Novel box girder diaphragm plate slurry leakage prevention formwork
The novel anti-leakage slurry formwork for box girder diaphragms addresses leakage issues by using extension plates and baffles to eliminate gaps, ensuring no leakage during wet joint pouring and maintaining bridge appearance while being environmentally friendly.
Patent Information
- Application Number
- CN202420803274.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-18
- Publication Date
- 2024-12-06
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing box girder diaphragm formwork fails to consider the connection with wet joint construction, leading to concrete cement slurry leakage through gaps, which affects bridge appearance and causes environmental pollution.
A novel anti-leakage slurry formwork comprising anti-leakage side and bottom formworks with extension plates and baffles, along with a fixing device, ensures the gap between the wet joint and diaphragm is eliminated, and the interface is made rough to prevent leakage.
The new formwork design prevents leakage during wet joint pouring, maintains appearance quality, and saves materials by using reusable steel formwork.
Smart Images

Figure CN222119954U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of bridge construction, and more specifically, particularly relates to a novel anti-leakage slurry template for a box beam transverse diaphragm. Background Art
[0002] Precast concrete box girders are widely used in highway bridges, and the diaphragms and wet joints must be cast in situ. The formwork used in the traditional box girder diaphragm construction is as follows: Figure 1 As shown, it is composed of a traditional side formwork 1' and a bottom formwork 4. When using this traditional box beam diaphragm formwork for construction, the connection with the next process, i.e., wet joint construction, is not considered. Figure 2 As shown, the wet joint formwork 12 is installed after the diaphragm 11 is cast, resulting in an inevitable gap between the wet joint formwork 12 and the diaphragm 11 at the right angle connection. When the wet joint is cast, the concrete cement slurry often leaks through the gap, causing pollution to the box girder body and the diaphragm 11, seriously affecting the appearance of the bridge. Utility Model Content
[0003] The utility model aims to overcome the problem that when using the existing box girder diaphragm formwork for construction, the connection with the wet joint construction is not considered, resulting in the concrete cement slurry often leaking through the gap between the wet joint formwork and the diaphragm during wet joint pouring. The utility model aims to provide a new box girder diaphragm leakage-proof slurry formwork that can solve the above problem.
[0004] A novel anti-leakage slurry formwork for box girder transverse diaphragm, comprising an anti-leakage slurry side formwork and a bottom formwork, two sets of the anti-leakage slurry side formwork are arranged opposite to each other, the anti-leakage slurry side formwork comprises a fixedly connected side formwork, a side formwork extension plate and an extension plate baffle, the side formwork is arranged vertically, the side formwork extension plate is arranged horizontally and one end is fixed to the top of the side formwork, and the other end extends to the outside of the side formwork, the extension plate baffle is fixed to the top surface of the side formwork extension plate away from the side formwork. The bottom formwork is arranged horizontally between the bottoms of the two side formworks, and the two ends are connected to the side formworks.
[0005] Furthermore, a slurry stop strip is provided on one side of the epitaxial plate baffle close to the side mold template.
[0006] Furthermore, the length of the side mold epitaxial plate is 10 cm.
[0007] Furthermore, the height of the epitaxial plate baffle is 2 cm.
[0008] Furthermore, the anti-leakage side formwork and bottom formwork are both made of steel plates.
[0009] Furthermore, the thickness of the anti-leakage side formwork and the bottom formwork are both 2cm-3cm.
[0010] Furthermore, the bottom template is fixedly connected to the side template.
[0011] Furthermore, it also includes a fixing device, which includes a tension screw, a fixing nut and a gasket, at least one of the tension screws horizontally penetrates the two side formworks, the fixing bolts are connected to both ends of the tension screw and are located on the outside of the side formworks, and the gasket is arranged between the side formworks and the fixing bolts.
[0012] Furthermore, the fixing device also includes vertical stiffening ribs, which are fixed to the outside of the side formwork and arranged in the middle of the side formwork in the horizontal direction. The tension screws pass through the vertical stiffening ribs, and the gaskets and fixing nuts are sequentially arranged on the side of the vertical stiffening ribs away from the side formwork.
[0013] Furthermore, the fixing device also includes transverse stiffening ribs, a plurality of the transverse stiffening ribs are arranged on the outside of the side formwork and fixedly connected to the side formwork, and the vertical stiffening ribs are fixedly connected to the side formwork via the transverse stiffening ribs.
[0014] Compared with the prior art, the beneficial effects of the utility model are:
[0015] The new box girder diaphragm leakage-proof template in the utility model is provided with a side form extension plate and an extension plate baffle extending to the outside at the top of the side form template, so that the top of the diaphragm after pouring extends outward. When the wet joint is poured later, the wet joint template is located below the concrete at the extension, thereby eliminating the gap at the right-angle connection between the wet joint template and the diaphragm. The thickness of the concrete at the extension is guaranteed by providing the extension plate baffle. The slurry-stopping strip is provided on the inner side of the extension plate baffle to make the interface of the poured concrete rough, thereby ensuring the effective combination of the new and old concrete. The new box girder diaphragm leakage-proof template in the utility model ensures that there will be no leakage during the wet joint pouring, ensures the appearance quality of the diaphragm, prevents environmental pollution caused by leakage, and saves materials. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:
[0017] Figure 1 It is an exploded view of a traditional box girder diaphragm formwork in the background technology.
[0018] Figure 2 It is a schematic diagram of a diaphragm cast using a conventional box girder diaphragm formwork in the background art.
[0019] Figure 3It is a schematic diagram of the use status of the new box beam cross diaphragm anti-leakage slurry template in the embodiment of the utility model.
[0020] Figure 4 yes Figure 3 Enlarged view of the structure in the middle.
[0021] Figure 5 It is a schematic diagram of the overall structure of a novel box beam transverse diaphragm anti-leakage slurry template in an embodiment of the utility model.
[0022] Figure 6 It is a schematic diagram of a diaphragm cast by a novel box girder diaphragm anti-leakage slurry template in an embodiment of the utility model.
[0023] In the figure: 1', traditional side formwork; 1, side formwork formwork; 2, side formwork extension plate; 3, extension plate baffle; 4, bottom formwork; 5, tension screws; 6, fixing nuts; 7, gaskets; 8, vertical stiffening ribs; 9, transverse stiffening ribs; 10, transverse diaphragm steel bars; 11, transverse diaphragm; 12, wet joint formwork; 13, box girder top plate. DETAILED DESCRIPTION
[0024] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0025] like Figure 3-Figure 6 As shown, the novel box girder transverse diaphragm anti-leakage slurry formwork in this embodiment includes an anti-leakage slurry side formwork and a bottom formwork 4. The two sets of anti-leakage slurry side forms are arranged oppositely. The anti-leakage slurry side formwork includes a fixedly connected side formwork template 1, a side formwork extension plate 2 and an extension plate baffle 3. The side formwork template 1 is arranged vertically, the side formwork extension plate 2 is arranged horizontally and one end is fixed to the top of the side formwork template 1, and the other end extends to the outside of the side formwork template 1. The extension plate baffle 3 is fixed to the top surface of the side formwork extension plate 2 away from the side formwork template 1. The bottom formwork 4 is horizontally arranged between the bottoms of the two side formwork templates 1, and the two ends are connected to the side formwork template 1.
[0026] In this embodiment, the anti-leakage side mold and the bottom mold plate 4 are both made of steel plates, and the side mold template 1, the side mold extension plate 2 and the extension plate baffle 3 are fixed by integral molding or welding. The length of the side mold extension plate 2 is 10 cm, the height of the extension plate baffle 3 is 2 cm, and the thickness of the anti-leakage side mold and the bottom mold plate 4 are both 2 cm-3 cm.
[0027] In this embodiment, the bottom mold plate 4 is fixedly connected to the side mold plate 1, and specifically, a welding connection is adopted.
[0028] The novel box girder diaphragm anti-leakage slurry formwork in this embodiment also includes a fixing device, which includes transverse stiffening ribs 9, vertical stiffening ribs 8, tension screws 5, fixing nuts 6 and gaskets 7. A plurality of transverse stiffening ribs 9 are horizontally arranged on the outside of the side formwork 1 and welded to the side formwork 1. The transverse stiffening ribs 9 can be made of angle steel or channel steel. The vertical stiffening ribs 8 are fixed to the outside of the transverse stiffening ribs 9 and are arranged in the middle of the side formwork 1 in the horizontal direction. The vertical stiffening ribs 8 are welded to the transverse stiffening ribs 9. At least one tension screw 5 horizontally penetrates the two side formworks 1 and the vertical stiffening ribs 8 on the outside of the side formwork 1. The fixing bolts are connected to the two ends of the tension screw 5 and are located on the outside of the vertical stiffening ribs 8. The gaskets 7 are arranged between the vertical stiffening ribs 8 and the fixing bolts.
[0029] When installing the new type of box beam transverse diaphragm anti-leakage grouting formwork in this embodiment, the side formwork 1 is installed on both sides of the transverse diaphragm reinforcement 10, the upper surface of the side form extension plate 2 is flush with the lower surface of the box beam top plate 13, and the tension screw 5, gasket 7 and fixing nut 6 are installed to fix the new type of box beam transverse diaphragm anti-leakage grouting formwork in this embodiment, and then the transverse diaphragm 11 is cast. The cast transverse diaphragm 11 is shown in FIG. Figure 6 As shown, the outer extension concrete is poured on both sides of the top of the diaphragm 11. After the diaphragm 11 is poured, the wet joint formwork 12 is installed. The wet joint formwork 12 is located below the outer extension concrete.
[0030] The working principle of the novel box beam diaphragm anti-leakage slurry template in this embodiment is:
[0031] By setting the side form extension plate 2 and the extension plate baffle 3 extending to the outside at the top of the side form template 1, the top of the diaphragm 11 after casting is extended outward. When the wet joint is cast later, the wet joint template 12 is located below the concrete at the extension, thereby eliminating the gap at the right-angle connection between the wet joint template 12 and the diaphragm 11. By setting the extension plate baffle 3, the thickness of the concrete at the extension is guaranteed. The slurry stop strip is set on the inner side of the extension plate baffle 3 to make the interface of the cast concrete rough, ensuring the effective combination of new and old concrete. The new box beam diaphragm anti-leakage slurry template in the utility model ensures that there will be no leakage during the wet joint casting, ensures the appearance quality of the diaphragm 11, and prevents environmental pollution caused by leakage, saving materials.
[0032] Reusable steel formwork is used to replace traditional wooden formwork. Steel formwork can be recycled, which is conducive to the conservation of resources and meets the requirements of energy conservation, low carbon and sustainable development.
[0033] Finally, it should be noted that the above description is only a preferred embodiment of the utility model and is not intended to limit the utility model. Although the utility model is described in detail with reference to the above embodiments, those skilled in the art can still modify the technical solutions recorded in the above embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.
Claims
1. A new type of box beam diaphragm anti-leakage slurry formwork, characterized in that: include: Two sets of anti-leakage slurry side forms are arranged opposite to each other, the anti-leakage slurry side forms comprising a fixedly connected side form template (1), a side form extension plate (2) and an extension plate baffle (3), the side form template (1) is arranged vertically, the side form extension plate (2) is arranged horizontally and one end is fixed to the top of the side form template (1), and the other end extends to the outside of the side form template (1), and the extension plate baffle (3) is fixed to the top surface of the side form extension plate (2) at one end away from the side form template (1); A bottom template (4), wherein the bottom template (4) is horizontally arranged between the bottoms of the two side templates (1), and the two ends of the bottom template are connected to the side templates (1).
2. The novel box beam diaphragm anti-leakage grout formwork according to claim 1 is characterized in that: A slurry stop strip is provided on one side of the extension plate baffle (3) close to the side mold template (1).
3. The novel box beam diaphragm anti-leakage grout formwork according to claim 1 is characterized in that: The length of the side mold epitaxial plate (2) is 10 cm.
4. The novel box girder diaphragm anti-leakage grout formwork according to claim 1 is characterized in that: The height of the epitaxial plate baffle (3) is 2 cm.
5. The novel box girder diaphragm anti-leakage grout formwork according to any one of claims 1 to 4, characterized in that: The anti-leakage slurry side formwork and the bottom formwork (4) are both made of steel plates.
6. The novel box girder diaphragm anti-leakage grout formwork according to claim 5 is characterized in that: The thickness of the anti-leakage slurry side formwork and the bottom formwork (4) are both 2cm-3cm.
7. The novel box girder diaphragm anti-leakage grout formwork according to claim 1 is characterized in that: The bottom mold plate (4) is fixedly connected to the side mold plate (1).
8. The novel box beam diaphragm anti-leakage grout formwork according to claim 7 is characterized in that: It also includes a fixing device, which includes a tension screw (5), a fixing nut (6) and a gasket (7), at least one of the tension screws (5) horizontally passes through the two side formworks (1), the fixing nut (6) is connected to the two ends of the tension screw (5) and is located on the outside of the side formwork (1), and the gasket (7) is arranged between the side formwork (1) and the fixing bolt.
9. The novel box beam diaphragm anti-leakage grout formwork according to claim 8 is characterized in that: The fixing device also includes a vertical stiffening rib (8), which is fixed to the outside of the side form template (1) and is arranged in the middle of the side form template (1) in the horizontal direction. The tension screw (5) passes through the vertical stiffening rib (8), and the gasket (7) and the fixing nut (6) are arranged in sequence on the side of the vertical stiffening rib (8) away from the side form template (1).
10. The novel box beam diaphragm anti-leakage grout formwork according to claim 9 is characterized in that: The fixing device also includes transverse stiffening ribs (9), a plurality of the transverse stiffening ribs (9) are arranged on the outside of the side formwork template (1) and are fixedly connected to the side formwork template (1), and the vertical stiffening ribs (8) are fixedly connected to the side formwork template (1) via the transverse stiffening ribs (9).