Settlement detection device for construction project detection
By designing an automated settlement detection device, using pulley sets and motor systems to achieve automated vertical placement and adjustment of the measurement ruler, the difficulty and inaccuracy of manually placing the measurement ruler in the prior art is solved, and the efficiency of completing settlement measurements is achieved by one person , accurate operation.
Patent Information
- Application Number
- CN202420339959.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-23
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2034-02-23
AI Technical Summary
The existing settlement measurement device requires manual placement of the measuring ruler, and it is difficult to ensure horizontal placement, affecting the measurement results.
A settlement detection device including pulley set, stabilizing plate, motor and electric push rod is designed. Through the synergy of the slide chute, support plate and motor, the automatic vertical placement and adjustment of the measuring ruler is realized, and powered by solar panels and batteries is used. Simplify operations.
It realizes the function of completing settlement measurements by one person, improves measurement efficiency and accuracy, simplifies the operation process, and the device is environmentally friendly and reliable.
Smart Images

Figure CN222047131U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of settlement detection devices, and more specifically, to a settlement detection device for construction engineering detection. Background Art
[0002] Settlement measurement, also known as subsidence measurement or vertical displacement measurement, is a measurement work carried out to determine the displacement size and direction of the elevation of a deformable body over time, explain the reasons, and provide deformation trends and stability forecasts.
[0003] For the reference point buried in the foundation, the first observation is carried out after the burial, and the subsequent observations are carried out continuously during the installation to obtain the settlement amount. However, when the existing measuring ruler (5) is placed on the leveling point or the settlement measurement point, it needs to be placed manually, which is difficult for one person to operate, and the measuring ruler has the problem of not being placed horizontally, which affects the measurement result. Therefore, in view of the above problems, a settlement detection device for construction engineering detection is specially proposed. Utility Model Content
[0004] 1. Technical issues to be resolved
[0005] In view of the deficiencies in the prior art, the purpose of the utility model is to provide a settlement detection device for construction engineering inspection, which has the characteristics of being able to automatically place a measuring ruler on a leveling point or a settlement measurement point, so that one person can complete a settlement measurement.
[0006] (II) Technical solution
[0007] To achieve the above-mentioned purpose, the utility model provides a settlement detection device for construction engineering detection, including a pulley block and a stabilizing plate, the stabilizing plate is provided with a through groove, a part of the pulley block is located in the through groove, the top of the pulley block is fixedly connected to the first support plate, the first support plate is provided with a first slide groove and a second slide groove, the first slide groove and the second slide groove are respectively slidably connected to the second support plate and the tooth plate, one side of the tooth plate is integrally fixed to one side of the second support plate, one side of the first support plate is installed with a first motor by a fixing bolt, the output shaft of the first motor is fixedly connected with a gear, the gear is meshed with the tooth plate, the second support plate is fixedly connected with a mounting frame, the mounting frame is installed with a second motor, the output shaft of the second motor is connected to a connecting rod by a bearing and a rotating shaft, and one end of the connecting rod is fixedly connected with a measuring ruler.
[0008] When using a settlement detection device for construction project inspection according to the technical solution, the height of the measuring ruler can be adjusted through the joint action of the first slide groove, the second slide groove, the first support plate, the second support plate and the first motor, and the direction of the measuring ruler can be adjusted under the joint action of the second motor and the connecting rod, so that the measuring ruler can be placed vertically on the leveling point or the settlement measurement point, and one person can complete a settlement measurement.
[0009] Furthermore, a fixing plate is integrally connected to one side of the first supporting plate, and a solar cell panel and a storage battery are mounted on the fixing plate.
[0010] Furthermore, an electric push rod is fixedly connected to the bottom of the pulley block, and the other end of the electric push rod is fixedly connected to the stabilizing plate.
[0011] Furthermore, a controller is installed on one side of the first support plate.
[0012] Furthermore, the mounting frame is U-shaped, the body of the second motor is mounted on the mounting frame by fixing bolts, the connecting rod is inserted into the mounting frame, the output shaft of the second motor is connected to the rotating shaft through a coupling, and one end of the rotating shaft is welded to the connecting rod.
[0013] (III) Beneficial effects
[0014] In summary, the utility model has the following beneficial effects:
[0015] Under the joint action of the first slide groove, the second slide groove, the first support plate, the second support plate and the first motor, the height of the measuring ruler can be adjusted, and under the joint action of the second motor and the connecting rod, the direction of the measuring ruler can be adjusted, so that the measuring ruler can be placed vertically on the leveling point or the settlement measurement point. When using the settlement measuring instrument for measurement, there is no need for one person to hold the measuring ruler and one person to observe the measuring instrument. One person can complete a settlement measurement, which is more convenient to use. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] In order to more clearly illustrate the specific implementation of the utility model or the technical solution in the prior art, the drawings required for describing the specific implementation or the prior art will be briefly introduced below. Obviously, the drawings described below are only one implementation of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0017] Figure 1 It is a schematic diagram of the three-dimensional structure of the utility model;
[0018] Figure 2 This is a schematic diagram of the first chute structure of the utility model;
[0019] Figure 3 This is a schematic diagram of the structure of the electric push rod of the utility model.
[0020] The symbols in the accompanying drawings are:
[0021] 1. Stabilizing plate; 2. Pulley block; 3. Through slot; 4. First support plate; 5. Measuring ruler; 6. Connecting rod; 7. Second motor; 8. Solar panel; 9. Battery; 10. Gear; 11. First motor; 12. Controller; 13. Second support plate; 14. Tooth plate; 15. Second slide slot; 16. First slide slot; 17. Electric push rod. DETAILED DESCRIPTION
[0022] In order to make the technical means, creative features, objectives and effects achieved by the utility model easy to understand, the technical scheme in the specific implementation mode of the utility model is clearly and completely described below to further illustrate the utility model. Obviously, the specific implementation mode described is only a part of the implementation mode of the utility model, rather than all styles.
[0023] Example:
[0024] The following is combined with Figure 1-3 The utility model is described in further detail.
[0025] See also Figure 1-3 The utility model provides a technical solution: a settlement detection device for construction engineering detection, including a pulley block 2 and a stabilizing plate 1, a through groove 3 is opened on the stabilizing plate 1, a part of the pulley block 2 is located in the through groove 3, the bottom of the pulley block 2 is fixedly connected with an electric push rod 17, the other end of the electric push rod 17 is fixedly connected to the stabilizing plate 1, under the action of the electric push rod 17, the stabilizing plate 1 can be made to contact with the ground, so that the whole device is fixed more stably, the top of the pulley block 2 is fixedly connected with a first support plate 4, a controller 12 is installed on one side of the first support plate 4, and a fixing plate is integrally connected to one side of the first support plate 4, and a solar cell panel 8 and a battery 9 are installed on the fixing plate. Through the arrangement of the solar cell panel 8 and the battery 9, the use of the whole device is more environmentally friendly.
[0026] The first support plate 4 is provided with a first slide groove 16 and a second slide groove 15, and the second support plate 13 and the tooth plate 14 are slidably connected in the first slide groove 16 and the second slide groove 15 respectively, and one side of the tooth plate 14 is integrally fixed with one side of the second support plate 13, and a first motor 11 is installed on one side of the first support plate 4 through a fixing bolt, and the output shaft of the first motor 11 is fixedly connected with a gear 10, and the gear 10 is meshed with the tooth plate 14. The second support plate 13 is fixedly connected with a mounting frame, and the mounting frame is installed with a second motor 7. The output shaft of the second motor 7 is connected with a connecting rod 6 through a bearing and a rotating shaft, and one end of the connecting rod 6 is fixedly connected with a measuring ruler 5, and the shape of the mounting frame is U-shaped, and the body of the second motor 7 is fixedly connected with a connecting rod 6 through a bearing and a rotating shaft. The fixing bolts are installed on the mounting frame, the connecting rod 6 is inserted in the mounting frame, the output shaft of the second motor 7 is connected to the rotating shaft through a coupling, and one end of the rotating shaft is welded to the connecting rod 6. Under the joint action of the first slide groove 16, the second slide groove 15, the first support plate 4, the second support plate 13 and the first motor 11, the height of the measuring ruler 5 can be adjusted, and under the joint action of the second motor 7 and the connecting rod 6, the direction of the measuring ruler 5 can be adjusted, so that the measuring ruler 5 can be placed vertically on the leveling point or the settlement measurement point. When using the settlement measuring instrument for measurement, there is no need for one person to hold the measuring ruler 5 and one person to observe the measuring instrument. One person can complete a settlement measurement, which is more convenient to use.
[0027] The working principle of the utility model is as follows: when in use, the whole device is moved to the vicinity of the leveling point or the settlement measuring point, the controller 12 controls the electric push rod 17 to bring the stabilizing plate 1 down, so that the stabilizing plate 1 is in contact with the ground, thereby achieving the purpose of fixing the device, and then the controller 12 controls the second motor 7 to rotate with the connecting rod 6, so that the measuring ruler 5 is rotated to the top of the leveling point or the settlement measuring point, and then the controller 12 controls the first motor 11 to rotate with the gear 10, and the gear 10 rotates in meshing with the toothed plate 14, so that the measuring ruler 5 can be brought into contact with the leveling point or the settlement measuring point, thereby facilitating the measuring instrument to measure the value at the leveling point or the settlement measuring point.
[0028] This specific embodiment is merely an explanation of the present invention and is not a limitation of the present invention. After reading this specification, those skilled in the art may make non-creative modifications to the present embodiment as needed, but such modifications are protected by patent law as long as they are within the scope of the claims of the present invention.
Claims
1. A settlement detection device for construction engineering detection, comprising a pulley block (2) and a stabilizing plate (1), Features: The stabilizing plate (1) is provided with a through groove (3), a part of the pulley block (2) is located in the through groove (3), the top of the pulley block (2) is fixedly connected with a first support plate (4), the first support plate (4) is provided with a first slide groove (16) and a second slide groove (15), the first slide groove (16) and the second slide groove (15) are respectively slidably connected with a second support plate (13) and a tooth plate (14), one side of the tooth plate (14) is integrally fixed with one side of the second support plate (13), a first motor (11) is installed on one side of the first support plate (4) by means of fixing bolts, the output shaft of the first motor (11) is fixedly connected with a gear (10), the gear (10) is meshedly connected with the tooth plate (14), the second support plate (13) is fixedly connected with a mounting frame, a second motor (7) is mounted on the mounting frame, the output shaft of the second motor (7) is connected with a connecting rod (6) through a bearing and a rotating shaft, and one end of the connecting rod (6) is fixedly connected with a measuring ruler (5).
2. A settlement detection device for construction engineering detection according to claim 1, Features: One side of the first support plate (4) is integrally connected with a fixing plate, on which a solar cell panel (8) and a storage battery (9) are mounted.
3. A settlement detection device for construction engineering detection according to claim 1, Features: The bottom of the pulley block (2) is fixedly connected to an electric push rod (17), and the other end of the electric push rod (17) is fixedly connected to the stabilizing plate (1).
4. A settlement detection device for construction engineering detection according to claim 1, Features: A controller (12) is installed on one side of the first support plate (4).
5. A settlement detection device for construction engineering detection according to claim 1, Features: The mounting frame is in a U-shape, the body of the second motor (7) is mounted on the mounting frame by means of fixing bolts, the connecting rod (6) is inserted into the mounting frame, the output shaft of the second motor (7) is connected to the rotating shaft by means of a coupling, and one end of the rotating shaft is welded to the connecting rod (6).