Hook-headed underground conveying line

By designing the chain transmission structure and drive parts of the hook head underground conveying line, the mechanized automatic handling of the hook head is realized, solving the problems of low manual handling efficiency and high cost, improving handling efficiency and saving labor costs.

CN222098722UActive Publication Date: 2024-12-03SHENHUA RAIL & FREIGHT WAGONS TRANSPORT
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420867307.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-24
Publication Date
2024-12-03
Estimated Expiration
2034-04-24

AI Technical Summary

Technical Problem

In the prior art, the method of manually carrying hooks leads to low handling efficiency and high labor costs.

Method used

A hook head underground conveying line is designed, using a chain transmission structure and a driving member. Through the meshing of the first sprocket assembly and the second sprocket assembly, the chain assembly and the hook head work-installation are driven to realize the mechanized automatic hook head on the base. Move.

Benefits of technology

It improves the efficiency of the hook head, saves labor costs, realizes automatic handling, and avoids the inefficiency and high cost problems of manual handling.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222098722U_ABST
    Figure CN222098722U_ABST
Patent Text Reader

Abstract

The utility model relates to a hook head underground conveying line, relates to the technical field of railway wagon hook head equipment, and is used for solving the problems of low carrying efficiency and high labor cost of a manual hook head carrying mode. Comprising a base; the first chain wheel assembly is rotatably arranged at one end of the machine base; the second chain wheel assembly is rotatably arranged at the other end of the machine base; the driving piece is arranged on the machine base, and the driving piece is connected with the first chain wheel assembly; the chain assembly is meshed with the first chain wheel assembly and the second chain wheel assembly; the plurality of hook head tools are fixed on the chain assembly, and the hook head tools are used for positioning hook heads; the driving piece can drive the first chain wheel assembly to rotate, and meanwhile the chain assembly drives the second chain wheel assembly to rotate and drives the multiple hook head tools to move in a reciprocating mode. According to the utility model, a manual carrying mode is replaced by a mechanical automatic carrying mode. Therefore, on-site hook head carrying efficiency is improved, and labor cost is saved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of railway freight car hook equipment, in particular to an underground hook conveyor line. Background Art

[0002] The hook head is a part of the railway freight car coupler, and the railway freight car coupler needs to be frequently inspected and assembled. Therefore, the railway freight car hook head needs to be transported between two points.

[0003] In the prior art, a rescue emergency tool vehicle is usually used to transport the hook head (for details, please refer to Chinese utility model patent: CN 216915870 U). This manual transport method will result in greater on-site labor intensity for the transport workers, lower transport efficiency, and higher labor costs.

[0004] That is to say, the manual method of carrying the hook head in the prior art has the problems of low carrying efficiency and high labor cost. Utility Model Content

[0005] The utility model provides an underground hook conveyor line, which is used to solve the problems of low carrying efficiency and high labor cost in a method of manually carrying the hook.

[0006] The utility model provides a hook underground conveyor line, comprising:

[0007] Machine base;

[0008] A first sprocket assembly is rotatably disposed on one end of the base;

[0009] A second sprocket assembly is rotatably disposed on the other end of the base;

[0010] A driving member, which is disposed on the machine base and connected to the first sprocket assembly; and

[0011] a chain assembly disposed on the first sprocket assembly and the second sprocket assembly and meshing with the first sprocket assembly and the second sprocket assembly; and

[0012] A plurality of hook head fixtures, which are fixed on the chain assembly, and the hook head fixtures are used to position the hook heads;

[0013] The driving member can drive the first sprocket assembly to rotate, while the chain assembly drives the second sprocket assembly to rotate, and drives the plurality of hook head tools to move back and forth between the first sprocket assembly and the second sprocket assembly.

[0014] In one embodiment, the first sprocket assembly comprises:

[0015] a rotating shaft rotatably disposed on one end of the base; and

[0016] a driving sprocket fixed to one end of the rotating shaft; and

[0017] A driven sprocket structure, which is fixed to the other end of the rotating shaft;

[0018] One end of the chain assembly is sleeved on the driving sprocket and the driven sprocket structure and meshed with the driving sprocket and the driven sprocket structure, and the driving member is connected to the rotating shaft.

[0019] In one embodiment, the driven sprocket structure includes two driven sprockets spaced apart from each other along the axial direction of the rotating shaft, one end of the chain assembly is meshed with the two driven sprockets at the same time, and the hook tooling is located between the two driven sprockets.

[0020] In one embodiment, the second sprocket assembly has the same structure as the first sprocket assembly.

[0021] In one embodiment, the chain assembly includes a first chain, a second chain and a third chain. Among them, one end of the first chain is sleeved on the driving sprocket of the first sprocket assembly, and the other end of the first chain is sleeved on the driving sprocket of the second sprocket assembly; one end of the second chain is sleeved on a driven sprocket in the driven sprocket structure of the first sprocket assembly, and the other end of the second chain is sleeved on a driven sprocket in the driven sprocket structure of the second sprocket assembly; one end of the third chain is sleeved on another driven sprocket in the driven sprocket structure of the first sprocket assembly, and the other end of the third chain is sleeved on another driven sprocket in the driven sprocket structure of the second sprocket assembly; the hook tooling is fixed on the second chain and the third chain.

[0022] In one embodiment, the distances between two adjacent hook head tools among the plurality of hook head tools are the same.

[0023] In one embodiment, the hook head underground conveyor line further includes a photoelectric switch and a control module. The photoelectric switch is arranged at both ends of the machine base; the control module is electrically connected to the photoelectric switch and the driving member; the control module can control the action of the driving member according to the signal fed back by the photoelectric switch to control the rotation of the first sprocket assembly.

[0024] In one embodiment, the driving member is a driving motor, a fixed end of the driving member is fixed to one end of the machine base, and a driving end of the driving member is connected to the first sprocket assembly.

[0025] In one embodiment, the machine base includes a support frame and a bottom plate. The bottom plate is arranged at the bottom of the support frame; the first sprocket assembly and the driving member are fixed on one end of the support frame, the second sprocket assembly is fixed on the other end of the support frame, the chain assembly is located in the support frame and above the bottom plate, and when the hook head tooling reciprocates between the first sprocket assembly and the driving member, the hook head tooling does not contact the bottom plate.

[0026] In one embodiment, a positioning hole is provided on the hook head, and the hook head tooling includes a plate body and a positioning column, wherein the plate body is fixed on the chain assembly; the positioning column is provided on the plate body; the positioning column is inserted into the positioning hole to limit the position of the hook head on the chain assembly.

[0027] Compared with the prior art, the advantage of the utility model is that a plurality of hook head fixtures are provided, and a plurality of hook heads are positioned by using the plurality of hook head fixtures. Then, the plurality of hook head fixtures are linearly moved between the first sprocket assembly and the second sprocket assembly by a chain transmission structure formed by the first sprocket assembly, the second sprocket assembly and the chain assembly. Thus, the transportation of the hook head between the first sprocket assembly and the second sprocket assembly is realized. In this way, the mechanized automatic handling method is adopted to replace the manual handling method in the prior art. Thus, the problem of low handling efficiency and high labor cost of the hook head caused by the manual handling method is avoided. Thus, the handling efficiency of the hook head on site is improved and the labor cost is saved. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] The present invention will be described in more detail below based on embodiments and with reference to the accompanying drawings.

[0029] Figure 1 It is a schematic diagram of the three-dimensional structure of the hook underground conveyor line in the embodiment of the utility model;

[0030] Figure 2 yes Figure 1 Main view of the middle hook underground conveyor line.

[0031] Reference numerals:

[0032] 10. Machine base; 11. Support frame; 12. Bottom plate; 20. First sprocket assembly; 21. Rotating shaft; 22. Driving sprocket; 23. Driven sprocket structure; 30. Second sprocket assembly; 40. Driving member; 50. Chain assembly; 51. First chain; 52. Second chain; 53. Third chain; 60. Hook tooling; 61. Plate; 62. Positioning column; 100. Hook. DETAILED DESCRIPTION

[0033] The utility model will be further described below in conjunction with the accompanying drawings.

[0034] like Figure 1 and Figure 2As shown, the utility model provides a hook head underground conveyor line, which includes a machine base 10, a first sprocket assembly 20, a plurality of hook head tools 60, a second sprocket assembly 30 and a chain assembly 50. Among them, a machine base 10 is placed below the ground; a first sprocket assembly 20 is rotatably disposed on one end of the machine base 10; a second sprocket assembly 30 is rotatably disposed on the other end of the machine base 10; a driving member 40 is disposed on the machine base 10, and the driving member 40 is connected to the first sprocket assembly 20; a chain assembly 50 is disposed on the first sprocket assembly 20 and the second sprocket assembly 30, and is engaged with the first sprocket assembly 20 and the second sprocket assembly 30; a plurality of hook head fixtures 60 are fixed on the chain assembly 50, and the hook head fixtures 60 are used to position the hook head 100; the driving member 40 can drive the first sprocket assembly 20 to rotate, and at the same time the chain assembly 50 drives the second sprocket assembly 30 to rotate, and drives the plurality of hook head fixtures 60 to reciprocate between the first sprocket assembly 20 and the second sprocket assembly 30.

[0035] In the above arrangement, a plurality of hook head fixtures 60 are provided, and a plurality of hook heads 100 are positioned by using the plurality of hook head fixtures 60. Then, the plurality of hook head fixtures 60 are linearly moved between the first sprocket assembly 20 and the second sprocket assembly 30 by a chain transmission structure formed by the first sprocket assembly 20, the second sprocket assembly 30 and the chain assembly 50. Thus, the transportation of the hook head 100 between the first sprocket assembly 20 and the second sprocket assembly 30 is realized. In this way, the mechanized automatic handling method is adopted to replace the manual handling method adopted in the prior art. Thus, the problem of low handling efficiency and high labor cost of the hook head 100 caused by the manual handling method is avoided. Thus, the handling efficiency of the hook head 100 on site is improved, and the labor cost is saved.

[0036] Specifically, Figure 1 and Figure 2 As shown, in one embodiment, the first sprocket assembly 20 includes a rotating shaft 21, a driving sprocket 22 and a driven sprocket structure 23. The rotating shaft 21 is rotatably arranged on one end of the machine base 10; the driving sprocket 22 is fixed on one end of the rotating shaft 21; the driven sprocket structure 23 is fixed on the other end of the rotating shaft 21; one end of the chain assembly 50 is sleeved on the driving sprocket 22 and the driven sprocket structure 23, and meshes with the driving sprocket 22 and the driven sprocket structure 23, and the driving member 40 is connected to the rotating shaft 21. In this way, the driving member 40 drives the rotating shaft 21 to rotate to drive the hook head tooling 60 and the hook head 100 thereon to move between the first sprocket assembly 20 and the second sprocket assembly 30.

[0037] Specifically, Figure 1 and Figure 2As shown, in one embodiment, the driven sprocket structure 23 includes two driven sprockets spaced axially along the rotating shaft 21, one end of the chain assembly 50 is simultaneously engaged with the two driven sprockets, and the hook head fixture 60 is located between the two driven sprockets. This can improve the stability of the chain transmission structure during transmission. Thereby improving the stability of the multiple hook head fixtures 60 and the multiple hook heads 100 thereon during movement.

[0038] Specifically, Figure 1 and Figure 2 As shown, in one embodiment, the second sprocket assembly 30 has the same structure as the first sprocket assembly 20 .

[0039] Furthermore, if Figure 1 and Figure 2 As shown, in one embodiment, the second sprocket assembly 30 includes a rotating shaft, a driving sprocket and a driven sprocket structure. The rotating shaft is rotatably arranged on the other end of the base; the driving sprocket is fixed on the other end of the rotating shaft; the driven sprocket structure is fixed on the other end of the rotating shaft; one end of the chain assembly is sleeved on the driving sprocket and the driven sprocket structure, and meshes with the driving sprocket and the driven sprocket structure.

[0040] Furthermore, if Figure 1 and Figure 2 As shown, in one embodiment, the driven sprocket structure of the second sprocket assembly 30 includes two driven sprockets spaced apart along the axial direction of the rotating shaft, the other end of the chain assembly 50 is simultaneously engaged with the two driven sprockets, and the hook head fixture 60 is located between the two driven sprockets. This can improve the stability of the chain transmission structure during transmission. Thereby improving the stability of the multiple hook head fixtures 60 and the multiple hook heads 100 thereon during movement.

[0041] Specifically, Figure 1 and Figure 2As shown, in one embodiment, the chain assembly 50 includes a first chain 51, a second chain 52 and a third chain 53. Among them, one end of the first chain 51 is sleeved on the driving sprocket 22 of the first sprocket assembly 20, and the other end of the first chain 51 is sleeved on the driving sprocket of the second sprocket assembly 30; one end of the second chain 52 is sleeved on one driven sprocket in the driven sprocket structure 23 of the first sprocket assembly 20, and the other end of the second chain 52 is sleeved on one driven sprocket in the driven sprocket structure of the second sprocket assembly 30; one end of the third chain 53 is sleeved on another driven sprocket in the driven sprocket structure 23 of the first sprocket assembly 20, and the other end of the third chain 53 is sleeved on another driven sprocket in the driven sprocket structure of the second sprocket assembly 30; the hook head fixture 60 is fixed on the second chain 52 and the third chain 53. That is, the second chain 52 and the third chain 53 simultaneously support and fix the hook head fixture 60. This improves the stability of the movement of the hook head tooling 60. Thus, the stability of the hook head 100 during movement is improved.

[0042] Specifically, Figure 1 and Figure 2 As shown, in one embodiment, the distance between two adjacent hook head tools 60 in the plurality of hook head tools 60 is the same, that is, the distance between two adjacent hook head tools 60 is the distance that the hook head 100 moves one station.

[0043] Specifically, Figure 1 and Figure 2 As shown, in one embodiment, the hook head underground conveyor line further includes a photoelectric switch and a control module. The photoelectric switch is arranged at both ends of the machine base 10; the control module is electrically connected to the photoelectric switch and the driving member 40; the control module can control the driving member 40 to move according to the signal fed back by the photoelectric switch, so as to control the rotation of the first sprocket assembly 20.

[0044] It should be noted that two photoelectric switches control the start of the driving component 40, that is, the photoelectric switch detects that there is a hook head 100 at the active end (the end where the first sprocket assembly 20 on the machine base 10 is located), and when there is no hook head 100 at the driven end (the end where the second sprocket assembly 30 on the machine base 10 is located), the driving motor is started to rotate, and the hook head 100 moves one station. The photoelectric switch at the driven end detects the presence of the hook head 100, and the active end detects the absence of the hook head 100, and the control signal stops the driving component 40, and the underground transportation of the hook head 100 is realized by reciprocating cycles.

[0045] It should be noted that the control module includes a control circuit, which is connected to the drive member 40 and the photoelectric switch, and is used to control the start and stop of the drive member 40 according to the signal fed back by the photoelectric switch. A built-in power supply is integrated in the control module. The control module and the photoelectric switch are prior art, and their structures are not described here.

[0046] Specifically, Figure 1 and Figure 2 As shown, in one embodiment, the driving member 40 is a driving motor, the fixed end of the driving member 40 is fixed to one end of the base 10, and the driving end of the driving member 40 is connected to the first sprocket assembly 20. Specifically, as Figure 1 and Figure 2 As shown, in one embodiment, the base 10 includes a support frame 11 and a bottom plate 12. The bottom plate 12 is arranged at the bottom of the support frame 11; the first sprocket assembly 20 and the driving member 40 are fixed on one end of the support frame 11, the second sprocket assembly 30 is fixed on the other end of the support frame 11, the chain assembly 50 is located in the support frame 11 and above the bottom plate 12, and the hook head tooling 60 does not contact the bottom plate 12 when the hook head tooling 60 reciprocates between the first sprocket assembly 20 and the driving member 40.

[0047] Specifically, Figure 1 and Figure 2 As shown, in one embodiment, a positioning hole is provided on the hook head 100, and the hook head tooling 60 includes a plate body 61 and a positioning column 62. The plate body 61 is fixed on the chain assembly 50; the positioning column 62 is provided on the plate body 61; the positioning column 62 is inserted into the positioning hole to limit the position of the hook head 100 on the chain assembly 50.

[0048] It should be noted that the device in the present application includes a machine base 10, a driving motor, a driving sprocket assembly structure (a first sprocket assembly 20), a driven sprocket assembly structure (a second sprocket assembly 30), a tensioning device, a single chain (a first chain 51), a double chain (a second and a third chain), and a hook head tooling 60. A driving motor is fixed at one end of the machine base, and the output shaft of the driving motor is coaxially connected to the driving sprocket assembly structure. A driven sprocket assembly structure is installed at the other end of the machine base. Two types of chains are assembled between the driving sprocket assembly structure and the driven sprocket assembly structure. The two chains are a single chain and a double chain. A hook head tooling 60 is fixed on the double chain. The driving motor is energized and rotates, driving the driving sprocket assembly structure to rotate, and the chain meshing with the sprocket realizes linear motion. The hook head is placed on the chain (on the first to third chains at the same time), and the tip of the hook head tooling is inserted into the hook head flat pin hole (positioning hole) to prevent the hook head 100 from moving or flipping during transportation. The hook head 100 moves linearly with the chain. A tensioning device is arranged at the end of the driven sprocket assembly structure. In the initial assembly and after working for a period of time, the tensioning device needs to be used to adjust the spacing between the driving sprocket assembly and the driven sprocket assembly.

[0049] It should be noted that the tensioning device is a prior art and does not require a drawing; the function of the tensioning device is the tensioning function, and the purpose of adjusting the spacing is tensioning.

[0050] Although the present invention has been described with reference to preferred embodiments, various modifications may be made thereto and parts thereof may be replaced with equivalents without departing from the scope of the present invention. In particular, the various technical features mentioned in the various embodiments may be combined in any manner as long as there is no structural conflict. The present invention is not limited to the specific embodiments disclosed herein, but includes all technical solutions falling within the scope of the claims.

Claims

1. A hook underground conveyor line, characterized in that: include: Machine base; A first sprocket assembly, which is rotatably disposed on one end of the base; A second sprocket assembly is rotatably disposed on the other end of the base; A driving member, which is disposed on the machine base and connected to the first sprocket assembly; as well as a chain assembly disposed on the first sprocket assembly and the second sprocket assembly and meshing with the first sprocket assembly and the second sprocket assembly; as well as A plurality of hook head fixtures, which are fixed on the chain assembly, and the hook head fixtures are used to position the hook heads; The driving member can drive the first sprocket assembly to rotate, while the chain assembly drives the second sprocket assembly to rotate, and drives the plurality of hook head tools to reciprocate between the first sprocket assembly and the second sprocket assembly.

2. The hook head underground conveyor line according to claim 1, characterized in that: The first sprocket assembly comprises: a rotating shaft rotatably disposed on one end of the base; and a driving sprocket fixed to one end of the rotating shaft; and A driven sprocket structure, which is fixed to the other end of the rotating shaft; Wherein, one end of the chain assembly is sleeved on the driving sprocket and the driven sprocket structure and meshed with the driving sprocket and the driven sprocket structure, and the driving member is connected to the rotating shaft.

3. The hook underground conveyor line according to claim 2, characterized in that: The driven sprocket structure comprises two driven sprockets spaced apart from each other along the axial direction of the rotating shaft, one end of the chain assembly is meshed with the two driven sprockets at the same time, and the hook tooling is located between the two driven sprockets.

4. The hook underground conveyor line according to claim 3, characterized in that: The second sprocket assembly has the same structure as the first sprocket assembly.

5. The hook underground conveyor line according to claim 4, characterized in that: The chain assembly comprises: a first chain, one end of which is sleeved on the driving sprocket of the first sprocket assembly, and the other end of which is sleeved on the driving sprocket of the second sprocket assembly; and a second chain, one end of which is sleeved on a driven sprocket in the driven sprocket structure of the first sprocket assembly, and the other end of the second chain is sleeved on a driven sprocket in the driven sprocket structure of the second sprocket assembly; and A third chain, one end of which is sleeved on another driven sprocket in the driven sprocket structure of the first sprocket assembly, and the other end of the third chain is sleeved on another driven sprocket in the driven sprocket structure of the second sprocket assembly; Wherein, the hook head tooling is fixed on the second chain and the third chain.

6. The hook underground conveyor line according to any one of claims 1 to 5, characterized in that: The distance between two adjacent hook head tools among the plurality of hook head tools is the same.

7. The hook underground conveyor line according to claim 6, characterized in that: Also includes: Photoelectric switches are arranged at both ends of the base; as well as A control module, which is electrically connected to the photoelectric switch and the driving element; Wherein, the control module can control the action of the driving member according to the signal fed back by the photoelectric switch to control the rotation of the first sprocket assembly.

8. The hook underground conveyor line according to any one of claims 1 to 5, characterized in that: The driving member adopts a driving motor, the fixed end of the driving member is fixed on one end of the machine base, and the driving end of the driving member is connected to the first sprocket assembly.

9. The hook underground conveyor line according to any one of claims 1 to 5, characterized in that: The base comprises: Support frame; and A bottom plate, which is arranged at the bottom of the supporting frame; Wherein, the first sprocket assembly and the driving member are fixed on one end of the supporting frame, the second sprocket assembly is fixed on the other end of the supporting frame, the chain assembly is located in the supporting frame and above the base plate, and when the hook head tooling reciprocates between the first sprocket assembly and the driving member, the hook head tooling does not contact the base plate.

10. The hook underground conveyor line according to any one of claims 1 to 5, characterized in that: The hook head is provided with a positioning hole, and the hook head tooling comprises: a plate body fixed on the chain assembly; and A positioning column, which is arranged on the plate body; Wherein, the positioning column is inserted into the positioning hole to limit the position of the hook head on the chain assembly.