Splicing type pipeline tunnel support
By designing a spliced pipeline tunnel support device with adjustable support rods, the problem that the existing technology cannot be applied to large pipelines is solved, and the support and convenient transportation of pipelines of different diameters is achieved, reducing the risk and difficulty of tunnel construction.
Patent Information
- Application Number
- CN202420683641.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-03
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2034-04-03
AI Technical Summary
The prior art cannot be applied to the installation of tunnel support for large pipelines, resulting in risk of pit wall collapse and inconvenience in construction.
A spliced pipe tunnel support device is designed. Through symmetrically arranged support plates and adjustable support rods, the installation position of the support rod can be adjusted according to the diameter of the pipe. It is suitable for pipes of different diameters, and adopts spliced structure and Drag the rope for easy transportation and movement.
It realizes safe support when placing large pipes in the tunnel, is suitable for pipes of different pipe diameters and sizes, and reduces the storage space and transportation difficulty of the device.
Smart Images

Figure CN222120262U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of tunnel support, in particular to a spliced pipeline tunnel support. Background Art
[0002] In the construction of drainage wells and water supply wells in engineering foundation pits, it is necessary to pre-buried pipes. Before pre-buried pipes, it is usually necessary to dig up the ground to form a working tunnel for construction workers to work in the tunnel. However, due to limited working space, the excavation and slope of the working surface are insufficient, or the pit wall is disturbed during construction, which can easily lead to pit wall collapse and cause safety accidents. Once the soil layer collapses and submerges people's chests, there is a risk of suffocation.
[0003] Chinese patent CN202322088561.9 discloses "Municipal Pipeline Groove Support Structure", publication number CN220486483U, the device includes soil wall, support plate, square wood, U-shaped slot, adjusting screw, adjusting nut, support rod. When the device is used, the support plate is first placed vertically and closely on the soil wall, and then the square wood is connected to the support plate. The square wood can increase the force area as the front rib of the support plate. After the support plates and square wood on both sides of the soil wall are placed, the U-shaped slot on one side of the adjusting screw is engaged with the square wood on one side, and then the adjusting nut is rotated according to the width of the pipeline groove. The rotation of the adjusting nut drives the support rod mounted on the adjusting screw to move until the U-shaped slot on the right side of the support rod is engaged with the square wood on the right soil wall. However, the device has some defects: when a large pipeline is placed in the tunnel, the setting position of the support rod on the device conflicts with the placement position of the pipeline, so the device cannot be used in tunnels where large pipelines are installed. Utility Model Content
[0004] In order to solve the above problems of the prior art, the utility model provides a spliced pipeline tunnel support. When assembling the device, the installation position of the support rod can be adjusted to be suitable for pipelines of different diameters.
[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a spliced pipeline tunnel support, including symmetrically arranged support plates, on which support rods are slidably connected for supporting the support plates; the support rods include a first force-bearing rod slidably connected to the support plates, and an extension rod connected to the first force-bearing rod, and connection holes are provided on the first force-bearing rod and the extension rod; a fixing plate is fixedly connected to the first force-bearing rod, and the fixing plate is fixedly connected to the support plate by bolts.
[0006] By adopting the above structural design, the installation position of the support rod can be adjusted according to the diameter of the buried pipeline, so that the installation position of the support rod does not hinder the buried pipeline.
[0007] Preferably, the first stress-bearing rod is U-shaped, the cross-section of the extension rod is I-shaped, and the first stress-bearing rod is plugged into the extension rod.
[0008] With the above structural design, the first force-bearing rod can be spliced onto the extension rod to increase the stability of the connection.
[0009] Preferably, the first force-bearing rod is hingedly connected to an oblique support rod, the oblique support rod is fixedly connected to a positioning plate, the positioning plate is penetrated by positioning bolts, and the supporting plate is provided with positioning holes matching the positioning bolts.
[0010] With the above structural design, the diagonal bracing rods can be retracted and expanded for easy storage, and the diagonal bracing rods can increase the stability of the connection between the supporting rods and the supporting plates.
[0011] Preferably, a towing rope is fixedly connected to the supporting plate, and a hook ring is fixedly connected to the towing rope.
[0012] With the above structural design, when the device needs to be moved in the tunnel, the staff can operate the trailer to connect the towing rope to move the device.
[0013] Preferably, the support plate includes a left support plate and a right support plate, and a splicing block fixedly connected to the left support plate, the right support plate is provided with a splicing groove matching the splicing block, the upper end of the left support plate is fixedly connected to a connecting plate, the connecting plate is provided with connecting bolts, and the connecting bolts pass through the connecting plate and are installed on the right support plate by threads.
[0014] With the above structural design, the support plates adopt a splicing structure, which reduces the area of a single support plate and facilitates the transportation of the device.
[0015] Compared with the prior art, the beneficial effects of the utility model are:
[0016] 1) When a large pipeline is placed in the tunnel, the device can adjust the setting position of the force transmission support rod according to the placement position of the pipeline, so that the device can be placed in the construction tunnel.
[0017] 2) Within a certain range, it is suitable for catheters of different diameters.
[0018] 3) The device adopts a splicing structure, which can reduce the storage space of the device and make the device easier to transport. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 It is a structural schematic diagram of the utility model;
[0020] Figure 2 It is a schematic diagram of the structure of the utility model from a top view;
[0021] Figure 3 It is a structural schematic diagram of the support plate of the utility model; DETAILED DESCRIPTION
[0022] See also Figure 1 , Figure 2 , Figure 3 The utility model provides a technical solution: a spliced pipeline tunnel support, including a symmetrically arranged support plate 1, on which a support rod for supporting the support plate 1 is slidably connected; two groups of support rods are provided, which are respectively arranged at both ends of the support plate 1; the support rod includes a first force-bearing rod 21 slidably connected to the support plate 1, and an extension rod 22 connected to the first force-bearing rod 21, and connecting holes are provided on the first force-bearing rod 21 and the extension rod 22; a fixing plate 26 is fixedly connected to the first force-bearing rod 21, and the fixing plate 26 is fixedly connected to the support plate 1 by bolts.
[0023] The first force-bearing rod 21 is fixedly connected to a circular splicing column at the end close to the supporting plate 1 , and correspondingly, a connecting groove matching the splicing column is provided on the supporting plate 1 .
[0024] The first force-bearing rod 21 is U-shaped, the cross section of the extension rod 22 is I-shaped, and the first force-bearing rod 21 is plugged into the extension rod 22 .
[0025] The diagonal support rod 23 is hinged on the first force-bearing rod 21, and the diagonal support rod 23 is hinged on the inner side wall of the U-shaped opening of the first force-bearing rod 21. The diagonal support rod 23 is fixedly connected to the positioning plate 24. The end of the diagonal support rod 23 close to the supporting plate 1 is fixedly connected to the positioning plate 24. A positioning bolt 25 is passed through the positioning plate 24, and a positioning hole matching the positioning bolt 25 is opened on the supporting plate 1.
[0026] The towing rope 3 is fixedly connected to the supporting plate 1 , a connecting seat is welded at the upper end of the supporting plate 1 , an end of the towing rope 3 is fixedly connected to the connecting seat, and a connecting ring 31 is fixedly connected to the towing rope 3 .
[0027] The support plate 1 includes a left support plate 11 and a right support plate 12, and a splicing block 13 fixedly connected to the left support plate 11. The right support plate 12 is provided with a splicing groove matching the splicing block 13. The upper end of the left support plate 11 is fixedly connected to a connecting plate 14, and a connecting bolt 15 is passed through the connecting plate 14 and is installed on the right support plate 12 by threads.
[0028] A first connecting plate is fixedly connected to the lower end of the right supporting plate 12, a first bolt is passed through the first connecting plate, and the first bolt passes through the first connecting plate and is installed on the left supporting plate through threads.
[0029] When the device is in use, first, the staff splices the left support plate 11 and the right support plate 12 together, inserts the splicing block 13 into the splicing groove, and then passes the connecting bolt 15 through the connecting plate 14 and installs it on the right support plate 12 through threading; the staff then selects the splicing height of the support rod according to the size of the diameter of the embedded pipe, and then the staff rotates the diagonal support rod 23 to fit the positioning plate 24 with the support plate 1, and then the staff inserts the splicing column into the connecting groove, moves the first force-bearing rod 21, and installs the fixing plate 26 on the support plate 1 with bolts, and then the staff uses the positioning bolt 25 to fix the diagonal support rod on the support plate 1, and then the staff puts the device into the tunnel, and protects the staff when they are constructing in the tunnel. When the staff are constructing the next section of the pipeline, the staff operates the trailer to connect the hook 31 of the towing rope 3, drags the device, moves the device in the tunnel, and moves the device to the construction site of the next section of the construction pipeline.
[0030] The structures, proportions, sizes, etc. illustrated in the drawings of this specification are only used to match the contents disclosed in the specification for people familiar with this technology to understand and read, and are not used to limit the limiting conditions for the implementation of the utility model, so they have no substantial technical significance. Any modification of the structure, change of the proportion relationship or adjustment of the size, without affecting the effect and purpose that can be achieved by the utility model, should still fall within the scope of the technical content disclosed by the utility model. At the same time, the terms such as "upper", "lower", "left", "right", "middle" and "one" quoted in this specification are only for the convenience of description, and are not used to limit the scope of the implementation of the utility model. The change or adjustment of their relative relationship should also be regarded as the scope of the implementation of the utility model without substantial change of the technical content.
[0031] The present invention is described above with reference to the preferred embodiments, but the protection scope of the present invention is not limited thereto, and all technical solutions falling within the scope of the claims are within the protection scope of the present invention. Various improvements may be made to the present invention and parts thereof may be replaced with equivalents without departing from the scope of the present invention. In particular, the various technical features mentioned in the various embodiments may be combined in any manner as long as there is no structural conflict.
Claims
1. A spliced pipeline tunnel support, comprising symmetrically arranged support plates (1), characterized in that: The support plate (1) is slidably connected to a support rod for supporting the support plate (1); the support rod comprises a first force-bearing rod (21) slidably connected to the support plate (1), and an extension rod (22) connected to the first force-bearing rod (21), and the first force-bearing rod (21) and the extension rod (22) are both provided with connection holes; the first force-bearing rod (21) is fixedly connected to a fixing plate (26), and the fixing plate (26) is fixedly connected to the support plate (1) by bolts.
2. The spliced pipeline tunnel support according to claim 1 is characterized in that: The first force-bearing rod (21) is U-shaped, the extension rod (22) has an I-shaped cross section, and the first force-bearing rod (21) is plugged into the extension rod (22).
3. The spliced pipeline tunnel support according to claim 1 is characterized in that: The first force-bearing rod (21) is hingedly connected to an oblique support rod (23), the oblique support rod (23) is fixedly connected to a positioning plate (24), a positioning bolt (25) is passed through the positioning plate (24), and a positioning hole matching the positioning bolt (25) is provided on the support plate (1).
4. The spliced pipeline tunnel support according to claim 1 is characterized in that: The support plate (1) is fixedly connected to a towing rope (3), and the towing rope (3) is fixedly connected to a hook ring (31).
5. A spliced pipeline tunnel support according to any one of claims 1 to 3, characterized in that: The support plate (1) comprises a left support plate (11) and a right support plate (12), and a splicing block (13) fixedly connected to the left support plate (11); a splicing groove matching the splicing block (13) is provided on the right support plate (12); the upper end of the left support plate (11) is fixedly connected to a connecting plate (14); a connecting bolt (15) is passed through the connecting plate (14) and is installed on the right support plate (12) by means of a thread.