hole 10 and the right tunnel main hole 10. The left side of the left tunnel main hole 10 is connected to the first guide hole 20, and the right side of the right tunnel main hole 10 is connected to the first guide hole 20. The second guide hole 40 is laterally connected to the left tunnel main hole 10, the middle tunnel main hole 10 and the right tunnel main hole 10 in sequence. The two first guide holes 20 on the left and right sides are connected with the second guide hole 40, so as to achieve the effect of facilitating the construction of the tunnel main hole and the subsequent rescue.

[0047] The remaining details are basically the same as those in Example 1 and will not be described in detail here.

[0048] Similarly, the pilot tunnel structure in this embodiment can also be applied to the situation where more than four tunnel main tunnels 10 are parallel.

[0049] The above description is only the preferred embodiment of the utility model, and is not intended to limit the utility model. For those skilled in the art, the utility model can have various modifications and changes. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.

Claims

1. A multifunctional guide tunnel structure suitable for the entrance of an extra-long highway tunnel, characterized in that: The invention comprises a first guide tunnel (20) for connecting the outermost main tunnel (10) of a tunnel to be constructed and a second guide tunnel (40) for connecting two adjacent main tunnels (10) of the tunnel to be constructed; the first end (22) of the first guide tunnel (20) passes through the mountain and connects with the outside to form a tunnel opening, the second end (21) of the first guide tunnel (20) is used to connect with the outermost main tunnel (10) of the tunnel to be constructed, wherein the tunnel opening section (12) and the tunnel body section (13) of the outermost main tunnel (10) of the tunnel to be constructed are respectively distributed on both sides of the second end (21), and the elevation gradually decreases from the second end (21) to the first end (22) to form a slope β (23); the second guide tunnel (40) is connected with the first guide tunnel (20).

2. The multifunctional guide tunnel structure applicable to the entrance of a super-long highway tunnel according to claim 1 is characterized in that: A guide tunnel ditch (24) is provided at the bottom of the first guide tunnel (20), and the guide tunnel ditch (24) is used to communicate with the main tunnel ditch (11) at the bottom of the tunnel main tunnel (10) after construction is completed. The elevation of the guide tunnel ditch (24) is lower than the elevation of the main tunnel ditch (11). A water diversion device (30) is provided between the main tunnel ditch (11) and the guide tunnel ditch (24) to transfer part or all of the water in the main tunnel ditch (11) to the guide tunnel ditch (24).

3. The multifunctional guide tunnel structure applicable to the portal of a super-long highway tunnel according to claim 2 is characterized in that: The water diversion device (30) comprises a water collection ditch (31) and a water diversion pipe (32). The water collection ditch (31) is arranged along the length direction of the tunnel main tunnel (10). The water diversion pipe (32) is installed between the main tunnel ditch (11) and the water collection ditch (31). One end of the water diversion pipe (32) is connected to the main tunnel ditch (11), and the other end of the water diversion pipe (32) is connected to the water collection ditch (31). Along the direction from the main tunnel ditch (11) to the water collection ditch (31), the elevation of the water diversion pipe (32) gradually decreases and forms a slope α (33).

4. The multifunctional guide tunnel structure applicable to the portal of a super-long highway tunnel according to claim 3 is characterized in that: The slope rate of the slope α (33) is controlled between 2% and 4%.

5. The multifunctional guide tunnel structure applicable to the portal of a super-long highway tunnel according to claim 3 is characterized in that: A plurality of water diversion pipes (32) are arranged along the length direction of the water collection ditch (31); the cross section of the water collection ditch (31) along its length direction is V-shaped; and the guide tunnel ditch (24) is connected to the V-shaped bottom of the water collection ditch (31).

6. The multifunctional guide tunnel structure applicable to the portal of a super-long highway tunnel according to claim 1 is characterized in that: An invert lining (41) is provided at the bottom of the second guide tunnel (40).

7. The multifunctional guide tunnel structure applicable to the portal of a super-long highway tunnel according to claim 1 is characterized in that: The width of the second guide tunnel (40) is not less than 6 meters, and the height is not less than 5 meters.

8. The multifunctional guide tunnel structure applicable to the portal of a super-long highway tunnel according to claim 1 is characterized in that: The first end (22) of the first guide tunnel (20) is in communication with an existing road (50).

9. The multifunctional guide tunnel structure applicable to the portal of a super-long highway tunnel according to claim 1 is characterized in that: The distance between the intersection of the first guide tunnel (20) and the main tunnel (10) and the opening of the main tunnel (10) is between 400 meters and 500 meters.

10. The multifunctional guide tunnel structure applicable to the portal of a super-long highway tunnel according to claim 2 is characterized in that: The slope of the guide tunnel ditch (24) is consistent with the slope β (23) of the first guide tunnel (20).