Anti-puncture pneumatic deicing device suitable for bogie cabin of high-speed train
By embedding the expansion body on the end plate of the bogie cabin of the high-speed train and controlling its volume changes using the fluid source component, the problem of snow melt water and ice is difficult to remove, and the safe operation of the high-speed train in cold areas is achieved.
Patent Information
- Application Number
- CN202420849618.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-23
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2034-04-23
AI Technical Summary
When high-speed trains operate in cold areas, the snow melt water and ice in the bogie compartment are difficult to remove, resulting in snow and icing that interfere with normal movement and affect safe operation.
A puncture-proof pneumatic deicing device is designed, including embedding an expansion body on the bogie cabin end plate, controlling the volume change of the expansion body through the fluid source assembly, and applying force to cause the snow and ice to fall off, using three levels and two The equipment of the stage pipeline, solenoid valve and other components achieve deicing.
It realizes effective deicing without stopping during high-speed train operation, ensuring the operation efficiency and safety of the train, and avoiding the interference of snow melting water and ice icing.
Smart Images

Figure CN222061987U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to a train accessory device, in particular to an anti-puncture pneumatic deicing device suitable for a bogie compartment of a high-speed train. Background Art
[0002] In winter, when high-speed trains run on snow-covered roads, snow particles will instantly melt on the surfaces of high-temperature components such as brake discs, forming a large amount of snowmelt water in the bogie compartment area, which will then splash under the influence of the train wind, and then accumulate snow and ice in the bogie compartment, especially in the end plate of the bogie compartment. The accumulation of snow and ice will cause squeezing movement, interfere with the normal movement of various parts of the bogie, and bring huge risks to the safe operation of high-speed trains. Therefore, real-time ice melting and deicing of the end plates of the bogie compartment of high-speed trains is crucial.
[0003] Currently, most existing high-speed train bogie compartments adopt an integrated fixed compartment design, which causes snowmelt water to condense and adhere to the end plate surface of the bogie compartment and cannot be effectively removed, seriously affecting the winter operation of high-speed trains in cold areas. Utility Model Content
[0004] The utility model provides an anti-puncture pneumatic deicing device suitable for a high-speed train bogie compartment, and aims to solve the problem that snow and ice layers in the bogie compartment are difficult to remove during the running of the high-speed train.
[0005] In order to achieve the above-mentioned object, an embodiment of the utility model provides an anti-puncture pneumatic deicing device suitable for a high-speed train bogie compartment, comprising:
[0006] A bogie compartment, the bogie compartment comprising an end plate, at least one deicing device being embedded in the end plate, the deicing device comprising:
[0007] A main plate for embedding the end plate, wherein the central area is recessed inwards to form an embedding area;
[0008] An expansion body, wherein a plurality of the expansion bodies are arranged in parallel on the first surface of the embedded area;
[0009] a fluid source assembly, in communication with the expansion body;
[0010] A control component, outputting an indication signal for controlling the working state of the fluid source component to the fluid source component;
[0011] The deicing device includes a first state and a second state. When the deicing device is in the first state, the fluid source component inputs fluid into the expansion body; when the deicing device is in the second state, the fluid source component extracts the fluid in the expansion body.
[0012] Preferably, the first surface of the embedded area is further provided with a plurality of parallel first accommodating grooves, each of the expansion bodies is arranged in the first accommodating groove, and when the deicing device is in the second state, the height of the expansion body is equal to the surface of the main board.
[0013] Preferably, the deicing device applicable to the bogie compartment further comprises a tertiary pipeline and a secondary pipeline;
[0014] The embedded area also has a second surface opposite to the first surface, and a third accommodating groove and a second accommodating groove are arranged on the second surface. The third accommodating groove is used to accommodate a tertiary pipeline, and the second accommodating groove is used to accommodate a secondary pipeline. Each of the tertiary pipelines is connected to each expansion body one by one, and the connection point between the tertiary pipeline and each expansion body is located at the center of the expansion body. Each tertiary pipeline is connected to the fluid source component through the secondary pipeline.
[0015] Preferably, two secondary pipelines are provided, one of which is connected to each odd-numbered tertiary pipeline, and the other is connected to each even-numbered tertiary pipeline;
[0016] Each of the three-stage pipelines is also provided with a first solenoid valve connected to the control component signal, and the first solenoid valve is arranged upstream of the connection point between the three-stage pipeline and the expansion body.
[0017] Preferably, the expansion body is a rubber tube, and the surface of the expansion body is coated with a protective layer, and the protective layer is made of polyurea material.
[0018] Preferably, the de-icing device also includes a protective cover arranged on the main board, the protective cover is located on the same side as the second surface, the protective cover has an edge and a protective body arranged between the two edges, the protective body protrudes in a direction away from the second surface, and the edge is arranged on the main board through an installation component.
[0019] Preferably, the mounting assembly comprises a polished bolt, a spring is sleeved on the polished bolt, and a threaded end of the polished bolt is passed through the edge and is screwed to the main board.
[0020] Preferably, the deicing device suitable for the bogie compartment further comprises a primary pipeline, the secondary pipeline of each deicing device is connected to the fluid source component through the primary pipeline, and a flow controller is also provided on the primary pipeline.
[0021] The above solution of the utility model has the following beneficial effects:
[0022] In the present application, a de-icing device is arranged on the end plate of the bogie cabin. When there is snow or ice on the end plate, the volume change of the expansion body exerts force on the snow or ice, causing the snow to fall off or the ice to crack and fall off, thereby achieving the de-icing effect.
[0023] This application does not require stopping for operation during the de-icing process and can be operated at any time according to demand to ensure the operating efficiency of high-speed trains.
[0024] Other features and advantages of the present invention will be described in detail in the subsequent specific implementation section. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 It is a front view schematic diagram of the de-icing device;
[0026] Figure 2 It is a schematic diagram of the reverse side of the de-icing device;
[0027] Figure 3 This is a schematic diagram of the reverse side of the motherboard;
[0028] Figure 4 It is a schematic diagram of the installation components;
[0029] Figure 5 It is a schematic diagram of the installation of the de-icing device.
[0030] [Description of Reference Numerals]
[0031] 100-main board, 200-embedded area, 210-third receiving groove, 220-second receiving groove, 230-through hole,
[0032] 300-expansion body, 400-protection cover, 410-edge, 420-protection body, 500-installation assembly, 510-bare rod bolt, 520-spring, 530-gasket, A-de-icing device, B-bogie compartment, B1-end plate, C-equipment compartment. DETAILED DESCRIPTION
[0033] In order to make the technical problems to be solved, technical solutions and advantages of the present invention more clear, a detailed description will be given below in conjunction with the accompanying drawings and specific embodiments.
[0034] like Figure 1-5As shown, the embodiment of the utility model provides an anti-puncture pneumatic deicing device suitable for a high-speed train bogie compartment, comprising a main board 100, an expansion body 300, a fluid source assembly and a control assembly. The main board 100 has a front side and a back side. The central area of the front side of the main board 100 is thinned so that the central area is recessed toward the center of the main board 100 along the thickness direction to form an embedded area 200. The embedded area 200 has a first surface and a second surface opposite to each other. The front side of the main board 100 is located on the same side as the first surface of the embedded area 200, and the back side of the main board 100 is located on the same side as the second surface of the embedded area 200. The front side of the main board 100 is higher than the first surface of the embedded area 200, and the back side of the main board 100 is flush with the second surface of the embedded area 200. Several expansion bodies 300 are arranged in parallel on the first surface of the embedded area 200 and are kept at a uniform interval. The expansion bodies 300 are also connected to the fluid source assembly. The control component sends an indication signal to the fluid source component, where the indication signal is used to instruct the fluid source component to fill or discharge fluid into or from the expansion body 300, or to indicate the rate at which the fluid source component fills or discharges fluid.
[0035] The deicing device A includes a first state and a second state. When the deicing device A is in the first state, the fluid source component inputs fluid into the expansion body 300, and the volume of the expansion body 300 increases; when the deicing device A is in the second state, the fluid source component extracts fluid from the expansion body 300, and the volume of the expansion body 300 decreases.
[0036] Furthermore, the aforementioned bogie compartment B is arranged below the train body. Generally speaking, the bogie compartment B includes a skirt plate in addition to the aforementioned end plate B1. Two end plates B1 are arranged in the length direction of the high-speed train, and several skirt plates are arranged in the width direction of the high-speed train. The space enclosed by the end plates B1 and the skirt plates is the bogie compartment B, which is used to install the bogie. The space on the other side of the end plate B1 usually forms an equipment compartment C.
[0037] When in use, the main board 100 of at least one de-icing device A is embedded in the end plate B1 and the expansion body 300 is directed toward the center of the bogie compartment B. The de-icing device A is switched between the first state and the second state, so that cracks appear in the ice layer attached to the de-icing device A and the ice layer falls off.
[0038] Preferably, when multiple de-icing devices A are installed, the multiple de-icing devices A can be arranged according to a certain pattern, such as being arranged in a straight line or in a matrix along the width direction of the bogie compartment.
[0039] Preferably, in the present application, the fluid flowing in the fluid source assembly may be a gas or a liquid that is not easily frozen in the train running environment.
[0040] Furthermore, a plurality of first accommodating grooves are provided on the first surface of the embedded area 200, each of which is arranged at intervals and parallel to each other, and each of the expansion bodies 300 is fixed in the first accommodating grooves. When the deicing device A is in the first state, the height of the expansion body 300 is higher than the front of the main board 100. When the deicing device A is in the second state, the height of the expansion body 300 is equal to the front of the main board 100.
[0041] In this embodiment, the expansion body 300 is fixed in the first receiving groove by gluing. Fixing the expansion body 300 in the first receiving groove helps to maintain the stability of the installation of the expansion body 300 on the one hand, and on the other hand, the first receiving groove limits the expansion direction of the expansion body 300, so that the expansion body 300 expands more toward the front direction of the mainboard 100, forming an effective volume change, so that the effect of breaking ice and removing ice is better.
[0042] Furthermore, the deicing device A further comprises a tertiary pipeline and a secondary pipeline, which are used for fluid flow. The number of each tertiary pipeline is the same as that of the expansion body 300 and they are connected to the expansion body 300 in a one-to-one manner. Each tertiary pipeline also converges on the secondary pipeline, which is connected to the fluid source assembly.
[0043] The fluid generated by the fluid source assembly passes through the secondary pipeline and is then divided into the tertiary pipeline. After being guided by the tertiary pipelines, the fluid enters each expansion body 300 , thereby increasing the volume of the expansion body 300 .
[0044] In this embodiment, the fluid source assembly causes each expansion body 300 to expand or contract synchronously by synchronously filling or discharging the fluid, which can more easily produce large-area cracks in the ice layer and is more suitable for large-area deicing.
[0045] The second surface of the embedded area 200 is opposite to the first surface, and a third accommodating groove 210 and a second accommodating groove 220 are arranged on the second surface, wherein the third accommodating groove 210 is used to accommodate the tertiary pipeline, and the second accommodating groove 220 is used to accommodate the secondary pipeline, which plays a role in protecting the secondary pipeline and the tertiary pipeline.
[0046] Preferably, a through hole 230 passing through the embedded area 200 is provided at the end of the third accommodating groove 210, and the tertiary pipeline is connected to the expansion body 300 through the through hole 230 through the embedded area 200, and the connection point between the tertiary pipeline and the expansion body 300 is located at the midpoint of the length of the expansion body 300, so that the fluid can uniformly change the volume of the expansion body 300.
[0047] Further, two secondary pipelines are provided, the odd-numbered tertiary pipelines are connected to one of the secondary pipelines, and the even-numbered tertiary pipelines are connected to the other secondary pipeline. In the present application, the number of tertiary pipelines is consistent with the number of expansion bodies 300, both of which are set to ten, wherein the tertiary pipelines at the first, third, fifth, seventh, and ninth positions are connected to one of the secondary pipelines, and the tertiary pipelines at the remaining positions are connected to the other secondary pipeline.
[0048] Furthermore, each tertiary pipeline is provided with a first solenoid valve, which is also connected to the control component signal, and the control component controls the on-off of the first solenoid valve, and the first solenoid valve is provided upstream of the connection between the tertiary pipeline and the expansion body 300. Preferably, the first solenoid valve is a three-way solenoid valve.
[0049] In this embodiment, each tertiary pipeline can be independently controlled to be on and off by the first solenoid valve. During de-icing, the operator can select any position and any number of expansion bodies 300 for inflation according to different needs. It can not only de-ice key areas, but also perform secondary de-icing on areas with poor de-icing effect. Moreover, by changing the fluid entry speed and entry sequence, more deformation effects can be produced, thereby promoting the separation and shedding of the ice layer and the surface of the expansion body 300, thereby improving the de-icing efficiency.
[0050] The aforementioned expansion body 300 is a low-temperature resistant rubber tube. In the second state, the top of the curved surface of the rubber tube is at the same height as the front of the main board 100. A protective layer is coated on the surface of the expansion body 300. The protective layer is made of an existing polyurea material. Due to the excellent puncture-proof properties of the polyurea material, it effectively prevents ice and snow from damaging the expansion body 300. During the de-icing process, the impact force generated by the fluid source component can quickly shatter the ice layer, while the protective layer can ensure that the expansion body 300 is not damaged and maintains its original integrity. At the same time, the excellent wear resistance and corrosion resistance of the polyurea material enable it to resist the erosion of natural environments such as ice, snow, wind and frost for a long time, with a long working cycle, easy maintenance and low maintenance costs.
[0051] The de-icing device A also includes a protective cover 400, which is arranged on the reverse side of the main board 100. The protective cover 400 has an edge 410 and a protective body 420 between the two edges 410. The edge 410 of the protective cover 400 is fixed to the main board 100 through an installation assembly 500. The protective body 420 of the protective cover 400 protrudes in a direction away from the second surface so that a cavity is formed between the protective body 420 and the main board 100, and the secondary pipeline and the tertiary pipeline are located in the cavity.
[0052] Furthermore, the aforementioned mounting assembly 500 includes a bare rod bolt 510, the screw rod of the bare rod bolt 510 has a bare axis at one end close to the nut and a threaded end at the end away from the nut, a spring 520 is sleeved on the bare rod bolt 510, the bare rod bolt 510 is passed through the protective cover 400 and the threaded section is screwed to the main board 100, one end of the spring 520 abuts against the nut, and the other end abuts against the edge 410.
[0053] Preferably, a gasket 530 is also sleeved on the polished rod bolt 510 , and the gasket 530 is located between the spring 520 and the edge 410 .
[0054] Furthermore, the deicing device A also includes a primary pipeline, and the secondary pipelines of each deicing device A converge on the primary pipeline, and the primary pipeline is connected to the aforementioned fluid source component.
[0055] In the present application, the fluid provided by the fluid source component to the expansion body 300 is air. The fluid source component includes an air compressor and an air pump. The air compressor, the air pump and the primary pipeline are provided with a second solenoid valve at the connection. The second solenoid valve is connected to the control component signal. Under the action of the third solenoid valve and the control component, the fluid source component is used to inflate the expansion body 300 or discharge the gas in the expansion body 300. Preferably, a flow controller is also provided on the primary pipeline. Preferably, the second solenoid valve is a three-way solenoid valve.
[0056] In the present application, the primary pipeline, the secondary pipeline and the tertiary pipeline respectively use hoses, which are arranged between the protective cover 400 and the main board 100. When the hose is filled with fluid, the protective cover 400 has freedom and can move in the direction of the protrusion of the protective cover 400, thereby avoiding contact between the hose and the equipment in the equipment compartment C and avoiding leakage caused by puncture of the hose by the equipment in the equipment compartment C.
[0057] The above is a preferred embodiment of the present invention. It should be pointed out that, for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principles of the present invention. These improvements and modifications should also be regarded as the protection scope of the present invention.
Claims
1. A puncture-proof pneumatic deicing device suitable for a high-speed train bogie compartment, characterized in that: include: A bogie compartment (B), the bogie compartment (B) comprising an end plate (B1), at least one deicing device (A) being embedded in the end plate (B1), the deicing device (A) comprising: A main plate (100) for embedding in the end plate (B1), wherein the central area is recessed inwards to form an embedding area (200); An expansion body (300), wherein a plurality of the expansion bodies (300) are arranged in parallel on the first surface of the embedded area (200); A fluid source component, connected to the expansion body (300); A control component, outputting an indication signal for controlling the working state of the fluid source component to the fluid source component; The deicing device (A) comprises a first state and a second state. When the deicing device (A) is in the first state, the fluid source component inputs fluid into the expansion body (300); when the deicing device (A) is in the second state, the fluid source component extracts the fluid from the expansion body (300).
2. The anti-puncture pneumatic deicing device for a high-speed train bogie compartment according to claim 1 is characterized in that: The first surface of the embedded area (200) is also provided with a plurality of parallel first accommodating grooves, each of the expansion bodies (300) is arranged in the first accommodating groove, and when the deicing device (A) is in the second state, the height of the expansion body (300) is equal to the surface of the main board (100).
3. The anti-puncture pneumatic deicing device for a high-speed train bogie compartment according to claim 2 is characterized in that: The de-icing device applicable to the bogie compartment also includes a tertiary pipeline and a secondary pipeline; The embedded area (200) also has a second surface opposite to the first surface, and a third accommodating groove (210) and a second accommodating groove (220) are arranged on the second surface, the third accommodating groove (210) is used to accommodate a tertiary pipeline, and the second accommodating groove (220) is used to accommodate a secondary pipeline, each of the tertiary pipelines is connected to each expansion body (300) in a one-to-one correspondence, and the connection point between the tertiary pipeline and each expansion body (300) is located at the center of the expansion body (300), and each tertiary pipeline is connected to the fluid source component through the secondary pipeline.
4. The anti-puncture pneumatic deicing device for a high-speed train bogie compartment according to claim 3 is characterized in that: There are two secondary pipelines, one of which is connected to each odd-numbered tertiary pipeline, and the other is connected to the even-numbered tertiary pipeline; Each of the three-stage pipelines is also provided with a first solenoid valve connected to the control component signal, and the first solenoid valve is arranged upstream of the connection point between the three-stage pipeline and the expansion body (300).
5. The anti-puncture pneumatic deicing device for a high-speed train bogie compartment according to claim 1 is characterized in that: The expansion body (300) is a rubber tube, and the surface of the expansion body (300) is coated with a protective layer, which is made of a polyurea material.
6. The anti-puncture pneumatic deicing device for a high-speed train bogie compartment according to claim 4 is characterized in that: The deicing device (A) further comprises a protective cover (400) arranged on the main board (100), the protective cover (400) being located on the same side as the second surface, the protective cover (400) comprising an edge (410) and a protective body (420) arranged between the two edges (410), the protective body (420) protruding in a direction away from the second surface, and the edge (410) being arranged on the main board (100) via a mounting assembly (500).
7. The anti-puncture pneumatic deicing device for a high-speed train bogie compartment according to claim 6 is characterized in that: The mounting assembly (500) comprises a polished bolt (510), a spring (520) is sleeved on the polished bolt (510), and a threaded end of the polished bolt (510) is passed through the edge (410) and is screwed to the main board (100).
8. The anti-puncture pneumatic deicing device for a high-speed train bogie compartment according to claim 4 is characterized in that: The deicing device suitable for the bogie compartment also includes a primary pipeline, and the secondary pipeline of each deicing device (A) is connected to the fluid source component through the primary pipeline. A flow controller is also arranged on the primary pipeline.
Citation Information
Cited By
Train equipment compartment area ice and snow prevention system for regulating and controlling wind and snow transportation characteristics
CN121650708A