Multilayer spliced wallboard

By setting sleeves and iron boxes in the wall panels and using multi-layer spliced ​​wall panel design with connecting rods and nuts locked, the problem of insufficient wall panel strength caused by through hole fixation in the prior art is solved, and structural stability is achieved and improve assembly convenience.

CN222183761UActive Publication Date: 2024-12-17SHANDONG XINHUOXIN MATERIAL TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420037815.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-08
Publication Date
2024-12-17
Estimated Expiration
2034-01-08

AI Technical Summary

Technical Problem

The connection method of existing prefabricated wall panels is fixed through through holes, which may damage the overall strength of the wall panels and lead to insufficient structural stability.

Method used

A multi-layer splicing wall panel design is adopted, in which the second wall is provided with a reserved connection hole, a sleeve is provided at one end of the first wall near the second wall, and an iron box is provided at one end of the third wall near the second wall. , lock it through the connecting rod and nut, and fill it with micro-expanded mortar in the gap to avoid excessive through holes damaging the main structure.

Benefits of technology

It effectively avoids wall panel strength damage, ensures structural stability, and simplifies the assembly process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222183761U_ABST
    Figure CN222183761U_ABST
Patent Text Reader

Abstract

The utility model relates to a multi-layer splicing type wallboard, which belongs to the field of assembly type buildings and comprises a first wall body, a second wall body and a third wall body which are mutually attached, a reserved connecting hole is formed in the second wall body, a reserved sleeve is arranged at one end, close to the second wall body, of the first wall body, and the third wall body is sleeved with the sleeve. A reserved iron box is arranged at the end, close to the second wall body, of the third wall body, the first wall body, the second wall body and the third wall body are fixed through a connecting rod, one end of the connecting rod is inserted into the reserved sleeve, and the other end of the connecting rod penetrates through the connecting hole and extends into the reserved iron box to be locked with a nut. The multi-layer splicing type wallboard disclosed by the utility model can ensure the strength of a wall body and is convenient to assemble.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of prefabricated wall panels, in particular to a multi-layer spliced ​​wall panel. Background Art

[0002] Compared with traditional buildings, prefabricated buildings have the advantages of saving construction manpower and time, reducing maintenance and operating costs. The Chinese invention patent application with publication number CN115749115A discloses a prefabricated wall panel, a special construction tool and a wall construction method. In this patent application, the prefabricated wall panels are provided with through holes that penetrate the top and the bottom, and the upper and lower layers of prefabricated wall panels are fixed by the penetration of steel bars. This method is also the main connection method of existing prefabricated wall panels. This connection method has obvious advantages and can ensure the stability of the connection between the wall panels; but the disadvantages are also obvious, because the setting of the through holes may destroy the overall strength of the wall panels.

[0003] Based on this, it is necessary to improve the connection method of prefabricated wall panels. Utility Model Content

[0004] Technical purpose: In order to overcome the shortcomings of the prior art, the utility model provides a multi-layer spliced ​​wall panel.

[0005] Technical solution: To achieve the above-mentioned purpose, the utility model discloses a multi-layer spliced ​​wall panel, comprising a first wall, a second wall and a third wall that fit together, wherein the second wall is provided with a reserved connecting hole, an end of the first wall close to the second wall is provided with a reserved sleeve, and an end of the third wall close to the second wall is provided with a reserved iron box, the first wall, the second wall and the third wall are fixed by a connecting rod, one end of the connecting rod is inserted into the reserved sleeve, and the other end of the connecting rod passes through the connecting hole and extends into the reserved iron box to be locked with a nut.

[0006] Furthermore, the second wall is defined as a floor slab, the first wall is defined as a wall panel, and the third wall is defined as a wall panel or a parapet.

[0007] Furthermore, it also includes a foundation, the foundation is provided with a groove opening upward, the bottom of the first wall extends into the groove, a protrusion is provided in the groove, and the bottom of the first wall is provided with a recess matched with the protrusion.

[0008] Furthermore, concrete is filled between the foundation and the first wall and the second wall.

[0009] Furthermore, the reserved iron box is filled with concrete.

[0010] Furthermore, when the two second walls are aligned left and right, a gap is left between the two adjacent second walls.

[0011] Furthermore, the gap between the connection hole and the first wall or the third wall is filled with micro-expansion mortar.

[0012] The multi-layer spliced ​​wallboard disclosed in the utility model has the following technical effects:

[0013] By reserving sleeves or iron boxes in the first wall and the third wall, it is avoided to set too many through holes in the first wall or the third wall, thereby avoiding damage to the strength of the main structure, ensuring the stability of the structure, and having the advantages of easy assembly. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 It is a structural schematic diagram of embodiment 1;

[0015] Figure 2 It is a structural schematic diagram of Embodiment 2;

[0016] Figure 3 This is a schematic diagram of the structure of Embodiment 3;

[0017] Figure 4 It is a structural diagram of embodiment 4.

[0018] In the figure, 1, first wall; 2, second wall; 3, third wall; 4, connecting hole; 5, sleeve; 6, iron box; 7, connecting rod; 8, nut; 9, foundation; 10, slot; 11, recess; 12, protrusion. DETAILED DESCRIPTION

[0019] The following is combined with Figure 1 To Attachment Figure 4 The principles and features of the present invention are described, and the examples given are only used to explain the present invention, and are not used to limit the scope of the present invention.

[0020] A multi-layer spliced ​​wall comprises a first wall 1, a second wall 2, a third wall 3 and a foundation 9 which are attached to each other. According to the different positions of the first wall 1, the second wall 2 and the third wall 3 on the building, the wall can be divided into the following four embodiments.

[0021] Embodiment 1, refer to the attached Figure 1 , this embodiment is a connection method of walls between two adjacent floors of buildings in a building structure.

[0022] In this embodiment, the first wall 1 is defined as a wall panel, the second wall 2 is defined as a floor slab, and the third wall 3 is defined as a wall panel. The first wall 1 is arranged below the second wall 2, and the third wall 3 is arranged above the second wall 2, and the adjacent surfaces of the first wall 1, the second wall 2 and the third wall 3 are mutually attached. A reserved sleeve 5 is arranged at one end of the first wall 1 close to the second wall 2 (i.e. the top of the first wall 1), and a reserved iron box 6 is arranged at one end of the third wall 3 close to the second wall 2 (i.e. the bottom of the third wall 3), and the second wall 2 is provided with a reserved connection hole 4, which is through. The first wall 1, the second wall 2, and the third wall 3 are fixed by a connecting rod 7, and the connecting rod 7 is a steel bar with a thread. One end of the connecting rod 7 is inserted into the reserved sleeve 5, and the other end of the connecting rod 7 passes through the connecting hole 4 and extends into the reserved iron box 6 to be locked with a nut 8. After the nut 8 is locked with the connecting rod 7, the reserved iron box 6 is filled with cement, and at the same time, the gap between the connecting hole 4 and the first wall 1 or the third wall 3 is filled with micro-expansion mortar to ensure the firmness of the connection between the first wall 1, the second wall 2 and the third wall 3.

[0023] Embodiment 2, refer to the attached Figure 2 In the first embodiment, a second wall 2 is disposed between the first wall 1 and the second wall 3; in the present embodiment, two second walls 2 are disposed between the first wall 1 and the second wall 3. It should be noted that a gap of about 5 mm should be left between the two second walls 2.

[0024] Embodiment 3, refer to the attached Figure 3 This embodiment is a fixed connection method between the parapet wall and the wall of the top floor of a building in a building structure.

[0025] In this embodiment, the first wall 1 is defined as a wall panel, the second wall 2 is defined as a floor slab, and the third wall 3 is defined as a parapet. The first wall 1 is arranged below the second wall 2, the third wall 3 is arranged above the second wall 2, and the adjacent surfaces of the first wall 1, the second wall 2 and the third wall 3 are in contact with each other. A sleeve 5 is arranged at one end of the first wall 1 close to the second wall 2, a reserved connection hole 4 is arranged in the second wall 2, and a reserved iron box 6 is arranged at one end of the third wall 3 close to the second wall 2. The first wall 1, the second wall 2 and the third wall 3 are relatively fixed by a connecting rod 7, and the connecting rod 7 is a steel bar with a thread. One end of the connecting rod 7 is inserted into the reserved sleeve 5, and the other end of the connecting rod 7 passes through the connecting hole 4 and extends into the reserved iron box 6 to be locked with a nut 8. After the nut 8 is locked with the connecting rod 7, the reserved iron box 6 is filled with cement, and the gap between the connecting hole 4 and the first wall 1 or the third wall 3 is filled with micro-expansion mortar to ensure the firmness of the connection between the first wall 1, the second wall 2 and the third wall 3. It should be noted that in this embodiment, not all connecting rods 7 are connected to the first wall 1, the second wall 2 and the third wall 3 at the same time. Some connecting rods 7 are only used to connect the first wall 1 and the second wall (see the attached Figure 3 The connecting rod 7 on the right side), at this time, it should be noted that the connecting rod 7 should not pass through the reserved connecting hole 4.

[0026] Embodiment 4, refer to the attached Figure 4 This embodiment is a connection method of the walls between the lowest floors of the building structure. The first wall 1 is defined as a wall panel, and the second wall 2 is defined as a floor slab. The bottom end of the first wall 1 is connected to the foundation 9, and the second wall 2 is placed on the upper end of the foundation 9.

[0027] The foundation 9 is fixed on the building ground, and is provided with an opening 10 which opens upward. The bottom of the first wall 1 extends into the opening 10, and a protrusion 12 is provided in the opening 10. The bottom of the first wall 1 is provided with a recess 11 which matches the protrusion 12, and a gap is left between the foundation 9 and the second wall 1 and the second wall 2.

[0028] Therefore, the first to fourth embodiments disclose the basic connection method of multi-story buildings with prefabricated wall panels.

[0029] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A multi-layer spliced ​​wall panel, characterized in that: The invention comprises a first wall (1), a second wall (2) and a third wall (3) which are fitted together, wherein the second wall (2) is provided with a reserved connection hole (4), the end of the first wall (1) close to the second wall (2) is provided with a reserved sleeve (5), the end of the third wall (3) close to the second wall (2) is provided with a reserved iron box (6), the first wall (1), the second wall (2) and the third wall (3) are fixed by a connecting rod (7), one end of the connecting rod (7) is inserted into the reserved sleeve (5), and the other end of the connecting rod (7) passes through the connection hole (4) and extends into the reserved iron box (6) to be locked with a nut (8).

2. The multi-layer spliced ​​wall panel according to claim 1, characterized in that: The second wall (2) is defined as a floor slab, the first wall (1) is defined as a wall panel, and the third wall (3) is defined as a wall panel or a parapet.

3. The multi-layer spliced ​​wall panel according to claim 1, characterized in that: The invention also comprises a foundation (9), wherein the foundation (9) is provided with an opening (10) opening upward, the bottom of the first wall (1) extends into the opening (10), a protrusion (12) is provided in the opening (10), and the bottom of the first wall (1) is provided with a recess (11) matching the protrusion (12).

4. The multi-layer spliced ​​wall panel according to claim 3, characterized in that: Concrete is filled between the foundation (9) and the first wall (1) and the second wall (2).

5. The multi-layer spliced ​​wall panel according to claim 1, characterized in that: The reserved iron box (6) is filled with concrete.

6. The multi-layer spliced ​​wall panel according to claim 1, characterized in that: When the two second walls (2) are aligned left and right, a gap is left between the two adjacent second walls (2).

7. The multi-layer spliced ​​wall panel according to claim 1, characterized in that: The gap between the connection hole (4) and the first wall (1) or the third wall (3) is filled with micro-expansion mortar.