Platform for quality inspection of concrete in mixer truck
By designing a submersible pump and water pipe system on the concrete quality inspection platform in the mixing vehicle, the admixture is transported to the metering barrel, which solves the problem of admixture occupying space, improves the activity space and safety of staff, and facilitates observation and The addition of admixtures improves the convenience of concrete status inspection.
Patent Information
- Application Number
- CN202420840252.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-18
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2034-04-18
AI Technical Summary
When the concrete quality inspection platform in the existing mixer truck is in use, admixtures occupy a large amount of space, resulting in limited space for staff members and it is impossible to easily observe the concrete status.
A quality inspection platform including a working platform, climbing structure, admixture storage box, submersible pump and water pipe was designed. The admixture was transported to the metering barrel through the submersible pump, and the metering barrel was moved to the mixer truck and poured into concrete. , avoiding the storage of admixtures on the working platform, combining support columns and fences to ensure safe and mobile space.
It effectively avoids the space occupied by admixtures, improves the activity space and safety of staff, facilitates observation and addition of admixtures, and improves the convenience of concrete status inspection.
Smart Images

Figure CN222115558U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of concrete detection, and in particular to a platform for concrete quality inspection in a mixer truck. Background Art
[0002] The quality of concrete directly affects the quality of the constructed building. Therefore, the state of concrete in the cement mixer truck needs to be checked before leaving the factory. The existing method generally sets up a quality inspection platform to lift the staff to a high place and observe the state of concrete through the feed port of the mixer truck. When the state of concrete does not meet the standard, the staff is generally required to add admixtures to the mixer truck.
[0003] The utility model patent with announcement number CN211141464U proposes a liftable platform, including a lifting component, a supporting platform, a first fixed component and a second fixed component. The supporting platform is installed on the top of the lifting component, the first fixed component is installed on one side of the outside of the supporting platform, and the second fixed component is installed on the other side of the outside of the supporting platform.
[0004] When the above-mentioned quality inspection platform is in use, the admixture needs to be placed on the supporting platform, which occupies a large amount of space, resulting in limited activity space for workers on the supporting platform, making it inconvenient for users to move around and observe the state of concrete in the mixer truck. Utility Model Content
[0005] The purpose of the utility model is to solve or at least alleviate the problem that the existing quality inspection platform needs to place admixtures on the support platform when in use, which occupies a large amount of space, resulting in limited activity space for workers on the support platform and inconvenience for users to observe the state of concrete in the mixer truck.
[0006] In order to achieve the above purpose, the utility model adopts the following technical solutions:
[0007] A platform for quality inspection of concrete in a mixer truck comprises a base with an upper surface fixedly connected to a working platform via a supporting structure, a protective structure is provided on the upper surface of the working platform, one end of the base is fixedly connected to a climbing structure for a user to climb onto the working platform to perform quality inspection work, an admixture storage box is fixedly connected to the base below the working platform, a partition is provided inside the admixture storage box for dividing the inner cavity of the admixture storage box into a plurality of accommodating cavities, a water delivery assembly is installed in each accommodating cavity, a plurality of faucets corresponding to the water delivery assemblies are also installed at one end of the working platform away from the climbing structure, and a metering bucket is suspended below the faucet.
[0008] By adopting the above technical solution, when the user needs to add admixtures to the concrete, the submersible pump installed inside the containing chamber for containing the admixture can be started, and the metering barrel can be moved to the bottom of the faucet connected to the submersible pump. At this time, the faucet is opened, and the admixture is discharged into the metering barrel along the water pipe and the faucet under the conveying action of the submersible pump. After the metering barrel receives an appropriate amount of admixture, the user can move the metering barrel to the top of the concrete mixer truck, thereby pouring the admixture into the concrete for mixing. There is no need to store the admixture on the working platform, and the problem of placing the admixture on the supporting platform when the existing quality inspection platform is in use is avoided as much as possible, which occupies a large amount of space, resulting in limited activity space for the staff on the supporting platform, and inconvenient for the user to observe the state of the concrete in the mixer truck.
[0009] Optionally, the base is a rectangular plate-shaped structure, and the supporting structure includes four supporting columns fixedly connected at four corners of the upper surface of the base, and the top of the supporting columns is fixedly connected to the lower surface of the working platform.
[0010] By adopting the above technical solution, four support columns are set between the base and the working platform to support the working platform to a suitable height, so that the user can observe whether the state of the concrete meets the standards through the feed port of the mixer truck at a high altitude.
[0011] Optionally, the protective structure includes four rows of fences arranged around the upper surface of the working platform, the bottom of the fences are fixedly connected to the working platform, and the height of the fences is not less than one hundred and twenty centimeters.
[0012] By adopting the above technical solution, a fence is set up to enclose the sides of the work platform to protect the workers working on the work platform and to avoid the problem of workers accidentally falling from a higher work platform and getting injured.
[0013] Optionally, the climbing structure includes a vertically arranged ladder fixedly connected between the base and one end of the working platform, and an anti-slip groove is provided on the pedal of the ladder.
[0014] By adopting the above technical solution, a ladder is set up to facilitate users to climb from the ground to the work platform to perform construction work, and anti-slip grooves are opened on the pedals to increase the friction between the pedals and the user's feet, so as to minimize the phenomenon of users slipping when climbing.
[0015] Optionally, a scale mark is engraved on the inner wall of the metering barrel, a steel cable is fixedly connected to the top of the metering barrel, and one end of the steel cable away from the metering barrel is tied to the fence.
[0016] By adopting the above technical solution, scale marks are engraved on the inner wall of the metering barrel, which is convenient for users to take an appropriate amount of admixture through the metering barrel for use. A steel cable is provided to fix the metering barrel. At the same time, since the steel cable can be bent arbitrarily, it is convenient for users to move the metering barrel with the admixture to the top of the concrete mixer truck, so as to pour the admixture into the concrete for mixing.
[0017] Optionally, the water delivery component includes a submersible pump installed in the accommodating cavity, a water delivery pipe is fixedly connected to the drainage end of the submersible pump, and one end of the water delivery pipe away from the submersible pump is fixedly connected to a corresponding faucet.
[0018] By adopting the above technical solution, when in use, the user turns on the submersible pump, and the additive is transported to the faucet through the water pipe installed on the submersible pump. At this time, the user turns on the faucet, and the additive can be discharged through the faucet into the inner cavity of the metering barrel below.
[0019] Optionally, the upper cover of the opening end of the additive storage box is provided with a box cover for sealing the additive storage box, and a plurality of sliding holes corresponding to the water pipe are opened on the box cover, and the middle section of the water pipe passes through the box cover through the sliding holes and is slidably connected to the box cover.
[0020] By adopting the above technical solution, a box cover is provided to seal the open end of the admixture storage box to prevent dust and impurities from falling into the admixture storage box and causing contamination to the admixture. A sliding hole is provided on the box cover so that the box cover can slide along the height direction of the water pipe to be opened and closed.
[0021] In summary, the beneficial effects of this application are as follows:
[0022] The present application coordinates structures such as a metering barrel, an admixture storage box, a partition, a submersible pump and a water pipe. When in use, the submersible pump is started and the metering barrel is moved under the faucet connected to the submersible pump, and the admixture is discharged into the metering barrel through the water pipe and the faucet. After taking an appropriate amount of admixture, the user can pour the admixture in the metering barrel into the concrete for mixing, and there is no need to store the admixture on the work platform. This avoids the problem that the existing quality inspection platform needs to place the admixture on the support platform when in use, which occupies a large amount of space, resulting in limited activity space for the staff on the support platform and inconvenience for the user to observe the state of the concrete in the mixer truck. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1 It is a schematic diagram of the overall cross-sectional structure of this application;
[0024] Figure 2 It is a schematic diagram of the connection structure of the climbing structure of the present application;
[0025] Figure 3 It is a schematic diagram of the connection structure between the water delivery component and the faucet of the present application.
[0026] Explanation of the reference numerals: 1. base; 2. ground nails; 3. support column; 4. working platform; 5. fence; 6. ladder; 7. anti-slip groove; 8. steel cable; 9. metering barrel; 10. additive storage box; 11. box cover; 12. partition; 13. submersible pump; 14. water pipe; 15. faucet. DETAILED DESCRIPTION
[0027] The following is combined with Figure 1-3 This application is described in further detail.
[0028] See also Figure 1-3 A concrete quality inspection platform in a mixer truck includes a base 1 with a working platform 4 fixedly connected to the upper surface through a supporting structure. Ground nails 2 are provided at both ends of the base 1. After the user determines the installation position of the quality inspection platform, the overall quality inspection platform can be fixed by the ground nails 2.
[0029] A protective structure is provided on the upper surface of the working platform 4, and the protective structure is provided to protect personnel working on the working platform 4 and to prevent the personnel from falling from a height and getting injured.
[0030] One end of the base 1 is fixedly connected to a climbing structure for users to climb up to the work platform 4 to perform quality inspection work. Since the work platform 4 is supported at a higher position by a supporting structure, a climbing structure is provided to facilitate workers to climb up the work platform 4 to perform work.
[0031] An admixture storage box 10 is fixedly connected to the base 1 below the working platform 4. A large amount of admixture is stored in the admixture storage box 10. The admixture storage box 10 and the admixture can be used to counterweight the base 1, thereby lowering the center of gravity of the entire device and preventing the entire device from becoming unstable or tipping over due to an excessively high center of gravity.
[0032] A partition 12 is provided inside the additive storage box 10 for dividing the inner cavity of the additive storage box 10 into a plurality of accommodating chambers. The partition 12 is used to separate the plurality of accommodating chambers so that the plurality of accommodating chambers are independent of each other, making it convenient for users to add and store different additives in different accommodating chambers.
[0033] A water delivery component is installed in each accommodating cavity. A plurality of faucets 15 corresponding to the water delivery components are installed at one end of the working platform 4 away from the climbing structure, and a metering bucket 9 is hung below the faucet 15 .
[0034] When the user needs to add an admixture to the concrete, the user can start the water delivery component installed in the corresponding admixture receiving chamber, open the faucet 15 installed corresponding to the water delivery component, and then place the metering bucket 9 under the faucet 15 to receive the admixture discharged through the faucet 15, and finally add the received appropriate amount of admixture into the concrete through the metering bucket 9.
[0035] Reference Figure 1 The base 1 is a rectangular plate-shaped structure, and the supporting structure includes four supporting columns 3 fixedly connected at four corners of the upper surface of the base 1, and the top of the supporting column 3 is fixedly connected to the lower surface of the working platform 4. Four supporting columns 3 are arranged between the base 1 and the working platform 4 to support the working platform 4 to a suitable height, so that the user can observe whether the state of the concrete meets the standard through the feed port of the mixer truck at a high place.
[0036] Reference Figure 1 The protective structure includes four rows of fences 5 arranged around the upper surface of the working platform 4. The bottom of the fence 5 is fixedly connected to the working platform 4. The height of the fence 5 is not less than 120 cm. The fence 5 is used to enclose the sides of the working platform 4 to protect the workers working on the working platform 4 and try to avoid the problem of workers accidentally falling from the higher working platform 4 and getting injured.
[0037] Reference Figure 2 The climbing structure includes a vertically arranged ladder 6 fixedly connected between a base 1 and one end of a working platform 4, and an anti-skid groove 7 is provided on the pedal of the ladder 6. The ladder 6 is provided to facilitate users to climb from the ground to the working platform 4 for construction work, and the anti-skid groove 7 is provided on the pedal to increase the friction between the pedal and the sole of the user's foot, so as to avoid the user from slipping when climbing.
[0038] Reference Figure 1 , a scale mark is engraved on the inner wall of the metering barrel 9, a steel cable 8 is fixedly connected to the top of the metering barrel 9, and one end of the steel cable 8 away from the metering barrel 9 is tied to the fence 5. A scale mark is engraved on the inner wall of the metering barrel 9, which is convenient for users to take an appropriate amount of admixture through the metering barrel 9 for use. The steel cable 8 is set to fix the metering barrel 9. At the same time, since the steel cable 8 can be bent arbitrarily, it is convenient for users to move the metering barrel 9 with the admixture to the top of the concrete mixer truck, so as to pour the admixture into the concrete for mixing.
[0039] Reference Figure 3 The water delivery assembly includes a submersible pump 13 installed in the accommodating cavity, a water delivery pipe 14 is fixedly connected to the drainage end of the submersible pump 13, and one end of the water delivery pipe 14 away from the submersible pump 13 is fixedly connected to a corresponding faucet 15. When in use, the user turns on the submersible pump 13, and the additive is delivered to the faucet 15 through the water delivery pipe 14 installed on the submersible pump 13. At this time, the user turns on the faucet 15, and the additive can be discharged through the faucet 15 into the inner cavity of the metering barrel 9 below.
[0040] Reference Figure 3The upper cover of the opening end of the admixture storage box 10 is provided with a box cover 11 for sealing the admixture storage box 10. The box cover 11 is provided with a plurality of sliding holes corresponding to the water pipe 14. The middle section of the water pipe 14 passes through the box cover 11 through the sliding holes and is slidably connected to the box cover 11. The box cover 11 is provided to seal the opening end of the admixture storage box 10 to prevent dust and impurities from falling into the admixture storage box 10 and contaminating the admixture. The sliding holes are provided on the box cover 11 so that the box cover 11 can slide along the height direction of the water pipe 14 to be opened and closed.
[0041] The implementation principle of the present application is as follows: when the user needs to add admixtures to the concrete, the submersible pump 13 installed inside the accommodating chamber for the admixture can be started, and the metering barrel 9 can be moved to below the faucet 15 connected to the submersible pump 13. At this time, the faucet 15 is opened, and the admixture is discharged into the metering barrel 9 along the water pipe 14 and the faucet 15 under the conveying action of the submersible pump 13. After the metering barrel 9 receives an appropriate amount of admixture, the user can move the metering barrel 9 to the top of the concrete mixer truck, thereby pouring the admixture into the concrete for mixing. There is no need to store the admixture on the working platform, and the problem that the existing quality inspection platform needs to place the admixture on the supporting platform when in use, which occupies a large amount of space, resulting in limited activity space for the staff on the supporting platform, and inconvenient for the user to observe the state of the concrete in the mixer truck is avoided as much as possible.
[0042] The above description is only a preferred embodiment of the utility model and is not intended to limit the utility model. Although the utility model is described in detail with reference to the above embodiments, those skilled in the art can still modify the technical solutions recorded in the above embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.
Claims
1. A platform for quality inspection of concrete in a mixer truck, comprising a base (1) having an upper surface fixedly connected to a work platform (4) via a supporting structure, the upper surface of the work platform (4) being provided with a protective structure, one end of the base (1) being fixedly connected to a climbing structure for a user to climb onto the work platform (4) to perform quality inspection, characterized in that: An admixture storage box (10) is fixedly connected to the base (1) below the working platform (4), and a partition (12) is provided inside the admixture storage box (10) for dividing the inner cavity of the admixture storage box (10) into a plurality of accommodating cavities, each of which is equipped with a water delivery component. A plurality of faucets (15) corresponding to the water delivery components are also installed at one end of the working platform (4) away from the climbing structure, and a metering bucket (9) is suspended below the faucet (15).
2. The concrete quality inspection platform in a mixer truck according to claim 1, characterized in that: The base (1) is a rectangular plate-shaped structure, and the support structure comprises four support columns (3) fixedly connected at four corners of the upper surface of the base (1), and the top ends of the support columns (3) are fixedly connected to the lower surface of the working platform (4).
3. The concrete quality inspection platform in a mixer truck according to claim 1, characterized in that: The protective structure comprises four rows of fences (5) arranged around the upper surface of the working platform (4), the bottom of the fences (5) being fixedly connected to the working platform (4), and the height of the fences (5) being not less than one hundred and twenty centimeters.
4. The concrete quality inspection platform in a mixer truck according to claim 1, characterized in that: The climbing structure comprises a vertically arranged ladder (6) fixedly connected between the base (1) and one end of the working platform (4), and an anti-slip groove (7) is provided on the pedal of the ladder (6).
5. The concrete quality inspection platform in a mixer truck according to claim 3, characterized in that: The inner wall of the metering barrel (9) is engraved with a scale mark, and the top of the metering barrel (9) is fixedly connected to a steel cable (8), and one end of the steel cable (8) away from the metering barrel (9) is connected to the fence (5).
6. The concrete quality inspection platform in a mixer truck according to claim 5, characterized in that: The water delivery assembly comprises a submersible pump (13) installed in the accommodating cavity, a water delivery pipe (14) being fixedly connected to the drainage end of the submersible pump (13), and an end of the water delivery pipe (14) away from the submersible pump (13) being fixedly connected to the corresponding faucet (15).
7. The concrete quality inspection platform in a mixer truck according to claim 6, characterized in that: The upper cover of the open end of the additive storage box (10) is provided with a box cover (11) for sealing the additive storage box (10); the box cover (11) is provided with a plurality of sliding holes corresponding to the water pipe (14); the middle section of the water pipe (14) passes through the box cover (11) through the sliding holes and is slidably connected to the box cover (11).