Gantry crane for bridge construction
By setting up a rectangular frame and a dual hydraulic cylinder structure on the gantry crane for bridge construction, combining telescopic support rods and reinforcement rods, the lifting instability and motor overload caused by excessive length of the rope is solved, and higher stability and safety are achieved , extends the service life of the equipment.
Patent Information
- Application Number
- CN202323654710.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-31
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2033-12-31
AI Technical Summary
During bridge construction, the lifting of the gantry crane is unstable due to the long lifting rope, which can easily cause the motor to be overloaded and affect the service life of the equipment.
A gantry crane for bridge construction was designed, and a rectangular frame and a dual hydraulic cylinder structure were installed at the bottom of the bearing main beam. The load bearing capacity and stability were improved through telescopic support rods and reinforcement rods, and a segmented structure and two-stage lifting design were adopted to avoid The rope is too long and the motor is overloaded.
It improves the stability of the lifting process, reduces the overload of the motor, extends the service life of the lifting equipment, and improves the safety of the load capacity.
Smart Images

Figure CN222063927U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of lifting equipment, and in particular relates to a gantry crane for bridge construction. Background Art
[0002] Gantry crane, also known as gantry crane, is a deformation of bridge crane. The metal structure is like a door-shaped frame and can walk directly on the guide rails on the ground. Most existing gantry cranes have two single pillars under the main beam, plus an inclined rod support structure. However, during the bridge construction and lifting process, the overall mass of the bridge deck is large and the relative thickness is small. The lifting equipment on the gantry crane main beam needs to be lowered with a long length of rope, which makes the bridge deck extremely unstable when lifting. At the same time, due to the large mass of the bridge deck and the long length of the rope, the bridge deck shakes unstably during the lifting process, which easily causes the overload of the motor of the lifting equipment on the main beam. Therefore, the utility model proposes a gantry crane for bridge construction to avoid the over-length of the rope, which causes instability during the lifting process and reduces the overload caused by the continuous output of the lifting equipment motor. Utility Model Content
[0003] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a gantry crane for bridge construction, comprising a load-bearing main beam, top frames are symmetrically fixed at both ends of the bottom of the load-bearing main beam, telescopic support rods are fixed at the four corners of the bottom of the top frame, an anti-fall structure is arranged inside the telescopic support rods, a reinforcement rod is fixed between adjacent telescopic support rods, a bottom frame is fixed at the bottom of the telescopic support rods, and first hydraulic cylinders are symmetrically arranged inside the four telescopic support rods, the cylinder body of the first hydraulic cylinder is fixed on the bottom frame, and the output end of the first hydraulic cylinder is fixedly connected to the top frame.
[0004] As a preferred technical solution of the present utility model, the load-bearing main beam is a segmented structure, and adjacent load-bearing main beam modules are fastened and connected by bolts.
[0005] As a preferred technical solution of the utility model, the telescopic support rod includes a fixed tube and an extension rod, the bottom shaft of the extension rod passes through the top of the fixed tube and is slidably connected to the inside of the fixed tube.
[0006] As a preferred technical solution of the utility model, the anti-fall assembly includes a second hydraulic cylinder and a socket, a plug rod is fixed to the output end of the second hydraulic cylinder, the socket is respectively opened on the fixed cylinder body and the extension rod body, and the plug rod and the socket are adapted to each other.
[0007] As a preferred technical solution of the utility model, pulleys are symmetrically fixed on both sides of the bottom of the base frame, guide rails are arranged outside the pulleys, and the guide rails are arranged in parallel.
[0008] As a preferred technical solution of the utility model, the connection between the load-bearing main beam and the corresponding top frame, and the connection between the telescopic support rod and the top frame, the reinforcement rod and the bottom frame are all fastened by bolts.
[0009] Compared with the prior art, the beneficial effects of the utility model are as follows: the utility model improves the overall bearing capacity and stability by arranging rectangular frames at both ends of the bottom of the load-bearing main beam, and at the same time symmetrically arranges double hydraulic cylinders at both ends for jacking, thereby ensuring safety and increasing the carrying capacity. Compared with the single-stage lifting of the single-column structure on both sides of the existing gantry crane, the utility model adopts a two-stage lifting structure as a whole, which avoids the instability caused by the lifting rope of the lifting equipment being lowered too long during the lifting of goods, and at the same time reduces the overload caused by the continuous output of the lifting equipment motor, thereby extending the service life of the lifting equipment. BRIEF DESCRIPTION OF THE DRAWINGS
[0010] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:
[0011] Figure 1 It is a schematic diagram of the overall structure of the utility model;
[0012] Figure 2 It is a structural schematic diagram of the utility model from another angle;
[0013] Figure 3 It is a schematic diagram of the cross-sectional structure of the telescopic support rod fixing tube in the utility model;
[0014] In the figure: 1. load-bearing main beam; 2. top frame; 3. telescopic support rod; 4. reinforcement rod; 5. bottom frame; 6. first hydraulic cylinder; 7. guide rail; 8. fixing cylinder; 9. extension rod; 10. second hydraulic cylinder; 11. socket; 12. plug rod; 13. pulley. DETAILED DESCRIPTION
[0015] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0016] Example
[0017] See also Figure 1-3The utility model provides the following technical solutions: a gantry crane for bridge construction, comprising a load-bearing main beam 1, top frames 2 are symmetrically fixed at both ends of the bottom of the load-bearing main beam 1, telescopic support rods 3 are fixed at the four corners of the bottom of the top frame 2, an anti-falling structure is arranged inside the telescopic support rods 3, a reinforcement rod 4 is fixed between adjacent telescopic support rods 3, a bottom frame 5 is fixed at the bottom of the telescopic support rods 3, and first hydraulic cylinders 6 are symmetrically arranged inside four telescopic support rods 3, the cylinder body of the first hydraulic cylinder 6 is fixed on the bottom frame 5, and the output end of the first hydraulic cylinder 6 is fixedly connected to the top frame 2. In this embodiment, rectangular frames are arranged at both ends of the bottom of the load-bearing main beam to improve the overall bearing capacity and stability, and double hydraulic cylinders are symmetrically arranged at both ends for jacking to ensure safety and improve the carrying capacity.
[0018] In order to facilitate disassembly and assembly, in this embodiment, as a preferred technical solution of the utility model, the load-bearing main beam 1 is a segmented structure, and adjacent modules of the load-bearing main beam 1 are fastened and connected by bolts.
[0019] In order to keep the load-bearing main beam stable when it rises, in this embodiment, as a preferred technical solution of the utility model, the telescopic support rod 3 includes a fixed tube 8 and an extension rod 9, and the bottom rod body of the extension rod 9 passes through the top of the fixed tube 8 and is slidably connected to the inside of the fixed tube 8.
[0020] In order to prevent the load-bearing main beam from falling after rising, in this embodiment, as a preferred technical solution of the utility model, the anti-falling assembly includes a second hydraulic cylinder 10 and a socket 11, and a plug rod 12 is fixed to the output end of the second hydraulic cylinder 10. The socket 11 is respectively opened on the body of the fixed cylinder 8 and the body of the extension rod 9, and the plug rod 12 and the socket 11 are adapted to each other.
[0021] In order to facilitate overall movement, in this embodiment, as a preferred technical solution of the utility model, pulleys 13 are symmetrically fixed on both sides of the bottom of the base frame 5, and guide rails 7 are arranged outside the pulleys 13, and the guide rails 7 are arranged in parallel.
[0022] In order to ensure the connection strength, in this embodiment, as a preferred technical solution of the utility model, the connection between the load-bearing main beam 1 and the corresponding top frame 2, the connection between the telescopic support rod 3 and the top frame 2, the reinforcement rod 4 and the bottom frame 5 are all fastened by bolts.
[0023] To sum up, with the help of the above-mentioned technical scheme of the utility model, when in use, the lifting equipment on the load-bearing main beam is used to lower the wire rope to lift the bridge deck to a certain height, and then the first hydraulic cylinder output is used to drive the top frame together with the load-bearing main beam to rise and adjust the height. At the same time, the extension rod is extended upward from the inside of the fixed tube to play a limiting role. After reaching the required height, the second hydraulic cylinder output is used to insert the insertion rod into the insertion hole of the extension rod and the fixed tube to fix it, and the bridge deck can be lowered using the lifting equipment on the load-bearing main beam.
[0024] Finally, it should be noted that in the present utility model, unless otherwise clearly stipulated and limited, terms such as "installation", "setting", "connection", "fixation", and "screw-on" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integrated connection; it can be a mechanical connection or an electrical connection; it can be directly connected or indirectly connected through an intermediate medium; it can be the internal connection of two elements or the interaction relationship between two elements. Unless otherwise clearly defined, ordinary technicians in this field can understand the specific meanings of the above terms in the utility model according to the specific circumstances.
[0025] The above description is only a preferred embodiment of the utility model and is not intended to limit the utility model. Although the utility model is described in detail with reference to the above embodiments, those skilled in the art can still modify the technical solutions recorded in the above embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.
Claims
1. A gantry crane for bridge construction, comprising a load-bearing main beam (1), characterized in that: A top frame (2) is symmetrically fixed at both ends of the bottom of the bearing main beam (1), telescopic support rods (3) are fixed at the four corners of the bottom of the top frame (2), an anti-falling structure is arranged inside the telescopic support rod (3), a reinforcement rod (4) is fixed between adjacent telescopic support rods (3), a bottom frame (5) is fixed at the bottom of the telescopic support rod (3), and first hydraulic cylinders (6) are symmetrically arranged inside the four telescopic support rods (3), the cylinder body of the first hydraulic cylinder (6) is fixed on the bottom frame (5), and the output end of the first hydraulic cylinder (6) is fixedly connected to the top frame (2).
2. A gantry crane for bridge construction according to claim 1, characterized in that: The load-bearing main beam (1) is a segmented structure, and adjacent modules of the load-bearing main beam (1) are fastened and connected by bolts.
3. A gantry crane for bridge construction according to claim 1, characterized in that: The telescopic support rod (3) comprises a fixed tube (8) and an extension rod (9); the bottom rod body of the extension rod (9) passes through the top of the fixed tube (8) and is slidably connected to the inside of the tube body of the fixed tube (8).
4. A gantry crane for bridge construction according to claim 1, characterized in that: The anti-fall structure comprises a second hydraulic cylinder (10) and a socket (11); an insertion rod (12) is fixed to the output end of the second hydraulic cylinder (10); the socket (11) is respectively provided on the body of the fixed cylinder (8) and the body of the extension rod (9); and the insertion rod (12) and the socket (11) are adapted to each other.
5. The gantry crane for bridge construction according to claim 1, characterized in that: Pulleys (13) are symmetrically fixed on both sides of the bottom of the base frame (5), guide rails (7) are arranged outside the pulleys (13), and the guide rails (7) are arranged in parallel.
6. A gantry crane for bridge construction according to claim 3, characterized in that: The connection between the load-bearing main beam (1) and the corresponding top frame (2), the connection between the telescopic support rod (3) and the top frame (2), the reinforcement rod (4) and the bottom frame (5) are all fastened and connected by bolts.