Coke oven raw gas reformed gas waste heat boiler and dry quenching boiler coupled power generation system

Through the coupled power generation system of the fire tube boiler and the dry quenching coke boiler, the problem of waste heat in the reforming gas of the high-temperature coke oven cannot be recovered, the production of high-pressure hot water and the generation of superheated steam are realized, and the waste heat utilization is utilized by steam turbine power stations. , improves the security and economics of the system.

CN222104492UActive Publication Date: 2024-12-03ACRE COKING & REFRACTORY ENG CONSULTING CORP DALIAN MCC
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420603112.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-27
Publication Date
2024-12-03
Estimated Expiration
2034-03-27

AI Technical Summary

Technical Problem

The extremely flammable and explosive gas reforming gas of high-temperature coke oven waste gas cannot directly enter the washing unit under high temperature conditions, resulting in the inability to effectively recover waste heat and waste energy.

Method used

The power generation system is used to couple the fire tube boiler and the dry quenching coke boiler to produce high-pressure hot water through the high-temperature coke oven waste gas reforming waste heat boiler, and heat it to superheated steam, so as to realize waste heat utilization by steam turbine power stations.

Benefits of technology

It improves the safety and stability of waste heat recovery of high-temperature coke oven waste gas reforming gas, reduces equipment investment and operation costs, and realizes uninterrupted waste heat recovery and utilization.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222104492U_ABST
    Figure CN222104492U_ABST
Patent Text Reader

Abstract

The utility model relates to a coke oven raw gas reformed gas waste heat boiler and dry quenching boiler coupled power generation system, which is characterized in that high-temperature coke oven raw gas reformed gas of each reforming furnace and boiler unit enters a reformed gas waste heat boiler from the reforming furnace, and boiler feed water of the reformed gas waste heat boiler is heated to near saturation temperature by the high-temperature coke oven raw gas reformed gas; the method comprises the following steps: recovering latent heat of high-temperature coke oven raw gas reformed gas, and respectively conveying to a plurality of dry quenching units; and high-temperature and high-pressure superheated steam generated by coupling of the dry quenching unit is fed into the steam turbine power generation unit for power generation. The device has the advantages that the safety and the stability of waste heat recovery of the raw gas reformed gas of the high-temperature coke oven are improved; the reformed gas waste heat boiler is coupled with the dry quenching unit, and waste heat recycling is achieved in a cascade mode. According to the invention, the equipment investment and operation cost are reduced, and uninterrupted waste heat recovery and utilization are realized.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of waste heat recovery and utilization, and particularly relates to a coke oven raw gas reforming gas waste heat boiler and a dry quenching coke boiler coupled power generation system. Background Art

[0002] In the process of directly reforming the high-temperature raw gas from the coking byproduct to produce hydrogen-rich reducing gas, the raw gas from the coke oven is used as the raw gas, and reacts in the reforming furnace to generate high-temperature reformed gas with a temperature of 1200℃~1300℃. The reformed gas at this temperature cannot directly enter the water washing unit, and must be cooled before entering the downstream unit for purification and processing. At the same time, the sensible heat of this part of the reformed gas is very huge, and it will cause great waste if the waste heat is not recovered.

[0003] In the prior art, patent publication number: CN 113955718 A discloses a high-temperature raw gas non-catalytic partial oxidation direct reforming process and system, which directly conducts non-catalytic partial oxidation reforming of the raw gas produced by the coke oven under high temperature, which can not only incompletely oxidize the methane in the raw gas into carbon monoxide and hydrogen, but also convert the tar and crude benzene in the raw gas into carbon monoxide and hydrogen through non-catalytic partial oxidation, greatly improving the yield of reducing gas. However, for the high-temperature coke oven raw gas reforming gas, its main components are hydrogen and carbon monoxide, which are extremely flammable and explosive gases, and the entire process flow is a negative pressure operation, so it is necessary to ensure the sealing of each part of the system in the entire process. In addition, since the raw gas drawn from the coke oven has been reacted in the reforming furnace, the dust concentration in the high-temperature reforming gas is not high.

[0004] According to the characteristics of the high-temperature coke oven raw gas reforming gas, necessary measures are taken to stably and effectively cool the reforming gas to achieve safe and efficient operation of the process; at the same time, combined with the upstream and downstream processes of coking, appropriate waste heat recovery methods are selected to achieve efficient energy utilization at low cost. Summary of the invention

[0005] The utility model aims to provide a power generation system of a coke oven raw gas reforming gas waste heat boiler and a coke dry quenching boiler coupled to produce high-pressure hot water to recover the latent heat of high-temperature coke oven raw gas reforming gas, and coupled with a coke oven dry quenching unit to heat the hot water to superheated steam, thereby realizing waste heat utilization by using a steam turbine power station.

[0006] To achieve the above purpose, the utility model is implemented through the following technical solutions:

[0007] A coke oven raw gas reforming gas waste heat boiler and a dry coke quenching boiler coupling power generation system, comprising a plurality of reforming furnaces and boiler units, a plurality of dry coke quenching units, the plurality of reforming furnaces and boiler units are connected to the plurality of dry coke quenching units, the dry coke quenching units comprising a dry coke quenching boiler feed water pipeline, a dry coke quenching boiler cooling water pipeline, a dry coke quenching boiler economizer, a dry coke quenching boiler evaporator, a dry coke quenching boiler primary superheater, a dry coke quenching boiler secondary superheater, a dry coke quenching boiler drum, a dry coke quenching boiler water spray desuperheater, and a pipeline mixer; the dry coke quenching boiler feed water pipeline Two routes, respectively entering the dry quenching boiler economizer from the dry quenching boiler feed water pipeline, and entering the pipeline mixer from the dry quenching boiler desuperheating water pipeline; the dry quenching boiler economizer is connected to the dry quenching boiler water spray desuperheater, the dry quenching boiler water spray desuperheater is connected to the dry quenching boiler drum, the dry quenching boiler evaporator is connected to the dry quenching boiler drum, the pipeline mixer is connected to the dry quenching boiler primary superheater and secondary superheater, the dry quenching boiler primary superheater is connected to the dry quenching boiler drum, and the dry quenching boiler secondary superheater is connected to the steam turbine power generation unit;

[0008] The hot water pipeline of the high-temperature coke oven raw gas reforming gas waste heat boiler is connected to the dry quenching boiler water spray desuperheater of each dry quenching unit.

[0009] The reforming furnace and boiler unit also includes a coke oven raw gas reforming furnace, and the coke oven raw gas reforming furnace is connected to the high-temperature coke oven raw gas reforming gas waste heat boiler via a high-temperature coke oven raw gas reforming gas pipe bundle.

[0010] The high-temperature coke oven raw gas reforming gas waste heat boiler is a fire tube boiler.

[0011] The number of the reforming furnace, boiler unit and dry coke quenching unit is more than 3, and the number of the reforming furnace, boiler unit and dry coke quenching unit is the same.

[0012] The number of the steam turbine power generation units is more than 2.

[0013] Compared with the prior art, the beneficial effects of the utility model are:

[0014] 1. The utility model improves the safety and stability of waste heat recovery of high-temperature coke oven raw gas reforming gas. The reaction center temperature of coke oven raw gas reforming gas in the reforming furnace can reach 2000°C, and the average temperature at the outlet of the reforming furnace is 1250°C; the main components of the reforming gas are H2 and CO, which are extremely flammable and explosive gases, and all the power for the flow of the reforming gas comes from the induced draft fan of the downstream section, so the entire reforming gas operates in a negative pressure state. The utility model adopts the method of producing hot water by a fire tube waste heat boiler to recover latent heat, ensuring the safety and stability of the waste heat recovery process. The reforming gas flows inside the tube bundle of the fire tube boiler, and the jacket of the fire tube boiler is high-pressure hot water for cooling the flue gas. Its outer shell is a pressure vessel, which also ensures that the high-pressure hot water absorbs heat stably and continuously produces. In addition, a regulating valve is set in the water supply pipeline to control the flow rate and thus control the temperature of the produced hot water, further ensuring the efficiency and stability of the cooling process.

[0015] 2. The reforming gas waste heat boiler is coupled with the dry coke quenching unit to realize waste heat recovery in cascade. Using the fire tube boiler to stably produce high-pressure hot water is a relatively safe operation and production method. The fire tube boiler is connected to the dry coke quenching boiler, and the high-temperature coke oven raw gas reforming gas and the dry coke quenching unit are coupled in a "relay" manner to realize waste heat recovery. While cooling different working fluids, the steam and water temperature rise and phase change are completed, and the steam quality is further improved to produce superheated steam that can be used for efficient power generation. Then it enters the steam turbine power generation unit to achieve stable waste heat utilization.

[0016] 3. The utility model reduces equipment investment and operating costs. First, the reformed gas waste heat boiler used in the utility model is a fire tube boiler, and the manufacturing, installation and operating costs are much lower than those of conventional water tube boilers for power generation. The system is simple and easy to maintain and operate. In addition, the coupling of the dry coke quenching unit for waste heat utilization not only realizes the cooling of the coke oven raw gas reformed gas and the dry coke quenching red coke at the same time, but also makes full use of the steam turbine power station and shares the waste heat recovery and utilization costs of different sections.

[0017] 4. The utility model realizes uninterrupted waste heat recovery and utilization. Multiple reforming furnaces and boiler units are set up. When any one unit is under maintenance or accident condition, the cooling and waste heat recovery of high-temperature raw coal gas reforming gas can be guaranteed to be uninterrupted. Multiple dry quenching units are set up to form a full dry quenching system to ensure that any one unit is under maintenance or accident condition, coupled waste heat recovery can be completed uninterruptedly. Two steam turbine power generation units are set up to ensure that any one unit is under maintenance or accident condition, and waste heat utilization can be completed uninterruptedly. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 It is a structural schematic diagram of a power generation system that couples a coke oven raw gas reforming gas waste heat boiler with a dry coke quenching boiler.

[0019] In the figure: 1-reforming furnace 2-tube bundle 3-reforming gas waste heat boiler 4-reforming gas waste heat boiler feed water pipeline 5-reforming gas waste heat boiler hot water pipeline 6-CDQ boiler feed water pipeline 7-CDQ boiler desuperheating water pipeline 8-CDQ boiler economizer 9-CDQ boiler evaporator 10-CDQ boiler primary superheater 11-CDQ boiler secondary superheater 12-CDQ boiler steam drum 13-CDQ boiler water spray desuperheater 14-pipeline mixer 15-steam turbine generator set. DETAILED DESCRIPTION

[0020] The present invention is described in detail below in conjunction with the accompanying drawings of the specification, but it should be noted that the implementation of the present invention is not limited to the following embodiments.

[0021] See Figure 1 The coke oven raw gas reforming gas waste heat boiler 3 is coupled with the dry quenching boiler for power generation, and the latent heat of the high-temperature coke oven raw gas reforming gas is recovered by producing high-pressure hot water, and the coke oven dry quenching unit is coupled to heat the hot water to superheated steam, and then the waste heat is utilized by the steam turbine power station.

[0022] The power generation system of the coke oven raw gas reforming gas waste heat boiler 3 coupled with the dry coke quenching boiler includes 3 reforming furnaces and boiler units, 3 dry coke quenching units, and 2 steam turbine power generation units; the high-temperature coke oven raw gas reforming gas of each reforming furnace and boiler unit enters the reforming gas waste heat boiler 3 from the reforming furnace 1, and the boiler feed water of the reforming gas waste heat boiler 3 is heated to a near saturation temperature by the high-temperature coke oven raw gas reforming gas, and the latent heat of the high-temperature coke oven raw gas reforming gas is recovered and then sent to multiple dry coke quenching units respectively; the high-temperature and high-pressure superheated steam generated by the dry coke quenching unit coupling is sent to the steam turbine power generation unit for power generation. Specifically:

[0023] Each reforming furnace and boiler unit includes a coke oven raw gas reforming furnace 1, and the coke oven raw gas reforming furnace 1 is connected to a high-temperature coke oven raw gas reforming gas waste heat boiler 3 through a tube bundle 2. The reforming gas waste heat boiler 3 is a fire tube boiler, and the reforming gas flows in the tube bundle 2. The jacket of the fire tube boiler is high-pressure hot water for cooling the reforming gas. The shell of the fire tube boiler is a pressure vessel, which ensures that the high-pressure hot water absorbs heat stably and continuously outputs. The lower part of the fire tube boiler is connected to the reforming gas waste heat boiler feed water pipeline 4, and the upper part is connected to the reforming gas waste heat boiler hot water pipeline 5. The reforming gas waste heat boiler hot water pipeline 5 is connected to the dry quenching boiler water spray desuperheater 13 of each dry quenching unit. The reforming gas waste heat boiler feed water pipeline 4 is provided with a regulating valve to control the flow rate and thus control the temperature of the produced hot water, further ensuring that the cooling process is efficient and stable. The tube bundle 2 is connected to the upstream and downstream sections by welding, and the welded pipeline is 100% intact after non-destructive testing to ensure that there is no leakage under the negative pressure operation environment.

[0024] The temperature of the reformed gas reaches 1250°C at the inlet of the reformed gas waste heat boiler 3. The reformed gas after cooling is cooled to 180±20°C. The reformed gas after cooling is sent to the downstream reformed gas water washing unit through the boiler outlet. The reformed gas flow power of the entire system is the negative pressure formed by the induced draft fan of the downstream unit. On the other hand, the boiler feed water (about 14MPa, 104°C) in the reformed gas waste heat boiler 3 is heated to a near-saturated temperature (about 12MPa, 320°C) by the high-temperature reformed gas, and is merged into a main pipe through the reformed gas waste heat boiler hot water pipe 5, and is divided into 3 routes by the main pipe and sent to 3 dry coke quenching units respectively. In this process, the high-temperature coke oven raw gas reformed gas is cooled, and the purpose of latent heat recovery of the reformed gas is also achieved.

[0025] The three reforming furnaces and boiler units operate at 67% load during normal operation. When any one unit is under maintenance or has an accident, the other two units operate at 100% of the rated load, thereby achieving uninterrupted high-temperature reforming gas cooling and high-pressure hot water production.

[0026] There are three dry quenching units in total, forming a complete dry quenching system for coke oven dry quenching. Each dry quenching unit includes a dry quenching boiler water supply pipe 6, a dry quenching boiler cooling water pipe 7, a dry quenching boiler economizer 8, a dry quenching boiler evaporator 9, a dry quenching boiler primary superheater 10, a dry quenching boiler secondary superheater 11, a dry quenching boiler drum 12, a dry quenching boiler water spray desuperheater 13, and a pipeline mixer 14; the dry quenching boiler water supply is divided into two routes, which enter the dry quenching boiler economizer 8 through the dry quenching boiler water supply pipe 6 and enter the pipeline mixer 14 through the dry quenching boiler cooling water pipe 7; the dry quenching boiler economizer 8 is connected to the dry quenching boiler water spray desuperheater 13, and the dry quenching boiler water spray desuperheater 13 is connected to the dry quenching boiler drum 12, and the water spray desuperheater is used to adjust the superheated steam temperature. The dry coke quenching boiler evaporator 9 is connected to the dry coke quenching boiler drum 12, the pipeline mixer 14 is connected to the dry coke quenching boiler primary superheater 10 and secondary superheater, the dry coke quenching boiler primary superheater 10 is connected to the dry coke quenching boiler drum 12, and the dry coke quenching boiler secondary superheater 11 is connected to the steam turbine power generation unit. The three dry coke quenching units constitute full dry quenching, and each unit operates at 67% load during normal operation; when any unit is under maintenance or an accident occurs, the other two units operate at 100% of the rated load, thereby achieving uninterrupted dry coke quenching red coke cooling and superheated steam production.

[0027] The dry coke quenching boiler receives high-temperature circulating gas (~960℃), passes through the dry coke quenching boiler secondary superheater 11, the dry coke quenching boiler primary superheater 10, the dry coke quenching boiler evaporator 9 and the dry coke quenching boiler economizer 8 to cool down to 165℃, and is discharged from the dry coke quenching boiler outlet. On the other hand, the dry coke quenching boiler feed water is sent to the dry coke quenching boiler economizer 8 through the dry coke quenching boiler feed water pipeline 6, and after being heated by the high-temperature circulating gas, it is combined with the high-pressure hot water sent from the reforming furnace and the boiler unit in the mixer, and then combined with the dry coke quenching boiler feed water heated by the dry coke quenching boiler economizer 8 and sent to the dry coke quenching drum for steam-water separation. The saturated steam in the drum is heated again by the dry coke quenching boiler primary and secondary superheaters 10 and 11 to become high-temperature and high-pressure steam (9.81MPa, 540℃), and is sent to the steam turbine power generation unit in three routes. In the CDQ unit, the hot water sent from the reforming furnace and boiler unit is used together with the CDQ boiler feed water as the working fluid to cool the CDQ hot cycle gas and realize the heat recovery of CDQ.

[0028] Two steam turbine power generation units are provided in total, which receive high-temperature and high-pressure steam sent from the CDQ boiler and enter two steam turbine generator sets 15 to generate electricity, thereby realizing the waste heat utilization process stably and efficiently.

[0029] The utility model selects a fire tube boiler as the equipment for recovering the waste heat of the reformed gas of the high-temperature coke oven raw gas. The high-temperature reformed gas flows in the tube bundle 2 in the furnace, which is more conducive to ensuring the gas tightness, preventing the reformed gas that is easy to burn and explode from leaking into the air, realizing the safe and stable operation of the entire process, and also reducing the equipment investment and installation and operation costs. At the same time, according to the characteristics of the fire tube boiler, high-pressure hot water is selected to achieve more stable heat recovery.

[0030] The utility model produces high-pressure hot water to recover latent heat while cooling the high-temperature coke oven raw gas reforming gas, and introduces the high-pressure hot water into the dry quenching boiler of the full dry quenching system, so that the reforming furnace and boiler system are coupled with the dry quenching system for heat recovery and utilization, and finally generates superheated steam to enter the steam turbine power generation unit for power generation. The utility model disassembles and reorganizes the system, fully utilizes the waste heat of each part, realizes safe and stable cooling of the working medium in each section, and completes the full recovery and utilization of waste heat.

Claims

1. A coke oven raw gas reforming gas waste heat boiler and a coke dry quenching boiler coupled power generation system, It is characterized in that It includes multiple reforming furnaces and boiler units, multiple dry coke quenching units, and steam turbine power generation units. Each reforming furnace and boiler unit is equipped with a reforming gas waste heat boiler. The high-temperature coke oven raw gas reforming gas enters the reforming gas waste heat boiler from the reforming furnace. The boiler feed water in the reforming gas waste heat boiler is heated to a nearly saturated temperature by the high-temperature reforming gas and is sent to multiple dry coke quenching units respectively; the dry coke quenching units are coupled to generate high-temperature and high-pressure superheated steam, which is then sent to the steam turbine power generation unit for power generation.

2. A coke oven raw gas reforming gas waste heat boiler and a coke dry quenching boiler coupled power generation system according to claim 1, It is characterized in that The dry coke quenching unit comprises a dry coke quenching boiler water supply pipeline, a dry coke quenching boiler cooling water pipeline, a dry coke quenching boiler economizer, a dry coke quenching boiler evaporator, a dry coke quenching boiler primary superheater, a dry coke quenching boiler secondary superheater, a dry coke quenching boiler drum, a dry coke quenching boiler water spray desuperheater, and a pipeline mixer; the dry coke quenching boiler water supply pipeline is divided into two routes, which respectively enter the dry coke quenching boiler economizer through the dry coke quenching boiler water supply pipeline and enter the pipeline mixer through the dry coke quenching boiler cooling water pipeline; the dry coke quenching boiler economizer is connected to the dry coke quenching boiler water spray desuperheater, the dry coke quenching boiler water spray desuperheater is connected to the dry coke quenching boiler drum, the dry coke quenching boiler evaporator is connected to the dry coke quenching boiler drum, the pipeline mixer is connected to the dry coke quenching boiler primary superheater and secondary superheater, the dry coke quenching boiler primary superheater is connected to the dry coke quenching boiler drum, and the dry coke quenching boiler secondary superheater is connected to the steam turbine power generation unit; The hot water pipeline of the high-temperature coke oven raw gas reforming gas waste heat boiler is connected to the dry quenching boiler water spray desuperheater of each dry quenching unit.

3. A coke oven raw gas reforming gas waste heat boiler and a coke dry quenching boiler coupled power generation system according to claim 1, It is characterized in that The reforming furnace and boiler unit also includes a coke oven raw gas reforming furnace, and the coke oven raw gas reforming furnace is connected to the high-temperature coke oven raw gas reforming gas waste heat boiler via a high-temperature coke oven raw gas reforming gas pipe bundle.

4. A coke oven raw gas reforming gas waste heat boiler and a coke dry quenching boiler coupled power generation system according to claim 1, It is characterized in that The high-temperature coke oven raw gas reforming gas waste heat boiler is a fire tube boiler.

5. A coke oven raw gas reforming gas waste heat boiler and a coke dry quenching boiler coupled power generation system according to claim 1, It is characterized in that The number of the reforming furnace and boiler units is the same as that of the dry coke quenching units.

6. A coke oven raw gas reforming gas waste heat boiler and a coke dry quenching boiler coupled power generation system according to claim 1, It is characterized in that The number of the reforming furnace, boiler unit and dry coke quenching unit is more than 3.

7. A coke oven raw gas reforming gas waste heat boiler and a coke dry quenching boiler coupled power generation system according to claim 1, It is characterized in that The number of the steam turbine power generation units is more than 2.