Machining tool for connecting pin holes of crankshaft and flywheel
Through the boring and drilling mold technology of combined manufacturing, the problem of insufficient machining accuracy of crankshaft and flywheel connection pin holes in diesel engines is solved, the process is simplified, the production efficiency and assembly reliability are improved, and the stable operation of the diesel engine is ensured.
Patent Information
- Application Number
- CN202420028148.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-05
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2034-01-05
AI Technical Summary
In diesel engine design, the machining accuracy of the connecting pin holes of the crankshaft and flywheel is insufficient, resulting in low assembly efficiency. Due to different suppliers, hinge assembly is required, which affects the normal operation of the production site.
The boring mold for crankshaft and drill mold for flywheel are used to process the connecting pin holes on the crankshaft and flywheel respectively. Through the split use of boring mold and drill mold, the supplier can be directly processed, reduce the reaming steps and improve the Productivity.
High-precision processing of crankshaft and flywheel connection pin holes is realized, the process is simplified, labor intensity and processing cost are reduced, production efficiency is improved, and assembly stability and reliability are ensured.
Smart Images

Figure CN222113617U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of diesel engine manufacturing, and in particular relates to a processing tool for a pin hole connecting a crankshaft and a flywheel. Background Art
[0002] The crankshaft is the core component of the diesel engine and is the output device that converts fuel thermal energy into mechanical energy. For diesel generator sets, the output flange of the crankshaft is generally connected to an energy storage component such as a flywheel or inertia disc to ensure stable ignition and continuous operation of the diesel engine, so that the generator can output a stable working voltage.
[0003] In the design of diesel engines, in order to allow the flywheel (or inertia disc) to have a sufficiently large moment of inertia, the diameter and thickness of the flywheel are designed to be relatively large. When designing the connection bolt holes, a certain number of connection pin holes are often configured, and the bolts with holes are installed to withstand the large instantaneous start-stop inertia torque to enhance the reliability of the bolt connection. The design number of connection pin holes is generally as few as 2 and as many as 8 to 12. In the design, the accuracy of the connection pin hole processing equipment is taken into consideration (the single hole processing position accuracy of the general equipment is about 0.02mm, but when the number of connection pin holes increases, the overall cumulative error will be relatively large, which will seriously affect the assembly). The drawings require that the crankshaft and flywheel connection pin holes leave a margin, and then perform matching after assembly; since the crankshaft and flywheel are generally supplied by different suppliers, after arrival, it is necessary to arrange personnel to assemble and arrange machine tools for matching. After marking the matching, they are disassembled and sent to the assembly workshop for formal assembly. This often impacts the production site, causing assembly stagnation and affecting installation efficiency. Therefore, in view of the above problems, it is necessary to design a drilling jig to solve the above technical problems. Utility Model Content
[0004] The technical problem solved by the utility model is as follows: a tooling is provided for processing the connecting pin holes of the crankshaft and the flywheel, wherein the connecting pin holes on the crankshaft and the flywheel are respectively processed by a combined crankshaft boring die and a flywheel drilling die, thereby solving the shortcomings of the original technical scheme and process method. The crankshaft boring die and the flywheel drilling die are manufactured in combination but used separately, thereby ensuring that the connecting pin holes on the crankshaft and the flywheel are directly processed in place by their respective suppliers according to the drilling die. After the finished products arrive, they do not need to be reamed and can meet the assembly connection requirements of the general assembly workshop. The utility model has a simple structure, is easy to use, has high production efficiency, and has stable and reliable processing quality.
[0005] The technical solution adopted by the utility model is as follows: a tooling for processing a pin hole connecting a crankshaft and a flywheel, comprising a crankshaft boring die and a flywheel drilling die, the crankshaft boring die and the flywheel drilling die facing side end surfaces are respectively provided with concave stoppers and convex stoppers that correspond in position and fit with each other, a plurality of reference pin holes corresponding in position are evenly distributed on the circumference of the end surfaces of the crankshaft boring die and the flywheel drilling die, a plurality of positioning holes corresponding to the bolt through-hole positions on the crankshaft are evenly distributed on the circumference of the flywheel drilling die, bushings are fitted and installed in the reference pin holes and the positioning holes, a quick-change drill sleeve is positioned and installed in the bushing in the reference pin hole on the flywheel drilling die, and the quick-change drill sleeve is fixed to the flywheel drilling die by a fastener provided on the flywheel drilling die, and a pin rod for inspection and positioning is fitted and positioned with the quick-change drill sleeve on the flywheel drilling die and the bushing in a concentric position on the crankshaft boring die.
[0006] Among them, the quick-change drill sleeve is a T-shaped sleeve structure with an avoidance cut surface on the step surface of the positioning boss at the large diameter end, and the small diameter end of the quick-change drill sleeve is adapted to the bushing in the reference pin hole on the flywheel drill jig, and the positioning boss of the quick-change drill sleeve is against the end face of the flywheel drill jig, and the quick-change drill sleeve is fixed to the flywheel drill jig through a fastener that is detachably fixed to the end face of the flywheel drill jig and pressed against the positioning boss.
[0007] Furthermore, the fastener is a clamping screw, the thread of which is fixedly connected to the end face of the flywheel drilling template, and the head of the clamping screw is against the positioning boss.
[0008] Furthermore, a positioning mark for aligning and positioning with a mark on the crankshaft is formed on the outer wall of the upper end of the crankshaft boring die.
[0009] Furthermore, a lifting eye screw is provided on the end surface of the flywheel drilling jig on the opposite side to the convex stop, and a lifting eye screw is also fixed at the position of the positioning mark on the outer wall of the crankshaft boring jig.
[0010] Furthermore, an alignment opening for aligning with the cross line on the flywheel is formed on the outer circumferential wall of the flywheel drilling jig, and in the alignment state, the center of the cross line on the flywheel is aligned with the straight edge of the alignment opening.
[0011] Furthermore, the pin rod is an integrated stepped rod consisting of a large diameter section in the middle and small diameter sections at both ends, and the diameter of the bushing in the reference pin hole on the crankshaft boring die and the flywheel drilling die is the same as the diameter of the large diameter section in the middle of the pin rod.
[0012] Furthermore, the reference pin holes on the crankshaft boring die and the flywheel drilling die are integrally processed after the crankshaft boring die and the flywheel drilling die are assembled.
[0013] Based on the method of using the tooling for machining the connecting pin holes between the crankshaft and the flywheel, the specific machining process of the connecting pin holes on the crankshaft and the flywheel is as follows:
[0014] The specific steps for machining the connecting pin hole on the crankshaft are as follows:
[0015] A1) Use the lifting eye screw on the crankshaft boring die to lift it until the positioning mark on the outer wall of the upper end of the crankshaft boring die is aligned with the mark on the crankshaft, and make the concave stop on the crankshaft boring die fit with the positioning boss on the outer end surface of the crankshaft, and then clamp the crankshaft boring die and the crankshaft;
[0016] A2) using two of the bushings on the crankshaft boring die, firstly process two connecting pin holes on the crankshaft, and then fit two pre-positioning pins to the two bushings and the connecting pin holes at the corresponding positions processed first respectively;
[0017] A3) Using the remaining bushings on the crankshaft boring die, process the remaining connecting pin holes on the crankshaft in sequence;
[0018] A4) Insert the inspection pins into the remaining connecting pin holes machined on the crankshaft one by one for inspection;
[0019] A5) The pin can be inserted normally, which means it is qualified and the connecting pin hole on the crankshaft is processed;
[0020] The specific steps for machining the connecting pin hole on the flywheel are as follows:
[0021] B1) Use the eye screws on the flywheel drilling jig to lift it until the alignment mouth is aligned with the cross line on the flywheel, and make the convex stop on the flywheel drilling jig fit with the positioning slot on the end face of the flywheel, and then clamp the flywheel drilling jig and the flywheel to fix;
[0022] B2) Select a quick-change drill sleeve corresponding to the processing procedure and insert it into the bushing on the flywheel drill jig for locating the processing position of the connecting pin hole, and make the clamping screw threadedly connected to the outer end surface of the flywheel drill jig press against the positioning boss on the outer end of the quick-change drill sleeve to achieve rapid fixation of the quick-change drill sleeve;
[0023] B3) using two bushings on the flywheel drilling jig for locating the connection pin hole processing position, firstly process two connection pin holes on the flywheel, and respectively fit two pre-positioning pins to the two bushings and the connection pin holes at the corresponding positions processed first;
[0024] B4) Use the remaining bushings on the flywheel drilling jig to process the bolt holes and connecting pin holes on the flywheel in sequence;
[0025] B5) Insert the inspection pins into the remaining connecting pin holes machined on the flywheel one by one for inspection;
[0026] B6) If the pin rod can be inserted normally, it is qualified and the connecting pin hole on the flywheel has been processed.
[0027] In the above step B2), the processing steps include drilling, expanding and reaming, and the inner hole diameter of the quick-change drill sleeve used in each step is different.
[0028] The advantages of this utility model compared with the prior art:
[0029] 1. This technical solution adopts a crankshaft boring die and a flywheel drilling die that are manufactured in combination to process the connecting pin holes on the crankshaft and the flywheel respectively, which solves the shortcomings of the original technical solution and process method. The crankshaft boring die and the flywheel drilling die are manufactured in combination but used separately, ensuring that the connecting pin holes on the crankshaft and the flywheel are directly processed in place by their respective suppliers according to the drilling die. After the finished products arrive, they can meet the assembly and connection requirements of the general assembly workshop without the need for reaming;
[0030] 2. This technical solution sets the eyebolt at the position with the positioning mark on the edge of the crankshaft boring die, so as to adapt to the boring of the connecting pin hole on the crankshaft output end flange on the horizontal processing equipment, facilitate the lifting of the crankshaft boring die, and ensure the consistency of the relative position of the crankshaft boring die and each crankshaft;
[0031] 3. The setting of the clamping screw of this technical solution provides replacement and fixing conditions for quick-change drill sleeves with different inner diameters, ensuring that the quick-change drill sleeves are reliably fixed on the drill jig for the flywheel;
[0032] 4. This technical solution has a simple structure and is easy to use. It simplifies the processing procedures of the connecting pin holes on the crankshaft and the flywheel, reduces labor intensity, improves production efficiency, reduces processing costs, and ensures stable and reliable processing quality. BRIEF DESCRIPTION OF THE DRAWINGS
[0033] Figure 1 It is a schematic diagram of the structure of the crankshaft boring die and the flywheel drilling die after being assembled;
[0034] Figure 2 for Figure 1 Middle AA section view;
[0035] Figure 3 It is a structural schematic diagram of the utility model after the flywheel drilling jig and the flywheel are adapted and connected;
[0036] Figure 4 for Figure 3 Middle BB section view;
[0037] Figure 5 It is a schematic diagram of the structure of the crankshaft boring die and the crankshaft after being adapted and connected;
[0038] Figure 6 for Figure 5 Middle CC section view. DETAILED DESCRIPTION
[0039] The following will be combined with the embodiment of the present utility model Figure 1-6 , clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of them. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0040] It should be noted that, in this article, unless otherwise stated, it should be understood that the terms "center", "upper", "lower", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating the orientation or positional relationship are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention. In addition, the terms "first", "second", "third", etc. are only used for descriptive purposes and cannot be understood as indicating or implying relative importance.
[0041] In this document, the terms "comprises", "comprising" or any other variation thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device comprising a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further limitations. The elements defined by the sentence "comprising a ..." do not exclude the presence of other identical elements in the process, method, article or device comprising the elements.
[0042] Tooling for machining the pin hole connecting the crankshaft and the flywheel, such as Figure 1-2As shown, it includes a crankshaft boring die 1 and a flywheel drilling jig 2, and the end faces facing each other are respectively provided with a concave stop 6 and a convex stop 7 that correspond in position and fit each other, and the end faces of the crankshaft boring die 1 and the flywheel drilling jig 2 are uniformly distributed with a plurality of reference pin holes 5 that correspond in position, wherein the reference pin holes 5 on the crankshaft boring die 1 and the flywheel drilling jig 2 are integrally processed after the crankshaft boring die 1 and the flywheel drilling jig 2 are assembled; the flywheel drilling jig 2 is uniformly distributed with a plurality of positioning holes 13 that correspond in position to the bolt through holes 15 on the crankshaft 3, and the reference pin holes 5 and the positioning holes 13 are both fitted with bushings 8, and the bushings 8 in the reference pin holes 5 on the flywheel drilling jig 2 are positioned and installed. A quick-change drill sleeve 9 is fixed to the flywheel drill jig 2 by a fastener provided on the flywheel drill jig 2. The inspection and positioning pin 10 is adapted and positioned with the quick-change drill sleeve 9 on the flywheel drill jig 2 and the concentric bushing 8 on the crankshaft boring jig 1. In the above structure, the crankshaft boring jig 1 and the flywheel drill jig 2 manufactured in combination are used to process the connecting pin holes 16 on the crankshaft 3 and the flywheel 4, respectively, which solves the shortcomings of the original technical solution and process method. The crankshaft boring jig 1 and the flywheel drill jig 2 are manufactured in combination but used separately, which ensures that the connecting pin holes 16 on the crankshaft 3 and the flywheel 4 are directly processed in place by their respective suppliers according to the drill jig. After the finished product arrives, it does not need to be reamed to meet the assembly connection requirements of the general assembly workshop.
[0043] The crankshaft boring die 1 and the flywheel drilling jig 2 are assembled as a whole before processing the reference pin hole 5, pre-tightened with bolts, and the concentricity of the holes in the middle of the two drilling templates is aligned within 0.005mm before being tightened, and then the reference pin hole 5 is precision bored. The position of the reference pin hole 5 is allowed to deviate in the same direction, and the consistency is ≤0.02mm; when the crankshaft boring die 1 and the flywheel drilling jig 2 are respectively processing the concave stop 6 and the convex stop 7, the inner hole is polished as the alignment reference. The crankshaft boring die 1 and the flywheel drilling jig 2 are assembled and precision bored. By accurately aligning the two inner hole references, the fitting clearance error between the female stop 6 and the male stop 7 can be eliminated. In this way, the position of the reference pin hole 5 processed on the crankshaft boring die 1 and the flywheel drilling die 2 relative to the female stop 6 and the male stop 7 has a high directional consistency, which is equivalent to completely copying the position of the connecting pin hole 16 on the crankshaft 3 to the flywheel 4; wherein, the role of the bushing 8 is to increase the wear resistance while positioning, and it is a high-carbon steel (or low-carbon steel after carburizing) quenched part with extremely high hardness.
[0044] The structure and installation of the quick-change drill sleeve 9 are specifically as follows: the quick-change drill sleeve 9 is a T-shaped sleeve structure with an avoidance cut surface on the step surface of the positioning boss 14 at the large diameter end, and the small diameter end of the quick-change drill sleeve 9 is adapted to the bushing 8 in the reference pin hole 5 on the flywheel drill jig 2, and the positioning boss 14 of the quick-change drill sleeve 9 is against the end face of the flywheel drill jig 2, and the quick-change drill sleeve 9 is fixed to the flywheel drill jig 2 by a fastener that is detachably fixed to the end face of the flywheel drill jig 2 and pressed against the positioning boss 14.
[0045] The fastener is specifically as follows: the fastener is a clamping screw 12, the clamping screw 12 is threadedly fixedly connected to the end surface of the flywheel drilling jig 2, and the head of the clamping screw 12 is against the positioning boss 14; in the above structure, the setting of the clamping screw 12 realizes the axial fixation of the quick drill sleeve 9, so that the quick-change drill sleeve 9 will not be brought out due to a large amount of iron filings coming out along the rotating drill bit during drilling, and at the same time, it provides replacement and fixing conditions for quick-change drill sleeves 9 with different inner diameters, ensuring that the quick-change drill sleeve 9 is reliably fixed on the flywheel drilling jig 2;
[0046] The outer wall of the upper end of the crankshaft boring die 1 is provided with a positioning mark 18 for aligning with the mark on the crankshaft 3; specifically, the end surface of the flywheel drilling jig 2 on the opposite side of the convex stop 7 is provided with two lifting eye screws 11, and the position of the positioning mark 18 on the outer wall of the crankshaft boring die 1 is also fixed with a lifting eye screw 11; specifically, the outer circumferential wall of the flywheel drilling jig 2 is provided with an alignment opening 17 for aligning with the cross line on the flywheel 4, and the center of the cross line on the flywheel 4 in the alignment state is centered on the flywheel 4. Aligned with the straight edge of the alignment mouth 17; in the above structure, the eye screw 11 is set at the position where the positioning mark 18 is on the edge of the crankshaft boring die 1 to adapt to the boring of the connecting pin hole 16 on the output end flange of the crankshaft 3 on the horizontal processing equipment, which is convenient for lifting the crankshaft boring die 1 and ensuring the consistency of the relative position of the crankshaft boring die 1 and each crankshaft 3; the flywheel drilling jig 2 sets the eye screw 11 on a large plane to facilitate the processing of the connecting pin hole 16 and the bolt through hole 15 on the flywheel 4 on the vertical radial drilling machine.
[0047] The specific structure of the pin rod 10 is as follows: the pin rod 10 is an integrated stepped rod consisting of a large diameter section in the middle and small diameter sections at both ends; the diameter of the inner sleeve 8 of the reference pin hole 5 on the crankshaft boring die 1 and the flywheel drilling die 2 is the same as the diameter of the large diameter section in the middle of the pin rod 10; wherein the small diameter section at the outer end of the pin rod 10 is a knurled handle, and the small diameter section at the other end is a positioning cylinder.
[0048] Only the hole position of the reference pin hole 5 is set on the crankshaft boring die 1, and the bolt through hole 15 on the end face of the crankshaft 3 is processed in advance by the equipment because the position accuracy requirement is not high; during processing, before the precision boring of the connecting pin hole 16 on the crankshaft 3, the center of the equipment main shaft must be accurately concentric with each hole on the crankshaft boring die 1 before processing. In order to prevent the tool tip from damaging the crankshaft boring die 1 when precision boring the connecting pin hole 16 on the crankshaft 3, the inner hole diameter of the bushing 8 is deliberately increased during design, and the pin rod 10 is also designed into a stepped structure.
[0049] A reference pin hole 5 and a positioning hole 13 are provided on the flywheel drilling jig 2. Since the position accuracy requirement of the bolt through hole 15 on the flywheel 4 is not high, only a bushing 8 is provided, which can be directly processed to the size by drilling at one time. A group of quick-change drill sleeves 9 with different inner diameters are provided at the reference pin hole 5 of the flywheel drilling jig 2, which respectively correspond to the drilling, expanding and reaming processes of the connecting pin hole 16 on the flywheel 4, and can be replaced after each process is processed.
[0050] Based on the method of using the tooling for machining the connecting pin hole between the crankshaft and the flywheel, the specific machining process of the connecting pin hole 16 on the crankshaft 3 and the flywheel 4 is as follows:
[0051] like Figure 5-6 As shown, the specific steps for machining the connecting pin hole 16 on the crankshaft 3 are as follows:
[0052] A1) Use the eye screw 11 on the crankshaft boring die 1 to lift it until the positioning mark 18 on the upper outer wall of the crankshaft boring die 1 is aligned with the mark on the crankshaft 3, and make the concave stop 6 on the crankshaft boring die 1 fit with the positioning boss on the outer end surface of the crankshaft 3, and then clamp the crankshaft boring die 1 and the crankshaft 3;
[0053] A2) Using two of the bushings 8 on the crankshaft boring die 1, two connecting pin holes 16 are first processed on the crankshaft 3, and then two pre-positioning pins 10 are respectively matched with the two bushings 8 and the connecting pin holes 16 at the corresponding positions processed first, as shown in FIG. Figure 5 The shadow-marked hole position is used for positioning pin 10;
[0054] A3) using the remaining bushings 8 on the crankshaft boring die 1, the remaining connecting pin holes 16 are processed on the crankshaft 3 in sequence;
[0055] A4) Insert the inspection pins 10 one by one into the remaining connecting pin holes 16 processed on the crankshaft 3 for inspection;
[0056] A5) The pin rod 10 can be inserted normally, which means it is qualified, and the connecting pin hole 16 on the crankshaft 3 is processed;
[0057] like Figure 3-4 As shown, the specific steps for machining the connecting pin hole 16 on the flywheel 4 are as follows:
[0058] B1) Use the eye screw 11 on the flywheel drilling jig 2 to lift it to the alignment opening 17 and align it with the cross line on the flywheel 4, and make the convex stop 2-7 on the flywheel drilling jig 2 fit with the positioning slot on the end face of the flywheel 4, and then clamp the flywheel drilling jig 2 and the flywheel 4;
[0059] B2) Selecting a quick-change drill sleeve 9 corresponding to the processing step and installing it into the bushing 8 on the flywheel drilling jig 2 for positioning the processing position of the connecting pin hole 16, and making the clamping screw 12 threadedly connected to the outer end surface of the flywheel drilling jig 2 press against the positioning boss 14 at the outer end of the quick-change drill sleeve 9 to achieve rapid fixation of the quick-change drill sleeve 9; specifically, the processing steps include a drilling step, a hole enlarging step and a reaming step, and the inner hole diameter of the quick-change drill sleeve 9 used in each step is different;
[0060] B3) Using two bushings 8 on the flywheel drilling jig 2 for locating the processing position of the connecting pin holes 16, first process two connecting pin holes 16 on the flywheel 4, and fit two pre-positioning pins 10 to the two bushings 8 and the connecting pin holes 16 at the corresponding positions processed first, respectively, as shown in FIG. Figure 3 As shown, the shadow-marked holes are used as positioning pins 10;
[0061] B4) using the remaining bushings 8 on the flywheel drilling jig 2, the bolt holes 15 and the connecting pin holes 16 are processed in sequence on the flywheel 4;
[0062] B5) Insert the inspection pins 10 one by one into the remaining connecting pin holes 16 processed on the flywheel 4 for inspection;
[0063] B6) The pin rod 10 can be inserted normally, which means it is qualified and the connecting pin hole 16 on the flywheel 4 is processed.
[0064] In this structure, a total of 6 pins 10 are configured, 3 of which are used for the crankshaft boring die 1 and the flywheel drilling die 2. Two of the pins 10 are used to position the two connecting pin holes 16 that are processed first. Figure 3 and Figure 5 The shaded holes in the figure, after all the connecting pin holes 16 on the crankshaft 3 and the flywheel 4 are processed, the third pin rod 10 is inserted into the connecting pin holes 16 one by one for simulated assembly inspection. This method predicts and inspects the assembly effect of the crankshaft 3 and the flywheel 4 with the reamed hole bolts in advance, discovers problems in advance, and avoids the situation where the assembly connection cannot be made during assembly; the crankshaft boring die 1 and the flywheel drilling die 2 used greatly improve the processing accuracy of the connecting pin holes 16 on the crankshaft 3 and the flywheel 4, and perfectly solves the problem that the reaming method occupies equipment and the assembly efficiency is low, while the use of CNC equipment to directly process the connecting pin holes 16 cannot achieve the assembly quality and affects the assembly effect. The innovative effect is very obvious.
[0065] The technical solution has a simple structure and is easy to use. It simplifies the processing steps of the connecting pin holes 16 on the crankshaft 3 and the flywheel 4, reduces labor intensity, improves production efficiency, reduces processing costs, and the processing quality has been verified to be very stable and reliable.
[0066] It is obvious to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above, and that the present invention can be implemented in other specific forms without departing from the spirit or essential features of the present invention. Therefore, the embodiments should be regarded as exemplary and non-restrictive from any point of view, and the scope of the present invention is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims be included in the present invention. Any reference numeral in a claim should not be regarded as limiting the claim to which it relates.
[0067] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.
Claims
1. A tooling for machining the pin hole connecting the crankshaft and the flywheel, characterized in that: The invention comprises a crankshaft boring die (1) and a flywheel drilling die (2), wherein the crankshaft boring die (1) and the flywheel drilling die (2) are respectively provided with concave stoppers (6) and convex stoppers (7) which are in corresponding positions and fit with each other on their facing side end surfaces, the crankshaft boring die (1) and the flywheel drilling die (2) are provided with a plurality of reference pin holes (5) which are in corresponding positions and are evenly distributed on their circumferences on their end surfaces, and the flywheel drilling die (2) is provided with a plurality of positioning holes (13) which are evenly distributed on their circumferences on their upper surfaces and correspond to the positions of the bolt through holes (15) on the crankshaft (3), Bushings (8) are fitted in the reference pin hole (5) and the positioning hole (13); a quick-change drill sleeve (9) is positioned and installed in the bushing (8) in the reference pin hole (5) on the flywheel drilling jig (2); and the quick-change drill sleeve (9) is fixed to the flywheel drilling jig (2) via a fastener provided on the flywheel drilling jig (2); a pin rod (10) for inspection and positioning is fitted and positioned with the quick-change drill sleeve (9) on the flywheel drilling jig (2) and the bushing (8) at a concentric position on the crankshaft boring jig (1).
2. The tooling for machining the pin hole connecting the crankshaft and the flywheel according to claim 1, characterized in that: The quick-change drill sleeve (9) is a T-shaped sleeve structure for avoiding the cut surface on the step surface of the positioning boss (14) at the large diameter end, and the small diameter end of the quick-change drill sleeve (9) is adapted to the bushing (8) in the reference pin hole (5) on the flywheel drilling jig (2), and the positioning boss (14) of the quick-change drill sleeve (9) abuts against the end surface of the flywheel drilling jig (2). The quick-change drill sleeve (9) is fixed to the flywheel drilling jig (2) by a fastener that is detachably connected to the end surface of the flywheel drilling jig (2) and abuts against the positioning boss (14).
3. The tooling for machining the pin hole connecting the crankshaft and the flywheel according to claim 2, characterized in that: The fastener is a clamping screw (12), which is threadedly fixed to the end surface of the flywheel drilling jig (2), and the head of the clamping screw (12) abuts against the positioning boss (14).
4. The tooling for machining the pin hole connecting the crankshaft and the flywheel according to claim 1, characterized in that: The outer wall of the upper end of the crankshaft boring die (1) is provided with a positioning engraved line (18) for aligning and positioning with the engraved line on the crankshaft (3).
5. The tooling for machining the pin hole connecting the crankshaft and the flywheel according to claim 4, characterized in that: A lifting eye screw (11) is provided on the end surface of the flywheel drilling jig (2) on the opposite side to the convex stop (7), and a lifting eye screw (11) is also fixed at the position of the positioning mark (18) on the outer wall of the crankshaft boring jig (1).
6. The tooling for machining the pin hole connecting the crankshaft and the flywheel according to claim 1, characterized in that: The outer circumferential wall of the flywheel drilling jig (2) is provided with an alignment opening (17) for aligning with the cross line on the flywheel (4), and in the alignment state, the center of the cross line on the flywheel (4) is aligned with the straight edge of the alignment opening (17).
7. The tooling for machining the pin hole connecting the crankshaft and the flywheel according to claim 1, characterized in that: The pin rod (10) is an integrated stepped rod consisting of a large diameter section in the middle and small diameter sections at both ends. The diameter of the inner bushing (8) of the reference pin hole (5) on the crankshaft boring die (1) and the flywheel drilling die (2) is the same as the diameter of the large diameter section in the middle of the pin rod (10).
8. The tooling for machining the pin hole connecting the crankshaft and the flywheel according to any one of claims 1 to 7, characterized in that: The reference pin hole (5) on the crankshaft boring die (1) and the flywheel drilling die (2) is formed by integrally processing the crankshaft boring die (1) and the flywheel drilling die (2) after the crankshaft boring die (1) and the flywheel drilling die (2) are assembled.