Horizontal monitoring device for girder of bridge girder erection machine

By installing the monitoring components of the static level and data acquisition box inside the main beam of the bridge mounter, the relative height difference of each leg is monitored and displayed in real time, the problem of cumbersome measurement of the horizontal status of the bridge mounter and safety hazards is solved, and the problem of improving the problem of high-level status of the main beam of the bridge mounter is improved. Construction safety.

CN222049018UActive Publication Date: 2024-11-22CHINA TIESIJU CIVIL ENGINEERING GROUP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420399424.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-01
Publication Date
2024-11-22
Estimated Expiration
2034-03-01

AI Technical Summary

Technical Problem

After the bridge stairs are completed, the horizontal state measurement of the main beam needs to be frequently carried out, resulting in construction troubles and safety hazards at night measurements.

Method used

A monitoring component including the first, second and third static level is designed, installed inside the main beam of the bridge mounter, and the relative height difference of each leg is monitored and displayed in real time through the data acquisition box and the display, avoiding the need. The climbing bridge builder performs measurement.

Benefits of technology

It realizes convenient monitoring of the horizontal status of the main beam of the bridge rigging machine, improves construction safety, and avoids the risk of night workers climbing the bridge rigging machine.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222049018U_ABST
    Figure CN222049018U_ABST
Patent Text Reader

Abstract

The utility model discloses a bridge girder erection machine girder levelness monitoring device which comprises a monitoring assembly installed in a bridge girder erection machine girder, the monitoring assembly comprises a first static force level gauge, a second static force level gauge and a third static force level gauge, and the first static force level gauge, the second static force level gauge and the third static force level gauge are all arranged in the bridge girder erection machine girder. A data acquisition electric box is fixedly mounted at the top of the inner wall of the bridge girder erection machine girder through a mounting plate, is electrically connected with the first static leveling instrument, the second static leveling instrument and the third static leveling instrument, and is electrically connected with a display; the first static force level gauge, the second static force level gauge and the third static force level gauge are used for horizontally monitoring the corresponding positions of the front, middle and rear bridge erecting machine supporting legs, and then the data acquisition electric box is used for transmitting data into the display for data processing and displaying, so that the display can display the relative height difference of the main beam at each supporting leg in real time; and operators can conveniently and correspondingly adjust the supporting legs.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of level monitoring, and in particular to a level monitoring device for a main beam of a bridge erecting machine. Background Art

[0002] The bridge-erecting machine is a lifting equipment that places prefabricated beams on prefabricated bridge piers. Its main function is to lift the beams, transport them to the location and then lower them. After the bridge-erecting machine has completed the hole-passing process, the main beam of the bridge-erecting machine needs to be adjusted to be horizontal or the main beam at the front leg is slightly higher than the middle leg by 50mm, so as to improve the stability of the bridge-erecting machine and ensure the safety of beam erection.

[0003] However, in the process of implementing relevant technical solutions, at least the following technical problems were found: after the bridge-building machine has passed through the hole, the technical staff usually goes to the main beam of the bridge-building machine and uses a level to measure the horizontal state of the main beam. According to the measurement results, the bridge deck workers are notified to adjust the legs of the bridge-building machine. The staff are required to climb the bridge-building machine and take multiple measurements, which makes the construction more troublesome. Climbing the bridge-building machine for measurement at night is also prone to safety hazards. Utility Model Content

[0004] The present application solves the problem of troublesome main beam horizontal status monitoring in the prior art by providing a bridge-building machine main beam horizontal monitoring device, and achieves the effect of monitoring the horizontal status of the bridge-building machine main beam using a static level.

[0005] The present application provides a horizontal monitoring device for a bridge-building machine main beam, including a monitoring component installed inside the bridge-building machine main beam, the monitoring component including: a first static level, a second static level and a third static level, the first static level, the second static level and the third static level are all arranged inside the bridge-building machine main beam, a data acquisition electrical box is fixedly installed on the top of the inner wall of the bridge-building machine main beam through a mounting plate, the data acquisition electrical box is electrically connected to the first static level, the second static level and the third static level, and the data acquisition electrical box is electrically connected to a display.

[0006] Furthermore, a transverse rib is provided inside the main beam of the bridge-building machine, and a plurality of vertical ribs are provided inside the main beam of the bridge-building machine. The first static level is horizontally installed on the transverse rib by bolts at a position corresponding to the front support leg of the bridge-building machine.

[0007] Furthermore, the second static level is horizontally mounted on the transverse rib plate by bolts at a position corresponding to the middle support leg of the bridge erecting machine.

[0008] Furthermore, the third static level is horizontally mounted on the transverse rib plate at a position corresponding to the rear support leg of the bridge erecting machine by means of bolts.

[0009] Furthermore, the monitoring component also includes: a liquid tank, which is installed on the vertical rib on the side through a connecting plate; a liquid pipe, which is arranged at the bottom of the liquid tank, and the liquid pipe will be connected in series with the liquid tank and the first static level, the second static level and the third static level; a gas pipe, which is arranged at the top of the liquid tank, and the gas pipe will be connected in series with the liquid tank and the first static level, the second static level and the third static level.

[0010] Furthermore, a data line is provided at the bottom of the data acquisition electrical box, and the data line connects the data acquisition electrical box, the liquid tank, the first static level, the second static level and the third static level in series.

[0011] The technical solution provided by this application has at least the following technical effects or advantages:

[0012] The first, second and third static levels are used to monitor the corresponding positions of the front, middle and rear legs of the bridge-building machine. The data is then transmitted to the monitor through the data acquisition box for processing and display. The relative height difference of the main beam of the bridge-building machine at each leg can be displayed on the monitor in real time, which is convenient for operators to make corresponding adjustments to the legs of the bridge-building machine and avoids the risk of operators climbing the bridge-building machine to measure the horizontal state at night. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] Figure 1 This is a schematic diagram of the overall structure of the monitoring device in the embodiment of the present application;

[0014] Figure 2 This is a schematic diagram of the cross-sectional structure of the main beam of the bridge erecting machine in the embodiment of the present application;

[0015] Figure 3 This is a schematic diagram of the structure of the monitoring component in the embodiment of the present application;

[0016] In the figure: 10, main beam of the bridge-building machine; 20, transverse ribs; 30, vertical ribs; 40, monitoring components; 50, data acquisition electrical box; 60, data line; 41, first static level; 42, second static level; 43, third static level; 44, liquid tank; 45, liquid pipe; 46, gas pipe. DETAILED DESCRIPTION

[0017] The embodiment of the present application discloses a device for monitoring the level of the main beam of a bridge-building machine, which monitors the height of the main beam 10 of the bridge-building machine at the corresponding positions of the front, middle and rear supporting feet of the bridge-building machine through a first static level 41, a second static level 42 and a third static level 43, and cooperates with a data acquisition box 50 to input data into a display for processing and display, so that the display can display the relative height difference of the main beam 10 of the bridge-building machine at the front, middle and rear supporting feet in real time, making it convenient for operators to make corresponding adjustments to the supporting feet of the bridge-building machine.

[0018] In order to better understand the above technical solution, the above technical solution will be described in detail below in conjunction with the accompanying drawings and specific implementation methods.

[0019] Please refer to Figure 1-Figure 3 The present embodiment provides a bridge erection machine main beam level monitoring device, including a monitoring component 40 installed inside the bridge erection machine main beam 10, the bridge erection machine main beam 10 is provided with a transverse rib plate 20, and the bridge erection machine main beam 10 is provided with a plurality of vertical rib plates 30. The monitoring component 40 includes: a first static level 41, a second static level 42, a third static level 43, a liquid tank 44, a liquid pipe 45, and a gas pipe 46. The first static level 41, the second static level 42, and the third static level 43 are all provided on the bridge erection machine main beam 10. The first static level 41 is installed horizontally on the transverse rib 20 by bolts and corresponds to the front leg of the bridge erecting machine. The second static level 42 is installed horizontally on the transverse rib 20 by bolts and corresponds to the middle leg of the bridge erecting machine. The third static level 43 is installed horizontally on the transverse rib 20 by bolts and corresponds to the rear leg of the bridge erecting machine. The liquid tank 44 is installed on the side vertical rib 30 by connecting plates. The liquid pipe 45 is arranged at the bottom of the liquid tank 44, and the liquid pipe 45 connects the liquid tank 44 with the first static level 41 and the third static level 43. The second static level 42 and the third static level 43 are connected in series, and the gas pipe 46 is arranged on the top of the liquid tank 44, and the gas pipe 46 connects the liquid tank 44 with the first static level 41, the second static level 42 and the third static level 43 in series. The liquid pipe 45 and the gas pipe 46 on the liquid tank 44 are arranged between the liquid tank 44 and the first static level 41, the first static level 41 and the second static level 42, and the second static level 42 and the third static level 43, so as to connect the liquid tank 44 with the first static level 41, the second static level 42 and the third static level 43. The second static level 42 and the third static level 43 are connected in series, the end of the liquid tube 45 extending from the third static level 43 is closed, and the end of the gas tube 46 extending from the third static level 43 is connected to the atmosphere, and the liquid is transported to the first static level 41, the second static level 42 and the third static level 43 through the liquid tank 44, so that the first static level 41, the second static level 42 and the third static level 43 can measure the pressure at the main beam 10 of the bridge erecting machine at the corresponding positions of the front, middle and rear legs of the bridge erecting machine.

[0020] Please refer to Figure 1-Figure 3 A data acquisition electric box 50 is fixedly installed on the top of the inner wall of the main beam 10 of the bridge erecting machine through a mounting plate. The data acquisition electric box 50 is electrically connected to the first static level 41, the second static level 42 and the third static level 43. The data acquisition electric box 50 is electrically connected to the display. A data line 60 is arranged at the bottom of the data acquisition electric box 50. The data line 60 connects the data acquisition electric box 50 and the liquid tank 44 in series with the first static level 41, the second static level 42 and the third static level 43. The data line 60 is arranged between the data acquisition electric box 50 and the first static level 41, the first static level 41 and the second static level 42, the second static level 42 and the third static level 43, and connects the data acquisition electric box 50 with the first static level 41, the first static level 41 and the second static level 42, the second static level 42 and the third static level 43. A static level 41, a second static level 42 and a third static level 43 are connected in series, and the data measured by the first static level 41, the second static level 42 and the third static level 43 are transmitted to the data acquisition box 50 through a data line 60. The data acquisition box 50 then transmits the data to a display for data processing and analysis, and displays the relative height difference of the bridge-building machine main beam 10 at each support leg on the display, so that the technician can notify the operator to make corresponding adjustments to the bridge-building machine legs based on the data, and the horizontal state of the bridge-building machine main beam 10 can be measured without using a level, which makes it more convenient to monitor the level of the bridge-building machine main beam 10 and avoids the risk of operators climbing the bridge-building machine to measure the horizontal state at night.

[0021] This application can explain its functional principle through the following operation methods:

[0022] When in use, the liquid tank 44 is installed on the vertical rib 30 on the side of the inner wall of the main beam 10 of the bridge erecting machine through the mounting plate, and the first static level 41, the second static level 42, and the third static level 43 are respectively installed horizontally on the transverse rib 20 on the inner wall of the main beam 10 of the bridge erecting machine, and the first static level 41, the second static level 42, and the third static level 43 are located at the positions in the main beam 10 of the bridge erecting machine corresponding to the front, middle, and rear legs of the bridge erecting machine, and then the liquid pipe 45 and the gas pipe 46 at the bottom and top of the liquid tank 44 are connected in series with the first static level 41, the second static level 42, and the third static level 43, so that the first static level 41, the second static level 42, and the third static level 43 are connected in series. The level 43 can measure the height of the front, middle and rear legs of the bridge-building machine corresponding to the main beam 10 of the bridge-building machine. The data acquisition box 50 is installed on the top of the inner wall of the main beam 10 of the bridge-building machine. The data line 60 at the bottom of the data acquisition box 50 connects the first static level 41, the second static level 42 and the third static level 43, so that the data measured by the first static level 41, the second static level 42 and the third static level 43 can be transmitted to the data acquisition box 50, and the data acquisition box 50 then transmits the data to the display for processing and analysis, and displays the relative height difference of the main beam 10 of the bridge-building machine at each leg on the display. The technician can notify the operating personnel to make corresponding adjustments to the legs of the bridge-building machine based on the data.

[0023] Obviously, those skilled in the art can make various changes and modifications to the present application without departing from the spirit and scope of the present application. Thus, if these modifications and variations of the present application fall within the scope of the claims of the present application and their equivalents, the present application is also intended to include these modifications and variations.

[0024] What has been described above is only a preferred specific implementation manner of the embodiments of the present application, but the protection scope of the present application is not limited thereto. Any technician familiar with the technical field can make equivalent substitutions or changes according to the technical scheme and concept of the present application within the technical scope disclosed in the present application, which should be covered by the protection scope of the present application.

Claims

1. A bridge erection machine main beam level monitoring device, comprising a monitoring component (40) installed inside a bridge erection machine main beam (10), characterized in that: The monitoring component (40) comprises: A first static level (41), a second static level (42) and a third static level (43), wherein the first static level (41), the second static level (42) and the third static level (43) are all arranged inside the main beam (10) of the bridge erecting machine, A data acquisition electric box (50) is fixedly installed on the top of the inner wall of the main beam (10) of the bridge-building machine via a mounting plate. The data acquisition electric box (50) is electrically connected to the first static level (41), the second static level (42) and the third static level (43). The data acquisition electric box (50) is electrically connected to a display.

2. The main beam level monitoring device for a bridge erecting machine according to claim 1, characterized in that: The main beam (10) of the bridge erecting machine is provided with a transverse rib (20) inside, and the main beam (10) of the bridge erecting machine is provided with a plurality of vertical ribs (30) inside. The first static level (41) is horizontally mounted on the transverse rib (20) by bolts at a position corresponding to the front support leg of the bridge erecting machine.

3. The bridge erection machine main beam level monitoring device according to claim 2, characterized in that: The second static level (42) is horizontally mounted on the transverse rib (20) by means of bolts at a position corresponding to the middle support foot of the bridge erecting machine.

4. The bridge erection machine main beam level monitoring device according to claim 2, characterized in that: The third static level (43) is horizontally mounted on the transverse rib (20) at a position corresponding to the rear support leg of the bridge erecting machine by means of bolts.

5. The bridge erection machine main beam level monitoring device according to claim 2, characterized in that: The monitoring component (40) further comprises: A liquid tank (44) is mounted on the vertical ribs (30) at the side through a connecting plate; a liquid pipe (45) disposed at the bottom of the liquid tank (44), and the liquid pipe (45) is connected in series with the liquid tank (44) and the first static level (41), the second static level (42) and the third static level (43); A gas pipe (46) is arranged at the top of the liquid tank (44), and the gas pipe (46) is connected in series with the liquid tank (44) and the first static level (41), the second static level (42) and the third static level (43).

6. The main beam level monitoring device for a bridge erecting machine according to claim 5, characterized in that: A data line (60) is provided at the bottom of the data acquisition electrical box (50), and the data line (60) connects the data acquisition electrical box (50) and the liquid tank (44) and the first static level (41), the second static level (42) and the third static level (43) in series.