Mine slope repairing and greening structure

By setting up support components on the mine slope to support the branches of green plants, the problems of swaying and damage of green plants in strong winds are solved, and the survival rate of green plants is improved.

CN222148472UActive Publication Date: 2024-12-13神木市店塔镇板墩焉村办煤矿
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420821623.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-19
Publication Date
2024-12-13
Estimated Expiration
2034-04-19

AI Technical Summary

Technical Problem

In strong winds, green plants on the mine slopes are prone to sway in the planting pit, resulting in damage to the branches and trunks and affecting survival rate.

Method used

A mine slope restoration green structure was designed, including mine slopes, pools, water transport modules and support components. The support components are composed of mounting frames, support sleeves, telescopic rods, limit springs, extruded arc blocks, rubber pads and auxiliary plates. It is composed of a support sleeve and an extruded arc block in contact with the green branch, and provides support with limiting springs and rubber pads to prevent the branches from bending and swaying.

Benefits of technology

It effectively prevents the swaying and damage of green plants in strong winds, and significantly improves the survival rate of green plants.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222148472U_ABST
    Figure CN222148472U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of ecological restoration, in particular to a mine slope restoration greening structure. Comprising a mine slope, a water pool, a water conveying module and multiple sets of supporting assemblies, each supporting assembly comprises a mounting frame, two supporting sleeves, two telescopic rods, two limiting springs and two extrusion arc blocks, the mounting frames are fixedly connected with the mine slope and located above planting pits, the two supporting sleeves are symmetrically arranged in the mounting frames, and the two telescopic rods are arranged in the water pool. The two ends of each telescopic rod are fixedly connected with the mounting frame and the corresponding supporting sleeve respectively, the two ends of each limiting spring are fixedly connected with the mounting frame and the corresponding supporting sleeve respectively, and each extrusion arc block is fixedly connected with the corresponding supporting sleeve. The green plants are prevented from swinging and being damaged, and the survival rate of the green plants is greatly increased.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of ecological restoration, in particular to a mine slope restoration and greening structure. Background Art

[0002] The exposed mining face formed by mining is difficult to recover quickly, which is extremely inconsistent with the surrounding environment and has a bad impact. At the same time, the slope structure is unstable and prone to rockfall, landslides and mud-rock flow, posing serious safety hazards to pedestrians and traffic in the surrounding area. The existing mine slope restoration is mainly carried out by planting green plants for greening.

[0003] In the prior art patent CN220383688U, a mine slope restoration greening structure is disclosed, in which green plants are planted in planting pits on the mine slope. The green plants on the slope are watered by utilizing the principle that water flows to lower places, and multiple water outlet pipes can be opened at the same time to water the green plants, thereby reducing the labor intensity of the staff.

[0004] However, in the above-mentioned prior art patent, when encountering strong winds, the green plants will sway in the planting pit, and the green plants are easily damaged, which will affect the survival rate of the green plants. Utility Model Content

[0005] The purpose of the utility model is to provide a mine slope repair greening structure, which solves the problem that when encountering strong winds, the green plants will sway in the planting pit, the green plants are easily damaged, and the survival rate of the green plants will be affected.

[0006] To achieve the above-mentioned purpose, the utility model adopts a mine slope repair and greening structure, including a mine slope, a pool, a water supply module and multiple groups of support components, the mine slope has multiple planting pits, the pool is arranged above the mine slope, the water supply module is connected to the pool and is located above the multiple planting pits, the support component includes a mounting frame, two support sleeves, two telescopic rods, two limit springs and two extrusion arc blocks, the mounting frame is fixedly connected to the mine slope and is located above the planting pits, the two support sleeves are symmetrically arranged in the mounting frame, the two ends of each of the telescopic rods are respectively fixedly connected to the mounting frame and the corresponding support sleeve, the two ends of each of the limit springs are respectively fixedly connected to the mounting frame and the corresponding support sleeve, and are respectively sleeved on the outside of the telescopic rod, and each of the extrusion arc blocks is respectively fixedly connected to the corresponding support sleeve and are respectively located on the outer side wall of the support sleeve.

[0007] Wherein, the support assembly further includes two rubber pads, which are respectively fixedly connected to the corresponding support sleeves and are respectively located on the inner side walls of the support sleeves.

[0008] Wherein, the support assembly further includes two auxiliary plates, and the two auxiliary plates are respectively fixedly connected to the corresponding support sleeves and are respectively located on the outer side walls of the support sleeves.

[0009] Wherein, the mine slope restoration and greening structure also includes a fixing component, and the fixing component is arranged below the installation frame.

[0010] Wherein, the fixing assembly includes two latches and two bonding plates, the two latches are fixedly connected to the installation frame and are both located below the installation frame, and the two bonding plates are respectively fixedly connected to the corresponding latches and are respectively sleeved on the outer walls of the corresponding latches.

[0011] Wherein, the fixing assembly further comprises a plurality of auxiliary pins, and the plurality of auxiliary pins are respectively fixedly connected to the corresponding bonding plates.

[0012] The utility model discloses a mine slope repair and greening structure. When planting green plants on the mine slope, the green plants are first planted in the planting pit, and then the installation frame is set on the mine slope, so that the two support sleeves move toward the green plants, and the extrusion arc blocks on the outside of the two support sleeves will first contact with the branches of the green plants, and each of the extrusion arc blocks will drive the support sleeve to move, and continue to drive the support sleeve to move, and then the green plants enter between the two support sleeves, and the action force of the limit spring will push the support sleeve to contact with the outer wall of the green plant branches and support the green plant branches to avoid bending of the green plant branches, and finally fix the installation frame on the mine slope to support and protect the green plants. Through the above method, it is achieved that the green plants can be supported in the planting pit, the green plants can be prevented from swaying, and the green plants can be avoided from being damaged, thereby greatly improving the survival rate of the green plants. BRIEF DESCRIPTION OF THE DRAWINGS

[0013] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0014] Figure 1 It is a schematic diagram of the overall structure of the first embodiment of the utility model.

[0015] Figure 2 It is a partial structural diagram of the first embodiment of the utility model.

[0016] Figure 3 It is a partial structural diagram of the second embodiment of the utility model.

[0017] Figure 4 The utility model Figure 3 A magnified view of the local structure at A.

[0018] 101- mine slope, 102- pool, 103- water delivery module, 104- installation frame, 105- support sleeve, 106- telescopic rod, 107- limit spring, 108- extrusion arc block, 109- rubber pad, 110- auxiliary plate, 111- planting pit, 201- latch, 202- laminating plate, 203- auxiliary pin. DETAILED DESCRIPTION

[0019] The embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are intended to be used to explain the present invention, and should not be construed as limiting the present invention.

[0020] First embodiment

[0021] See also Figure 1 and Figure 2 ,in Figure 1 is a schematic diagram of the overall structure of the first embodiment, Figure 2 It is a schematic structural diagram of part of the first embodiment.

[0022] The utility model provides a mine slope repair greening structure: including a mine slope 101, a pool 102, a water delivery module 103 and multiple groups of support components, wherein the support components include a mounting frame 104, two support sleeves 105, two telescopic rods 106, two limit springs 107, two extrusion arc blocks 108, two rubber pads 109 and two auxiliary plates 110. The above-mentioned solution solves the existing problem that when encountering strong winds, the green plants will sway in the planting pit, the green plants are easily damaged, and the survival rate of the green plants will be affected.

[0023] According to this specific embodiment, the mine slope 101 has a plurality of planting pits 111, the water pool 102 is arranged above the mine slope 101, the water supply module 103 is connected to the water pool 102, and is located above the plurality of the planting pits 111, and green plants are planted in the planting pits 111 of the mine slope 101. The water pool 102 provides water to the water supply module 103, and the water supply module 103 provides water to the green plants in the planting pits 111, thereby ensuring the normal growth of the green plants.

[0024] Among them, the installation frame 104 is fixedly connected to the mine slope 101 and is located above the planting pit 111. The two support sleeves 105 are symmetrically arranged in the installation frame 104. The two ends of each telescopic rod 106 are respectively fixedly connected to the installation frame 104 and the corresponding support sleeve 105. The two ends of each limit spring 107 are respectively fixedly connected to the installation frame 104 and the corresponding support sleeve 105, and are respectively sleeved on the outside of the telescopic rod 106. Each extrusion arc block 108 is respectively fixedly connected to the corresponding support sleeve 105 and is respectively located on the outer side wall of the support sleeve 105. When planting green plants on the mine slope 101, the green plants are first planted in the planting pit 111, and then the installation frame 104 is installed on the mine slope 1 01 is arranged so that the two support sleeves 105 move toward the green plant, and the extrusion arc blocks 108 outside the two support sleeves 105 will first contact the branches of the green plant, and each of the extrusion arc blocks 108 will drive the support sleeve 105 to move, and continue to drive the support sleeve 105 to move, and then the green plant enters between the two support sleeves 105, and the action force of the limit spring 107 will push the support sleeve 105 to contact the outer wall of the green plant branches and support the green plant branches to avoid bending of the green plant branches, and finally fix the mounting frame 104 on the mine slope 101 to support and protect the green plant. Through the above method, it is possible to support the green plants in the planting pit 111 to prevent the green plants from swaying and being damaged, thereby greatly improving the survival rate of the green plants.

[0025] Secondly, the two rubber pads 109 are fixedly connected to the corresponding support sleeves 105 and are respectively located on the inner walls of the support sleeves 105. The rubber pads 109 are arranged on the inner walls of the support sleeves 105. The rubber pads 109 are elastic and can increase the protective effect of the support sleeves 105 on the green plants.

[0026] At the same time, the two auxiliary plates 110 are fixedly connected to the corresponding support sleeves 105 and are respectively located on the outer walls of the support sleeves 105. By arranging the auxiliary plates 110 on the support sleeves 105, the auxiliary plates 110 can increase the support efficiency of the green plants and facilitate the protection of the green plants.

[0027] When planting green plants on the mine slope 101, the green plants are first planted in the planting pit 111, and then the mounting frame 104 is set on the mine slope 101, so that the two support sleeves 105 move toward the green plants, and the extrusion arc blocks 108 outside the two support sleeves 105 will first contact the branches of the green plants, and each of the extrusion arc blocks 108 will drive the support sleeve 105 to move, and continue to drive the support sleeve 105 to move, and then the green plants enter between the two support sleeves 105, and the force of the limit spring 107 will push the support sleeve 105 and the auxiliary plate 1 10 contacts the outer wall of the trunk of the green plant and supports the trunk of the green plant to avoid bending of the trunk of the green plant. Finally, the mounting frame 104 is fixed on the mine slope 101 to support and protect the green plant. In addition, by arranging the rubber pad 109 on the inner wall of the support sleeve 105, the rubber pad 109 is elastic and can increase the protective effect of the support sleeve 105 on the green plant. Through the above method, it is possible to support the green plants in the planting pit 111, prevent the green plants from swaying, avoid damage to the green plants, and greatly improve the survival rate of the green plants.

[0028] Second embodiment

[0029] See also Figure 3 and Figure 4 ,in Figure 3 is a schematic diagram of a part of the structure of the second embodiment, Figure 4 yes Figure 3 A magnified view of the local structure at A.

[0030] On the basis of the first embodiment, a mine slope restoration and greening structure of the utility model further includes a fixing component, and the fixing component includes two latch pins 201 , two bonding plates 202 and a plurality of auxiliary pins 203 .

[0031] The fixing component is arranged below the installation frame 104. By arranging the fixing component below the installation frame 104, the installation frame 104 can be stabilized on the mine slope 101 through the fixing component, which is beneficial to the support and protection of green plants.

[0032] The two latches 201 are fixedly connected to the installation frame 104 and are both located below the installation frame 104. The two bonding plates 202 are respectively fixedly connected to the corresponding latches 201 and are respectively sleeved on the outer walls of the corresponding latches 201. The installation frame 104 is inserted into the mine slope 101 through the two latches 201. The two bonding plates 202 are tightly attached to the mine slope 101, so that the installation frame 104 is stable on the mine slope 101, avoiding the installation frame 104 from moving on the mine slope 101, which is beneficial to the support and protection of green plants.

[0033] The plurality of auxiliary pins 203 are respectively fixedly connected to the corresponding bonding plates 202. When the latch 201 under the mounting frame 104 is fixed on the mine slope 101, the plurality of auxiliary pins 203 under the bonding plates 202 are all inserted into the mine slope 101, so that the mounting frame 104 can be fixed on the mine slope 101 more stably.

[0034] The installation frame 104 is inserted into the mine slope 101 through the two pins 201, and the two bonding plates 202 are tightly attached to the mine slope. At the same time, the multiple auxiliary pins 203 under the bonding plates 202 are all inserted into the mine slope, so that the installation frame 104 is stable on the mine slope 101, avoiding the installation frame 104 from moving on the mine slope 101, which is beneficial to the support and protection of green plants.

[0035] The above disclosures are only two preferred embodiments of the present invention, which certainly cannot be used to limit the scope of the present invention. A person skilled in the art can understand that all or part of the processes of the above embodiments and equivalent changes made according to the claims of the present invention still fall within the scope of the present invention.

Claims

1. A mine slope restoration and greening structure, comprising a mine slope, a pool and a water delivery module, wherein the mine slope has a plurality of planting pits, the pool is arranged above the mine slope, the water delivery module is connected to the pool and is located above the plurality of planting pits, characterized in that: It also includes multiple groups of support components, which include a mounting frame, two support sleeves, two telescopic rods, two limit springs and two extrusion arc blocks. The mounting frame is fixedly connected to the mine slope and is located above the planting pit. The two support sleeves are symmetrically arranged in the mounting frame. The two ends of each telescopic rod are respectively fixedly connected to the mounting frame and the corresponding support sleeve. The two ends of each limit spring are respectively fixedly connected to the mounting frame and the corresponding support sleeve, and are respectively sleeved on the outside of the telescopic rod. Each extrusion arc block is respectively fixedly connected to the corresponding support sleeve and is respectively located on the outer side wall of the support sleeve.

2. The mine slope restoration greening structure according to claim 1, characterized in that: The support assembly also includes two rubber pads, which are fixedly connected to the corresponding support sleeves and are respectively located on the inner side walls of the support sleeves.

3. The mine slope restoration greening structure according to claim 2, characterized in that: The support assembly also includes two auxiliary plates, which are fixedly connected to the corresponding support sleeves and are respectively located on the outer side walls of the support sleeves.

4. The mine slope restoration greening structure according to claim 1, characterized in that: The mine slope restoration and greening structure also includes a fixing component, which is arranged below the installation frame.

5. The mine slope restoration greening structure according to claim 4, characterized in that: The fixing assembly includes two latches and two bonding plates. The two latches are fixedly connected to the installation frame and are located below the installation frame. The two bonding plates are respectively fixedly connected to the corresponding latches and are respectively sleeved on the outer walls of the corresponding latches.

6. The mine slope restoration greening structure according to claim 5, characterized in that: The fixing assembly further comprises a plurality of auxiliary pins, and the plurality of auxiliary pins are respectively fixedly connected to the corresponding bonding plates.

Citation Information

Cited By

  • Mine slope repairing and treating device

    CN121647125A