Primary support concrete core drilling equipment suitable for small-section oil pipe tunnel
By designing a primary concrete core drilling equipment suitable for small-section oil pipe tunnels, the problem of construction quality inspection in small-section tunnels is solved, efficient and stable drilling and dregs dust protection is achieved, and construction safety and efficiency are improved.
Patent Information
- Application Number
- CN202420441834.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-07
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2034-03-07
AI Technical Summary
During the construction of small-section oil pipe tunnels, existing large core drilling equipment cannot be used, resulting in the inability to effectively detect the quality of the tunnel construction, which poses safety hazards.
A first-support concrete drilling core equipment including a fixed support, a compensation slide rod, a rotating motor, a rotating fixing rod and a drill bit is designed. The fixed support is connected to the side wall of the tunnel through the fixed support, and the compensation slide rod and a rotating fixing rod are used to realize the equipment. Stable movement and drilling, equipped with protective plates to prevent dust from falling, adapting to the operating space and operation needs of small-section tunnels.
It realizes efficient, accurate and stable drill core detection in small-section tunnels, simplifies operations, and improves construction safety and efficiency.
Smart Images

Figure CN222101955U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of primary support concrete core drilling, and more specifically, to a primary support concrete core drilling device suitable for small-section oil pipe tunnels. Background Art
[0002] For tunnel engineering, one of the most concerned issues is the quality of tunnel construction - the strength of shotcrete. This is self-evident, because the quality of tunnel construction determines the size of the tunnel's safety hazards.
[0003] After tunnel excavation, physical inspection is an essential part, and concrete core drilling inspection is the most direct way to inspect the physical quality. In the construction of small-section oil pipeline tunnels, due to the small tunnel section, large core drilling equipment cannot be used, and only small equipment can be used. Therefore, large core drilling equipment is not suitable for small-section oil pipeline tunnels. Utility Model Content
[0004] In order to achieve these purposes and other advantages according to the utility model, a preferred embodiment of the utility model provides a primary support concrete core drilling device suitable for a small-section oil pipe tunnel, comprising:
[0005] Fixed support;
[0006] A compensating slide rod, one end of which is vertically connected to the fixed support, and a surface of the compensating slide rod is provided with threads;
[0007] A rotating motor, the rotatable thread sleeve of which is mounted on the compensating slide rod;
[0008] A rotating fixed rod, which is fixedly mounted on the rotating motor;
[0009] The drill bit is mounted on the output shaft of the rotary motor, and the drill bit rotates along with the rotation of the rotary motor.
[0010] According to a preferred embodiment of the utility model, a hand-held handle is provided on the compensation slide bar.
[0011] According to a preferred embodiment of the present utility model, a handle is installed at one end of the compensating slide rod away from the fixed support.
[0012] According to a preferred embodiment of the present invention, a side surface of the fixed support away from the compensating slide bar is an arc surface, and a concave side of the arc surface faces the compensating slide bar.
[0013] According to a preferred embodiment of the utility model, the drill bit includes a drill rod, a drill head and a protective plate, one end of the drill rod is connected to the output shaft of the rotary motor, the drill head is coaxially installed at the end of the drill rod away from the rotary motor, the protective plate is sleeved on the drill rod, and the protective plate is a disc-shaped structure.
[0014] According to a preferred embodiment of the utility model, a circle of protective baffles are installed around the protective plate.
[0015] According to a preferred embodiment of the present utility model, an anti-sliding block is provided on a side surface of the fixed support away from the compensating sliding rod.
[0016] The utility model at least includes the following beneficial effects: the primary support concrete core drilling equipment of the utility model can adapt to the limitations of the working space of a small-section tunnel, has small requirements for the working space, is easy to operate, convenient to move, has accurate drilling and core drilling, good stability, and is simple and labor-saving to operate.
[0017] Other advantages, objectives and features of the present invention will be embodied in part through the following description, and in part will be understood by those skilled in the art through research and practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 It is a structural schematic diagram of the primary support concrete core drilling equipment in a technical solution of the utility model.
[0019] Figure 2 It is a structural schematic diagram of a drill bit in another technical solution of the utility model. DETAILED DESCRIPTION
[0020] The present invention will be further described in detail below in conjunction with the accompanying drawings so that those skilled in the art can implement the invention with reference to the description.
[0021] The following description is used to disclose the utility model so that those skilled in the art can implement the utility model. The preferred embodiments described below are only examples, and those skilled in the art can think of other obvious variations. The basic principles of the utility model defined in the following description can be applied to other embodiments, variations, improvements, equivalents, and other technical solutions that do not deviate from the spirit and scope of the utility model.
[0022] Those skilled in the art should understand that, in the disclosure of the present invention, the terms "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship are based on the orientation or position relationship shown in the drawings, which are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation. Therefore, the above terms should not be understood as limiting the present invention.
[0023] It is to be understood that the term "one" should be understood as "at least one" or "one or more", that is, in one embodiment, the number of an element may be one, while in another embodiment, the number of the element may be multiple, and the term "one" should not be understood as a limitation on the quantity.
[0024] like Figure 1-2 As shown, a preferred embodiment of the utility model provides a primary support concrete core drilling device suitable for a small-section oil pipe tunnel, comprising:
[0025] Fixed support 1;
[0026] A compensating slide rod 2, one end of which is vertically connected to the fixed support 1, and a surface of the compensating slide rod 2 is provided with threads;
[0027] The motor 3 is rotatably threaded and mounted on the compensating slide rod 2.
[0028] A rotating fixed rod 4, which is fixedly mounted on the rotating motor 3;
[0029] The drill bit 5 is mounted on the output shaft of the rotary motor 3 , and as the rotary motor 3 rotates, the drill bit 5 rotates accordingly.
[0030] In the above technical solution, the fixed support 1 is fixed to the side wall of the tunnel by expansion bolts as the main force support. The rotating fixed rod 4, the rotating motor 3, and the drill bit 5 are a whole, which can be rotated up and down on the compensating slide bar 2. During the drilling process, the construction personnel hold the entire equipment by hand to ensure the overall stability, and realize the overall movement on the compensating slide bar 2 for drilling by rotating the rotating fixed rod 4; after the drill bit drills to a certain depth, the fixed rod 4 is rotated back to realize the overall outward movement, and the coring is completed.
[0031] According to a preferred embodiment of the utility model, a hand-held handle 6 is provided on the compensating slide bar 2 for holding during drilling operation to maintain the stability of the entire device.
[0032] According to a preferred embodiment of the present invention, a handle 7 is installed at one end of the compensating slide bar 2 away from the fixed support 1, so as to facilitate lifting the entire device by hand.
[0033] According to a preferred embodiment of the utility model, the side surface of the fixed support 1 away from the compensating slide bar 2 is an arc surface, and the concave side of the arc surface faces the compensating slide bar 2. This is because considering that the tunnel side wall is arc-shaped, the side of the fixed support 1 in contact with the tunnel side wall is set to be arc-shaped, which is more suitable.
[0034] According to a preferred embodiment of the utility model, the drill bit 5 includes a drill rod 5-1, a drill head 5-2 and a protective plate 5-3, one end of the drill rod 5-1 is connected to the output shaft of the rotary motor 3, the drill head 5-2 is coaxially installed at the end of the drill rod 5-1 away from the rotary motor, and the protective plate 5-3 is sleeved on the drill rod, and the protective plate is a disc-shaped structure.
[0035] In the above technical solution, the front end of the drill head 5-2 is sharp and rotates to drill. When drilling a hole directly above the primary support, a lot of residue and dust will inevitably fall and fall on the operator. A protective plate is used here to receive the residue and dust to prevent it from falling directly on the operator.
[0036] According to a preferred embodiment of the utility model, a circle of protective baffles 5-4 are installed around the protective plate to prevent slag and dust from falling from the side of the protective plate as much as possible.
[0037] According to a preferred embodiment of the utility model, an anti-sliding block is provided on a side surface of the fixed support away from the compensating slide rod, which can increase the friction between the fixed support and the primary support and prevent the fixed support 1 from moving during the drilling process.
[0038] Although the implementation scheme of the utility model has been disclosed as above, it is not limited to the applications listed in the specification and implementation modes. It can be fully applied to various fields suitable for the utility model. For those familiar with the art, additional modifications can be easily implemented. Therefore, without departing from the general concept defined by the claims and the scope of equivalents, the utility model is not limited to the specific details and the illustrations shown and described herein.
Claims
1. A primary concrete core drilling device suitable for small-section oil pipe tunnels, characterized in that: include: Fixed support; A compensating slide rod, one end of which is vertically connected to the fixed support, and a surface of the compensating slide rod is provided with threads; A rotating motor, the rotatable thread sleeve of which is mounted on the compensating slide rod; A rotating fixed rod, which is fixedly mounted on the rotating motor; The drill bit is mounted on the output shaft of the rotary motor, and the drill bit rotates along with the rotation of the rotary motor.
2. The primary support concrete core drilling equipment suitable for small-section oil pipeline tunnels according to claim 1 is characterized in that: A hand-held handle is arranged on the compensation slide bar.
3. The primary support concrete core drilling equipment suitable for small-section oil pipeline tunnels according to claim 1 is characterized in that: A handle is installed at one end of the compensation slide bar away from the fixed support.
4. The primary support concrete core drilling equipment suitable for small-section oil pipeline tunnels according to claim 1 is characterized in that: A side surface of the fixed support away from the compensation sliding rod is an arc surface, and a concave side of the arc surface faces the compensation sliding rod.
5. The primary support concrete core drilling equipment suitable for small-section oil pipeline tunnels according to claim 1 is characterized in that: The drill bit includes a drill rod, a drill head and a protective plate. One end of the drill rod is connected to the output shaft of the rotary motor. The drill head is coaxially installed on the end of the drill rod away from the rotary motor. The protective plate is sleeved on the drill rod and is a disc-shaped structure.
6. The primary support concrete core drilling equipment suitable for small-section oil pipeline tunnels according to claim 5 is characterized in that: A circle of protective baffles are installed around the protective plate.
7. The primary support concrete core drilling equipment suitable for small-section oil pipeline tunnels according to claim 5 is characterized in that: An anti-sliding block is provided on a side surface of the fixed support away from the compensating sliding rod.