Municipal engineering pipeline jacking construction structure

By introducing support plates, clamping components, lifting components, moisture-proof components and reinforcement components into the pipeline top pipe construction structure, combined with the design of bidirectional screws and universal joints, the pipeline support is not firm and the lifting mechanism is easy to develop in the prior art. The problem of rust has achieved more efficient pipeline fixation and extended equipment life.

CN222046878UInactive Publication Date: 2024-11-22HUBEI ZHUHE CONSTR ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420846981.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-23
Publication Date
2024-11-22
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

When used, the existing pipeline top pipe construction structure is prone to cause the support mechanism to disengage due to external forces, and the lifting mechanism is prone to rust, affecting the fixing firmness and service life.

Method used

A structure including support plate, clamping assembly, lifting assembly, moisture-proof assembly and reinforcement assembly was designed. The triangular fixation of the pipe was achieved through bidirectional screws and universal joints, and the use of telescopic tubes and desiccants were used to prevent rust and improve the use of equipment. Lifespan and load bearing strength.

Benefits of technology

It effectively avoids the disengagement and impact of the pipeline due to external forces, extends the service life of the equipment, and improves the support firmness of the pipeline and the efficiency of construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222046878U_ABST
    Figure CN222046878U_ABST
Patent Text Reader

Abstract

The utility model discloses a municipal engineering pipeline jacking construction structure which comprises a supporting plate and a base, a clamping assembly is installed at the top of the supporting plate, the clamping assembly comprises a side plate and a clamping plate, a lifting assembly is installed at the bottom of the supporting plate, the lifting assembly comprises a thread sleeve and a two-way screw rod, a moisture-proof assembly is installed at the bottom of the supporting plate, and the moisture-proof assembly is installed at the bottom of the supporting plate. The moisture-proof assembly comprises a telescopic pipe and a drying agent, a pushing assembly is installed on the clamping plate, and the pushing assembly comprises a screw rod and a universal joint I. According to the municipal engineering pipeline jacking construction structure, the dryness of the two-way screw rod and the screw sleeve can be guaranteed, and the situation that the two-way screw rod cannot rotate due to rusting is avoided; the clamping plate and the cutting board are used for conducting triangular fixing on the pipeline, the situation that the pipeline is disengaged and collides with the equipment due to external force and vibration is avoided, the supporting firmness and safety of the pipeline are guaranteed, and the pipe jacking fixing device is suitable for being used for pipe jacking fixing in pipeline laying.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of pipeline jacking construction equipment, in particular to a municipal engineering pipeline jacking construction structure. Background Art

[0002] When laying pipelines, in order to facilitate the support and fixation of pipelines, it is often necessary to use pipeline jacking construction equipment. The utility model patent with patent application number CN202321910456.2 discloses a gas pipeline jacking construction device, which can support the gas pipeline through a receiving sleeve. The height of the receiving sleeve can be adjusted by the operation of a telescopic motor to make it parallel to the pipeline to be spliced. The receiving base can be pushed by manpower to make the receiving sleeve slide in the movable slide groove, so that the pipelines can be docked, which is convenient for fixing operations, saving time and effort, and improving the inconvenience of traditional equipment without assistance and purely manual allocation of pipeline positions. According to the technical solution disclosed by the utility model patent, when the existing pipeline jacking construction structure is used, on the one hand, it can often only support the pipeline upward. After being subjected to external force, the pipeline is prone to separation and collision with the supporting mechanism, which is not conducive to ensuring the firmness and safety of the pipeline. On the other hand, the lifting mechanism is prone to rust after being placed for a long time, which is not conducive to ensuring the service life and working reliability of the lifting mechanism.

[0003] Therefore, how to design a pipe jacking construction structure for municipal engineering has become our current problem to be solved. Utility Model Content

[0004] In view of the deficiencies in the prior art, the purpose of the utility model is to provide a municipal engineering pipeline jacking construction structure to solve the problems raised in the above-mentioned background technology. The utility model has a reasonable design and is relatively convenient to use, and is suitable for fixing jacking pipes in pipeline laying.

[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a municipal engineering pipeline jacking construction structure, including a support plate and a base, a clamping assembly is installed on the top of the support plate, and the clamping assembly includes a side plate and a splint, a lifting assembly is installed on the bottom of the support plate, and the lifting assembly includes a screw sleeve and a bidirectional screw, a moisture-proof assembly is installed on the bottom of the support plate, and the moisture-proof assembly includes a telescopic tube and a desiccant, a pushing assembly is installed on the splint, and the pushing assembly includes a screw and a universal joint, and a reinforcement assembly is installed on the support plate, and the reinforcement assembly includes an arc plate and a reinforcing plate.

[0006] Furthermore, the screw sleeves are welded to the top of the base and the bottom of the support plate respectively, and the top and bottom ends of the bidirectional screw are both clamped on the inner side of the screw sleeves.

[0007] Furthermore, an internal thread 1 is provided on the inner side of the screw sleeve, and an external thread 1 is provided on the outer side of the bidirectional screw, and the internal thread 1 matches the external thread 1.

[0008] Furthermore, a sealing ring is bonded to the top of the base, the top of the telescopic tube is bonded to the bottom of the support plate, the bottom end of the telescopic tube is sealed and inserted inside the sealing ring, the telescopic tube sleeve is arranged on the outside of the screw sleeve and the bidirectional screw, and the desiccant is bonded to the inner side of the top of the telescopic tube.

[0009] Furthermore, the side panels are integrally formed on both sides of the top of the support plate, the bottom of the clamping plate is installed on the top of the support plate through a rotating shaft, and the clamping plate is clamped on the inner side of the side panels.

[0010] Furthermore, the universal joint 1 is installed on the inner side of the clamping plate, and one end of the screw rod is installed on the inner side of the universal joint 1 through a rotating shaft.

[0011] Furthermore, a universal joint 2 is installed on the inner side of the side plate, the other end of the screw rod passes through the universal joint 2 and extends to the outer side of the side plate, an internal thread 2 is provided on the inner side of the universal joint 2, and an external thread 2 is provided on the screw rod, and the internal thread 2 cooperates with the external thread 2.

[0012] Furthermore, the reinforcing plate is welded to the bottom of the support plate, the bottom of the arc plate is welded to the top of the support plate, both sides of the arc plate are welded to the side plates, and an anvil is installed on the top of the support plate.

[0013] Beneficial effects: 1. When the municipal engineering pipeline jacking construction structure is in use, the base is installed at the bottom of the pipeline, and then the bottom end of the telescopic tube is pulled out from the inner side of the sealing ring, and the telescopic tube is compressed upward, and then the bidirectional screw is rotated. The bidirectional screw pushes the screw sleeves at both ends outward, thereby moving the support plate upward and supporting the bottom of the pipeline, and then the bottom end of the telescopic tube is sealed and inserted into the inner side of the sealing ring. At the same time, the desiccant is used to dry and absorb the water vapor that penetrates into the telescopic tube to ensure the dryness of the bidirectional screw and the screw sleeve, and avoid the bidirectional screw from being unable to rotate due to rust, which is convenient for subsequent adjustment, replacement and disassembly work, and ensures the service life of the equipment.

[0014] 2. When the municipal engineering pipeline jacking construction structure is in use, the bottom of the pipeline is supported on the top of the support plate through the anvil plate, and then the screw is rotated. The screw cooperates with the external thread 2 and the internal thread 2 to make the screw pass through the inner side of the universal joint 2 and move to the inner side of the side plate, so that the screw pushes the clamping plate to the outside of the pipeline through the universal joint 1. The clamping plate rotates through the rotating shaft and is clamped on the top of both sides of the pipeline respectively. The pipeline is triangularly fixed with the clamping plate and the anvil plate to prevent the pipeline from being separated and colliding with the equipment due to external force and vibration, thereby ensuring the support firmness and safety of the pipeline. The support plate and the side plate are strengthened with arc plates and reinforcing plates to improve the bearing strength of the equipment.

[0015] 3. The pipe jacking construction structure of this municipal engineering project is reasonably designed, more efficient and convenient to use, and is suitable for the fixing of pipe jacking during pipeline laying. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 This is a structural schematic diagram of a municipal engineering pipeline jacking construction structure of the utility model;

[0017] Figure 2 This is a cross-sectional view of a municipal engineering pipeline jacking construction structure of the utility model;

[0018] In the figure: 1. support plate; 2. side plate; 3. base; 4. screw sleeve; 5. bidirectional screw; 6. telescopic tube; 7. sealing ring; 8. anvil; 9. clamping plate; 10. universal joint one; 11. universal joint two; 12. screw; 13. arc plate; 14. reinforcement plate; 15. desiccant. DETAILED DESCRIPTION

[0019] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0020] See also Figure 1 to Figure 2The utility model provides a technical solution: a municipal engineering pipeline jacking construction structure, including a support plate 1 and a base 3, a clamping assembly is installed on the top of the support plate 1, and the clamping assembly includes a side plate 2 and a clamping plate 9, a lifting assembly is installed on the bottom of the support plate 1, and the lifting assembly includes a screw sleeve 4 and a bidirectional screw 5, a moisture-proof assembly is installed on the bottom of the support plate 1, and the moisture-proof assembly includes a telescopic tube 6 and a desiccant 15, a pushing assembly is installed on the clamping plate 9, and the pushing assembly includes a screw 12 and a universal joint 10, a reinforcement assembly is installed on the support plate 1, and the reinforcement assembly includes an arc plate 13 and a reinforcing plate 14, an internal thread 1 is opened on the inner side of the screw sleeve 4, and an external thread 1 is opened on the outer side of the bidirectional screw 5, and the internal thread 1 cooperates with the external thread 1, a sealing ring 7 is bonded to the top of the base 3, and the top of the telescopic tube 6 is bonded to At the bottom of the support plate 1, the bottom end of the telescopic tube 6 is sealed and inserted into the inner side of the sealing ring 7, the telescopic tube 6 is sleeved on the outer side of the screw sleeve 4 and the bidirectional screw 5, and the desiccant 15 is bonded to the inner side of the top of the telescopic tube 6. When in use, the base 3 is installed at the bottom of the pipeline, and then the bottom end of the telescopic tube 6 is pulled out from the inner side of the sealing ring 7, and the telescopic tube 6 is compressed upward, and then the bidirectional screw 5 is rotated, and the bidirectional screw 5 pushes the screw sleeves 4 at both ends outward, so that the support plate 1 moves upward and supports the bottom of the pipeline, and then the bottom end of the telescopic tube 6 is sealed and inserted into the inner side of the sealing ring 7, and at the same time, the desiccant 15 is used to dry and absorb the water vapor that penetrates into the telescopic tube 6, so as to ensure the dryness of the bidirectional screw 4 and the screw sleeve 5, and avoid the bidirectional screw 5 from being unable to rotate due to rust, so as to facilitate the subsequent adjustment, replacement and disassembly work, and ensure the service life of the equipment.

[0021] In this embodiment, the screw sleeve 4 is welded to the top of the base 3 and the bottom of the support plate 1 respectively, the top and bottom ends of the bidirectional screw 5 are clamped on the inner side of the screw sleeve 4, and the side plates 2 are respectively integrally formed on both sides of the top of the support plate 1, the bottom of the splint 9 is installed on the top of the support plate 1 through a rotating shaft, the splint 9 is clamped on the inner side of the side plate 2, the universal joint 10 is installed on the inner side of the splint 9, one end of the screw 12 is installed on the inner side of the universal joint 10 through a rotating shaft, and a universal joint 2 11 is installed on the inner side of the side plate 2, the other end of the screw 12 passes through the universal joint 2 11 and extends to the outer side of the side plate 2, the inner side of the universal joint 2 11 is provided with an internal thread 2, and the screw 12 is provided with an external thread 2, and the internal thread 2 cooperates with the external thread 2, the reinforcing plate 14 is welded to the bottom of the support plate 1, and the arc plate 13 The bottom is welded to the top of the support plate 1, and both sides of the arc plate 13 are welded to the side plate 2. The top of the support plate 1 is installed with an anvil plate 8. When in use, the bottom of the pipe is supported on the top of the support plate 1 by the anvil plate 8, and then the screw 12 is rotated. The screw 12 cooperates with the external thread 2 and the internal thread 2, so that the screw 12 passes through the inner side of the universal joint 11 and moves to the inner side of the side plate 2, so that the screw 12 pushes the clamping plate 9 to the outer side of the pipe through the universal joint 10. The clamping plate 9 rotates through the rotating shaft and is clamped on the top of both sides of the pipe respectively. The clamping plate 9 and the anvil plate 8 are used to triangularly fix the pipe to prevent the pipe from being separated and colliding with the equipment due to external force and vibration, thereby ensuring the support firmness and safety of the pipe. The arc plate 13 and the reinforcing plate 14 are used to strengthen the support plate 1 and the side plate 2 to improve the bearing strength of the equipment.

[0022] When the municipal engineering pipeline jacking construction structure is in use, the base 3 is installed at the bottom of the pipeline, and then the bottom end of the telescopic tube 6 is pulled out from the inner side of the sealing ring 7, and the telescopic tube 6 is compressed upward, and then the bidirectional screw 5 is rotated, and the bidirectional screw 5 pushes the screw sleeves 4 at both ends outward, so that the support plate 1 moves upward and supports the bottom of the pipeline, and then the bottom end of the telescopic tube 6 is sealed and inserted into the inner side of the sealing ring 7, and at the same time, the desiccant 15 is used to dry and absorb the water vapor that penetrates into the telescopic tube 6, so as to ensure the dryness of the bidirectional screw 4 and the screw sleeve 5, and avoid the bidirectional screw 5 from being unable to rotate due to rust, so as to facilitate the subsequent adjustment, replacement and disassembly work, and ensure the service life of the equipment. The bottom of the pipeline is supported on the top of the support plate 1 through the anvil plate 8, and then the screw 12 is rotated. The screw 12 cooperates with the external thread 2 and the internal thread 2, so that the screw 12 passes through the inner side of the universal joint 11 and moves to the inner side of the side plate 2, and then the screw 12 pushes the clamping plate 9 to the outer side of the pipeline through the universal joint 10. The clamping plate 9 rotates through the rotating shaft and is clamped on the top of both sides of the pipeline respectively. The clamping plate 9 and the anvil plate 8 are used to triangularly fix the pipeline to prevent the pipeline from being separated and colliding with the equipment due to external force and vibration, thereby ensuring the support firmness and safety of the pipeline. The arc plate 13 and the reinforcing plate 14 are used to strengthen the support plate 1 and the side plate 2 to improve the bearing strength of the equipment.

[0023] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.

Claims

1. A municipal engineering pipeline jacking construction structure, comprising a support plate (1) and a base (3), a clamping assembly is installed on the top of the support plate (1), and the clamping assembly comprises a side plate (2) and a clamping plate (9), characterized in that: A lifting assembly is installed at the bottom of the support plate (1), and the lifting assembly includes a screw sleeve (4) and a bidirectional screw (5). A moisture-proof assembly is installed at the bottom of the support plate (1), and the moisture-proof assembly includes a telescopic tube (6) and a desiccant (15). A pushing assembly is installed on the clamping plate (9), and the pushing assembly includes a screw (12) and a universal joint (10). A reinforcement assembly is installed on the support plate (1), and the reinforcement assembly includes an arc plate (13) and a reinforcing plate (14).

2. A municipal engineering pipeline jacking construction structure according to claim 1, characterized in that: The screw sleeve (4) is welded to the top of the base (3) and the bottom of the support plate (1) respectively, and the top and bottom ends of the bidirectional screw (5) are both clamped on the inner side of the screw sleeve (4).

3. A municipal engineering pipeline jacking construction structure according to claim 2, characterized in that: An internal thread 1 is formed on the inner side of the screw sleeve (4), and an external thread 1 is formed on the outer side of the bidirectional screw rod (5), wherein the internal thread 1 matches the external thread 1.

4. A municipal engineering pipeline jacking construction structure according to claim 3, characterized in that: A sealing ring (7) is bonded to the top of the base (3), the top end of the telescopic tube (6) is bonded to the bottom of the support plate (1), the bottom end of the telescopic tube (6) is sealed and inserted inside the sealing ring (7), the telescopic tube (6) is sleeved on the outside of the screw sleeve (4) and the bidirectional screw (5), and the desiccant (15) is bonded to the inside of the top end of the telescopic tube (6).

5. A municipal engineering pipeline jacking construction structure according to claim 1, characterized in that: The side panels (2) are integrally formed on both sides of the top of the support plate (1), the bottom of the clamping plate (9) is mounted on the top of the support plate (1) via a rotating shaft, and the clamping plate (9) is clamped on the inner side of the side panel (2).

6. A municipal engineering pipeline jacking construction structure according to claim 5, characterized in that: The universal joint 1 (10) is installed on the inner side of the clamping plate (9), and one end of the screw rod (12) is installed on the inner side of the universal joint 1 (10) via a rotating shaft.

7. A municipal engineering pipeline jacking construction structure according to claim 6, characterized in that: A universal joint 2 (11) is installed on the inner side of the side plate (2), and the other end of the screw rod (12) passes through the universal joint 2 (11) and extends to the outer side of the side plate (2). An internal thread 2 is provided on the inner side of the universal joint 2 (11), and an external thread 2 is provided on the screw rod (12), and the internal thread 2 matches the external thread 2.

8. A municipal engineering pipeline jacking construction structure according to claim 7, characterized in that: The reinforcing plate (14) is welded to the bottom of the support plate (1), the bottom of the arc plate (13) is welded to the top of the support plate (1), both sides of the arc plate (13) are welded to the side plate (2), and an anvil (8) is installed on the top of the support plate (1).