Efficient tunnel construction equipment

By combining a full-section rock tunnel boring machine and mixer, the gravel transport device and screening machine are used to mix gravel with sand and cement to form concrete, which solves the problem of low efficiency of gravel and concrete transportation in traditional tunnel construction and achieves high efficiency Construction and cost savings.

CN222102036UActive Publication Date: 2024-12-03HUADIAN HEAVY IND CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420289616.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-08
Publication Date
2024-12-03
Estimated Expiration
2034-02-08

AI Technical Summary

Technical Problem

In the construction of the pumping and storage power station tunnel, the traditional full-section rock tunnel boring machine needs to transport gravel and concrete from outside the hole to the hole, resulting in high construction costs, low efficiency, and affecting construction efficiency.

Method used

Design an efficient tunnel construction equipment, combines a full-section rock tunnel boring machine and a mixer, and use a gravel transport device and a screening machine to siev the excavated gravel and directly transport it to the mixer for mixing with sand and cement to form concrete. Reduce materials transported from abroad and improve construction efficiency.

Benefits of technology

By using local materials to excavate broken stones, unnecessary processes for conveying gravel and concrete are reduced, construction costs are reduced, construction efficiency and convenience are improved, transportation weight is reduced, and transportation capacity is saved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222102036U_ABST
    Figure CN222102036U_ABST
Patent Text Reader

Abstract

The utility model discloses efficient tunnel construction equipment which comprises a full-section rock tunnel boring machine and a stirring machine, one end of a rock ballast conveying device is arranged at the tail of the full-section rock tunnel boring machine, a screening machine is arranged at the other end of the rock ballast conveying device, the output end of the screening machine is connected with a feeding port of the stirring machine, and the discharging port of the stirring machine is connected with a discharging port of the tunnel boring machine. And the output end of the stirrer is connected with the full-section rock tunnel boring machine. According to the utility model, local materials are used, excavated and crushed stone blocks are utilized, sand, cement and water which are conveyed externally and rock ballast crushed by the full-section rock tunnel boring machine are stirred by using the in-hole stirrer to prepare concrete, the unnecessary working procedure of externally conveying the rock ballast is saved, the equipment is saved, and the construction efficiency is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to high-efficiency tunnel construction equipment, belonging to the technical field of tunnel construction equipment. Background Art

[0002] There are many underground caverns in pumped storage power stations, including water diversion tunnels and tailwater tunnels, as well as auxiliary caverns, such as traffic tunnels, construction tunnels, ventilation tunnels, drainage tunnels, etc. These caverns are relatively long, usually 0.5 to 2 km, and usually have engineering characteristics such as good surrounding rock integrity, dense and hard rock, and long distance.

[0003] The traditional full-section rock tunnel boring machine is a large-scale special equipment that relies on the rotation of hard rock cutter disc to break rock and advance, and simultaneously carries out tunnel support and slag discharge, and forms the entire section of the tunnel in one go. It integrates tunneling, support, slag discharge and transportation, and has good economic benefits when continuously excavating long tunnels.

[0004] In the prior art, a full-section rock tunnel boring machine transports the excavated slag to the outside of the tunnel through a belt conveyor at the tail. For pumped-storage power station tunnels, especially water diversion and tailwater tunnels, it is necessary to install a concrete lining on the inside of the rock tunnel after excavation, or to backfill and grout between the steel pipe lining and the tunnel. These require the concrete to be transported from outside the tunnel to inside the tunnel by a belt conveyor. The transportation of slag to the outside of the tunnel and the transportation of concrete to the inside of the tunnel require the installation of corresponding transportation equipment, which increases construction costs, wastes transportation capacity, is time-consuming and labor-intensive, and affects construction efficiency. Based on the above problems, we propose a high-efficiency tunnel construction equipment to solve the problem of pump material transportation outside and inside the tunnel. Utility Model Content

[0005] The purpose of the utility model is to provide an efficient tunnel construction equipment, which uses excavated and crushed stones as raw materials for grouting slow-setting soil in the tunnel, saving materials transported from outside to inside, and at the same time saving unnecessary processes for transporting slag to the outside, thereby improving construction efficiency and convenience.

[0006] In order to solve the above technical problems, the utility model adopts the following technical solutions: a high-efficiency tunnel construction equipment, including a full-section rock tunnel boring machine and a mixer, wherein the tail of the full-section rock tunnel boring machine is provided with one end of a slag conveying device, and the other end of the slag conveying device is provided with a screening machine, the output end of the screening machine is connected to the feed port of the mixer, and the output end of the mixer is connected to the full-section rock tunnel boring machine;

[0007] It also includes an external conveying device, the output end of which is connected to the feed port of the mixer.

[0008] In the aforementioned efficient tunnel construction equipment, the output end of the screening machine is connected to the feed port of the mixer via a slag pipe.

[0009] In the aforementioned high-efficiency tunnel construction equipment, the output end of the mixer is connected to the full-section rock tunnel boring machine through a concrete pipe.

[0010] The aforementioned high-efficiency tunnel construction equipment, the full-section rock tunnel boring machine includes a main machine, a support system and ancillary devices, the front of the main machine is provided with a support system, the ancillary devices are placed at the rear of the main machine, the rear end of the main machine is provided with a mixing spraying system, the mixing spraying system is connected to a mixer, and the slag conveying device is arranged at the top of the rear end of the main machine.

[0011] The aforementioned efficient tunnel construction equipment, the main machine includes a cutter disc, a head frame, a shield, a drive system, a main beam, a thrust cylinder, a support shoe system and a rear support, the supporting device is placed on the top of the rear support, the slag conveying device and the mixed spraying system are both arranged at the tail end of the rear support, the front end of the rear support is provided with a support shoe system, the front end of the support shoe system is provided with a main beam, the main beam is provided with a thrust cylinder, the front end of the main beam is provided with a drive system, a shield, a head frame and a cutter disc in sequence.

[0012] The aforementioned efficient tunnel construction equipment, the support system includes an anchor drilling rig and a sprayed anchor system, the anchor drilling rig and the sprayed anchor system are both arranged on the main beam, and the sprayed anchor system is placed at the tail of the driving system, and the anchor drilling rig is placed at the tail of the sprayed anchor system.

[0013] The aforementioned efficient tunnel construction equipment, the supporting devices include a hydraulic power station, a transformer, a distribution cabinet, a cable and water pipe reel, and a dust removal and ventilation equipment, and the hydraulic power station, transformer, distribution cabinet, cable and water pipe reel, and dust removal and ventilation equipment are all arranged on the rear support.

[0014] The aforementioned efficient tunnel construction equipment, wherein the screening machine is equipped with a crushing device.

[0015] The aforementioned efficient tunnel construction equipment, wherein a traveling device is provided at the bottom of the mixer.

[0016] The aforementioned efficient tunnel construction equipment has supporting devices arranged around the bottom of the mixer, the supporting devices comprising a hydraulic telescopic device and a base, the top end of the hydraulic telescopic device is arranged at the bottom of the mixer, and the bottom end of the hydraulic telescopic device is arranged with a base.

[0017] Compared with the prior art, the utility model uses local materials, utilizes excavated and crushed stones, and utilizes an in-tunnel mixer to mix sand, cement, and water transported from the outside with the slag crushed by a full-section rock tunnel boring machine to make concrete, thereby saving the unnecessary process of transporting slag from outside, saving equipment, and improving construction efficiency; at the same time, the raw materials are transported into the tunnel, and the mixing amount and mixing time of the concrete can be controlled in real time according to the excavation speed, thereby improving construction convenience; and the weight of materials transported from the outside to the inside is reduced, thereby saving transportation capacity. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 It is a structural schematic diagram of the utility model;

[0019] Figure 2 It is a schematic diagram of the structure of the mixer of the utility model.

[0020] Figure numerals: 1-full-section rock tunnel boring machine, 2-mixer, 3-slag conveying device, 4-screening machine, 5-external conveying device, 6-slag pipeline, 7-concrete pipeline, 8-main machine, 9-support system, 10-supporting device, 11-mixing spraying system, 12-cutter head, 13-head frame, 14-shield, 15-drive system, 16-main beam, 17-thrust cylinder, 18-support shoe system, 19-rear support, 20-anchor drilling rig, 21-spraying anchor system, 22-traveling device, 23-support device, 24-hydraulic telescopic device, 25-base.

[0021] The utility model is further described below in conjunction with the accompanying drawings and specific implementation methods. DETAILED DESCRIPTION

[0022] Embodiment 1 of the utility model: A tunnel high-efficiency construction equipment, comprising a full-section rock tunnel boring machine 1 and a mixer 2, wherein the tail of the full-section rock tunnel boring machine 1 is provided with one end of a slag conveying device 3, and the other end of the slag conveying device 3 is provided with a screening machine 4, the output end of the screening machine 4 is connected to the feed port of the mixer 2, and the output end of the mixer 2 is connected to the full-section rock tunnel boring machine 1, the slag mined by the full-section rock tunnel boring machine 1 is transported to the screening machine 4 through the slag conveying device 3, the screening machine 4 screens the slag, and transports the slag that can be used as a concrete raw material into the mixer 2;

[0023] It also includes an external conveying device 5, the output end of which is connected to the feed port of the mixer 2. The external conveying device 5 conveys materials outside the hole to the mixer 2. The external materials include sand, cement, and water. The mixer 2 mixes the sand, cement, water, and screened slag to make concrete.

[0024] Embodiment 2 of the present utility model: A tunnel high-efficiency construction equipment, comprising a full-section rock tunnel boring machine 1 and a mixer 2, wherein the tail of the full-section rock tunnel boring machine 1 is provided with one end of a slag conveying device 3, and the other end of the slag conveying device 3 is provided with a screening machine 4, the output end of the screening machine 4 is connected to the feed port of the mixer 2, and the output end of the screening machine 4 is connected to the feed port of the mixer 2 through a slag pipe 6, the output end of the mixer 2 is connected to the full-section rock tunnel boring machine 1, and the output end of the mixer 2 is connected to the full-section rock tunnel boring machine 1 through a concrete pipe 7, the slag mined by the full-section rock tunnel boring machine 1 is transported to the screening machine 4 through the slag conveying device 3, the screening machine 4 screens the slag, and transports the slag that can be used as a concrete raw material to the mixer 2;

[0025] It also includes an external conveying device 5, the output end of which is connected to the feed port of the mixer 2. The external conveying device 5 conveys materials outside the tunnel to the mixer 2. The external materials include sand, cement, and water. The mixer 2 mixes the sand, cement, water, and screened slag to make concrete, which is used for concrete lining or backfill grouting between the steel pipe lining and the tunnel.

[0026] Embodiment 3 of the present utility model: A tunnel high-efficiency construction equipment, comprising a full-section rock tunnel boring machine 1 and a mixer 2, wherein the tail of the full-section rock tunnel boring machine 1 is provided with one end of a slag conveying device 3, and the other end of the slag conveying device 3 is provided with a screening machine 4, the output end of the screening machine 4 is connected to the feed port of the mixer 2, and the output end of the screening machine 4 is connected to the feed port of the mixer 2 through a slag pipeline 6, the output end of the mixer 2 is connected to the full-section rock tunnel boring machine 1, and the output end of the mixer 2 is connected to the full-section rock tunnel boring machine 1 through a concrete pipeline 7, the slag mined by the full-section rock tunnel boring machine 1 is transported to the screening machine 4 through the slag conveying device 3, the screening machine 4 screens the slag, and transports the slag that can be used as a concrete raw material to the mixer 2;

[0027] It also includes an external conveying device 5, the output end of which is connected to the feed port of the mixer 2. The external conveying device 5 conveys materials outside the tunnel to the mixer 2. The external materials include sand, cement, and water. The mixer 2 mixes the sand, cement, water, and screened slag to make concrete, which is used for concrete lining or backfill grouting between the steel pipe lining and the tunnel.

[0028] The full-section rock tunnel boring machine 1 includes a main machine 8, a support system 9 and an ancillary device 10. The front part of the main machine 8 is provided with a support system 9 to provide initial support and lining for the rock wall after the main machine is excavated. The ancillary device 10 is placed at the rear part of the main machine 8. The rear end of the main machine 8 is provided with a mixing and spraying system 11, and the mixing and spraying system 11 is connected to the mixer 2. The slag conveying device 3 is arranged at the top of the rear end of the main machine 8.

[0029] The main machine 8 includes a cutter disc 12, a head frame 13, a shield 14, a drive system 15, a main beam 16, a thrust cylinder 17, a support shoe system 18 and a rear support 19. The supporting device 10 is placed on the top of the rear support 19. The slag conveying device 3 and the mixed spraying system 11 are both arranged at the tail end of the rear support 19. The front end of the rear support 19 is provided with a support shoe system 18. The front end of the support shoe system 18 is provided with a main beam 16. The main beam 16 is provided with a thrust cylinder 17. The front end of the main beam 16 is provided with a drive system 15, a shield 14, a head frame 13 and a cutter disc 12 in sequence.

[0030] The support system 9 provides initial support and lining for the rock wall after the main engine 8 is excavated. The support system 9 includes an anchor drill 20 and a sprayed anchor system 21. The anchor drill 20 and the sprayed anchor system 21 are both arranged on the main beam 16, and the sprayed anchor system 21 is placed at the tail of the drive system 15, and the anchor drill 20 is placed at the tail of the sprayed anchor system 21.

[0031] The supporting device 10 provides power, wind, water, electricity, gas and other guarantees for the construction of the main machine 8, and provides other auxiliary construction. The supporting device 10 includes a hydraulic power station, a transformer, a distribution cabinet, a cable and water pipe reel, and dust removal and ventilation equipment. The hydraulic power station, transformer, distribution cabinet, cable and water pipe reel, and dust removal and ventilation equipment are all arranged on the rear support 19.

[0032] Embodiment 4 of the present utility model: A tunnel high-efficiency construction equipment, comprising a full-section rock tunnel boring machine 1 and a mixer 2, wherein the tail of the full-section rock tunnel boring machine 1 is provided with one end of a slag conveying device 3, and the other end of the slag conveying device 3 is provided with a screening machine 4, the output end of the screening machine 4 is connected to the feed port of the mixer 2, and the output end of the screening machine 4 is connected to the feed port of the mixer 2 through a slag pipe 6, the output end of the mixer 2 is connected to the full-section rock tunnel boring machine 1, and the output end of the mixer 2 is connected to the full-section rock tunnel boring machine 1 through a concrete pipe 7, the slag mined by the full-section rock tunnel boring machine 1 is transported to the screening machine 4 through the slag conveying device 3, the screening machine 4 screens the slag, and transports the slag that can be used as a concrete raw material to the mixer 2;

[0033] It also includes an external conveying device 5, the output end of which is connected to the feed port of the mixer 2. The external conveying device 5 conveys materials outside the tunnel to the mixer 2. The external materials include sand, cement, and water. The mixer 2 mixes the sand, cement, water, and screened slag to make concrete, which is used for concrete lining or backfill grouting between the steel pipe lining and the tunnel.

[0034] The screening machine 4 is equipped with a crushing device, so that the screening machine 4 has a crushing function, which can further crush large stones and ensure the gradation of concrete raw materials.

[0035] Embodiment 5 of the present utility model: A tunnel high-efficiency construction equipment, comprising a full-section rock tunnel boring machine 1 and a mixer 2, wherein the tail of the full-section rock tunnel boring machine 1 is provided with one end of a slag conveying device 3, and the other end of the slag conveying device 3 is provided with a screening machine 4, the output end of the screening machine 4 is connected to the feed port of the mixer 2, and the output end of the screening machine 4 is connected to the feed port of the mixer 2 through a slag pipe 6, the output end of the mixer 2 is connected to the full-section rock tunnel boring machine 1, and the output end of the mixer 2 is connected to the full-section rock tunnel boring machine 1 through a concrete pipe 7, the slag mined by the full-section rock tunnel boring machine 1 is transported to the screening machine 4 through the slag conveying device 3, the screening machine 4 screens the slag, and transports the slag that can be used as a concrete raw material to the mixer 2;

[0036] It also includes an external conveying device 5, the output end of which is connected to the feed port of the mixer 2. The external conveying device 5 conveys materials outside the tunnel to the mixer 2. The external materials include sand, cement, and water. The mixer 2 mixes the sand, cement, water, and screened slag to make concrete, which is used for concrete lining or backfill grouting between the steel pipe lining and the tunnel.

[0037] The full-section rock tunnel boring machine 1 includes a main machine 8, a support system 9 and an ancillary device 10. The front part of the main machine 8 is provided with a support system 9 to provide initial support and lining for the rock wall after the main machine is excavated. The ancillary device 10 is placed at the rear part of the main machine 8. The rear end of the main machine 8 is provided with a mixing and spraying system 11, and the mixing and spraying system 11 is connected to the mixer 2. The slag conveying device 3 is arranged at the top of the rear end of the main machine 8.

[0038] The main machine 8 includes a cutter disc 12, a head frame 13, a shield 14, a drive system 15, a main beam 16, a thrust cylinder 17, a support shoe system 18 and a rear support 19. The supporting device 10 is placed on the top of the rear support 19. The slag conveying device 3 and the mixed spraying system 11 are both arranged at the tail end of the rear support 19. The front end of the rear support 19 is provided with a support shoe system 18. The front end of the support shoe system 18 is provided with a main beam 16. The main beam 16 is provided with a thrust cylinder 17. The front end of the main beam 16 is provided with a drive system 15, a shield 14, a head frame 13 and a cutter disc 12 in sequence.

[0039] The support system 9 provides initial support and lining for the rock wall after the main engine 8 is excavated. The support system 9 includes an anchor drill 20 and a sprayed anchor system 21. The anchor drill 20 and the sprayed anchor system 21 are both arranged on the main beam 16, and the sprayed anchor system 21 is placed at the tail of the drive system 15, and the anchor drill 20 is placed at the tail of the sprayed anchor system 21.

[0040] The supporting device 10 provides power, wind, water, electricity, gas and other guarantees for the construction of the main machine 8, and provides other auxiliary construction. The supporting device 10 includes a hydraulic power station, a transformer, a distribution cabinet, a cable and water pipe reel, and dust removal and ventilation equipment. The hydraulic power station, transformer, distribution cabinet, cable and water pipe reel, and dust removal and ventilation equipment are all arranged on the rear support 19.

[0041] The screening machine 4 is equipped with a crushing device, so that the screening machine 4 has a crushing function, which can further crush large stones and ensure the gradation of concrete raw materials.

[0042] Specifically, a traveling device 22 is provided at the bottom of the mixer 2, and the traveling device 22 can be a roller, a crawler, or the like.

[0043] Specifically, support devices 23 are arranged around the bottom of the mixer 2, and the support device 23 includes a hydraulic telescopic device 24 and a base 25. The top of the hydraulic telescopic device 24 is arranged at the bottom of the mixer 2, and the bottom of the hydraulic telescopic device 24 is arranged with a base 25. When the hydraulic telescopic device 24 is extended, the base 25 supports the ground and makes the traveling device 22 leave the ground to stabilize the position of the mixer 2. At the same time, the extension lengths of the four hydraulic telescopic devices 24 are adjusted respectively to adjust the level of the mixer 2. When the hydraulic telescopic device 24 is retracted, the traveling device 22 supports the ground and the base 25 is folded upward and leaves the ground to facilitate the movement of the mixer 2.

[0044] The working principle of an embodiment of the utility model is as follows: when the utility model is in use, the full-section rock tunnel boring machine 1 performs mining work, and the slag mined by the full-section rock tunnel boring machine 1 is transported to the screening machine 4 through the slag conveying device 3. The screening machine 4 screens the slag and transports the slag that can be used as concrete raw materials to the mixer 2. Sand, cement, water and other materials outside the tunnel are transported to the mixer 2 through the conveying device 5. The mixer 2 mixes the sand, cement, water and the screened slag to make concrete, which is used for concrete lining or backfill grouting between the steel pipe lining and the tunnel; when the mixer 2 needs to be fixed, the hydraulic telescopic device 24 is extended, the base 25 supports the ground, and the traveling device 22 is lifted off the ground to stabilize the position of the mixer 2, and the level of the mixer 2 can be adjusted by adjusting the extension lengths of the four hydraulic telescopic devices 24 respectively; when the mixer 2 needs to be moved, when the hydraulic telescopic device 24 is retracted, the traveling device 22 supports the ground, and the base 25 is retracted upward and leaves the ground to facilitate the movement of the mixer 2.

Claims

1. A tunnel high-efficiency construction equipment, characterized in that: The invention comprises a full-section rock tunnel boring machine (1) and a mixer (2), wherein the tail of the full-section rock tunnel boring machine (1) is provided with one end of a slag conveying device (3), and the other end of the slag conveying device (3) is provided with a screening machine (4), the output end of the screening machine (4) is connected to the feed port of the mixer (2), and the output end of the mixer (2) is connected to the full-section rock tunnel boring machine (1); It also comprises an external conveying device (5), the output end of the external conveying device (5) is connected to the feed port of the mixer (2).

2. The high-efficiency tunnel construction equipment according to claim 1, characterized in that: The output end of the screening machine (4) is connected to the feed port of the mixer (2) via a slag pipeline (6).

3. The high-efficiency tunnel construction equipment according to claim 2, characterized in that: The output end of the mixer (2) is connected to the full-face rock tunnel boring machine (1) via a concrete pipe (7).

4. The high-efficiency tunnel construction equipment according to claim 1, characterized in that: The full-face rock tunnel boring machine (1) comprises a main machine (8), a support system (9) and a matching device (10), wherein the support system (9) is arranged at the front of the main machine (8), the matching device (10) is arranged at the rear of the main machine (8), a mixing and spraying system (11) is arranged at the rear end of the main machine (8), the mixing and spraying system (11) is connected to a mixer (2), and the slag conveying device (3) is arranged at the top of the rear end of the main machine (8).

5. The high-efficiency tunnel construction equipment according to claim 4, characterized in that: The main machine (8) comprises a cutter disc (12), a head frame (13), a shield (14), a driving system (15), a main beam (16), a propulsion cylinder (17), a support shoe system (18) and a rear support (19); the supporting device (10) is placed on the top of the rear support (19); the slag conveying device (3) and the mixed spraying system (11) are both arranged at the tail end of the rear support (19); the front end of the rear support (19) is provided with a support shoe system (18); the front end of the support shoe system (18) is provided with a main beam (16); the main beam (16) is provided with a propulsion cylinder (17); the front end of the main beam (16) is provided with a driving system (15), a shield (14), a head frame (13) and a cutter disc (12) in sequence.

6. The high-efficiency tunnel construction equipment according to claim 5, characterized in that: The support system (9) comprises an anchor drilling machine (20) and a spray anchor system (21), wherein the anchor drilling machine (20) and the spray anchor system (21) are both arranged on the main beam (16), and the spray anchor system (21) is arranged at the rear of the driving system (15), and the anchor drilling machine (20) is arranged at the rear of the spray anchor system (21).

7. The high-efficiency tunnel construction equipment according to claim 6, characterized in that: The supporting device (10) comprises a hydraulic power station, a transformer, a power distribution cabinet, a cable water pipe drum and a dust removal and ventilation device, and the hydraulic power station, the transformer, the power distribution cabinet, the cable water pipe drum and the dust removal and ventilation device are all arranged on the rear support (19).

8. The high-efficiency tunnel construction equipment according to claim 1, characterized in that: The screening machine (4) is equipped with a crushing device.

9. The high-efficiency tunnel construction equipment according to claim 1, characterized in that: A traveling device (22) is provided at the bottom of the mixer (2).

10. The high-efficiency tunnel construction equipment according to claim 9, characterized in that: Support devices (23) are arranged around the bottom of the mixer (2), and the support device (23) includes a hydraulic telescopic device (24) and a base (25). The top end of the hydraulic telescopic device (24) is arranged at the bottom of the mixer (2), and the bottom end of the hydraulic telescopic device (24) is provided with a base (25).

Citation Information

Cited By

  • Rock slag conveying equipment for tail part of TBM (Tunnel Boring Machine)

    CN119801563A