Temperature and humidity control dry and wet circulation box suitable for soil test
By designing an automated temperature-controlled wet and dry cycle box in geotechnical tests, using PLC controller and sensor automatic control device, the problem of low manual control efficiency in the existing technology is solved, and efficient and accurate dry cycle test is achieved .
Patent Information
- Application Number
- CN202420636374.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-29
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2034-03-29
AI Technical Summary
Existing dry and wet cycle experiments require manual control of relevant parameters and device opening and closing, resulting in low test efficiency and accuracy.
A temperature-controlled, wet and dry circulation box is designed, using a PLC controller and sensor automatic control rotor dehumidification device, a temperature-controlled atomization device and a temperature-controlled blower device to achieve automatic operation through the control panel setting parameters.
It improves the test efficiency and accuracy, reduces manual intervention, ensures accurate control of temperature and humidity, and enhances the degree of automation of the test.
Smart Images

Figure CN222105863U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the field of geotechnical tests, and in particular relates to a temperature-controlled and humidity-controlled dry-wet cycle box suitable for geotechnical tests. Background Art
[0002] In engineering construction, temperature and humidity often change due to different factors, such as groundwater level changes, climate change, etc., which lead to obvious humidity changes in the soil of backfill, slope, roadbed and other projects in a short period of time. Therefore, it is more important to simulate both dry-wet cycles and soil conditions at actual temperatures. It can help engineers better predict the performance and life of materials, thereby ensuring the quality of the project. The purpose of simulating dry-wet cycles in geotechnical tests is to evaluate the durability of materials under different humidity conditions. Dry-wet cycles refer to the process in which materials undergo alternating dryness and wetness in a constantly changing humidity environment. Such environmental conditions may cause expansion, contraction, cracking and other problems in the material, affecting the performance and life of the material. By simulating dry-wet cycles, we can better understand the impact of environmental changes that materials may encounter in actual use on their performance. This helps to evaluate the durability, stability and reliability of materials, guide engineering design and material selection, and ensure the safety and reliability of engineering structures.
[0003] However, existing dry-wet cycle experiments mostly require manual control of relevant parameters and the opening and closing of various devices, which greatly reduces the test efficiency and the accuracy of the test results. Therefore, there is a need for a temperature-controlled and humidity-controlled dry-wet cycle box suitable for geotechnical tests with high test efficiency and high test result accuracy. Utility Model Content
[0004] The utility model provides a temperature-controlled and humidity-controlled dry-wet circulation box suitable for geotechnical tests in order to solve the deficiencies in the prior art. The utility model comprises a rotary dehumidification device, a temperature-controlled atomization device, a temperature-controlled blowing device and a PLC controller electrically connected to each device to control the opening and closing of each device, and a plurality of sample supports, temperature sensors and humidity sensors are arranged inside the box. The temperature sensor and humidity sensor signals are connected to the PLC controller, and the temperature sensor, humidity sensor and the PLC controller are electrically connected to the control panel, so as to realize automatic measurement of the moisture content of the sample, and automatically control the opening and closing of each device according to the temperature and humidity set on the control panel during the test to achieve the test purpose. There is no need for test personnel to open or close each device based on experience, thereby improving the test efficiency and the accuracy of the test results, and effectively solving the technical problems of low efficiency and low test accuracy of existing manual tests.
[0005] In order to solve the above technical problems, the utility model adopts the following technical solutions:
[0006] A temperature-controlled and humidity-controlled dry-wet cycle box suitable for geotechnical tests comprises a box body, a control panel and a box door are arranged on the front of the box body, a PLC controller is built in the control panel, a temperature-insulating cavity is arranged between the inner wall and the outer wall of the other sides of the box body, a corresponding rotary dehumidification device, a temperature-controlled atomization device, and a temperature-controlled blasting device are installed in the temperature-insulating cavity, and the rotary dehumidification device, the temperature-controlled atomization device, and the temperature-controlled blasting device are all electrically connected to the PLC controller;
[0007] A plurality of sample supports, temperature sensors and humidity sensors are arranged inside the box. The temperature sensor and humidity sensor signals are connected to the PLC controller, and the temperature sensor, humidity sensor and the PLC controller are electrically connected to the control panel.
[0008] An exhaust fan connected to the inside and outside of the box is arranged on the top of the box, and a bubble level is installed on the outside of the top of the box;
[0009] An air inlet is arranged at the bottom of the box, and feet with leveling bolts are installed at the four outer corners of the bottom.
[0010] The temperature-controllable atomizing device comprises a temperature-controlled heat-insulating water storage tank and an atomizing nozzle connected to the inside of the tank. A water inlet is arranged on the tank. The temperature-controllable atomizing device is connected to the water inlet equipment outside the tank through a water inlet pipe passing through the water inlet.
[0011] A weighing sensor is installed at the bottom of the sample support, and the material of the sample support is silicon oxide fiber material.
[0012] The door is provided with a rotating door handle. The middle part of the door is made of double-layer thickened glass for observing the internal situation of the box. The edge of the door is installed with sealing strips corresponding to the box.
[0013] The control panel is provided with a switch button, a moisture content setting button, a time setting button, a temperature setting button, a dry mass setting button and a dry-wet cycle number setting button.
[0014] The rotary dehumidification device comprises a dehumidifier and a dehumidification pipeline connected to the inside of the box.
[0015] The temperature-controllable air blowing device is connected to the interior of the box through an air supply duct.
[0016] The outer wall of the box is composed of a stainless steel anti-corrosion layer, an electrolytic grinding layer, a thickened insulation layer, and an electrostatically sprayed stainless steel layer from the inside to the outside.
[0017] There are two air inlets, four temperature sensors and four humidity sensors, which are respectively arranged on the top, left side, right side and rear side of the box body. There is one temperature-controllable blowing device and two temperature-controllable atomizing devices, and each temperature-controllable atomizing device is equipped with four atomizing nozzles.
[0018] By adopting the above technical scheme, when the utility model is used, it is firstly leveled by means of the feet with leveling bolts installed at the four outer corners of the bottom of the box body in conjunction with the bubble level, so that the bubble of the bubble level is centered to ensure that the box body is in a horizontal state, and then the box door is opened by the rotary door handle, the sample is placed on the sample support, and the test can be carried out by turning on the corresponding switch on the control panel. During the process, after the test personnel set the corresponding parameters through the control panel, there is no need to manually control the opening and closing of each device. The temperature sensor, humidity sensor and the corresponding PLC controller automatically control the opening and closing of each device according to the parameters set on the control panel to complete the test, thereby improving the test efficiency and test accuracy.
[0019] To sum up, the utility model has a simple structure, is convenient and fast, and has high feasibility. The test personnel only need to set the relevant parameters of the test through the control panel. There is no need to manually control the opening and closing of each device during the test. It is convenient and fast, improves the test efficiency and test accuracy, and effectively solves the technical problems of low efficiency and low test accuracy of existing manual tests. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 It is a structural schematic diagram of the control panel and the box door of the utility model;
[0021] Figure 2 It is a schematic diagram of the top view of the structure of the utility model in which an exhaust fan is installed on the top of the box;
[0022] Figure 3 It is a schematic diagram of the structure of the bottom installation foot of the box body of the utility model when viewed from above;
[0023] Figure 4 It is a schematic diagram of the elevation structure of the sample support inside the box of the utility model;
[0024] Figure 5 It is an enlarged schematic diagram of the outer wall of the box body of the utility model;
[0025] Figure 6 It is a schematic diagram of the distribution of temperature sensors and humidity sensors inside the box of the utility model;
[0026] Figure 7 It is a schematic diagram of installing various devices in the thermal insulation cavity of the utility model. DETAILED DESCRIPTION
[0027] The following is a further description of the embodiments of the present invention in conjunction with the accompanying drawings.
[0028] like Figure 1-7As shown, the utility model is a temperature-controlled and humidity-controlled dry-wet cycle box suitable for geotechnical tests, comprising a box body 1, a control panel and a box door 2 are arranged on the front of the box body 1, a PLC controller is built in the control panel, and a temperature-insulating cavity is arranged between the inner wall and the outer wall of the other surfaces of the box body 1, and a corresponding rotary dehumidification device 3, a temperature-controlled atomization device 4, and a temperature-controlled blasting device 5 are installed in the temperature-insulating cavity, and the rotary dehumidification device 3, the temperature-controlled atomization device 4, and the temperature-controlled blasting device 5 are all electrically connected to the PLC controller;
[0029] The box 1 is provided with a plurality of sample supports 30, a temperature sensor 6 and a humidity sensor 7. The temperature sensor 6 and the humidity sensor 7 are connected to the PLC controller, and the temperature sensor 6, the humidity sensor 7 and the PLC controller are electrically connected to the control panel. In addition, the box 1 is provided with a corresponding drain port 14 and a reflux time slot 15. The drain port 14 is provided with a slope to facilitate water discharge. The accuracy of the weighing sensor 31 is 0.1g. Figure 4 As shown, the bottom surface of the box body has a certain slope, which is higher in the middle and lower on the four sides, and a drainage outlet is set at the lowest point.
[0030] An exhaust fan 8 connecting the inside and outside is arranged on the top of the box 1, and a bubble level 10 is installed on the outside of the top of the box 1; when the box 1 is in a horizontal state, the bubble is centered. The exhaust fan 8 includes a fan and a closing device for mounting the fan on the box. When the exhaust fan is started, the closing device opens and the fan starts to exhaust. When the exhaust fan stops working, the exhaust fan stops rotating and the closing device closes. The closing device is in a closed state during the non-exhaust time period to reduce the air exchange between the inside and outside of the box.
[0031] An air inlet 13 is provided at the bottom of the box body 1, and feet 9 with leveling bolts are installed at the four outer corners of the bottom.
[0032] The temperature-controlled atomizing device 4 includes a temperature-controlled heat-insulating water storage tank, an atomizing nozzle 11 connected to the inside of the box body 1, and a water inlet 12 is provided on the box body 1. The temperature-controlled atomizing device 4 is connected to the water inlet device outside the box body 1 through a water inlet pipe passing through the water inlet 12. The air outlet temperature of the temperature-controlled air blowing device 5 is 0-60°C, the temperature of the rotary dehumidification device 3 is 1-60°C, and the water storage tank of the temperature-controlled atomizing device 4 can heat water to 60°C and cool water to 1 degree Celsius. The temperature sensor 6 and the humidity sensor 7 can adopt a temperature probe and a humidity probe. The temperature-controlled heat-insulating water storage tank is equipped with a heating and cooling device, and can output cold water or hot water.
[0033] A weighing sensor 31 is installed at the bottom of the sample support 30. The sample support 30 is made of silicon oxide fiber material, specifically silicon oxide fiber mesh.
[0034] A rotary door handle 16 is provided on the door 2 . The middle portion 18 of the door 2 is made of double-layer thickened glass for observing the interior of the box body 1 . A sealing strip 17 corresponding to the box body 1 is installed at the edge of the door 2 .
[0035] The control panel is provided with a switch button 32, a moisture content setting button 19, a time setting button 20, a temperature setting button 21, a dry mass setting button 22 and a dry-wet cycle number setting button 23. The switch button 32 includes a power switch, a temperature control switch, a mist switch and a dehumidification switch.
[0036] The rotary dehumidification device 3 includes a dehumidifier and a dehumidification pipe 24 connected to the interior of the housing 1 .
[0037] The temperature-controllable air blowing device 5 is connected to the interior of the box body 1 through the air supply duct 25 .
[0038] The outer wall of the box body 1 is composed of a stainless steel anti-corrosion layer 26, an electrolytic grinding layer 27, a thickened thermal insulation layer 28, and an electrostatically sprayed stainless steel layer 29 from the inside to the outside.
[0039] There are two air inlets 13, four temperature sensors 6 and four humidity sensors 7, which are respectively arranged on the top, left side, right side and rear side of the box body, one temperature-controllable air blowing device 5, two temperature-controllable atomizing devices 4, and each temperature-controllable atomizing device 4 is equipped with four atomizing nozzles 11. The present application can automatically measure the moisture content of the sample in real time to ensure that the humidity and temperature coupling control act on the sample.
[0040] When the dry-wet cycle box of the utility model is used for geotechnical test, firstly, the foot 9 with leveling bolts installed at the four corners of the bottom outer side of the box body 1 is used for leveling with the bubble level 10, so that the bubble of the bubble level 10 is centered to ensure that the box body 1 is in a horizontal state; then, the box door 2 is opened through the rotary door handle 16, and the mass of the sample in the drying state is input through the dry mass setting button 22 in the dry mass setting panel according to the experimental conditions, and then the prepared sample is placed on the sample support 30 and the box door 2 is closed; according to the test plan, the moisture content range of the dry-wet cycle, the temperature required for the test, the duration after reaching the maximum and minimum temperatures of the test, and the number of dry-wet cycles are set through the moisture content setting button 19, the time setting button 20, the temperature setting button 21, and the number setting button 23 on the control panel. Then, the corresponding switch is turned on through the switch button 32, and the PLC controller built in the control panel calculates the sample mass at the highest and lowest moisture contents according to the mass of the sample in the drying state input and the highest and lowest moisture contents required for the test.
[0041] The temperature-controlled blowing device 5 is started to heat or cool according to the set temperature of the experiment. The water tank in the temperature-controlled atomizing device 4 also starts to heat up or cool down accordingly. The rotary dehumidification device 3 and the exhaust fan 8 stop working. After the temperature-controlled blowing device reaches the set temperature, the temperature sensor 6 transmits the corresponding temperature signal to the PLC controller, so that the temperature-controlled blowing device 5 stops working and enters the standby state. The temperature-controlled atomizing device 4 starts working, and the water reaching the set temperature is evenly sprayed into the interior of the box 1 by the atomizing nozzle 11 of the temperature-controlled atomizing device 4, so that the overall temperature and humidity of the internal space of the box 1 are more uniform, thereby improving the accuracy of the dry-wet cycle test.
[0042] Under high temperature condition (30-60℃): humidity sensor 7 starts to measure the moisture content of the sample in real time, and temperature sensor 6 measures the internal temperature. When the temperature is higher than the set temperature, temperature-controlled blower 5 starts cooling and starts to lower the internal air temperature until the data measured by temperature sensor 6 reaches the test set temperature (if the temperature is lower than the test set temperature, exhaust fan 8 is turned on until the data measured by temperature sensor 6 reaches the test set temperature).
[0043] Under low temperature conditions (1-30°C): humidity sensor 7 starts to measure the moisture content of the sample in real time, while temperature sensor 6 measures the internal temperature. When the temperature is higher than the set temperature, temperature-controlled blower 5 starts to start cooling, thereby lowering the internal air temperature until the data measured by temperature sensor 6 reaches the test set temperature (if the temperature is lower than the test set temperature, exhaust fan 8 is turned on until the data measured by temperature sensor 6 reaches the test set temperature).
[0044] The temperature during the whole test process is in the temperature range required for the test. The atomizing nozzle 11 sprays high-purity water to continuously wet the sample. When the weighing sensor 31 measures that the sample mass reaches the maximum water content determined by the test, the temperature-controlled atomizing device 4 stops working, and a feedback signal is given to the PLC controller. The timing starts according to the set time. After the timing ends, the rotary dehumidification device 3 starts working, and the dehumidification pipe 24 starts to absorb the moisture inside the box 1. When the water content data collected by the weighing sensor 31 reaches the set minimum water content, the rotary dehumidification device 3 stops working, and a feedback signal is given to the PLC controller. The timing starts according to the set time. This is a dry-wet cycle. Repeat the above process according to the set number of cycles until the test is completed.
[0045] The dry-wet cycle box of the utility model can set dry-wet cycle tests under different conditions according to the test requirements. After entering various condition requirements through the control panel before the test starts, the equipment starts to operate automatically, and no manual control is required during the experiment.
[0046] The test accuracy and automation of the dry-wet cycle are improved, thereby saving human resources. In addition, the utility model adopts a rotary dehumidification device, which can still work stably under low temperature conditions (1-30 degrees Celsius), and realizes dry-wet cycle under constant temperature.
[0047] It should be emphasized that the PLC controller, weighing sensor 31, temperature sensor 6, humidity sensor 7, temperature-controlled air blowing device 5, rotary dehumidification device 3, control panel, and temperature-controlled atomization device 4 in the present utility model are all existing conventional technologies, and the specific structure and principle are not repeated. The automatic control involved in the present utility model does not involve a new computer program.
[0048] This embodiment does not impose any formal restrictions on the shape, material, structure, etc. of the utility model. Any simple modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the utility model are within the protection scope of the technical solution of the utility model.
Claims
1. A temperature-controlled and humidity-controlled dry-wet cycle box suitable for geotechnical tests. Features: It includes a box body, a control panel and a box door are arranged on the front of the box body, a PLC controller is built in the control panel, a temperature-insulating cavity is arranged between the inner wall and the outer wall of the other sides of the box body, a corresponding rotary dehumidification device, a temperature-controllable atomization device, and a temperature-controllable air blowing device are installed in the temperature-insulating cavity, and the rotary dehumidification device, the temperature-controllable atomization device, and the temperature-controllable air blowing device are all electrically connected to the PLC controller; A plurality of sample supports, temperature sensors and humidity sensors are arranged inside the box. The temperature sensor and humidity sensor signals are connected to the PLC controller, and the temperature sensor, humidity sensor and the PLC controller are electrically connected to the control panel.
2. The temperature-controlled and humidity-controlled dry-wet cycle box suitable for geotechnical testing according to claim 1, Features: An exhaust fan connected to the inside and outside of the box is arranged on the top of the box, and a bubble level is installed on the outside of the top of the box; An air inlet is arranged at the bottom of the box, and feet with leveling bolts are installed at the four outer corners of the bottom.
3. The temperature-controlled and humidity-controlled dry-wet cycle box suitable for geotechnical testing according to claim 2, Features: The temperature-controllable atomizing device comprises a temperature-controlled heat-insulating water storage tank and an atomizing nozzle connected to the inside of the tank. A water inlet is arranged on the tank. The temperature-controllable atomizing device is connected to the water inlet equipment outside the tank through a water inlet pipe passing through the water inlet.
4. The temperature-controlled and humidity-controlled dry-wet cycle box suitable for geotechnical testing according to claim 1, Features: A weighing sensor is installed at the bottom of the sample support, and the material of the sample support is silicon oxide fiber material.
5. The temperature-controlled and humidity-controlled dry-wet cycle box suitable for geotechnical testing according to claim 1, Features: The door is provided with a rotating door handle. The middle part of the door is made of double-layer thickened glass for observing the internal situation of the box. The edge of the door is installed with sealing strips corresponding to the box.
6. The temperature-controlled and humidity-controlled dry-wet cycle box suitable for geotechnical testing according to claim 1, Features: The control panel is provided with a switch button, a moisture content setting button, a time setting button, a temperature setting button, a dry mass setting button and a dry-wet cycle number setting button.
7. The temperature-controlled and humidity-controlled dry-wet cycle box suitable for geotechnical testing according to claim 1, Features: The rotary dehumidification device comprises a dehumidifier and a dehumidification pipeline connected to the inside of the box.
8. The temperature-controlled and humidity-controlled dry-wet cycle box suitable for geotechnical testing according to claim 1, Features: The temperature-controllable air blowing device is connected to the interior of the box through an air supply duct.
9. The temperature-controlled and humidity-controlled dry-wet cycle box suitable for geotechnical testing according to claim 1, Features: The outer wall of the box is composed of a stainless steel anti-corrosion layer, an electrolytic grinding layer, a thickened insulation layer, and an electrostatically sprayed stainless steel layer from the inside to the outside.
10. The temperature-controlled and humidity-controlled dry-wet cycle box suitable for geotechnical testing according to claim 3, Features: There are two air inlets, four temperature sensors and four humidity sensors, which are respectively arranged on the top, left side, right side and rear side of the box body. There is one temperature-controllable blowing device and two temperature-controllable atomizing devices, and each temperature-controllable atomizing device is equipped with four atomizing nozzles.