Equal-thickness cement-soil continuous wall structure

By using pillar components and positioning components in an equal thickness cement continuous wall structure, the stress area of ​​the support steel is increased and connected, the settlement problem during construction is solved, and the uniformity and strength of the construction is improved. It is suitable for high moisture content and ultra-soft Foundation pit construction of land strata.

CN222100811UActive Publication Date: 2024-12-03ANHUI TIANLING CONSTR GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420779906.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-16
Publication Date
2024-12-03
Estimated Expiration
2034-04-16

AI Technical Summary

Technical Problem

In high moisture content ultra-soft soil strata, during the construction of the continuous wall of equal thickness cement, due to the small stress area of ​​the bottom of the support steel, settlement is prone to occur, which affects the uniformity and continuity of the molded wall, and thus affects subsequent construction.

Method used

The pillar components and positioning components are adopted, and the pillar components and the top of the foundation pit body are installed to increase the stress area of ​​the support steel, and the H-shaped structure is formed by connecting steel and triangular steel plates, and the U-shaped steel is fixed by using screws and nuts. Improve the overall support and positioning ability to prevent disparity in height and settlement.

Benefits of technology

It effectively reduces settlement phenomenon, improves the uniformity and continuity of the molded wall, enhances the overall strength and water stopping ability, and reduces the impact on subsequent construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222100811U_ABST
    Figure CN222100811U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of cement soil walls, and discloses an equal-thickness cement soil continuous wall structure which comprises a foundation pit body, a supporting column assembly used for supporting a cement soil wall is installed on the inner side of the foundation pit body, and a positioning assembly used for auxiliary positioning is installed at the top of the supporting column assembly. The interior of the foundation pit body is filled with a cement soil continuous wall pouring material. The supporting column assembly comprises bottom plates which abut against the bottom of the foundation pit body and are evenly distributed, ground nails which are fixedly connected to the bottoms of the bottom plates and are evenly distributed, two pieces of fixing steel fixedly connected to the tops of the bottom plates, and connecting steel fixedly connected between the opposite sides of the two pieces of corresponding fixing steel. According to the equal-thickness cement-soil continuous wall structure, the influence of sedimentation on subsequent construction can be reduced as much as possible, the effect of reducing sedimentation is achieved by increasing the stress area of the supporting profile steel, the overall strength and the water stopping and retaining capacity after cement forming can be improved, and the equal-thickness cement-soil continuous wall structure is very practical.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of cement soil walls, and in particular to a cement soil continuous wall structure of equal thickness. Background Art

[0002] Conventional retaining structures include underground continuous walls, pile walls, SMW retaining walls, equal-thickness cement continuous walls, etc., which are combined with supports inside the foundation pit to form a foundation pit support system. These retaining structures are widely used in actual projects and have achieved good results. Among them, equal-thickness cement continuous walls have the characteristics of equal-thickness one-piece molding. Compared with general retaining walls, equal-thickness cement continuous walls have higher strength and better waterproof and water-retaining properties, and are therefore widely used in foundation pit construction in ultra-soft soil strata with high water content.

[0003] The existing cement continuous wall of equal thickness is generally first excavated horizontally inside the soil by a vertically arranged tool, and then supporting steel is inserted to increase the stiffness and strength of the wall after forming, and finally the cement mixture is poured. After waiting for solidification, a cement wall of equal thickness can be formed. However, this construction method still has certain inconveniences when applied to the construction of ultra-soft soil layers with high water content. When inserting the supporting steel, the bottom end needs to be inserted into the bottom of the foundation pit. Since the soil is soft and the bottom bearing area of ​​the supporting steel is small, settlement is likely to occur when the cement mixture is injected and waiting for solidification. This will cause the heights of the supporting steels to be different, affecting the uniformity and continuity of the formed wall, and also affecting the subsequent construction on the ground. In this regard, the present application provides a cement soil continuous wall structure of equal thickness to solve the above problems. Utility Model Content

[0004] In response to the shortcomings of the prior art, the present application provides a cement-soil continuous wall structure of equal thickness, which has the advantages of being able to minimize the impact of settlement on subsequent construction, and solves the disadvantage that the existing cement-soil continuous wall of equal thickness is prone to settlement during the construction process, thus affecting the subsequent construction process.

[0005] To achieve the above-mentioned purpose, the present application provides the following technical solutions: a cement-soil continuous wall structure of equal thickness, comprising a foundation pit main body, a support assembly for supporting the cement-soil wall is installed on the inner side of the foundation pit main body, a positioning assembly for auxiliary positioning is installed on the top of the support assembly, and the interior of the foundation pit main body is filled with cement-soil continuous wall casting material;

[0006] The pillar assembly includes a base plate that is evenly distributed and abuts against the bottom of the foundation pit body, ground nails that are evenly distributed and fixedly connected to the bottom of the base plate, two fixing steels that are evenly distributed and fixedly connected to the top of the base plate, connecting steels that are fixedly connected between the opposite sides of the two corresponding fixing steels, and triangular steel plates that are evenly distributed and fixedly connected to the left and right sides of the connecting steels; evenly distributed connecting holes are opened on the right side of the connecting steel.

[0007] By adopting the above technical scheme, the impact of settlement on subsequent construction can be reduced as much as possible. By increasing the force-bearing area of ​​the supporting steel, the settlement is reduced. At the same time, the supporting steels are connected so that they can support each other, further preventing the occurrence of uneven heights. This greatly reduces the impact on subsequent construction work on the ground, and at the same time can improve the uniformity and continuity of the formed wall, and can also improve the overall strength and water-stopping capacity of the cement after forming.

[0008] Furthermore, the positioning assembly includes two U-shaped steels respectively abutting between the front side of the front fixing steel and the back side of the back fixing steel, screws passing through the two U-shaped steels on opposite sides and evenly distributed, nuts threadedly connected to the outside of the screws, and a plurality of reinforcement blocks fixedly connected to the inside of the U-shaped steel; the fixing steel is provided with two mounting holes for the corresponding screws to pass through.

[0009] By adopting the above technical solution, the use of the positioning component can play an auxiliary supporting and positioning role for the fixed steel, thereby preventing the occurrence of uneven heights.

[0010] Furthermore, the fixing steel and the corresponding connecting steel are vertically arranged, an H shape is formed between the corresponding two fixing steels and the connecting steel, and the triangular steel plates are symmetrically distributed front to back.

[0011] By adopting the above technical solution, the H-shaped structure formed by two parallel fixed steels and a connecting steel vertically arranged between the two fixed steels can be used as the supporting steel of the cement soil continuous wall.

[0012] Furthermore, the front side of the triangular steel plate on the front side is fixedly connected to the back side of the front fixing steel, and the back side of the triangular steel plate on the back side is fixedly connected to the front side of the back fixing steel.

[0013] By adopting the above technical solution, the triangular steel plate can provide additional support for the front and back fixed steels, thereby improving the overall strength.

[0014] Furthermore, the triangular steel plate corresponds to the position of the connecting hole, and the inner side of the connecting hole is circular.

[0015] By adopting the above technical solution, the cement soil continuous wall casting material flowing through the connecting holes can connect various connecting steels.

[0016] Furthermore, the number of the screws is twice the number of the fixing steels, and the corresponding two mounting holes are symmetrically distributed with the corresponding connecting steel as the center.

[0017] By adopting the above technical solution, the screws can be stably set on the fixing steel.

[0018] Furthermore, the front side of the nut on the front side abuts against the back side of the front fixing steel, and the back side of the nut on the back side abuts against the front side of the back fixing steel.

[0019] By adopting the above technical solution, the U-shaped steel can be stably installed on the outside of the fixed steel through the cooperation between the screw and the nut.

[0020] Furthermore, the reinforcement blocks are symmetrically distributed up and down, and the reinforcement blocks are evenly distributed on the inner side of the corresponding U-shaped steel.

[0021] By adopting the above technical solution, the strength of the U-shaped steel can be improved by the reinforcement block, thereby reducing the deformation of the U-shaped steel due to other unstable factors at the construction site.

[0022] Compared with the prior art, the technical solution of this application has the following beneficial effects:

[0023] This type of cement-soil continuous wall structure of equal thickness can minimize the impact of settlement on subsequent construction through the coordinated use of the pillar components on the inner side of the foundation pit body and the positioning components on the top. It can also reduce settlement by increasing the force-bearing area of ​​the supporting steel sections. At the same time, the supporting steel sections are connected so that they can support each other, further preventing the occurrence of uneven heights and greatly reducing the impact on subsequent construction work on the ground. At the same time, it can improve the uniformity and continuity of the formed wall, and can also improve the overall strength and water-stopping capacity of the cement after forming, which is very practical. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] Figure 1 This is a schematic diagram of the structure of this application;

[0025] Figure 2 For this application structure Figure 1 A three-dimensional schematic diagram of the middle connecting steel connection structure;

[0026] Figure 3 For this application structure Figure 1 Top view of the U-shaped steel connection structure.

[0027] In the figure: 1. foundation pit body; 200. pillar assembly; 201. bottom plate; 202. ground nails; 203. fixing steel; 204. connecting steel; 205. connecting hole; 206. triangular steel plate; 300. positioning assembly; 301. U-shaped steel; 302. screws; 303. nuts; 304. mounting holes; 305. reinforcement blocks; 4. cement soil continuous wall casting material. DETAILED DESCRIPTION

[0028] The technical solutions in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, rather than all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present application.

[0029] See also Figure 1-3 The present application provides a technical solution: a cement soil continuous wall structure of equal thickness, comprising a foundation pit body 1, a support assembly 200 for supporting the cement soil wall is installed on the inner side of the foundation pit body 1, a positioning assembly 300 for auxiliary positioning is installed on the top of the support assembly 200, and the interior of the foundation pit body 1 is filled with cement soil continuous wall casting material 4;

[0030] Through the coordinated use of the support assembly 200 on the inner side of the foundation pit body 1 and the positioning assembly 300 on the top, the impact of settlement on subsequent construction can be reduced as much as possible. By increasing the force-bearing area of ​​the supporting steel, the settlement is reduced. At the same time, the various supporting steels are connected so that the supporting steels can support each other, further preventing the occurrence of uneven heights and greatly reducing the impact on subsequent construction work on the ground. At the same time, the uniformity and continuity of the formed wall can be improved, and the overall strength and water-stopping ability of the cement after forming can also be improved, which is very practical.

[0031] In this embodiment, the support assembly 200 is a structure used to strengthen the support of the formed cement soil continuous wall and reduce settlement.

[0032] like Figure 1 , Figure 2 and Figure 3 As shown, the pillar assembly 200 includes a base plate 201 that is evenly distributed and abuts against the bottom of the foundation pit body 1, ground nails 202 that are evenly distributed and fixedly connected to the bottom of the base plate 201, two fixing steels 203 that are evenly connected to the top of the base plate 201, a connecting steel 204 that is fixedly connected between the opposite sides of the two corresponding fixing steels 203, and triangular steel plates 206 that are evenly distributed and fixedly connected to the left and right sides of the connecting steel 204; evenly distributed connecting holes 205 are opened on the right side of the connecting steel 204.

[0033] It should be noted that the fixing steel 203 and the corresponding connecting steel 204 are vertically arranged, and an H shape is formed between the corresponding two fixing steels 203 and the connecting steel 204. The H-shaped structure formed by the two parallel fixing steels 203 and the connecting steel 204 vertically arranged between the two fixing steels 203 can be used as the supporting steel of the cement soil continuous wall. The triangular steel plates 206 are symmetrically distributed front to back, and the front side of the front triangular steel plate 206 is fixedly connected to the back side of the front fixing steel 203, and the back side of the back triangular steel plate 206 is fixedly connected to the front side of the back fixing steel 203. Under the action of the triangular steel plates 206, the front and back fixing steels 203 can be provided with additional support, thereby improving the overall strength.

[0034] In addition, the positions of the triangular steel plate 206 and the connecting hole 205 correspond to each other, so that the triangular steel plate 206 can be used for reinforcement in conjunction with the solidified cement soil continuous wall casting material 4. The inner side of the connecting hole 205 is circular, and the cement soil continuous wall casting material 4 flowing through the connecting hole 205 can connect each connecting steel 204.

[0035] In this embodiment, the positioning assembly 300 is a structure for auxiliary support positioning.

[0036] like Figure 1 , Figure 2 and Figure 3 As shown, the positioning assembly 300 includes two U-shaped steels 301 respectively abutting between the front side of the front fixing steel 203 and the back side of the back fixing steel 203, screws 302 penetrating the opposite sides of the two U-shaped steels 301 and evenly distributed, nuts 303 threadedly connected to the outside of the screws 302, and a plurality of reinforcement blocks 305 fixedly connected to the inside of the U-shaped steel 301; the fixing steel 203 is provided with two mounting holes 304 for the corresponding screws 302 to pass through.

[0037] It should be noted that the number of screws 302 is twice the number of fixing steel 203, and the corresponding two mounting holes 304 are symmetrically distributed with the corresponding connecting steel 204 as the center, so that the screws 302 can be stably set on the fixing steel 203, and the front side of the front nut 303 abuts against the back side of the front fixing steel 203, and the back side of the back nut 303 abuts against the front side of the back fixing steel 203. Through the cooperation between the screws 302 and the nuts 303, the U-shaped steel 301 can be stably installed on the outside of the fixing steel 203.

[0038] In addition, the reinforcement blocks 305 are symmetrically distributed up and down, and the reinforcement blocks 305 are evenly distributed on the inner side of the corresponding U-shaped steel 301. The reinforcement blocks 305 can improve the strength of the U-shaped steel 301, thereby reducing the deformation of the U-shaped steel 301 due to other unstable factors at the construction site.

[0039] The working principle of the above embodiment is:

[0040] When constructing a cement soil continuous wall structure of equal thickness, the foundation pit body 1 is dug out from the ground by means of relevant equipment, and the inner side of the foundation pit body 1 is compacted, the bottom plate 201 is placed inside the foundation pit body 1, and the top of the connecting steel 204 is knocked to insert the ground nails 202 into the ground. Under the action of the bottom plate 201, the force bearing area between the fixing steel 203 and the connecting steel 204 and the bottom of the foundation pit body 1 can be increased. After the bottom plate 201 is set, the cement soil continuous wall casting material 4 is slowly poured inside the foundation pit body 1 to make it flow into each connecting hole 205, and the U-shaped steel 301 is placed on the fixing steel 203 on the same side. Between the front and back sides, screws 302 are inserted into the inside of the mounting holes 304, and nuts 303 are tightened, so that the fixing steel 203 can be connected and fixed with the U-shaped steel 301 through the cooperation between the screws 302 and the nuts 303. The U-shaped steel 301 can play an auxiliary positioning and supporting role for the overall structure. After waiting for the cement soil continuous wall casting material 4 to solidify, the cement soil continuous wall casting material 4 located in the connecting hole 205 can connect the various connecting steels 204 to form a whole, and under the action of the triangular steel plate 206, the overall strength can be further improved, and the construction of the cement soil continuous wall structure of equal thickness can be completed.

[0041] Compared with the prior art, the cement-soil continuous wall structure of equal thickness can reduce the influence of settlement on subsequent construction as much as possible through the coordinated use of the pillar assembly 200 on the inner side of the foundation pit main body 1 and the positioning assembly 300 on the top, and reduces settlement by increasing the force-bearing area of ​​the supporting steel. At the same time, the supporting steels are connected so that the supporting steels can support each other, further preventing the occurrence of uneven heights and greatly reducing the influence on subsequent construction work on the ground. At the same time, the uniformity and continuity of the formed wall can be improved, and the overall strength and water-stopping capacity of the cement after forming can also be improved. It is very practical and solves the shortcomings of the existing cement continuous wall of equal thickness that is prone to settlement during construction and affects the subsequent construction process.

Claims

1. A cement soil continuous wall structure of equal thickness, comprising a foundation pit main body (1), characterized in that: A support assembly (200) for supporting a cement soil wall is installed on the inner side of the foundation pit body (1); a positioning assembly (300) for assisting positioning is installed on the top of the support assembly (200); and the interior of the foundation pit body (1) is filled with cement soil continuous wall casting material (4); The support assembly (200) comprises a base plate (201) abutting against the bottom of the foundation pit body (1) and evenly distributed, ground nails (202) fixedly connected to the bottom of the base plate (201) and evenly distributed, two fixing steels (203) fixedly connected to the top of the base plate (201), a connecting steel (204) fixedly connected between opposite sides of the two corresponding fixing steels (203), and triangular steel plates (206) fixedly connected to the left and right sides of the connecting steels (204) and evenly distributed; evenly distributed communication holes (205) are opened on the right side of the connecting steel (204).

2. The cement soil continuous wall structure of equal thickness according to claim 1, characterized in that: The positioning assembly (300) comprises two U-shaped steels (301) respectively abutting between the front sides of the front fixing steels (203) and the back sides of the back fixing steels (203), screws (302) penetrating the two U-shaped steels (301) on opposite sides and evenly distributed, nuts (303) threadedly connected to the outsides of the screws (302), and a plurality of reinforcing blocks (305) fixedly connected to the insides of the U-shaped steels (301); the fixing steels (203) are provided with two mounting holes (304) for the corresponding screws (302) to penetrate.

3. The cement soil continuous wall structure of equal thickness according to claim 1, characterized in that: The fixing steels (203) and the corresponding connecting steels (204) are arranged vertically, an H shape is formed between the corresponding two fixing steels (203) and the connecting steels (204), and the triangular steel plates (206) are symmetrically distributed frontward and rearward.

4. The cement soil continuous wall structure of equal thickness according to claim 1, characterized in that: The front side of the triangular steel plate (206) on the front side is fixedly connected to the back side of the front fixing steel (203), and the back side of the triangular steel plate (206) on the back side is fixedly connected to the front side of the back fixing steel (203).

5. The cement soil continuous wall structure of equal thickness according to claim 1, characterized in that: The triangular steel plate (206) corresponds to the position of the communication hole (205), and the inner side of the communication hole (205) is circular.

6. The cement soil continuous wall structure of equal thickness according to claim 2, characterized in that: The number of the screws (302) is twice the number of the fixing steel (203), and the corresponding two mounting holes (304) are symmetrically distributed with the corresponding connecting steel (204) as the center.

7. The cement soil continuous wall structure of equal thickness according to claim 2, characterized in that: The front side of the nut (303) abuts against the back side of the front fixing steel (203), and the back side of the nut (303) abuts against the front side of the back fixing steel (203).

8. The cement soil continuous wall structure of equal thickness according to claim 2, characterized in that: The reinforcement blocks (305) are distributed symmetrically up and down, and the reinforcement blocks (305) are evenly distributed on the inner side of the corresponding U-shaped steel (301).