Continuous circulation type gravity energy storage power generation system based on vertical shaft
By adopting multi-rope friction ring lifting system and automated loading and unloading technology in the shaft system, the problem of low efficiency of gravity energy storage systems in the existing technology is solved, and continuous, efficient and stable heavy logistics transportation is achieved, which improves energy storage and The stability of power generation and the potential of commercial application of systems.
Patent Information
- Application Number
- CN202420926541.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-29
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2034-04-29
AI Technical Summary
The existing vertical shaft-based gravity energy storage system is difficult to achieve continuous, efficient and stable heavy block transport, resulting in low system efficiency and unsuitable for commercial applications.
A continuous cycle gravity energy storage power generation system based on vertical shafts was designed, and a multi-rope friction lifting system was formed by using an annular steel wire rope and multiple friction drive wheels. Through automatic de-release and unloading and automatic cable loading, a uniform speed and stable weight was achieved. Logistics and optimize the loading and unloading process through double ring tracks and retractable automatic lifting platform.
It realizes the stability of energy storage and power generation processes, reduces equipment impact, improves system efficiency and loading and unloading efficiency, extends the service life of the wire rope, and adapts to the modular configuration of different engineering needs.
Smart Images

Figure CN222046019U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of gravity energy storage power generation, and specifically relates to a continuous circulation gravity energy storage power generation system based on a vertical shaft. Background Art
[0002] The gravity energy storage system mainly consists of two parts: energy storage and discharge. When storing energy, the material (heavy block) is lifted from the low-altitude storage yard (lower warehouse) to the high-altitude storage yard (upper warehouse), and the electrical energy is finally converted into the gravitational potential energy of the material for temporary storage; when discharging, the material is transported from the high-altitude storage yard to the low-altitude storage yard, and the generator is driven by the transmission device to generate electricity, and the gravitational potential energy is finally converted into electrical energy. As a commercial and engineering power project, the success of the gravity energy storage project depends on whether it can provide continuous and stable current, which depends on the stability of the weight and speed of the lifting weight. As a new energy storage solution, gravity energy storage has no production cases in China, and the first gravity energy storage project in China is under construction. Gravity energy storage based on the shaft (vertical shaft) uses the height difference between the upper and lower parts of the shaft as a conveying channel for energy storage weight blocks. Existing patents, such as the Chinese invention patent with application publication number CN109665430A, but the weight blocks are lifted and lowered separately, which makes it difficult to achieve continuous discharge, and the system efficiency is low, which does not meet the conditions for commercial application. Utility Model Content
[0003] The technical problem to be solved by the utility model is to provide a continuous circulation gravity energy storage power generation system based on a vertical shaft, so as to solve the problem that the existing technology cannot achieve continuity, high efficiency and stability, and to form a uniform, stable and circulating heavy flow through the gravity energy storage system that continuously transports bulk materials, thereby avoiding the impact on the power grid.
[0004] According to the technical solution of the utility model, the utility model provides a continuous circulation gravity energy storage power generation system based on a vertical shaft, including a vertical shaft, an upper warehouse is arranged at the upper part of the vertical shaft, and a lower warehouse is arranged at the lower part of the vertical shaft; the upper warehouse is provided with an upper warehouse conveying and loading and unloading system, and the lower warehouse is provided with a lower warehouse conveying and loading and unloading system; it also includes a gravity turbine system, the gravity turbine system includes an electric generator integrated machine arranged in the upper warehouse, the electric generator integrated machine is connected to a friction drive wheel, a derrick is arranged above the vertical shaft, the derrick is provided with two upper well redirecting wheels, and the vertical shaft is provided with an underground well redirecting wheel and a tensioning device below the lower warehouse; between the friction drive wheel, the two An annular steel wire rope is mounted on each of the above-ground redirecting wheels and the underground redirecting wheel to form a transmission connection; the upper warehouse conveying and loading and unloading system and the lower warehouse conveying and loading and unloading system both include a double annular track, which includes a main track connected to the shaft of the vertical shaft and two sub-tracks formed by branches on both sides of the main track, the sub-tracks are curved in annular shape, and the two sub-tracks meet again on the other side of the vertical shaft to form a main track and connect with the shaft of the vertical shaft; it also includes a plurality of lifting containers, the sides of the lifting containers are provided with a detachable rope gripper for cooperating with the annular steel wire rope, and the bottom of the lifting containers are provided with a track wheel for cooperating with the double annular track.
[0005] Furthermore, a plurality of lanes are arranged outside the sub-tracks of the double-circular track, and a conveying vehicle and a shelf are arranged in each lane, and heavy blocks are placed on the shelf.
[0006] Furthermore, there are at least two annular steel wire ropes arranged in parallel; there are multiple detachable rope grippers, which are arranged in at least two horizontal rows and two vertical columns; the annular steel wire ropes correspond to the vertical columns of the detachable rope grippers one by one.
[0007] Furthermore, the detachable rope gripping device is arranged on the outer sides of two opposite sides of the lifting container, and the other two opposite sides of the lifting container are the entrances and exits of the heavy object blocks.
[0008] Furthermore, an in-container conveying device is provided at the bottom of the inner side of the lifting container, and / or a vehicle-mounted conveying device is provided above the conveying vehicle.
[0009] Furthermore, a retractable automatic lifting platform is provided at the shaft opening near the upper warehouse, and the retractable automatic lifting platform includes a lifting mechanism, the lifting mechanism is connected to a retractable mechanism, and the end of the retractable mechanism has a retractable track for connecting with the double ring track, so that the retractable track can be lifted and lowered in the shaft, and extended and retracted.
[0010] Compared with the prior art, the beneficial technical effects of the utility model are as follows:
[0011] 1. The utility model is based on the shaft of the continuous circulation type gravity energy storage power generation system from the perspective of power engineering application. The designed gravity energy storage system is driven by the wire rope to continuously circulate the lifting container. During the operation, the lifting container and the heavy object block can be automatically unloaded and automatically loaded by holding the rope, forming a uniform and stable heavy flow. The energy storage and power generation output are stable, which greatly reduces the impact on equipment, motors, and generators, and effectively suppresses the output fluctuations of current and voltage during the system power generation process.
[0012] 2. In the vertical shaft-based continuous circulation gravity energy storage power generation system of the utility model, a lifting container equipped with a detachable rope gripper runs at high speed with the circular wire rope before detachment, ensuring high-efficiency operation of energy storage and power generation; after detachment, the lifting container can run slowly, fully meeting the time interval required for automatic loading and unloading of heavy objects, thereby ensuring stable and environmentally friendly operation of the system, effectively overcoming the contradiction in the existing patents that both operating efficiency and loading and unloading efficiency cannot be guaranteed at the same time.
[0013] 3. In the vertical shaft-based continuous circulation gravity energy storage power generation system of the utility model, double circular tracks are arranged in both the above-ground loading and unloading area and the underground loading and unloading area. Through the reasonable control of the control system, the lifting containers after being detached are respectively entered into different tracks of the double circular tracks in turn, thereby increasing the running interval between two adjacent lifting containers and further reducing the running speed of the lifting containers on the track, thus creating conditions for the smooth loading and unloading of heavy objects.
[0014] 4. In the vertical shaft-based continuous circulation gravity energy storage power generation system of the utility model, when the system is shut down, all lifting containers can be detached from the circular wire rope and parked on the double circular tracks above or below the well, respectively, to reduce the load borne by the wire rope during the shutdown process and improve the performance and service life of the wire rope.
[0015] 5. In the vertical shaft-based continuous circulation gravity energy storage power generation system of the utility model, there are at least two circular steel ropes, forming a multi-rope friction type circular lifting system, which can effectively improve the carrying capacity of the system and achieve a large installed capacity. At the same time, the lifting container and multiple steel ropes are locked and fixed to ensure the stability of the lifting container during operation, effectively avoiding torsion, overload and shaking.
[0016] 6. The shaft-based continuous circulation gravity energy storage power generation system of the utility model can be designed and adjusted according to the needs of the project and actual environmental conditions. For example, the effective height of the shaft can be adjusted, and the number and size of the lifting containers and weight blocks can be adjusted, so as to configure the installed capacity required by the project. In addition, the gravity energy storage system of the utility model can be modularized according to the actual project needs to form multiple sets of gravity energy storage power generation systems in parallel operation to achieve a larger installed capacity. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 It is a structural schematic diagram of a gravity energy storage power generation system according to an embodiment of the utility model.
[0018] Figure 2 It is a schematic diagram of the top view of the upper bin or the lower bin according to one embodiment of the utility model.
[0019] Figure 3 It is a front view schematic diagram of a lifting container according to an embodiment of the utility model.
[0020] Figure 4 yes Figure 3 A schematic side view of a lifting container is shown.
[0021] Figure 5 yes Figure 3 A schematic top view of a lifting container is shown.
[0022] Description of reference numerals in the accompanying drawings:
[0023] 1. Vertical shaft; 11. Derrick; 2. Upper warehouse; 3. Lower warehouse; 41. Friction drive wheel; 42. Redirecting wheel on the shaft; 43. Redirecting wheel underground; 44. Tensioning device; 45. Annular wire rope; 5. Double annular track; 51. Main track; 52. Sub-track; 53. Tunnel; 54. Transport vehicle; 55. Automatic detaching and hanging area on the shaft; 56. Automatic rope holding area on the shaft; 57. Automatic detaching and hanging area underground; 58. Automatic rope holding area underground; 6. Lifting container; 61. Detachment and rope holding device; 62. Track wheel; 63. Transport device in container; 7. Heavy object block. DETAILED DESCRIPTION
[0024] The utility model provides a continuous circulation gravity energy storage power generation system based on a vertical shaft, which solves the problem that the prior art cannot achieve continuity, high efficiency and stability. A uniform, stable and circulating heavy flow is formed through a gravity energy storage system that continuously conveys bulk materials, thereby avoiding impact on the power grid.
[0025] See also Figures 1 to 3 A continuous circulation gravity energy storage power generation system based on a vertical shaft according to an embodiment of the utility model comprises a vertical shaft 1, an upper warehouse 2 (or an above-the-hole storage warehouse) is provided at the upper part of the vertical shaft 1, a lower warehouse 3 (or an underground storage warehouse) is provided at the lower part of the vertical shaft 1, the upper warehouse 2 has an upper warehouse conveying and loading and unloading system, and the lower warehouse 3 has a lower warehouse conveying and loading and unloading system.
[0026] It also includes a gravity turbine system, which includes an electric generator integrated machine arranged in the upper warehouse 2, the electric generator integrated machine is connected to a friction drive wheel 41, a derrick 11 is arranged directly above the vertical shaft 1, and two upper shaft redirecting wheels 42 are arranged on the derrick 11, and the vertical shaft 1 is provided with an underground redirecting wheel 43 and a tensioning device 44 below the lower warehouse 3. The underground redirecting wheel 43 is connected to the bottom or side wall of the vertical shaft 1 below the lower warehouse 3 through the tensioning device 44, and the tensioning device 44 can control the longitudinal position of the underground redirecting wheel 43, so that the annular wire rope 45 can be tensioned. An annular wire rope 45 is mounted on the friction drive wheel 41, the two upper shaft redirecting wheels 42 and the underground redirecting wheel 43 to form a transmission connection. The positions of the two upper shaft redirecting wheels 42 and the underground redirecting wheel 43 meet the requirement that the annular wire rope 45 is vertical in the shaft of the vertical shaft 1. There are at least two annular steel wire ropes 45 arranged in parallel, preferably four, six, etc., to form a multi-rope friction annular lifting system, which can effectively improve the bearing capacity of the system and achieve a large installed capacity.
[0027] Both the upper warehouse conveying and loading and unloading system and the lower warehouse conveying and loading and unloading system include a double ring track 5, which includes a main track 51 connected to the shaft of the shaft 1 and two sub-tracks 52 formed by branches on both sides of the main track 51, and the sub-tracks 52 are curved in a ring shape. The two sub-tracks 52 meet again on the other side of the shaft 1 to form a main track 51 and connect with the shaft of the shaft 1; in other words, the double ring track 5 is in the shape of an "8".
[0028] Further, a plurality of lanes 53 are provided outside the sub-tracks 52 of the double ring track 5, and the lanes 53 can be arranged in parallel or radially, etc. A conveying vehicle 54 and a shelf are provided in each lane 53, and a heavy object block 7 is placed on the shelf.
[0029] In some embodiments, the outer end of the tunnel 53 away from the vertical shaft 1 is also connected to a transfer tunnel. The transfer tunnel is, for example, in a ring shape surrounding the outer side. Multiple tunnels 53 are connected to the transfer tunnel at different positions. A transfer mother car is provided in the transfer tunnel. The transfer mother car can move along the transfer tunnel to reach the entrance of any tunnel 53, and then the transport vehicle 54 can be moved to the transfer mother car; for example, after the heavy blocks 7 in a tunnel 53 are emptied, the transport vehicle 54 in the tunnel 53 can be moved to other tunnels 53 for continued transportation through the transfer mother car. Such a setting can achieve a smaller number of transport vehicles, and there is no need to equip each tunnel 53 with a transport vehicle 54, which has higher equipment utilization and is more economical.
[0030] Also includes a plurality of lifting containers 6, such as Figures 3 to 5As shown, the lifting container 6 is generally in the shape of a rectangular parallelepiped, and a detachable rope gripper 61 for cooperating with the circular steel wire rope 45 is provided on the side of the lifting container 6. The detachable rope gripper 61 is arranged on the outside of the two opposite sides of the lifting container 6, and the other two opposite sides of the lifting container 6 are open entrances and exits for heavy objects. There are multiple detachable rope grippers 61, at least arranged in two horizontal rows and two vertical columns; preferably, for example, two horizontal rows are arranged near the upper and lower ends of the lifting container 6, and four detachable rope grippers 61 are arranged in each horizontal row, thereby forming four vertical columns. The circular steel wire rope 45 corresponds to the number and position of the vertical columns of the detachable rope gripper 61 one by one. In this multi-rope friction type circular lifting system, the lifting container 6 is locked and fixed with multiple steel wire ropes to ensure the stability of the lifting container 6 during operation, and effectively avoid torsion, overload and shaking.
[0031] The bottom of the outer side of the lifting container 6 is provided with a track wheel 62 for cooperating with the double ring track 5. The track wheel 62 has a driving device. After the lifting container enters the double ring track 5, it automatically connects to the power supply system laid along the track, and the driving device starts to drive the lifting container 6 to run slowly. The whole system is equipped with a multi-vehicle interactive task control system, which sends instructions through wireless communication to control the lifting container 6 to move along the set sub-track 52. For example, the lifting container 6 is moved alternately to the left and right sub-tracks 52 one by one, and then moved alternately to the main track 51 one by one after loading or unloading. At the same time, the lifting container 6 can wirelessly transmit the position information, running speed, loading and unloading action information, etc. to the multi-vehicle interactive task control system to realize remote unmanned intelligent control and improve the system operation stability and efficiency.
[0032] See also Figure 1 , the lifting container 6 can move along the double ring track 5 in the upper warehouse 2 and the lower warehouse 3, and can be lifted and lowered between the upper warehouse 2 and the lower warehouse 3 along the vertical shaft 1. The place where the upper warehouse 2 ground meets the shaft of the vertical shaft 1 can be called the wellhead platform, and the place where the lower warehouse 3 ground meets the shaft of the vertical shaft 1 can be called the well bottom platform; under normal operation, the highest position of the lifting container 6 is the wellhead platform, where the bottom of the lifting container 6 is basically level with the height of the upper warehouse 2 ground, so that the heavy object 7 can be stably transported into / out of the lifting container 6 to complete the loading and unloading work; similarly, the lowest position of the lifting container 6 is the well bottom platform.
[0033] Preferably, a retractable automatic lifting platform is provided at the shaft opening near the upper warehouse 2. Specifically, the part of the shaft opening platform of the upper warehouse 2 located on the upward side of the annular wire rope 45 forms an automatic detachable area 55 on the shaft, and a retractable automatic lifting platform is provided at this position, and the retractable automatic lifting platform includes a lifting mechanism connected to the shaft 1, the lifting mechanism is, for example, a slide rail structure, and the lifting direction is vertical; the lifting mechanism is connected to a telescopic mechanism, the telescopic mechanism is, for example, a slide rail structure, and the telescopic direction is horizontal; the end of the telescopic mechanism has a section of telescopic track for connecting with the double annular track 5 (main track 51), so that the telescopic track can be lifted and lowered in the shaft 1, and can be extended and retracted in the radial direction of the cross section of the shaft 1; the extension and retraction are, for example, horizontal extension or other methods such as flipping. In short, in the retracted state, it can allow the lifting container 6 to be lifted and lowered, and in the extended state, it can provide support for the lifting container 6. The retractable automatic lifting platform can automatically operate through the control system according to information such as the position and speed of the lifting container 6. More specifically, the rising speed of the retractable automatic lifting platform is consistent with the running speed of the lifting container 6. The extension of the retractable track is completed during the rising process. When the lifting container 6 runs to above the wellhead platform, the retractable automatic lifting platform reaches the wellhead platform position at the same time, and the retractable track is fully extended. After the lifting container 6 is detached, it automatically enters the retractable track, and then runs to the double ring track 5. Then the retractable track automatically retracts and quickly descends to a low position, following the rise of the next lifting container 6, and the cycle is repeated. The part of the wellhead platform of the upper warehouse 2 located on the downward side of the circular wire rope 45 forms an automatic rope holding area 56 on the well. A retractable automatic lifting platform of the same or similar structure is also provided at this position. When the lifting container 6 runs to the wellhead position along the double circular track 5, the retractable lifting platform has risen to the wellhead platform position and ensures that the telescopic track is extended. The lifting container 6 enters the automatic rope holding area and is automatically locked with the wire rope. After that, the telescopic track and the lifting container 6 are kept at the same speed or faster and descend to a low position. During the descent, the telescopic track is completely retracted, and then it rises quickly to the wellhead position of the upper warehouse 2. The telescopic track is quickly extended to cooperate with the operation and rope holding of the next lifting container 6, and the operation is cyclical. It can be imagined that in other embodiments, the retractable automatic lifting platform of the upper warehouse 2 can also be replaced by other structural forms such as a rocking platform to achieve similar functions. The part of the lower warehouse 3 located on the downward side of the circular wire rope 45 is the underground automatic detachment area 57, and the underground automatic detachment area 57 of the lower warehouse 3 located on the upward side of the circular wire rope 45. The underground automatic detachment area 57 and the underground automatic detachment area 57 can be selected as the ground.
[0034] The lifting container 6 is detached / caged at the corresponding automatic detachment area / automatic rope grabbing area, thereby realizing the above-mentioned movement and lifting process of the lifting container 6. Multiple lifting containers 6 are locked and fixed on the circular wire rope at a certain interval, which can form a continuous circulation of heavy logistics; when storing energy, the heavy-loaded lifting containers are distributed on the upward side of the circular wire rope 45, and the empty lifting containers are distributed on the downward side of the circular wire rope 45; when releasing energy, the heavy-loaded lifting containers are distributed on the downward side of the circular wire rope 45, and the empty lifting containers are distributed on the upward side of the circular wire rope 45.
[0035] The bottom of the inner side of the lifting container 6 is provided with an in-container conveying device 63, and / or a vehicle-mounted conveying device is provided above the conveying vehicle 54; thereby realizing the transfer of the heavy object 7 between the conveying vehicle 54 and the lifting container 6. In a specific embodiment, as Figure 2 As shown, the shelf has two frames arranged along the lane 53, and the two sides of the heavy object block 7 are placed on the shelves, and multiple heavy object blocks 7 are arranged and stacked along the shelves. The conveying vehicle 54 moves on the ground between the two frames of the shelf and is located below the heavy object block 7. The conveying vehicle 54 has, for example, a lifting device on top, so that the heavy object block 7 can be lifted up and taken away. Similarly, the heavy object block 7 can be lowered and placed on the shelf. It is preferred to have a vehicle-mounted conveying device and a container conveying device 63 at the same time. The vehicle-mounted conveying device and the container conveying device 63 can both be roller conveyor structures, and the conveying direction is parallel to the length direction of the lane 53 and the connection direction of the two heavy object block entrances and exits. Thereby, continuous and stable transfer and transportation between the two is realized. It is conceivable that in other embodiments, only one of the vehicle-mounted conveying device and the container conveying device 63 can be selected, or a separate loading and unloading conveyor is provided at the lane entrance, and a cradle-type structure is provided on one side or both sides so that transfer can be completed with only one conveying device.
[0036] The shaft-based continuous circulation gravity energy storage power generation system also includes the required current conversion equipment and control system, etc. These descriptions based on the prior art and this solution are clear and easy to implement, and will not be repeated here.
[0037] Based on the shaft-based continuous circulation gravity energy storage power generation system of the utility model, the utility model provides a shaft-based continuous circulation gravity energy storage power generation method, according to some embodiments, which includes the following steps:
[0038] When storing energy, the electric generator is started, driving the friction drive wheel 41 to rotate, and the circular wire rope 45 circulates under the action of friction; the empty lifting container 6 on the circular wire rope 45 is transported down to the automatic unloading area in the lower warehouse 3 located on the downward side of the circular wire rope 45, and the unloading gripper 61 on the side of the empty lifting container 6 is automatically disconnected from the downward side of the circular wire rope 45, and the empty lifting container 6 enters the double circular track 5 of the lower warehouse 3 and runs to the underground loading and unloading area at the specific entrance of the tunnel 53. 7 is transported to the underground loading and unloading area by the conveyor vehicle 54, and then the heavy object 7 is transferred to the empty lifting container 6 waiting in position. After loading is completed, the heavy-loaded lifting container 6 moves along the double ring track 5 to the underground automatic rope holding area located on the upward side of the ring wire rope 45 in the lower warehouse 3. The detachable rope holding device 61 on the side of the heavy-loaded lifting container 6 automatically locks with the upward side of the ring wire rope 45, and the ring wire rope 45 drives the heavy-loaded lifting container 6 to move upward along the vertical shaft 1 to the automatic detachable rope holding area on the upward side of the ring wire rope 45 in the upper warehouse 2, and the detachable rope holding device 61 on the side of the heavy-loaded lifting container 6 automatically locks with the upward side of the ring wire rope 45. The ring wire rope 45 drives the heavy-loaded lifting container 6 to move upward along the vertical shaft 1 to the upper automatic detachable rope holding area on the upward side of the ring wire rope 45 in the upper warehouse 2, and the detachable rope holding device 61 on the side of the heavy-loaded lifting container 6 automatically locks with the upward side of the ring wire rope 45, and the ... The gripper 61 is automatically disengaged from the circular wire rope 45, the heavily loaded lifting container 6 enters the double circular track 5 of the upper warehouse 2 and moves to the loading and unloading area on the shaft at the entrance of a specific tunnel 53, the heavy object 7 is transferred from the lifting container 6 to the conveying vehicle 54 of the upper warehouse 2, the unloaded lifting container 6 moves along the double circular track 5 to the automatic gripping area on the shaft on the downward side of the circular wire rope 45 in the upper warehouse 2, the detachable gripper 61 on the side of the unloaded lifting container 6 is automatically locked with the downward side of the circular wire rope 45, and is transported down the shaft 1 to the shaft along the circular wire rope 45. The automatic detaching zone is lowered, thus completing the cyclic movement of a lifting container 6; the whole system has multiple lifting containers 6, which can simultaneously load, lift, transport and unload heavy blocks 7; adjacent lifting containers 6 are locked and fixed at a certain distance on the circular wire rope 45 to form a continuous circulation of heavy logistics; the heavy-loaded lifting containers 6 are distributed on the upward side of the circular wire rope 45, and the empty lifting containers 6 are distributed on the downward side of the circular wire rope 45, until all the heavy blocks 7 in the lower warehouse 3 are transported to the upper warehouse 3, completing the rated energy storage capacity;
[0039] When releasing energy, the main difference from the energy storage process is that the heavily loaded lifting containers 6 are distributed on the downstream side of the circular steel wire rope 45, and the unloaded lifting containers 6 are distributed on the upstream side of the circular steel wire rope 45. Under the action of gravity, the circular steel wire rope 45 is driven to move by a plurality of heavily loaded lifting containers 6, which drives the friction drive wheel 41 to rotate, and then drives the electric generator to rotate and generate electricity, which is then fed back to the power grid through the inverter. Other loading and unloading processes are similar. The specific operation process is as follows: the empty lifting container 6 on the upward side of the circular wire rope 45 is transported to the automatic detaching area on the well, the empty lifting container 6 is automatically detached from the circular wire rope 45, enters the double circular track 5 of the upper warehouse 2 and runs to a specific position, and at the same time, the heavy object block 7 of the upper warehouse 2 is sent to the loading and unloading area on the well by the conveying vehicle 54, and the conveying vehicle 54 transfers the heavy object block 7 to the empty lifting container 6 waiting in position, and after loading is completed, the heavy-loaded lifting container 6 runs along the double circular track 5 to the automatic rope holding area on the well, and the detaching rope holding device 61 on the side of the heavy-loaded lifting container 6 is automatically locked with the downward side of the circular wire rope 45, and the heavy-loaded lifting container 6 runs downward along the vertical shaft 1 to the well under the action of gravity. In the automatic detachment area, the heavily loaded lifting container 6 is automatically detached from the circular steel wire rope 45, and the heavily loaded lifting container 6 enters the double circular track 5 of the lower warehouse 3 and moves to a specific position. The heavy objects 7 are transferred from the lifting container 6 to the conveying vehicle 54 of the lower warehouse 3, and the unloaded lifting container 6 moves along the double circular track 5 to the automatic rope holding area underground. The detachment rope holding device 61 on the side of the unloaded lifting container 6 is automatically locked with the upward side of the circular steel wire rope 45, and moves upward along the vertical shaft 1 with the circular steel wire rope 45 to the automatic detachment area above the well, thus completing the circulation movement of a lifting container 6; multiple lifting containers 6 are circulated at the same time until all the heavy objects 7 in the upper warehouse 2 are transported to the lower warehouse 3, and the rated power generation capacity is completed.
[0040] In a preferred embodiment, the lifting container 6 runs at a first speed with the circular steel wire rope 45 before being detached, and runs at a second speed after being detached. The first speed is greater than the second speed. Different operating speeds can be set according to different weight block sizes and different lifting container spacings. For example, the first speed can reach 2.5m / s to 8m / s, and the second speed can be controlled below 1m / s. In this solution, the lifting container 6 runs at a high speed with the circular steel wire rope 45 before being detached, ensuring high-efficiency operation in the energy storage and power generation states; it can run at a slow speed after being detached, fully meeting the time interval required for automatic loading and unloading of weight blocks, thereby ensuring system stability and environmentally friendly operation, and effectively overcoming the contradiction in the prior art that both operating efficiency and loading and unloading efficiency cannot be guaranteed at the same time.
[0041] In a preferred embodiment, the lifting container 6 after being detached enters the different sub-tracks 52 of the double-circular track 5 alternately in turn to increase the running interval between two adjacent lifting containers 6 and further reduce the running speed of the lifting container 6 on the sub-track 52, thereby creating conditions for the smooth loading and unloading of the heavy blocks 7.
[0042] In a preferred embodiment, when the system is shut down, all lifting containers 6 are detached from the circular steel wire rope 45 and parked on the double circular tracks 5 of the upper warehouse 2 and / or the lower warehouse 3 to reduce the load borne by the circular steel wire rope 45 during the shutdown process and improve the performance and service life of the steel wire rope.
[0043] To sum up, the utility model is based on the shaft of the continuous circulation type gravity energy storage power generation system from the perspective of power engineering application. The designed gravity energy storage system is driven by the wire rope to continuously circulate the lifting container. During the operation, the lifting container and the heavy object block can be automatically unloaded and automatically loaded by holding the rope, forming a uniform and stable heavy flow of materials. The energy storage and power generation output are stable, which greatly reduces the impact on equipment, motors, and generators, and effectively suppresses the output fluctuations of current and voltage during the system power generation process.
Claims
1. A continuous circulation gravity energy storage power generation system based on a vertical shaft, characterized in that: The invention comprises a vertical shaft (1), an upper warehouse (2) is arranged at the upper part of the vertical shaft (1), and a lower warehouse (3) is arranged at the lower part of the vertical shaft (1); the upper warehouse (2) has an upper warehouse conveying and loading and unloading system, and the lower warehouse (3) has a lower warehouse conveying and loading and unloading system; The utility model also comprises a gravity turbine system, which comprises an electric generator integrated machine arranged in the upper warehouse (2), the electric generator integrated machine being connected to a friction driving wheel (41), a derrick (11) being arranged above the vertical shaft (1), two upper shaft redirecting wheels (42) being arranged on the derrick (11), and a downhole redirecting wheel (43) and a tensioning device (44) being arranged below the lower warehouse (3) of the vertical shaft (1); an annular steel wire rope (45) is mounted on the friction driving wheel (41), the two upper shaft redirecting wheels (42) and the downhole redirecting wheel (43) to form a transmission connection; The upper warehouse conveying and loading and unloading system and the lower warehouse conveying and loading and unloading system both include a double annular track (5), the double annular track (5) including a main track (51) connected to the shaft of the vertical shaft (1) and two sub-tracks (52) formed by branches from the main track (51) on both sides, the sub-tracks (52) are curved in annular shape, and the two sub-tracks (52) are again joined to form a main track (51) on the other side of the vertical shaft (1) and connected to the shaft of the vertical shaft (1); It also includes a plurality of lifting containers (6), the side of each lifting container (6) is provided with a detachable rope gripper (61) for cooperating with an annular steel wire rope (45), and the bottom of each lifting container (6) is provided with a track wheel (62) for cooperating with a double annular track (5).
2. The shaft-based continuous circulation gravity energy storage power generation system according to claim 1 is characterized in that: A plurality of lanes (53) are arranged outside the sub-tracks (52) of the double-circular track (5), and each lane (53) is provided with a transport vehicle (54) and a shelf, on which a heavy object block (7) is placed.
3. The shaft-based continuous circulation gravity energy storage power generation system according to claim 2 is characterized in that: There are at least two annular steel wire ropes (45) arranged in parallel; there are multiple detachable rope grippers (61), arranged in at least two horizontal rows and two vertical columns; the annular steel wire ropes (45) correspond to the vertical columns of the detachable rope grippers (61) one by one.
4. The shaft-based continuous circulation gravity energy storage power generation system according to claim 2 is characterized in that: The detachable rope gripping device (61) is arranged on the outer sides of two opposite side surfaces of the lifting container (6), and the other two opposite side surfaces of the lifting container (6) are the entrances and exits of the weight blocks.
5. The shaft-based continuous circulation gravity energy storage power generation system according to claim 2, characterized in that: An in-container conveying device (63) is provided at the bottom of the inner side of the lifting container (6), and / or a vehicle-mounted conveying device is provided above the conveying vehicle (54).
6. The shaft-based continuous circulation gravity energy storage power generation system according to claim 2, characterized in that: A retractable automatic lifting platform is arranged at the shaft opening near the upper warehouse (2), and the retractable automatic lifting platform comprises a lifting mechanism, the lifting mechanism is connected to a retractable mechanism, and the end of the retractable mechanism has a retractable track for connecting with a double ring track (5), so that the retractable track can be lifted and lowered, and extended and retracted in the shaft (1).
Citation Information
Cited By
Continuous circulation type gravity energy storage power generation system and method based on vertical shaft
CN118375578A