Wall surface fine galling auxiliary device for building construction

By designing wall fine-pull auxiliary devices for telescopic support rods, telescopic top holders, supporting vertical beams and engaging parts, the problems of low construction efficiency and complex structure of existing tools at different heights are solved, and efficient and stable are achieved The wall fine-pull operation and modification effect.

CN222066039UActive Publication Date: 2024-11-26SUZHOU HUATING CONSTR ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420674028.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-03
Publication Date
2024-11-26
Estimated Expiration
2034-04-03

AI Technical Summary

Technical Problem

Existing wall fine-tie tools are inefficient, complex in structure, high in cost when dealing with walls of different heights, and cannot meet the modification needs, and cannot effectively adapt to construction needs of different heights.

Method used

A wall fine-pull auxiliary device including a telescopic support rod, a telescopic top holder, a supporting vertical beam and a engaging member is designed. The removable connection and clamp of the vertical beam are supported by the height adjustment of the telescopic support rod and the top holder. The clamping mechanism of the engaging parts realizes convenient wall fine woven operation, with a wide range of application, compact structure, high reliability and low cost.

Benefits of technology

It improves construction efficiency, reduces manual adjustment time, applies to walls of different heights, enhances construction stability and aesthetics, meets wall modification needs, and reduces manufacturing costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222066039U_ABST
    Figure CN222066039U_ABST
Patent Text Reader

Abstract

The utility model discloses a wall surface fine galling auxiliary device for building construction, and belongs to the technical field of building construction equipment. Comprising a pair of telescopic supporting rods which are vertically arranged in a bilateral symmetry mode, and the bottom ends of the telescopic supporting rods are supported on the ground of a room; the telescopic jacking pieces can stretch out and draw back up and down in the vertical direction and are used for jacking a ceiling of a room; the supporting vertical beams are detachably connected to the front portions of the telescopic supporting rods corresponding to the supporting vertical beams respectively, and a plurality of positioning pieces are installed on the supporting vertical beams at equal intervals; the end parts of the two ends of the transverse floating rule in the length direction are erected on the positioning pieces of the supporting vertical beams on the two sides; the clamping pieces are installed on the supporting vertical beams at intervals and used for achieving connection between the telescopic supporting rods and the supporting vertical beams. The device has the advantages of assisting wall surface fine napping construction operation, being convenient to operate, high in working efficiency, good in effect and attractive and neat in effect; and the telescopic jacking piece can be suitable for wall surfaces of different heights, assembling is convenient and fast, and the remarkable popularization significance is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of building construction equipment, and in particular relates to a wall surface roughening auxiliary device for building construction. Background Art

[0002] Roughening is an indispensable construction process for wall surface treatment in construction. Its main purpose is to increase the roughness of the wall surface, improve the adhesion of the wall surface, and make the tiles more firmly laid. If the wall surface is not roughened before laying tiles, it may leave safety hazards. The tiles laid on the wall may fall off after three to five years due to insufficient adhesion. In severe cases, large areas of falling off may occur, and even serious safety accidents may occur. The specific steps of the roughening operation are to mix the special wall solidifying material for wall roughening with the bonding material in proportion, stir into a uniform slurry, and roll it on the smooth wall surface with a roughening roller. After drying, a roughened surface that is conducive to bonding is formed, which enhances the adhesion of the wall surface and makes the original concrete or cement mortar leveling wall surface treated into a serrated cement mortar bonding layer. The above-mentioned fine roughening of the wall surface is the last process before the acceptance of the construction. The effect of fine roughening is directly reflected in the visual sense. Whether the fine roughening lines are straight, whether the fine roughening is completely carried out, and the neatness of the fine roughening surface directly affect the acceptance. In the prior art, the wall surface is generally roughened manually with a spatula. However, this not only increases the labor intensity, but also the scratches on the wall surface may be uneven. At the same time, the height and width of the stripes formed after the roughening cannot be unified, the construction quality is poor, and it is inconvenient to adjust the height of the roughening operation during construction. It is inconvenient to roughen the higher wall surface, resulting in poor construction effect, which not only affects the smoothness of the wall surface, but also is not convenient for subsequent construction. In addition, the wall surface of the house may have cracks and other conditions that need to be repaired before delivery, and after local repairs, the wall surface still has defects of gaps and scars. Without white putty, the existing wall roughening tools cannot meet the wall decoration needs in this situation.

[0003] In order to solve the above problems, existing construction units have also made many useful attempts. For example, the Chinese utility model patent with publication number CN206189818U discloses a "wall fine roughening auxiliary device", which includes two vertically placed support frames and a cross bar horizontally mounted on the support frames. The support frames are provided with a number of vertically spaced frame rods for supporting the cross bars on the wall side. The main rod of the support frame includes an inner tube fixed on the base, an outer tube that is mutually socketed with the inner tube, and a locking piece provided on the side wall of the outer tube. The advantage is that the height of the outer tube is adjustable, which can meet the construction requirements of different heights and improve the beauty and neatness of the fine roughening construction. However, it still has the following disadvantages: although the inner tube and the outer tube in the main pole can be extended and retracted to adjust the height of the main pole, manual adjustment is required during the adjustment process, which is time-consuming and labor-intensive, and takes a lot of time, which invisibly reduces work efficiency. At the same time, the height adjustment range of the inner tube and the outer tube is limited, and the applicable scenarios are not comprehensive. There is still a defect that it cannot be applied to the construction needs of walls of different heights; and this technical solution has many overall connecting parts, and the assembly is time-consuming and labor-intensive, resulting in high manufacturing costs. It also cannot effectively guarantee the reliability of long-term use, and its overall structure has a lot of room for improvement.

[0004] In view of the above problems, it is necessary to design a wall roughening auxiliary device with simple structure, convenient and reliable assembly, time-saving and labor-saving, good stability in use, and capable of meeting the construction requirements of walls of different heights. To this end, the applicant has cleverly designed the following technical solution. Utility Model Content

[0005] The purpose of the utility model is to provide a wall roughening device for construction which has a compact structure, a wide range of applications, high reliability and low production cost. It helps to conveniently adjust its own height by optimizing the structure and can meet the needs of fine roughening of walls of different heights. It is conducive to reliable and convenient assembly between components to ensure the horizontal stability of construction while effectively improving work efficiency and saving labor.

[0006] The purpose of the utility model is achieved in this way. A wall fine roughening auxiliary device for construction includes: a pair of telescopic support rods, the two telescopic support rods are vertically arranged symmetrically and the bottom ends of the two are supported on the floor of the room; a pair of telescopic top holding members, the two telescopic top holding members are respectively installed on the top ends of the telescopic support rods corresponding to them, and the telescopic top holding members can be telescoped up and down in the vertical direction and used to hold to the ceiling of the room; a pair of supporting vertical beams, the two supporting vertical beams are both vertically arranged and both can be detachably connected to the front position of the corresponding telescopic support rods, and a plurality of positioning members are installed at equal intervals along the vertical direction on the side surface of the supporting vertical beam opposite to the telescopic support rod; a horizontal scraper, the horizontal scraper is horizontally arranged along the horizontal direction, and the two end ends of the horizontal scraper in the length direction are mounted on the positioning members of the supporting vertical beams on both sides that are in the same horizontal plane; a plurality of clamping members, a plurality of the clamping members are installed on the supporting vertical beams at intervals and are used to realize the connection between the telescopic support rod and the supporting vertical beam.

[0007] In a specific embodiment of the present invention, the telescopic support rod includes a plurality of connecting rods which are sequentially fitted and connected together; and a telescopic support rod base is installed at the bottom end of a connecting rod at the bottom of the telescopic support rod, and the bottom part of the telescopic support rod base can be supported on the floor of the room.

[0008] In another specific embodiment of the present invention, the plurality of connecting rods are circular tubes or rectangular tubes.

[0009] In another specific embodiment of the present invention, the telescopic supporting member includes a supporting sleeve, a return spring, a supporting rod and a supporting seat; wherein, the supporting sleeve is installed at the top end of a connecting rod at the top of the telescopic support rod, and the supporting sleeve is extended in the vertical direction and its interior is hollow to form a supporting sleeve inner cavity, the return spring is arranged at the bottom of the supporting sleeve inner cavity, the supporting rod is passed through the supporting sleeve and protrudes upward from the supporting sleeve inner cavity, and the bottom end of the supporting rod abuts against the top of the return spring, and the supporting seat is mounted on the top end of the supporting rod, and the supporting seat can support to the ceiling of the room.

[0010] In another specific embodiment of the present invention, the material of the supporting seat is rubber or silicone.

[0011] In another specific embodiment of the present invention, multiple engaging parts are each provided with a mounting base, an elastic clamping body, a buffer pad and a pair of clamping wheels; wherein, the mounting base is a flat plate structure and is fixedly mounted on the main body of the supporting vertical beam, the elastic clamping body is connected to the mounting base and is used to clamp the telescopic support rod, the elastic clamping body has an elastic clamping body cavity that passes through from top to bottom, and an elastic clamping body opening is formed at one end of the elastic clamping body cavity away from the mounting base, the buffer pad is mounted on the inner cavity wall of the elastic clamping body cavity and is arranged at a position corresponding to the rear part of the elastic clamping body opening, and claw arms are further provided on both sides of the elastic clamping body, the two claw arms are relatively arranged and correspond to the left and right sides of the elastic clamping body opening, the two clamping wheels are respectively mounted on their corresponding claw arms, the telescopic support rod can be clamped in the elastic clamping body cavity and the telescopic support rod is clamped by the two clamping wheels.

[0012] In a further specific embodiment of the present invention, the clamping wheel is a rubber clamping wheel or a foam plastic clamping wheel.

[0013] In yet another specific embodiment of the present invention, the positioning member is a nail body structure, which includes a nail rod and a nail cap. The nail rod is inserted into the supporting vertical beam body, and the nail cap is formed at an end position of the nail rod away from the supporting vertical beam in the length direction, and a scraper positioning groove is formed between the nail cap and the supporting vertical beam. The bottom part of the transverse scraper can be fitted in the scraper positioning groove, thereby realizing the positioning and installation of the transverse scraper.

[0014] In yet another specific embodiment of the present invention, a transverse scraper slope is formed on the top of the transverse scraper and along its length direction; and the transverse scraper is made of aluminum alloy.

[0015] After the utility model adopts the above structure, it has the beneficial effects: firstly, by arranging a telescopic top holding member that can shrink and expand up and down at the top of the telescopic support rod, the telescopic top holding member can conveniently adjust its own height after it is supported to the ceiling of the room, and the telescopic support rod itself can also achieve height adjustment, so that it can meet the needs of fine roughening of walls of different heights, has a wide range of applicable scenes, and reduces construction time. While optimizing the adjustment structure, it can reduce the number of parts, thereby effectively reducing manufacturing costs; secondly, by installing a plurality of snap-fitting members on the support vertical beam, the snap-fitting members can effectively achieve a detachable connection between the support vertical beam and the support telescopic rod, and can firmly install the support vertical beam on the connecting rod of the support telescopic rod, and through the clamping wheel of the snap-fitting member It can effectively clamp the connecting rod and provide reliable hanging support for the supporting vertical beam. It is easy to use, improves work efficiency, saves time and effort in assembly, can further shorten the construction time, and can make the supporting vertical beam move up and down relative to the supporting telescopic rod by pushing and pulling the supporting vertical beam up and down, so as to adjust the relative position of the supporting vertical beams on both sides, effectively ensuring that the supporting vertical beams on both sides remain in a relatively horizontal state, and further ensuring the accuracy and stability of construction. Furthermore, the overall structure of the technical solution is compact, the components are tightly combined, the application range is wide, the reliability is high, and the operating durability is good. On the one hand, it can improve the adhesion and aesthetics of the putty on the painted surface during construction, and on the other hand, it can effectively meet the needs of decorative and beautiful decoration of the wall of the house without white putty. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 This is a schematic diagram of the three-dimensional structure of an embodiment of the utility model;

[0017] Figure 2 for Figure 1 A schematic diagram of the connection structure between the telescopic support rod and the supporting vertical beam in the illustrated embodiment;

[0018] Figure 3 for Figure 1 A schematic diagram of the three-dimensional structure of the engaging member in the illustrated embodiment.

[0019] In the figure: 1. telescopic support rod, 11. connecting rod, 12. telescopic support rod base; 2. telescopic top holding member, 21. top holding sleeve, 211. top holding sleeve inner cavity, 22. return spring, 23. top holding rod, 24. top holding seat; 3. supporting vertical beam, 31. positioning member, 311. nail rod, 312. nail cap, 313. scraper ruler positioning groove; 4. transverse scraper ruler, 41. transverse scraper ruler slope; 5. engaging member, 51. mounting base plate, 52. elastic clamping body, 521. elastic clamping body inner cavity, 522. elastic clamping body opening, 523. clamping claw clamping arm, 53. buffer pad, 54. clamping wheel. DETAILED DESCRIPTION

[0020] The specific implementation methods of the present invention are described in detail below in conjunction with the accompanying drawings, but the description of the embodiments is not a limitation of the technical solution. Any changes in form rather than substance based on the concept of the present invention should be regarded as the protection scope of the present invention.

[0021] In the following description, all concepts related to up, down, left, right, front and back directions or orientations are based on Figure 1 The positions shown are for reference only and thus cannot be understood as a special limitation on the technical solution provided by the present utility model.

[0022] See also Figures 1 to 3 , shows an auxiliary device for wall roughening for construction, comprising: a pair of telescopic support rods 1, the two aforementioned telescopic support rods 1 are vertically arranged symmetrically on the left and right, and the bottom ends of both are supported on the floor of the room; a pair of telescopic top holding members 2 are also shown, the two aforementioned telescopic top holding members 2 are respectively installed on the top ends of the corresponding telescopic support rods 1, and the telescopic top holding members 2 can be telescoped up and down in the vertical direction and used to support the ceiling of the room; a pair of supporting vertical beams 3, the two aforementioned supporting vertical beams 3 are both vertically arranged and both can be detachably connected to the front position of the corresponding telescopic support rods 1, and on the side surface of the supporting vertical beams 3 opposite to the aforementioned telescopic support rods 1, the vertical A plurality of positioning members 31 are installed at equal intervals in the vertical direction, and the distance between the plurality of positioning members 31 can be adjusted according to specific construction requirements, preferably 10CM to 15CM; a horizontal scraper 4, the aforementioned horizontal scraper 4 is horizontally arranged along the horizontal direction, and the two end portions of the horizontal scraper 4 in the length direction are mounted on a positioning member 31 on the same horizontal plane of the supporting vertical beams 3 on both sides, and the user can use a sponge block or a soft brush to perform fine roughening operations on the wall along the horizontal scraper 4; it should be noted that in actual use, a spirit level can be provided on the horizontal scraper 4, and the spirit level can be used to ensure that the horizontal scraper 4 is in a horizontal position, thereby ensuring the beauty and neatness of the fine roughening operation. Figure 1 and Figure 2 Also shown are a plurality of snap-fit ​​parts 5, which are installed at intervals on the support vertical beam 3 and are used to achieve the connection between the telescopic support rod 1 and the support vertical beam 3; the aforementioned telescopic support rod 1 can be quickly and conveniently assembled into the snap-fit ​​parts 5, making the assembly connection convenient and reliable.

[0023] Furthermore, the telescopic support rod 1 comprises a plurality of connecting rods 11 which are sequentially connected together; and a telescopic support rod base 12 is installed at the bottom end of the lowest connecting rod 11 of the telescopic support rod 1, and the bottom part of the telescopic support rod base 12 can be supported on the floor of the room; Figure 1As shown in the figure, the number of connecting rods 11 is two, of course, its number is not limited to this. During operation, the height of the telescopic support rod 1 can be adjusted by adjusting the number of the aforementioned connecting rods 11, that is, the telescopic support rod 1 can be telescoped in the height direction, and in some specific embodiments, the aforementioned connecting rods 11 are steel pipes, and the steel pipes are connected by joints. The setting of the joints can quickly connect multiple connecting rods 11, and cotter pins or cylindrical pins can also be provided at the connection to improve the fixity of the connection. These are all technical means commonly used by those skilled in the art and will not be elaborated here.

[0024] Preferably, the plurality of connecting rods 11 are circular or rectangular tube structures.

[0025] See Continue See Figure 1 and Figure 2 The telescopic top holding member 2 includes a top holding sleeve 21, a return spring 22, a top holding rod 23 and a top holding seat 24; wherein the top holding sleeve 21 is installed at the top end of a connecting rod 11 at the top of the telescopic support rod 1, and the top holding sleeve 21 is extended in the vertical direction and its interior is hollow to form a top holding sleeve inner cavity 211, the return spring 22 is arranged at the bottom of the top holding sleeve inner cavity 211, the top holding rod 23 is penetrated in the top holding sleeve 21 and protrudes upward from the top holding sleeve inner cavity 211, and the bottom end of the top holding rod 23 abuts against the top of the return spring 22, and the top holding seat 24 is sleeved on the top of the top holding rod 23, and the top holding seat 24 can be supported to the ceiling of the room; in actual use, the telescopic top holding member 2 The top holding rod 23 and the top holding seat 24 are moved upward by the elastic force of the return spring 22, and the top height of the telescopic top holding member 2 is generally preset to be higher than the room height. The staff first makes the top holding seat 24 of the top holding member 2 abut against the ceiling of the room and allows the top holding rod 23 to move downward, while the return spring 22 is compressed. When the fine roughening operation is completed, the staff takes out the telescopic support rod 1 and the telescopic top holding member 2, and the top holding rod 23 and the top holding seat 24 will be expanded upward again by the elastic force of the return spring 22 to meet the construction needs of another space, so that the technical solution of the utility model can be suitable for the fine roughening use needs of walls of different heights, and it is easy to adjust, saves time and effort, is strong and durable, and can reduce the number of parts while optimizing the adjustment structure, effectively reducing the manufacturing cost.

[0026] Preferably, the material of the supporting seat 24 is rubber or silicone.

[0027] In this embodiment, please refer to Figure 3, the plurality of aforementioned engaging members 5 are each provided with a mounting base plate 51, an elastic clamping body 52, a buffer pad 53 and a pair of clamping wheels 54; wherein the aforementioned mounting base plate 51 is a flat plate structure and is fixedly mounted on the body of the aforementioned supporting vertical beam 3, the aforementioned elastic clamping body 52 is connected to the mounting base plate 51 and is used to clamp the aforementioned telescopic support rod 1, the elastic clamping body 52 has an elastic clamping body inner cavity 521 which passes through from top to bottom, and an elastic clamping body opening 522 is formed at one end of the elastic clamping body inner cavity 521 away from the mounting base plate 51, the aforementioned buffer pad 53 is mounted on the inner cavity wall of the elastic clamping body inner cavity 521 and is arranged at a position corresponding to the rear of the aforementioned elastic clamping body opening 522, and claw arms are also provided on both sides of the aforementioned elastic clamping body 52 523, the two claw arms 523 are relatively arranged and correspond to the left and right sides of the opening 522 of the elastic clamping body, and the two clamping wheels 54 are respectively installed on the corresponding claw arms 523. The telescopic support rod 1 can be clamped in the inner cavity 521 of the elastic clamping body and clamped by the two clamping wheels 54, and the clamping wheel 54 can clamp the connecting rods 11 of different sizes, which has a good range of application and can ensure that the supporting vertical beam 3 remains upright, thereby improving the reliability of use. In addition, the buffer pad 53 can prevent the connecting rod 11 entering the inner cavity 521 of the elastic clamping body from impacting the elastic clamping body 52, and absorb the displacement energy generated by the forward movement of the connecting rod 11 to avoid damage during use.

[0028] Preferably, the clamping wheel 54 is a rubber clamping wheel or a foam plastic clamping wheel; Figure 3 As shown in the figure, the clamping wheel 54 is a plum blossom-shaped structure. Of course, it can also be a regular polyhedron structure or a cylindrical structure design. Anti-slip corrugations can be provided on the outer circumferential surface of the clamping wheel 54. The setting of the anti-slip corrugations can increase the friction between the clamping wheel 54 and the connecting rod 11 of the telescopic support rod 1, thereby ensuring the stability and firmness of the connection.

[0029] When fixing the supporting vertical beam 3 in the utility model and the multiple connecting rods 11 of the telescopic supporting rod 1, first align the elastic clamping body opening 522 on the engaging member 5 with the connecting rod 11, and then force the connecting rod 11 to penetrate into the elastic clamping body cavity 521, and at the same time, the two clamping wheels 54 can tightly clamp the connecting rod 11 body, thereby effectively achieving the fixation of the supporting vertical beam 3 and the multiple connecting rods 11.

[0030] Please continue to see Figure 1 and Figure 2The positioning member 31 is a nail body structure, and the positioning member 31 has a nail rod 311 and a nail cap 312. The nail rod 311 is inserted into the supporting vertical beam 3 body, and the nail cap 312 is formed at an end position of the nail rod 311 in the length direction away from the supporting vertical beam 3, and a scraper positioning groove 313 is formed between the nail cap 312 and the supporting vertical beam 3, and the bottom part of the horizontal scraper 4 can be installed in the scraper positioning groove 313, thereby realizing the positioning and installation of the horizontal scraper 4.

[0031] Furthermore, a transverse scraper slope 41 is formed at the top of the transverse scraper 4 and along its length direction. When performing fine roughening operations on the wall, the user can use a sponge block or a soft brush to perform fine roughening operations on the wall along the transverse scraper slope 41. The setting of the transverse scraper slope 41 can easily achieve the positioning of the sponge block or the soft brush, further facilitating the operation; and the transverse scraper 4 is made of aluminum alloy.

[0032] See also Figures 1 to 3The applicant briefly describes the working principle of the technical solution provided by the utility model: before the fine roughening operation of the wall surface, the wall surface is first treated with a base layer, watered and moistened, sprayed and slurried, and the surface layer is applied. Then, the wall fine roughening auxiliary device for building construction is used. First, two telescopic support rods 1 are vertically arranged on both sides of the wall surface, so that the telescopic support rod base 12 can be supported on the ground, and then the connecting rod 11 in the two telescopic support rods 1 is expanded according to the construction requirements, and then the top support seat 24 of the top support member 2 can be abutted against the room. The ceiling can make the top holding rod 23 move downward, and the return spring 22 is compressed at the same time. Then, the two supporting vertical beams 3 are connected to the corresponding two telescopic supporting rods 1 through the clamping of the clamping parts 5, and the two supporting vertical beams 3 can be erected on both sides of the wall. Finally, the horizontal scraper 4 is set on the positioning parts 31 of the two supporting vertical beams 3 on the same horizontal plane. The staff can hold the horizontal scraper in one hand and the sponge or soft brush in the other hand to perform fine roughening operation on the wall along the horizontal scraper 4, reciprocating from top to bottom or from bottom to top. Multiple roughening operations are performed on the wall; when the fine roughening operation is completed, the staff will take out the telescopic support rod 1 and the telescopic top holding piece 2, and the top holding rod 23 and the top holding seat 24 will be expanded upward again by the elastic force of the reset spring 22 to facilitate the construction needs of another space. The construction is convenient, and after the construction is completed, multiple neat stripes can be presented on the wall, which is beautiful and generous, and has significant promotion significance; in addition, the fine roughening operation assisted by the technical solution provided by the utility model can also meet the developer's wall decoration and aesthetic construction requirements that do not require white putty. Specifically, the wall of a house may have cracks and other problems that need to be repaired before the house is handed over, and after local repairs, there are still defects such as gaps and scars on the wall. After the auxiliary device performs fine roughening on the wall, the gaps and scars on the wall can be repaired into one piece, and can be repeatedly repaired and roughened to ensure that the overall finish color is consistent and beautiful after covering and has a cohesive roughness. In addition, it can also ensure that the owner does not need to scrape the white wall after the house is handed over, and can directly apply whitewash without falling off, thereby effectively improving the adhesion of putty after painting and improving the overall appearance of the wall.

[0033] It should be noted that the above embodiments can be freely combined as needed. The above are only preferred implementations of the utility model. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principle of the utility model, and these improvements and modifications should also be regarded as the protection scope of the utility model.

[0034] In summary, the technical solution provided by the utility model makes up for the shortcomings of the existing technology, successfully completes the invention task, and faithfully realizes the technical effects stated by the applicant in the technical effect column above.

Claims

1. A wall roughening auxiliary device for building construction, It is characterized in that include: A pair of telescopic support rods (1), the two telescopic support rods (1) are vertically arranged symmetrically on the left and right, and the bottom ends of the two telescopic support rods are supported on the floor of the room; a pair of telescopic top holding members (2), the two telescopic top holding members (2) are respectively installed on the top ends of the telescopic support rods (1) corresponding to them, and the telescopic top holding members (2) can be telescoped up and down in the vertical direction and used to hold the room ceiling; a pair of supporting vertical beams (3), the two supporting vertical beams (3) are both vertically arranged and can be detachably connected to the front position of the telescopic support rods (1) corresponding to them, and A plurality of positioning members (31) are installed at equal intervals along the vertical direction on the surface of the supporting vertical beam (3) on the side opposite to the telescopic supporting rod (1); a transverse scraper (4), the transverse scraper (4) is arranged transversely along the horizontal direction, and the two end portions of the transverse scraper (4) in the length direction are mounted on the positioning members (31) on the same horizontal plane of the supporting vertical beams (3) on both sides; and a plurality of engaging members (5), the plurality of engaging members (5) are installed at intervals on the supporting vertical beam (3) and are used to realize the connection between the telescopic supporting rod (1) and the supporting vertical beam (3).

2. A wall roughening auxiliary device for construction according to claim 1, Features: The telescopic support rod (1) comprises a plurality of connecting rods (11) which are sequentially fitted and connected together; and a telescopic support rod base (12) is installed at the bottom end of a connecting rod (11) at the bottom of the telescopic support rod (1), and the bottom part of the telescopic support rod base (12) can be supported on the floor of a room.

3. A wall roughening auxiliary device for construction according to claim 2, Features: The plurality of connecting rods (11) are circular tubes or rectangular tubes.

4. The wall roughening auxiliary device for building construction according to claim 1, Features: The telescopic supporting member (2) comprises a supporting sleeve (21), a return spring (22), a supporting rod (23) and a supporting seat (24); wherein the supporting sleeve (21) is mounted on the top end of a connecting rod (11) at the top of the telescopic support rod (1), and the supporting sleeve (21) is extended in the vertical direction and is hollow inside to form a supporting sleeve inner cavity (211), the return spring (22) is arranged at the bottom of the supporting sleeve inner cavity (211), the supporting rod (23) is inserted into the supporting sleeve (21) and protrudes upward from the supporting sleeve inner cavity (211), and the bottom end of the supporting rod (23) abuts against the top of the return spring (22), and the supporting seat (24) is sleeved on the top end of the supporting rod (23), and the supporting seat (24) can support the ceiling of the room.

5. A wall roughening auxiliary device for construction according to claim 4, Features: The material of the supporting seat (24) is rubber or silica gel.

6. The wall roughening auxiliary device for construction according to claim 1, Features: The plurality of engaging members (5) are each provided with a mounting base (51), an elastic clamping body (52), a buffer pad (53) and a pair of clamping wheels (54); wherein the mounting base (51) is a flat plate structure and is fixedly mounted on the main body of the supporting vertical beam (3); the elastic clamping body (52) is connected to the mounting base (51) and is used to clamp the telescopic support rod (1); the elastic clamping body (52) has an elastic clamping body inner cavity (521) which passes through the upper and lower parts, and an elastic clamping body opening (522) is formed at one end of the elastic clamping body inner cavity (521) away from the mounting base (51); the buffer pad (53) is provided at the lower end of the elastic clamping body inner cavity (521) which is away from the mounting base (51); The impact pad (53) is installed on the inner wall of the inner cavity (521) of the elastic clamping body and is arranged at a position corresponding to the rear of the opening (522) of the elastic clamping body, and claw arms (523) are also provided on both sides of the elastic clamping body (52). The two claw arms (523) are arranged opposite to each other and correspond to the left and right sides of the opening (522) of the elastic clamping body. The two clamping wheels (54) are respectively installed on their corresponding claw arms (523). The telescopic support rod (1) can be clamped in the inner cavity (521) of the elastic clamping body and the telescopic support rod (1) is clamped by the two clamping wheels (54).

7. A wall roughening auxiliary device for construction according to claim 6, Features: The clamping wheel (54) is a rubber clamping wheel or a foam plastic clamping wheel.

8. The wall roughening auxiliary device for building construction according to claim 1, Features: The positioning member (31) is a nail body structure, and the positioning member (31) is provided with a nail rod (311) and a nail cap (312). The nail rod (311) is inserted into the supporting vertical beam (3) body, and the nail cap (312) is formed at an end position of the nail rod (311) away from the supporting vertical beam (3) in the length direction, and a scraper ruler positioning groove (313) is formed between the nail cap (312) and the supporting vertical beam (3), and the bottom part of the transverse scraper ruler (4) can be installed in the scraper ruler positioning groove (313), thereby realizing the positioning installation of the transverse scraper ruler (4).

9. The wall roughening auxiliary device for building construction according to claim 1, Features: A transverse scraper slope (41) is formed at the top of the transverse scraper (4) and along its length direction; and the transverse scraper (4) is made of aluminum alloy.