By setting the first middle chute and rear chute connected in an arc-shaped manner at the rear end of the front chute of the first transporter, the problem of limited height lifting of the rear of the transporter is solved, and a larger angle inclination and stable operation is achieved, thereby avoiding the chain phenomenon. Reduced processing costs.
Patent Information
- Application Number
- CN202420910657.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-28
- Publication Date
- 2024-11-29
- Estimated Expiration
- 2034-04-28
AI Technical Summary
The existing first transport aircraft is limited in increasing the tail height, and the solution to increase the inclination angle and length has problems such as limited angle and increased cost, which is difficult to meet the height requirements of the truck cabin.
By setting the first middle chute at the rear end of the front chute, an arc-shaped surface connection is formed to avoid sharp angles, raise the height of the tail of the transport machine, and ensure a smooth transition at the connection through the design of the rear chute to avoid chain clamping.
It realizes that the tail height of the transport aircraft is significantly improved without changing the front-end inclination angle, avoiding chain problems, and ensuring transportation stability and cost-effectiveness.
Smart Images

Figure CN222084506U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of mining machinery and equipment, in particular to a first conveyor and excavation equipment. Background Art
[0002] The tunnel boring machine is one of the main equipment of the tunnel boring machine. The function of the first conveyor is to transport the materials that fall to the ground after excavation at the front of the tunnel boring machine to the rear of the tunnel boring machine. The tail of the first conveyor is equipped with a transport vehicle to transport the materials to the transport vehicle, such as a truck. The tail height of the first conveyor is required to be higher than the truck compartment. In order to make the height of the tail of the first conveyor meet the requirements, it is usually necessary to increase the inclination angle or length of the first conveyor. However, due to the overall structure of the tunnel boring machine, the inclination angle and length of the first conveyor are limited, resulting in the tail height of the first conveyor still unable to meet the requirements. Therefore, how to increase the height of the tail of the first conveyor is an urgent problem that the industry needs to solve. Utility Model Content
[0003] The utility model provides a first conveyor and excavation equipment, which are used for raising the tail height of the first conveyor.
[0004] The first aspect of the utility model provides a first transport aircraft, comprising:
[0005] front chute;
[0006] The first middle chute has a first end and a second end; the first end is connected to the rear end of the front chute, an arc surface is formed between the first end and the second end, and the second end is located above the first end.
[0007] The first transporter provided by the utility model further includes:
[0008] A rear chute, the front end of which is connected to the second end.
[0009] According to the first conveyor provided by the utility model, the length direction of the front chute is the first direction, and the length direction of the rear chute is the second direction; the first direction and the second direction form a first angle, and the first angle is not less than 5 degrees and not more than 15 degrees.
[0010] The first transporter provided by the utility model further includes:
[0011] A chain pressing plate is arranged in the first middle chute along the length direction of the first middle chute, one side of the chain pressing plate is connected to the first middle chute, and two adjacent chain pressing plates are abutted.
[0012] According to the first conveyor provided by the utility model, the first middle chute includes:
[0013] Two first middle side plates are arranged along the width direction of the first middle chute, and a first middle chute gap is formed between the two first middle side plates; the lower edge of the first middle side plate is arc-shaped.
[0014] According to the first conveyor provided by the utility model, the circumferential radius of the arc is not less than 7m.
[0015] According to the first conveyor provided by the utility model, the first middle chute also includes:
[0016] The first reinforcing plate is connected between the two first middle side plates.
[0017] The first transporter provided by the utility model further includes:
[0018] The second middle chute is connected between the rear end of the front chute and the first end; or / and, is connected to the second end.
[0019] A second aspect of the utility model provides a tunneling device, comprising a tunneling device body, and a first conveyor as described in any one of the above items, wherein the first conveyor is connected to the tunneling device body.
[0020] According to the excavation equipment provided by the utility model, the excavation equipment body includes a boring machine and / or an anchor machine.
[0021] The first conveyor and excavation equipment provided by the utility model can keep the front end inclination angle of the first conveyor unchanged by setting the first middle chute at the rear end of the front chute, and can avoid the front end parts of the excavation machine. Because the first end of the first middle chute and the second end of the first middle chute form an arc surface, the connection between the rear end of the front chute and the first end can achieve a smooth transition, avoid forming a sharp angle, and avoid the problem of chain jamming. Because the second end is located above the first end, the height of the tail of the first conveyor can be raised.
[0022] The tunneling equipment of the present invention includes the first conveyor mentioned above, and thus has at least the above advantages. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] In order to more clearly illustrate the technical solutions in the present invention or the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0024] Figure 1 It is a three-dimensional structural schematic diagram of the first transporter provided by the utility model;
[0025] Figure 2 It is a structural schematic diagram of the first transporter provided by the utility model in a first visual perspective;
[0026] Figure 3 It is a structural schematic diagram of the first transport machine provided by the utility model under the second visual perspective.
[0027] Reference numerals:
[0028] 100, front chute; 110, front side plate; 120, second reinforcement plate;
[0029] 200, first middle chute; 210, first end; 220, second end; 230, first middle side plate; 240, first reinforcing plate;
[0030] 300, rear chute; 400, second middle chute; 500, chain pressing plate;
[0031] 600, first connecting component; 610, connecting plate; 620, third connecting member; 630, fourth connecting member;
[0032] 700, first flange assembly; 710, first flange plate; 720, second flange plate; 730, first connecting member;
[0033] 800, second flange assembly; 810, third flange plate; 820, fourth flange plate; 830, second connecting member;
[0034] 10. Driving assembly; 20. Scraper chain; 30. Tensioning cylinder. DETAILED DESCRIPTION
[0035] In order to make the purpose, technical solution and advantages of the utility model clearer, the technical solution of the utility model will be described clearly and completely in conjunction with the drawings in the utility model. Obviously, the described embodiments are part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0036] In the description of the embodiments of the present utility model, it should be noted that the terms "center", "longitudinal", "lateral", "upper", "lower", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the embodiments of the present utility model and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the embodiments of the present utility model. In addition, the terms "first", "second", and "third" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance.
[0037] In the description of the embodiments of the present utility model, it should be noted that, unless otherwise clearly specified and limited, the terms "connected" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be directly connected or indirectly connected through an intermediate medium. For ordinary technicians in this field, the specific meanings of the above terms in the embodiments of the present utility model can be understood according to specific circumstances.
[0038] In the embodiments of the present invention, unless otherwise clearly specified and limited, the first feature being "above" or "below" the second feature may mean that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, the first feature being "above", "above" and "above" the second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. The first feature being "below", "below" and "below" the second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.
[0039] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the utility model embodiment. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.
[0040] At present, the means adopted to increase the height of the tail of the first conveyor are to increase the inclination angle of the first conveyor and to extend the length of the first conveyor. The scheme for increasing the inclination angle specifically includes adding an inclined trough. The existing scheme for increasing the inclination angle can only achieve a small increase in angle, and the inclination angle can usually be increased to 3° to 5°. If the inclination angle increases by more than 5°, there will be a problem of chain jamming at the connection between the inclined trough and other chute structures, causing the first conveyor to be unable to operate normally. If the scheme of extending the length of the first conveyor is adopted, firstly, the limitation of the structure of the whole machine leads to a limited increase in the length of the first conveyor. In addition, increasing the length of the first conveyor will also increase the cost. Therefore, how to increase the height of the tail of the first conveyor is still an urgent problem to be solved in the industry.
[0041] Combine the following Figures 1 to 3 The first transporter of the utility model is described in detail. Figure 1 It is a three-dimensional structural schematic diagram of the first transporter provided by the utility model; Figure 2 It is a structural schematic diagram of the first transporter provided by the utility model in a first visual perspective; Figure 3 It is a structural schematic diagram of the first transport machine provided by the utility model under the second visual perspective.
[0042] like Figures 1 to 3 As shown, a specific embodiment of the first aspect of the utility model provides a first conveyor. The first conveyor includes a front chute 100 and a first middle chute 200; the first middle chute 200 has a first end 210 and a second end 220; the first end 210 is connected to the rear end of the front chute 100, and an arc surface is formed between the first end 210 and the second end 220, and the second end 220 is located above the first end 210.
[0043] In a specific embodiment of the utility model, by setting the first middle chute 200 at the rear end of the front chute 100, the front end inclination angle of the first conveyor can be kept unchanged, and the front end parts of the tunnel boring machine can be avoided. Because the first end 210 of the first middle chute 200 and the second end 220 of the first middle chute 200 form an arc surface, the connection between the rear end of the front chute 100 and the first end 210 can achieve a smooth transition, avoid forming a sharp angle, and avoid the problem of chain jamming. Because the second end 220 is located above the first end 210, the height of the tail of the first conveyor can be raised.
[0044] Furthermore, because an arc surface is formed between the first end 210 of the first middle chute 200 and the second end 220 of the first middle chute 200, a smooth transition between the front chute and the first middle chute can be achieved without improving the existing front chute, further saving processing costs while having universal applicability.
[0045] It should be noted that the smooth transition between the first end 210 and the front end of the front chute 100 means that there is no sharp angle that can be identified by the naked eye at the connection between the first middle chute 200 and the front chute 100. Specifically, in the projection of the entire first conveyor on the vertical plane, there is no sharp angle that can be identified by the naked eye at the connection between the first middle chute 200 and the front chute 100.
[0046] In a specific embodiment of the present invention, the first conveyor further comprises a rear chute 300, the front end of which is connected to the second end 220. By arranging the rear chute 300 at the second end 220 of the first intermediate chute 200, not only can a smooth transition between the front end of the rear chute 300 and the second end 220 be achieved, a chain jamming phenomenon can be avoided at the connection between the rear chute 300 and the first intermediate chute 200, and the normal operation of the first conveyor can be ensured; but also installation space is provided for the driving assembly 10 of the first conveyor, etc., the length of the first conveyor is extended, and the height of the tail of the first conveyor is further increased.
[0047] like Figure 1 and Figure 2 As shown, in a specific embodiment of the utility model, the length direction of the front chute 100 is the first direction, and the length direction of the rear chute 300 is the second direction; the first direction and the second direction form a first angle α, and the first angle is not less than 5 degrees and not greater than 15°. Compared with the solution of increasing the inclination angle in the prior art, the degree of increase in the inclination angle of this embodiment is significantly higher, and a large increase in the inclination angle can be achieved, and the chain jamming phenomenon can also be avoided at the connection, ensuring the stable operation of the first conveyor. Because the first angle is not greater than 15°, the transported material can be prevented from moving in the opposite direction under the action of its own weight, ensuring that the material can be normally transported to the tail of the first conveyor.
[0048] Furthermore, the degree of the first angle α satisfies: 5°≤α≤10°, which can not only achieve the purpose of increasing the height of the tail of the first conveyor, but also prevent the transported materials from moving downward, thereby ensuring smooth material transportation.
[0049] In a specific embodiment of the present invention, the first conveyor further includes a chain pressing plate 500; the chain pressing plate 500 is arranged in the first middle chute 200 along the length direction of the first middle chute 200, one side of the chain pressing plate 500 is connected to the first middle chute 200, and two adjacent chain pressing plates 500 are in contact with each other. In other words, the chain pressing plate 500 is fully loaded in the first middle chute 200, which can limit the jumping amplitude of the scraper chain 20 in the first middle chute, ensuring the normal operation of the first conveyor.
[0050] In a specific embodiment of the utility model, the first middle chute 200 includes two first middle side plates 230; the two first middle side plates 230 are arranged along the width direction of the first middle chute 200, and a first middle slot gap is formed between the two first middle side plates 230; the lower edge of the first middle side plate 230 is arc-shaped. By improving the shape of the first middle side plate 230, an arc-shaped surface can be formed between the first end 210 and the second end 220, which is easy to process.
[0051] Specifically, the chain pressing plate 500 is located in the gap of the first middle trough, and the two first middle side plates 230 are provided with the chain pressing plate 500 along the length direction of the first middle chute 200, and the chain pressing plates 500 of the two first middle side plates 230 are symmetrically arranged, and the two adjacent chain pressing plates 500 along the length direction of the first middle chute 200 are abutted to realize that the chain pressing plate 500 is fully loaded in the first middle chute 200.
[0052] In a specific embodiment of the present invention, the circumferential radius of the arc is not less than 7 m, ensuring that the first angle α is not less than 5°, avoiding the problem of chain jamming, and ensuring the stable operation of the first conveyor.
[0053] In a specific embodiment of the present invention, the first middle chute 200 further includes a first reinforcing plate 240 ; the first reinforcing plate 240 is connected between the two first middle side plates 230 to increase the installation stability of the two first middle side plates 230 .
[0054] In some embodiments, a hollow area is formed in the middle of the first reinforcing plate 240 to save raw materials and reduce the weight and cost of the entire machine.
[0055] In a specific embodiment of the utility model, the front chute 100 includes two front side plates 110, and the two front side plates 110 are arranged along the width direction of the front chute 100. A front trough gap is formed between the two front side plates 110. The lower edges of the two front side plates 110 are straight lines, and the connection between the front side plates 110 and the first middle side plate 230 is smoothly transitioned to avoid the problem of chain jamming and ensure the stable operation of the first conveyor.
[0056] In some embodiments, a chain pressing plate 500 is provided in the front groove gap, and along the first direction, the two front side plates 110 are connected to one side of the chain pressing plate 500, and along the first direction, two adjacent chain pressing plates 500 abut against each other, so that the front chute 100 is fully loaded with the chain pressing plate 500.
[0057] In a specific embodiment of the present invention, the front chute 100 further includes a second reinforcing plate 120 . The second reinforcing plate 120 is connected between the two front side plates 110 to increase the installation stability of the front side plates 110 .
[0058] In some embodiments, a hollow area is formed in the middle of the second reinforcing plate 120 to save raw materials and reduce the weight and cost of the entire machine.
[0059] In a specific embodiment of the present invention, the first conveyor further includes a first connecting assembly 600; the rear end of the front chute 100 and the first end 210 of the first middle chute 200 are detachably connected via the first connecting assembly 600, which facilitates disassembly and assembly and improves the convenience of transportation.
[0060] In some embodiments, the first connecting assembly 600 includes a connecting plate 610, a third connecting member 620 and a fourth connecting member 630. Specifically, the number of the connecting plates 610 is at least one, that is, the connecting plates 610 can be one, two or more, and are flexibly arranged according to actual needs. Optionally, the connecting plate 610 includes an inner connecting plate and an outer connecting plate; the inner connecting plate is located on the inner side of the first conveyor, and the outer connecting plate is located on the outer side of the first conveyor. Further, the third connecting member 620 is connected to the front side plate 110 of the front chute 100 through the connecting plate 610, and the fourth connecting member 630 is connected to the first middle side plate 230 of the first middle chute 200 through the connecting plate 610, so as to realize the detachable connection between the front chute 100 and the first middle chute 200.
[0061] In a specific embodiment of the present invention, the rear chute 300 includes two rear side plates; the two rear side plates are arranged along the width direction of the rear chute 300, and a rear trough gap is formed between the two rear side plates; the lower edge of the rear side plate is a straight line, and the connection between the lower edge of the rear side plate and the first middle chute 200 is smoothly transitioned to avoid the chain jamming problem.
[0062] In a specific embodiment of the utility model, the first conveyor includes a driving assembly 10 and a scraper chain 20; the driving assembly 10 is arranged in the rear chute 300. The scraper chain 20 is arranged through the front chute 100, the first middle chute 200 and the rear chute 300, and the scraper chain 20 is transmission-connected with the driving assembly 10. The driving assembly 10 can drive the scraper chain 20 to operate, so that the first conveyor transports the front material to the rear.
[0063] In a specific embodiment of the utility model, the first conveyor further includes a chain pressing plate 500; the chain pressing plate 500 is fully loaded in the first middle chute 200 along the length direction of the first middle chute 200. It can be understood that the chain pressing plate 500 is located above the scraper chain 20 to prevent the scraper chain 20 from being disengaged and to limit the jumping amplitude of the scraper chain 20. The scraper chain 20 passes under the chain pressing plate 500, bypasses the drive assembly 10, and then goes back from the chain return cavity of the first conveyor to form a closed loop.
[0064] In some embodiments, at least one chain pressing plate 500 is disposed in the front chute 100. In other words, the chain pressing plate 500 may not fully fill the front chute 100.
[0065] In some embodiments, at least one chain pressing plate 500 is disposed in the rear chute 300 . In other words, the chain pressing plate 500 may not fully fill the rear chute 300 .
[0066] It should be noted that the chain pressing plate 500 fully fills the front chute 100, which means that two adjacent chain pressing plates 500 abut against each other along the first direction; in other words, the chain pressing plate 500 does not fully fill the front chute 100, which means that a gap is formed between two adjacent chain pressing plates 500 along the first direction to expose the scraper chain 20. The chain pressing plate 500 fully fills the front chute 100, which can prevent the scraper chain 20 from being disengaged, ensure the normal operation of the first conveyor, and improve the operation stability.
[0067] In a specific embodiment of the present invention, the first conveyor further includes a second middle chute 400; the second middle chute 400 is connected between the rear end of the front chute 100 and the first end 210; or / and, connected to the second end 220. By providing the second middle chute 400, the length of the first conveyor can be increased, and the height of the tail of the first conveyor can be further increased.
[0068] In some embodiments, the second middle chute 400 is connected between the rear end of the front chute 100 and the first end 210 of the first middle chute 200 .
[0069] In some embodiments, the second middle chute 400 is connected between the second end 220 of the first middle chute 200 and the front end of the rear chute 300 .
[0070] It is understood that, in some embodiments, the length direction of the second middle chute 400 and the length direction of the front chute 100 may be parallel to each other. In other embodiments, the length direction of the second middle chute 400 and the length direction of the front chute 100 may form a second angle of no more than 5°, which may further increase the tail height of the first conveyor.
[0071] It can be understood that, in some embodiments, the length direction of the second middle chute 400 is parallel to the length direction of the rear chute 300. In other embodiments, the length direction of the second middle chute 400 and the length direction of the rear chute 300 may also form a third angle of no more than 5°, which can further increase the tail height of the first conveyor.
[0072] It is understandable that the number of the second middle chutes 400 can be one, two, three, etc., and the number of the second middle chutes 400 is not limited in the specific embodiment of the present utility model.
[0073] In a specific embodiment of the present invention, the second middle chute 400 includes two second middle side plates; the two second middle side plates are arranged along the width direction of the second middle chute 400, and a second middle chute gap is formed between the two second middle chute 400.
[0074] In some embodiments, the chain pressing plate 500 is symmetrically disposed in the second middle chute 400 and connected to the second middle side plate.
[0075] In a specific embodiment of the utility model, the second middle chute 400 is detachably connected to the first middle chute 200 via a first flange assembly 700. It is convenient for the staff to disassemble and assemble the first middle chute 200 and the second middle chute 400, and avoid the transportation being unchanged due to the excessive mass or size of a certain part. The flange connection can improve the connection strength. Specifically, the first middle side plate 230 is detachably connected to the second middle side plate via the first flange assembly 700.
[0076] In a specific embodiment of the utility model, the second middle chute 400 and the rear chute 300 are detachably connected by a second flange assembly 800. It is convenient for the staff to disassemble and assemble the rear chute 300 and the second middle chute 400, and avoid the transportation being unchanged due to the excessive mass or size of a certain part. The flange connection can improve the connection strength. Specifically, the second middle side plate is detachably connected to the rear side plate by the second flange assembly 800.
[0077] In some embodiments, the first flange assembly 700 includes a first flange plate 710, a second flange plate 720 and a first connecting member 730; the first flange plate 710 is arranged at the second end 220 of the first middle chute 200, the second flange plate 720 is arranged at an end of the second middle chute 400 close to the first middle chute 200, and the first connecting member 730 is passed through the first flange plate 710 and the second flange plate 720 to realize a detachable connection between the second end 220 of the first middle chute 200 and the second middle chute 400.
[0078] It is understandable that the number of the first connecting members 730 may be one or two, and in this embodiment, there is no limitation on the number of the first connecting members 730. The first connecting members 730 may be flexibly arranged according to actual needs.
[0079] In some embodiments, the second flange assembly 800 includes a third flange plate 810, a fourth flange plate 820 and a second connecting member 830; the third flange plate 810 is arranged at one end of the second middle chute 400 away from the first middle chute 200, the fourth flange plate 820 is arranged at the front end of the rear chute 300, and the second connecting member 830 is passed through the third flange plate 810 and the fourth flange plate 820 to realize a detachable connection between the second middle chute 400 and the rear chute 300.
[0080] It is understandable that the number of the second connecting members 830 may be one or two, and in this embodiment, there is no limitation on the number of the second connecting members 830. The second connecting members 830 may be flexibly arranged according to actual needs.
[0081] In a specific embodiment of the present invention, the scraper chain 20 is disposed through the front chute 100 , the first middle chute 200 , the second middle chute 400 and the rear chute 300 .
[0082] In a specific embodiment of the utility model, the first conveyor further includes a tensioning cylinder 30; the tensioning cylinder 30 is disposed in the rear chute 300, and the tensioning cylinder 30 is connected to the drive assembly 10. By providing the tensioning cylinder 30, the drive assembly 10 can be moved relative to the rear chute 300, and the relative position of the drive assembly 10 and the rear chute 300 can be changed to adjust the slack of the scraper chain 20. Optionally, after the drive assembly 10 is inserted from the rear end of the rear chute 300, the tensioning cylinder 30 is fixed to the rear chute 300 by bolts, and the rear end of the tensioning cylinder 30 is fixed to the drive assembly 10 by bolts, thereby completing the installation of the tensioning cylinder 30 and the drive assembly 10.
[0083] Working principle: The motor in the driving assembly 10 rotates to drive the scraper chain 20 to rotate, and the scraper of the scraper chain 20 is used to transport the material from the front end to the rear end, and then the material falls on the transport vehicle. Since an arc surface is formed between the first end 210 and the second end 220 of the first middle chute 200, and the second end 220 is located above the first end 210, the chain jam phenomenon can be avoided, and the tail of the first conveyor can be raised.
[0084] A specific embodiment of the second aspect of the utility model provides a tunneling device, which includes a tunneling device body and a first conveyor according to any of the above embodiments, wherein the first conveyor is connected to the tunneling device body.
[0085] Since the excavation equipment of this embodiment includes the first conveyor, it has at least the above advantages.
[0086] In a specific embodiment of the present utility model, the tunneling equipment body includes but is not limited to a tunneling machine and / or an anchor bolter.
[0087] In some embodiments, the tunneling equipment body is a tunneling machine, and the front end of the front chute 100 of the first conveyor is connected to the tunneling machine to transport the materials that fall to the ground after excavation at the front of the tunneling machine to the rear of the tunneling machine.
[0088] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the utility model, rather than to limit it. Although the utility model has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the various embodiments of the utility model.
Claims
1. A first transport aircraft, It is characterized in that include: Front chute(100); A first middle chute (200), wherein the first middle chute (200) has a first end (210) and a second end (220); the first end (210) is connected to the rear end of the front chute (100), an arcuate surface is formed between the first end (210) and the second end (220), and the second end (220) is located above the first end (210).
2. The first transport aircraft according to claim 1, It is characterized in that Also includes: A rear chute (300), wherein the front end of the rear chute (300) is connected to the second end (220).
3. The first transport aircraft according to claim 2, It is characterized in that The length direction of the front chute (100) is a first direction, and the length direction of the rear chute (300) is a second direction; the first direction and the second direction form a first angle, and the first angle is not less than 5 degrees and not more than 15 degrees.
4. The first transport aircraft according to claim 1, It is characterized in that Also includes: A chain pressing plate (500) is arranged in the first middle chute (200) along the length direction of the first middle chute (200), one side of the chain pressing plate (500) is connected to the first middle chute (200), and two adjacent chain pressing plates (500) are abutted.
5. The first transport aircraft according to claim 1, It is characterized in that The first chute (200) comprises: Two first middle side plates (230), the two first middle side plates (230) are arranged along the width direction of the first middle chute (200), and a first middle chute gap is formed between the two first middle side plates (230); the lower edge of the first middle side plate (230) is arc-shaped.
6. The first transporter according to claim 5, It is characterized in that The circumferential radius of the arc is not less than 7m.
7. The first transport aircraft according to claim 5, It is characterized in that The first chute (200) further comprises: A first reinforcing plate (240) is connected between the two first middle side plates (230).
8. The first transport aircraft according to any one of claims 1 to 7, It is characterized in that Also includes: The second middle chute (400) is connected between the rear end of the front chute (100) and the first end (210); or / and, is connected to the second end (220).
9. A tunneling device, It is characterized in that It comprises a tunneling equipment body, and the first conveyor according to any one of claims 1 to 8, wherein the first conveyor is connected to the tunneling equipment body.
10. The tunneling device according to claim 9, It is characterized in that The excavation equipment body includes a tunneling machine and / or an anchor bolter.