Telescopic steering chute for concrete pouring

By designing telescopic and adjustable curved chute components, the problem that traditional chutes cannot adapt to complex terrain and narrow working surfaces is solved, efficient concrete pouring is achieved, suitable for casting environments of different heights, and construction efficiency is improved.

CN222066186UActive Publication Date: 2024-11-26CHINA HYDROPOWER ELEVENTH ENG BUREAU (ZHENGZHOU) CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420523434.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-18
Publication Date
2024-11-26
Estimated Expiration
2034-03-18

AI Technical Summary

Technical Problem

The traditional concrete pouring chute lacks retractable steering function and cannot adapt to complex terrain and narrow working surfaces, resulting in low efficiency in concrete pouring, especially in construction scenarios with small spaces.

Method used

A concrete pouring chute including a retractable first chute assembly and a adjustable curved second chute assembly is designed. By adjusting the length and curvature of the chute assembly, it can adapt to casting environments of different heights and widths, combined with the guide assembly. Connect with threads to achieve flexible installation and stability of chutes.

Benefits of technology

It significantly improves the efficiency of concrete pouring, can be used for pouring goals of different heights, and does not need to adjust the parking space angle. The chute components can be detached and easy to store, solving the technical difficulties of traditional chutes that cannot adapt to complex terrain and narrow environments.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222066186U_ABST
    Figure CN222066186U_ABST
Patent Text Reader

Abstract

The utility model discloses a telescopic steering chute for concrete pouring, which comprises a first chute component with telescopic length, a detachable second chute component is mounted at one end of the first chute component, and the curvature of the second chute component can be adjusted; the first chute assembly comprises a first chute and a second chute, and the first chute is arranged in the second chute in a sliding mode. The second chute assembly comprises a plurality of third chutes which are sequentially arranged, and the widths of the third chutes are gradually decreased one by one. The chute has the beneficial effects that by adjusting the length of the first chute assembly and then adjusting the bending degree of the second chute assembly, the far ends of the second chute assembly and the first chute assembly correspond to a discharging opening and a pouring face of the cement tanker respectively, and therefore different pouring operation environments can be met; the defect that a traditional chute for concrete pouring cannot stretch out and draw back can be overcome, a concrete tank truck does not need to adjust the parking space angle when the space is narrow, and the construction efficiency is remarkably improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of construction, in particular to a telescopic diverting chute for concrete pouring. Background Art

[0002] Traditional chutes for concrete pouring generally do not have a retractable and steerable function, or have only one of the functions. In this case, the chute cannot meet adverse working conditions such as complex terrain and narrow working surface, cannot be used for pouring targets at different heights, and cannot adapt to construction scenarios where the space is small and the concrete tank truck is not suitable for adjusting the parking angle. Combined with the practical experience of the construction front line, the retractable and steerable functions are organically integrated on the basis of the traditional concrete pouring chute structure to form a retractable and steerable concrete pouring chute, which will greatly improve the concrete pouring efficiency and solve the technical difficulties of traditional chutes in adapting to the narrow working surface and complex terrain environment for pouring concrete. Summary of the invention

[0003] In order to solve the above problems, the purpose of the utility model is to provide a telescopic diverting chute for concrete pouring, as described below.

[0004] In order to achieve the above purpose, the utility model provides the following technical solutions:

[0005] The utility model provides a telescopic chute for concrete pouring, comprising a first chute assembly whose length can be telescopic, a detachable second chute assembly being installed at one end of the first chute assembly, and the curvature of the second chute assembly being adjustable;

[0006] The first chute assembly comprises a chute 1 and a chute 2, wherein the chute 1 is slidably disposed in the chute 2;

[0007] The second chute assembly includes a plurality of chutes three, which are arranged in sequence and have decreasing widths, two adjacent chutes three rotate through a rotating shaft, and a chute three with a smaller width is located inside a chute three with a larger width, and there is a gap between the side walls of the two adjacent chutes three;

[0008] Both sides of the chute three are threadedly connected with bolts three, and the bolts three correspond to the side surfaces of the chute three with a smaller width.

[0009] The above-mentioned retractable steerable concrete pouring chute is used, and the chute device is placed between the discharge port of the cement tank truck and the pouring surface. The length of the first chute assembly is adjusted according to the width of the pouring surface. At the same time, the curvature of the second chute assembly is adjusted according to the specific position of the working surface, so that the distal ends of the second chute assembly and the first chute assembly correspond to the discharge port of the cement tank truck and the pouring surface respectively.

[0010] Preferably, rubber pads are provided on both sides of the three ends of the chute to cover the gap between the three side walls of two adjacent chutes.

[0011] Preferably, the rotating shaft is located at the midpoint of the three widths of the chute.

[0012] Preferably, the three bottom plates of two adjacent chutes are in contact.

[0013] Preferably, the first chute and the second chute are clearance-matched.

[0014] Preferably, the chute one is slidably connected to the chute three having the largest width and is fixed by a plurality of bolts two.

[0015] Preferably, the second side surface of the chute is threadedly connected with a plurality of bolts, and an end of one bolt corresponds to one side surface of the chute.

[0016] Preferably, a guide assembly is provided between chute one and chute two to enable chute two to move along the length direction of chute one.

[0017] Preferably, the guide assembly comprises two guide rods, which are respectively arranged on both sides of the chute, and fixed sleeves are slidably arranged on the surface of the guide rods, and the two fixed sleeves are respectively fixed on both sides of the chute, and a handle is fixed on the chute.

[0018] The beneficial effects are:

[0019] 1. By adjusting the length of the first chute assembly and then adjusting the curvature of the second chute assembly, the distal ends of the second chute assembly and the first chute assembly correspond to the discharge port of the cement tank truck and the casting surface respectively, so as to meet different casting working environments, solve the drawback that the chute for traditional concrete casting cannot be extended, and can be used for casting targets of different heights. When the space is narrow, there is no need for the concrete tank truck to adjust the parking angle, which significantly improves the construction efficiency;

[0020] 2. The first chute assembly and the second chute assembly are detachable, which saves space and is easy to store. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0022] Figure 1 This is a front view structural schematic diagram of the utility model;

[0023] Figure 2It is a three-dimensional structural schematic diagram of the utility model;

[0024] Figure 3 It is a schematic diagram of the bending state of the second chute component of the utility model.

[0025] The following are the descriptions of the reference numerals:

[0026] 1. First chute assembly; 2. Second chute assembly; 3. Chute one; 4. Chute two; 5. Guide assembly; 6. Guide rod; 7. Fixed sleeve; 8. Bolt one; 9. Handle; 10. Bolt two; 11. Chute three; 12. Rubber pad; 13. Bolt three; 14. Rotating shaft. DETAILED DESCRIPTION

[0027] In order to make the purpose, technical solution and advantages of the utility model clearer, the technical solution of the utility model will be described in detail below. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other implementation methods obtained by ordinary technicians in this field without creative work belong to the scope of protection of the utility model.

[0028] See also Figure 1-Figure 3 As shown, the utility model provides a telescopic chute for concrete pouring, comprising a first chute assembly 1 whose length can be telescopic, a detachable second chute assembly 2 is installed at one end of the first chute assembly 1, and the curvature of the second chute assembly 2 can be adjusted;

[0029] The first chute assembly 1 includes a chute 1 3 and a chute 2 4, and the chute 1 3 is slidably arranged in the chute 2 4;

[0030] The second chute assembly 2 includes a plurality of chutes 11, which are arranged in sequence and have decreasing widths. Two adjacent chutes 11 rotate through a rotating shaft 14, and a chute 11 with a smaller width is located inside a chute 11 with a larger width, and there is a gap between the side walls of the two adjacent chutes 11.

[0031] Both sides of the chute 3 11 are threadedly connected with bolts 3 13, and the bolts 3 13 correspond to the side of the chute 3 11 with a smaller width;

[0032] By rotating the bolt three 13 on one side, the bolt three 13 pushes the corresponding chute three 11 to rotate, and by operating all the bolts three 13, all the chutes three 11 are swung in this way, the curvature adjustment of the second chute assembly 2 can be achieved, and the more the number of chutes three 11 is, the greater the maximum curvature of the second chute assembly 2 is.

[0033] As an optional embodiment, rubber pads 12 are provided on both sides of the end of the chute three 11 to cover the gap between the side walls of two adjacent chutes three 11. In order to achieve curvature adjustment of the second chute assembly 2, a gap must be left between two adjacent chutes three 11. However, during the process of transferring cement, cement will also enter the gap, increasing the work of subsequent cleaning. The rubber pad 12 can close the gap to prevent cement from entering.

[0034] The rotating shaft 14 is located at the midpoint of the width of the chute three 11, so that the chute three 11 can swing equally in both directions.

[0035] The bottom plates of two adjacent chutes are in contact to avoid gaps that may cause cement leakage.

[0036] The chute 1 3 and the chute 2 4 are clearance matched.

[0037] The chute 1 3 is slidably connected to the chute 3 11 with the largest width and is fixed by a plurality of bolts 2 10 .

[0038] The side of the chute 2 4 is threadedly connected with a plurality of bolts 8, and the ends of the bolts 8 correspond to the side of the chute 3. The chute 2 4 can move along the chute 3 to adjust the length of the chute 3. After the adjustment is completed, the bolts 8 are rotated to support the chute 3, thereby fixing the relative positions of the chute 3 and the chute 2 4.

[0039] A guide assembly 5 is provided between the chute 1 3 and the chute 2 4 to enable the chute 2 4 to move along the length direction of the chute 1 3 . The guide assembly 5 can improve the stability of the chute 2 4 during the movement process.

[0040] The guide assembly 5 includes two guide rods 6, which are respectively arranged on both sides of the chute 3. A fixing sleeve 7 is slidably arranged on the surface of the guide rod 6. The two fixing sleeves 7 are respectively fixed on both sides of the chute 4. A handle 9 is fixed on the chute 4.

[0041] By adopting the above structure, the chute device is placed between the discharge port of the cement tank truck and the casting surface. The length of the first chute component 1 is adjusted according to the width of the casting surface. At the same time, the curvature of the second chute component 2 is adjusted according to the specific position of the working surface, so that the distal ends of the second chute component 2 and the first chute component 1 correspond to the discharge port of the cement tank truck and the casting surface respectively.

[0042] The above is only a specific implementation of the utility model, but the protection scope of the utility model is not limited thereto. Any technician familiar with the technical field can easily think of changes or substitutions within the technical scope disclosed by the utility model, which should be included in the protection scope of the utility model. Therefore, the protection scope of the utility model should be based on the protection scope of the claims.

Claims

1. A telescopic diverting chute for concrete pouring, characterized in that: It comprises a first chute assembly (1) whose length can be extended and retracted, a detachable second chute assembly (2) being mounted on one end of the first chute assembly (1), and the curvature of the second chute assembly (2) being adjustable; The first chute assembly (1) comprises a chute 1 (3) and a chute 2 (4), wherein the chute 1 (3) is slidably arranged in the chute 2 (4); The second chute assembly (2) comprises a plurality of chute threes (11), wherein the plurality of chute threes (11) are arranged in sequence and their widths decrease one by one, and two adjacent chute threes (11) rotate via a rotating shaft (14), and a chute three (11) with a smaller width is located inside a chute three (11) with a larger width, and there is a gap between the side walls of the two adjacent chute threes (11); Both sides of the chute three (11) are threadedly connected with bolts three (13), and the bolts three (13) correspond to the side of the chute three (11) with a smaller width.

2. The telescopic diverter chute for concrete pouring according to claim 1, characterized in that: Rubber pads (12) are provided on both sides of the ends of the chute three (11) to cover the gap between the side walls of two adjacent chute three (11).

3. The telescopic diverter chute for concrete pouring according to claim 1, characterized in that: The rotating shaft (14) is located at the midpoint of the width of the chute three (11).

4. The telescopic diverter chute for concrete pouring according to claim 1, characterized in that: The bottom plates of two adjacent chutes three (11) are in contact.

5. The telescopic diverting concrete pouring chute according to claim 1, characterized in that: The chute 1 (3) and the chute 2 (4) are clearance-matched.

6. The telescopic diverter chute for concrete pouring according to claim 1, characterized in that: The chute one (3) is slidably connected to the chute three (11) with the largest width, and is fixed by a plurality of bolts two (10).

7. The telescopic diverter chute for concrete pouring according to claim 1, characterized in that: The side surface of the chute two (4) is threadedly connected with a plurality of bolts one (8), and the end of the bolt one (8) corresponds to the side surface of the chute one (3).

8. The telescopic diverter chute for concrete pouring according to claim 1, characterized in that: A guide assembly (5) is provided between the first chute (3) and the second chute (4) to enable the second chute (4) to move along the length direction of the first chute (3).

9. The telescopic diverting concrete pouring chute according to claim 8, characterized in that: The guide assembly (5) comprises two guide rods (6), the two guide rods (6) are respectively arranged on both sides of the chute one (3), a fixing sleeve (7) is slidably arranged on the surface of the guide rod (6), the two fixing sleeves (7) are respectively fixed on both sides of the chute one (3), and a handle (9) is fixed on the chute one (3).