Three-dimensional mixture steam preheating device for shuttle material bin of sintering machine
By setting up a three-dimensional steam preheating device in the sintered shuttle fabric silo, the problem of uneven steam preheating is solved by using the cross heating of the center and edge steam pipelines, and the uniform heating of the mixture and efficient utilization of waste heat are achieved. Improves the efficiency of sintering production.
Patent Information
- Application Number
- CN202323507166.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-22
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2033-12-22
AI Technical Summary
The steam preheating in the sintering shuttle fabric silo is uneven, resulting in slow heating of the mixing center and insufficient heat utilization, which affects the yield of the sintered ore.
A three-dimensional mix steam preheating device is adopted, and by setting a steam pipeline in the center of the silo and outside the silo wall, three-dimensional cross-heating of the two steam pipelines is realized, and heating is combined with the central beam pipe and the side nozzle.
The mixture is fully and uniformly heated, the waste heat utilization efficiency is improved, and the efficiency and output of sintering production are improved.
Smart Images

Figure CN222069313U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of sintering machine shuttle material bunkers, in particular to a three-dimensional mixed material steam preheating device for a sintering machine shuttle material bunker. Background Art
[0002] Sintering shuttle silo is a device used to store and supply sintering raw materials during the sintering process. Sintering is a process in which fine powder materials are condensed into blocks through high temperature treatment. It is commonly used in industries such as metallurgy and mining.
[0003] The traditional technology of steam preheating of sintering shuttle bunker is to add some steam nozzles around the bottom of the bunker wall of the sintering shuttle bunker to preheat the mixture with steam. The disadvantage of this technology is that most of the steam spreads along the bunker wall after leaving the nozzle, the heat transfer is uneven, the heating rate of the center of the mixture is slow, the steam easily escapes along the edge, and the waste heat is not fully utilized. If the temperature of the mixture at the center of the sintering bunker is lower than the dew point temperature (60-65℃), this part of the material will form an over-wet layer below the drying zone of the sintering material layer, reducing the permeability of the mixture layer and reducing the output of sintered ore. Utility Model Content
[0004] The purpose of the utility model is to provide a three-dimensional mixed material steam preheating device for a shuttle cloth silo of a sintering machine in view of the shortcomings and defects in the prior art. The equipment comprises a steam pipeline arranged in the center of the silo and a steam pipeline surrounding the outside of the silo wall. Under the three-dimensional cross-heating effect of the two steam pipelines, the silo mixture is fully and evenly heated, thereby improving the utilization efficiency of waste heat, and further improving the quality and efficiency of sintering production.
[0005] To achieve the above purpose, the utility model adopts the following technical scheme: a three-dimensional mixed material steam preheating device for a sintering machine shuttle material bunker, which includes a gas-liquid separator 2, a second connecting pipe 6, a third connecting pipe 13, a fourth connecting pipe 19, a front pipe nozzle group 21, and a side pipe nozzle group 23. A heat source connecting pipe 1 is installed on one side of the gas-liquid separator 2, and a steam water separator 15 is installed on the other side of the gas-liquid separator 2. The top of the gas-liquid separator 2 is connected to the second connecting pipe 6 through the first connecting pipe 5. The second connecting pipe 6 is sequentially installed with a pipeline stop valve 7, a manual regulating valve 8 from the outside to the inside. and flow meter 9, and the end of the second connecting pipe 6 is connected to the third connecting pipe 13 and the fourth connecting pipe 19, the third connecting pipe 13 is provided with a second stop valve group 11 and a flange short pipe group 12, the third connecting pipe 13 is provided with a plurality of side pipe nozzle groups 23, the fourth connecting pipe 19 is provided with a plurality of front pipe nozzle groups 21, a center beam pipe 20 is provided between the two fourth connecting pipes 19, the outer sides of the front pipe nozzle group 21 and the side pipe nozzle group 23 are both installed with internal threaded ball valves 22, and the inner outlets of the front pipe nozzle group 21 and the side pipe nozzle group 23 are installed with edge nozzles 24.
[0006] Furthermore, a first stop valve group 3 is installed between the heat source connecting pipe 1 and the gas-liquid separator 2 .
[0007] Furthermore, a steam dehumidifier valve 14 is installed between the gas-liquid separator 2 and the steam dehumidifier 15 .
[0008] Furthermore, the gas-liquid separator 2 is provided with a flange-type spring safety valve 201 for protecting the gas-liquid separator 2 from the influence of overpressure and a pressure gauge 202 for the staff to check the pressure.
[0009] Furthermore, the third connecting pipe 13 and the fourth connecting pipe 19 are respectively installed on the side pipe bracket 10 and the front pipe bracket 18 , and a pipe clip 17 is installed below the front pipe bracket 18 .
[0010] Furthermore, a third stop valve group 16 is installed on one side of the third connecting pipe 13 .
[0011] Furthermore, the second connecting pipe 6 is provided with a pressure transmitter 601 for measuring and converting pressure signals and a thermal resistor 602 for measuring temperature.
[0012] Furthermore, an inspection component 4 is provided between the heat source connecting pipe 1 and the second connecting pipe 6 .
[0013] Furthermore, the heat source connecting pipe 1 is used to connect to the steam heat source of the pipeline network.
[0014] After adopting the above technical scheme, the beneficial effect of the utility model is as follows: the equipment comprises a steam pipeline arranged in the center of the silo and a steam pipeline surrounding the outside of the silo wall. Under the three-dimensional cross-heating effect of the two steam pipelines, the silo mixture can be fully and evenly heated, thereby improving the utilization efficiency of waste heat, and further improving the quality and efficiency of sintering production. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.
[0016] Figure 1 It is a structural schematic diagram of the utility model.
[0017] Figure 2 yes Figure 1 Schematic diagram of the left view structure after removing the inspection component.
[0018] Figure 3 yes Figure 2 Schematic diagram of the top view of the structure after removing the sintering shuttle cloth bin.
[0019] Figure 4 yes Figure 1 Enlarged structural diagram at A in the middle.
[0020] Explanation of the reference numerals: heat source connecting pipe 1, gas-liquid separator 2, first stop valve group 3, inspection assembly 4, first connecting pipe 5, second connecting pipe 6, pipeline stop valve 7, manual regulating valve 8, flow meter 9, side pipeline bracket 10, second stop valve group 11, flange short pipe group 12, third connecting pipe 13, water separator valve 14, steam water separator 15, third stop valve group 16, pipeline clamp 17, front pipeline bracket 18, fourth connecting pipe 19, center beam pipe 20, front pipe nozzle group 21, internal thread ball valve 22, side pipe nozzle group 23, edge nozzle 24, flange spring safety valve 201, pressure gauge 202, pressure transmitter 601, thermal resistor 602. DETAILED DESCRIPTION
[0021] See also Figure 1-Figure 4As shown, the technical solution adopted in this specific embodiment is: it includes a gas-liquid separator 2, a second connecting pipe 6, a third connecting pipe 13, a fourth connecting pipe 19, a front pipe nozzle group 21, and a side pipe nozzle group 23. A heat source connecting pipe 1 is installed on one side of the gas-liquid separator 2, and a steam water separator 15 is installed on the other side of the gas-liquid separator 2. The top of the gas-liquid separator 2 is connected to the second connecting pipe 6 through the first connecting pipe 5. The second connecting pipe 6 is sequentially installed with a pipeline stop valve 7, a manual regulating valve 8 and a flow meter 9 from the outside to the inside, and the second connecting pipe 6 is connected to its third connecting pipe 13 and the fourth connecting pipe 19, the third connecting pipe 13 is provided with a second stop valve group 11 and a flange short pipe group 12, the third connecting pipe 13 is provided with a plurality of side pipe nozzle groups 23, the fourth connecting pipe 19 is provided with a plurality of front pipe nozzle groups 21, a center beam pipe 20 is provided between the two fourth connecting pipes 19, the outer sides of the front pipe nozzle group 21 and the side pipe nozzle group 23 are both installed with internal thread ball valves 22, and the inner outlets of the front pipe nozzle group 21 and the side pipe nozzle group 23 are installed with edge nozzles 24.
[0022] More specifically, a first stop valve group 3 is installed between the heat source connecting pipe 1 and the gas-liquid separator 2. The staff can adjust and control the amount of steam heat source entering the pipe network through the first stop valve group 3.
[0023] More specifically, a water separator valve 14 is installed between the gas-liquid separator 2 and the steam water separator 15. The water separator valve 14 can be used to adjust and control the amount of steam entering the steam water separator 15.
[0024] More specifically, the gas-liquid separator 2 is provided with a flange-type spring safety valve 201 for protecting the gas-liquid separator 2 from the influence of overpressure and a pressure gauge 202 for the staff to check the pressure.
[0025] More specifically, the third connecting pipe 13 and the fourth connecting pipe 19 are respectively installed on the side pipe bracket 10 and the front pipe bracket 18, and a pipe clip 17 is installed below the front pipe bracket 18. The side pipe bracket 10 and the front pipe bracket 18 can better support and place the third connecting pipe 13 and the fourth connecting pipe 19, and can also place the sintering shuttle cloth bin.
[0026] More specifically, a third stop valve group 16 is installed on one side of the third connecting pipe 13. The third stop valve group 16 is used to control and adjust the third connecting pipe 13.
[0027] To be more specific, the second connecting pipe 6 is provided with a pressure transmitter 601 for measuring and converting pressure signals and a thermal resistor 602 for measuring temperature.
[0028] More specifically, an inspection assembly 4 is provided between the heat source connecting pipe 1 and the second connecting pipe 6. The inspection assembly 4 can facilitate the staff to inspect and repair their equipment.
[0029] More specifically, the heat source connecting pipe 1 is used to connect to the steam heat source of the pipeline network. The operating pressure of the steam heat source of the pipeline network is not less than 0.3-0.6Mpa.
[0030] The working principle of the utility model is as follows: steam is supplied to the gas-liquid separator 2 from the steam main pipe, the outlet pressure of the gas-liquid separator 2 is set to 0.3-0.6MPa, and two branch pipes are provided to supply the third connecting pipe 13 and the fourth connecting pipe 19. The fourth connecting pipe 19 passes through the silo wall to connect the two vertical central beam pipes 20 in the center of the silo. A group of large nozzles are installed at the ends of the central beam pipes 20, and the large nozzles are processed with a plurality of injection holes. The high-temperature steam is dispersed through the injection holes to reach the central material layer, which can effectively increase the material temperature. The steam pipeline of the third connecting pipe 13 is arranged at the bottom of the silo, and a plurality of edge nozzles 24 are arranged around the outside of the silo to pass through the silo wall, and the steam is used to increase the temperature of the outer layer of the silo. Under the three-dimensional cross-heating effect of the third connecting pipe 13 and the fourth connecting pipe 19, the mixed material in the silo is fully and evenly heated, thereby improving the utilization efficiency of waste heat.
[0031] The above is only used to illustrate the technical solution of the utility model rather than to limit it. Other modifications or equivalent substitutions made to the technical solution of the utility model by ordinary technicians in this field should be included in the scope of the claims of the utility model as long as they do not depart from the spirit and scope of the technical solution of the utility model.
Claims
1. A three-dimensional mixed material steam preheating device for a sintering machine shuttle bunker, characterized in that: It comprises a gas-liquid separator (2), a second connecting pipe (6), a third connecting pipe (13), a fourth connecting pipe (19), a front pipe nozzle group (21), and a side pipe nozzle group (23). A heat source connecting pipe (1) is installed on one side of the gas-liquid separator (2), a steam smelter (15) is installed on the other side of the gas-liquid separator (2), and the top of the gas-liquid separator (2) is connected to the second connecting pipe (6) through the first connecting pipe (5). The second connecting pipe (6) is sequentially installed with a pipeline stop valve (7), a manual regulating valve (8) and a flow meter (9) from the outside to the inside, and the end of the second connecting pipe (6) is connected to the third connecting pipe (5). A connecting pipe (13) and a fourth connecting pipe (19), the third connecting pipe (13) being provided with a second stop valve group (11) and a flange short pipe group (12), the third connecting pipe (13) being provided with a plurality of side pipe nozzle groups (23), the fourth connecting pipe (19) being provided with a plurality of front pipe nozzle groups (21), a central beam pipe (20) being provided between the two fourth connecting pipes (19), the outer sides of the front pipe nozzle groups (21) and the side pipe nozzle groups (23) being provided with internal thread ball valves (22), and the inner side outlets of the front pipe nozzle groups (21) and the side pipe nozzle groups (23) being provided with edge nozzles (24).
2. The three-dimensional mixed material steam preheating device for the shuttle material bunker of a sintering machine according to claim 1 is characterized in that: A first stop valve group (3) is installed between the heat source connecting pipe (1) and the gas-liquid separator (2).
3. The three-dimensional mixed material steam preheating device for the shuttle material bunker of a sintering machine according to claim 1 is characterized in that: A steam separator valve (14) is installed between the gas-liquid separator (2) and the steam separator (15).
4. The three-dimensional mixed material steam preheating device for the shuttle material bunker of a sintering machine according to claim 1 is characterized in that: The gas-liquid separator (2) is provided with a flange-type spring safety valve (201) for protecting the gas-liquid separator (2) from the influence of overpressure, and a pressure gauge (202) for workers to check the pressure.
5. The three-dimensional mixed material steam preheating device for the shuttle material bunker of a sintering machine according to claim 1 is characterized in that: The third connecting pipe (13) and the fourth connecting pipe (19) are respectively installed on the side pipe bracket (10) and the front pipe bracket (18), and a pipe clip (17) is installed below the front pipe bracket (18).
6. The three-dimensional mixed material steam preheating device for the shuttle material bunker of a sintering machine according to claim 1 is characterized in that: A third stop valve group (16) is installed on one side of the third connecting pipe (13).
7. The three-dimensional mixed material steam preheating device for the shuttle material bunker of a sintering machine according to claim 1 is characterized by: The second connecting pipe (6) is provided with a pressure transmitter (601) for measuring and converting pressure signals and a thermal resistor (602) for measuring temperature.
8. The three-dimensional mixed material steam preheating device for the shuttle material bunker of a sintering machine according to claim 1 is characterized in that: An inspection component (4) is provided between the heat source connecting pipe (1) and the second connecting pipe (6).
9. The three-dimensional mixed material steam preheating device for the shuttle material bunker of a sintering machine according to claim 1, characterized in that: The heat source connecting pipe (1) is used to connect to the steam heat source of the pipe network.