Rapid and automatic pipeline coating system
By designing a quick and automatic pipeline coating system, using multi-angle spraying and immediate drying technology, the problems of low production efficiency and paint film damage in the existing technology are solved, and high-quality pipeline coating is achieved.
Patent Information
- Application Number
- CN202420865121.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-24
- Publication Date
- 2024-12-27
- Estimated Expiration
- 2034-04-24
AI Technical Summary
The existing pipeline coating production lines cannot achieve multi-process mixed line production, resulting in low production efficiency. The paint film after spraying is easily damaged during the transportation process, and the position drying of the paint film cannot be achieved, resulting in unqualified quality.
A rapid automatic pipeline coating system is designed, including a spraying device and a drying device, which realizes multi-angle spraying and immediate drying of the pipeline through multiple rollers and clamping devices, and protects drying with ultraviolet lamps and rotary mechanisms. The device ensures that the paint film is evenly dry.
The production efficiency and quality of pipeline coating are improved, and the integration of spraying and drying is achieved, ensuring uniform drying of the paint film is avoided, and the adaptability and efficiency of the production line is improved.
Smart Images

Figure CN222240992U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of pipeline coating, in particular to a pipeline rapid automatic coating system. Background Art
[0002] The pipeline coating process generally consists of pre-treatment, spraying, drying and other processes. Pre-treatment is to polish the outer wall of the pipeline, spraying is to spray paint on the pipeline, and drying is to dry the paint film after spraying. However, the product specifications of most existing large-scale pipeline coating production lines are relatively simple, and it is impossible to achieve mixed production of multiple processes, which leads to low production efficiency in the production process. It is difficult for a simple spraying production line for pipelines to produce high-quality coating products.
[0003] During the pipeline painting process, multi-angle spraying is required to achieve the effect of uniform paint film thickness. The pipeline that has been sprayed needs to be transported to the next drying stage. During the transportation process, the paint film on the pipeline is very easy to be bumped and scratched, that is, the paint film drying process cannot be carried out at the position where the spraying is completed on the pipeline, resulting in unqualified pipeline quality and low pipeline painting production efficiency. Utility Model Content
[0004] 1. Technical issues to be resolved
[0005] In view of the above-mentioned shortcomings and deficiencies of the prior art, the utility model provides a rapid automatic painting system for pipelines, which solves the hidden dangers of the paint film of the pipeline that has been sprayed failing to be quickly solidified and the paint film being damaged during the transportation process of the pipeline, that is, the process of drying the paint film at the position where the spraying is completed on the pipeline cannot be realized, thereby resulting in unqualified quality of the pipeline and further leading to the technical problem of low production efficiency of pipeline painting.
[0006] (II) Technical solution
[0007] In order to achieve the above-mentioned purpose, the main technical solutions adopted by the utility model include:
[0008] The utility model provides a pipeline rapid automatic coating system, including a spraying device and a drying device; the spraying device includes a first box, a plurality of first rollers, a spraying mechanism and a clamping device, the first box is provided with openings at the bottom and both ends, the plurality of first rollers are rotatably installed on the bottom wall of the first box at intervals, the pipeline is placed flat on the plurality of first rollers, the axial direction of the pipeline is perpendicular to the axial direction of the first rollers, the clamping device can be lifted into the first box or located below the first box, and the clamping device can clamp the pipeline and drive the pipeline to rotate around the axis of the pipeline when it is inside the first box, a long through hole along the length direction of the first box is provided on the top wall of the first box directly above the pipeline, the spraying mechanism is movably installed in the long through hole through a first track; the plurality of drying devices are installed at equal intervals on the upper part of the side walls on both sides of the first box, and the drying device can be opened or closed to immediately dry the pipeline after spraying.
[0009] Preferably, the drying device includes a mounting seat, an ultraviolet lamp, a protective cover and a rotating mechanism; one side of the mounting seat is connected to the upper part of the side wall of the first box body and a groove is provided on the side wall of the mounting seat opposite to the side wall of the first box body, the two ends of the ultraviolet lamp are connected to the side walls of the groove through a connecting rod, the protective cover is placed in the groove and the two ends of the protective cover are mounted on the connecting rod through the rotating mechanism, and the rotating mechanism can drive the protective cover to rotate around the axis of the connecting rod to turn on or off the drying of the pipeline.
[0010] Preferably, the cross-sections of the groove and the protective cover are both semicircular.
[0011] Preferably, the rotating mechanism includes a gear, two rollers, a latch and a first oil cylinder; the two rollers are respectively mounted on the two connecting rods and the outer walls of the two rollers are respectively connected to the two ends of the protective cover, and the gear is connected to one of the rollers; the fixed end of the first oil cylinder is installed on the side wall of the first box body, and the protruding end of the first oil cylinder is connected to one end of the latch, and the latch is engaged with the gear.
[0012] Preferably, the clamping device includes a first clamping mechanism and a second clamping mechanism; the first clamping mechanism and the second clamping mechanism are relatively arranged in a direction perpendicular to the first roller and the axes of the first clamping mechanism and the second clamping mechanism are always consistent during the lifting process; the first clamping mechanism is fixedly installed at the bottom of the first box body, and the second clamping mechanism is movably installed at the bottom of the first box body, and the second clamping mechanism can move in a direction close to or away from the first clamping mechanism.
[0013] Preferably, the first clamping mechanism includes a first fixed seat, a first lifting cylinder, a first clamping piece and a first bearing; the first fixed seat is located below the first box body, the fixed end of the first lifting cylinder is connected to the top of the first fixed seat, the extended end of the first lifting cylinder is detachably connected to the first clamping piece through the first bearing, and the axis of the first lifting cylinder is perpendicular to the axis of the first clamping piece; the second clamping mechanism includes a second fixed seat, a second lifting cylinder, a first motor, a second clamping piece, a moving seat, a second track and a second cylinder; the fixed ends of the second track and the second cylinder are both installed below the first box body, the moving seat is movably installed on the second track and the tail end of the moving seat is connected to the extended end of the second cylinder, the second lifting cylinder is installed on the top of the moving seat through the second fixed seat, the first motor is installed on the top of the second lifting cylinder and the motor is detachably connected to the second clamping piece, and the axis of the second clamping piece is perpendicular to the axis of the second lifting cylinder.
[0014] Preferably, the first clamping member and the second clamping member are both conical, and the cones of the first clamping member and the cones of the second clamping member are arranged opposite to each other.
[0015] Preferably, it also includes a grinding device; the grinding device includes a second box body, a plurality of second rollers and a grinding mechanism; the second box body is provided with openings at the bottom and both ends, the plurality of second rollers are rotatably installed at the bottom of the second box body at intervals, and the grinding mechanism is placed inside the second box body; the axis of the pipeline is consistent with the axis of the grinding mechanism and the pipeline is placed flat on the plurality of second rollers, the axial direction of the pipeline is perpendicular to the axial direction of the second rollers and the pipeline can pass through the grinding mechanism, so that the grinding mechanism grinds the outer wall of the pipeline.
[0016] Preferably, the grinding mechanism includes a first rotating drum, a second rotating drum, a third rotating drum, a plurality of mounting plates, a plurality of grinding pieces, a plurality of screws and a second motor; the first rotating drum, the second rotating drum and the third rotating drum are connected in sequence and have consistent axes, and the output end of the second motor is connected in series with the second rotating drum through a belt or a chain to drive the first rotating drum, the second rotating drum and the third rotating drum to rotate simultaneously; the plurality of mounting plates, the plurality of grinding pieces and the plurality of screws correspond to each other one by one and are circumferentially arrayed around the axis of the third rotating drum, the side walls of the plurality of grinding pieces facing the axis of the third rotating drum form a circle, the screw passes through the outer wall of the third rotating drum and the screw, the mounting plate and the grinding pieces are connected in sequence.
[0017] Preferably, the spraying mechanism comprises a spray gun and a telescopic member; the spray gun is installed on the first track through the telescopic member, and the telescopic member can drive the spray gun to rise and fall vertically.
[0018] (III) Beneficial effects
[0019] The beneficial effects of the utility model are:
[0020] 1. The utility model provides a rapid automatic coating system for pipelines. By arranging a plurality of first rollers at the bottom of the first box body, the friction force of the pipeline when moving on the plurality of rollers is smaller, which is more conducive to the movement of the pipeline on the plurality of rollers; by opening a first long through hole at the top of the first box body and installing a first track at the first long through hole, the spraying mechanism can reciprocate on the first track, thereby realizing the spraying of the pipeline; by arranging a clamping device, the pipeline can be clamped, and since the clamping device can rotate, it can drive the pipeline to rotate around the axis of the pipeline, thereby realizing the spraying mechanism to spray various angles of the pipeline, avoiding that a certain part of the pipeline is not sprayed by the spraying mechanism, thereby causing the quality of the pipeline to be reduced; by arranging a drying device on the upper part of the side walls on both sides close to the top wall of the first box body, it can immediately start the drying mechanism to dry the sprayed pipeline after the spraying mechanism completes the spraying of the pipeline, thereby realizing the integration of spraying and drying, improving the production efficiency, and at the same time improving the coating quality of the pipeline.
[0021] 2. The utility model provides a rapid automatic coating system for pipelines, which comprises a mounting base, an ultraviolet lamp, a protective cover and a rotating mechanism. The rotating mechanism can drive the protective cover to rotate around the axis of the ultraviolet lamp, so that the protective cover covers the ultraviolet lamp during spraying, thereby preventing the paint from being sprayed onto the outer wall of the ultraviolet lamp during spraying, thereby preventing the drying efficiency of the ultraviolet lamp from being reduced. After spraying, the rotating mechanism can drive the protective cover to rotate, so that the protective cover is hidden in the groove, so that the ultraviolet lamp can dry the paint film on the sprayed pipeline. Since the rotating mechanism is mounted on the connecting rod, the protective cover can rotate, but the ultraviolet lamp is fixed.
[0022] 3. The utility model provides a pipeline rapid automatic coating system, which can achieve that the protective cover does not interfere with the mounting seat when rotating around the axis of the ultraviolet lamp by setting the cross-sections of the groove and the protective cover to be semicircular. By setting the gear, the latch and the first oil cylinder, the first oil cylinder extends to drive the latch to move, and the gear rotates as the latch engages with the gear, thereby driving the protective cover to rotate around the axis of the ultraviolet lamp, thereby protecting the ultraviolet lamp.
[0023] 4. The utility model provides a rapid automatic painting system for pipelines, which can clamp the pipelines by relatively arranging a first clamping mechanism and a second clamping mechanism. Since the second clamping mechanism is movably installed below the first box body, it can move toward or away from the first clamping mechanism, thereby clamping pipelines of different lengths, improving the adaptability and practicality of the clamping device; and, the axes of the first clamping mechanism and the second clamping mechanism are always consistent during the lifting process, which can avoid angle changes of the pipeline, thereby avoiding uneven spraying of the pipeline during the spraying process and avoiding reduction in the quality of the pipeline.
[0024] 5. The utility model provides a pipeline rapid automatic painting system. By setting a first lifting cylinder and a second lifting cylinder, the lifting and lowering of the first clamp and the second clamp are realized. In the initial state, the first clamp and the second clamp are lowered to the bottom of the first box, so that the pipeline can quickly enter the first box from the second box; when spraying, the first clamp and the second clamp rise to the inside of the first box, thereby clamping the pipeline; by setting a first motor, the second clamp can be driven to rotate. Since the first clamp is connected to the first lifting cylinder through the first bearing, the first clamp can rotate with the rotation of the second clamp, thereby driving the pipeline to rotate; by setting a second cylinder, a second track and a moving seat, the second clamp can be driven to move along the track, thereby adapting to clamping pipelines of different lengths. By setting the first clamp and the second clamp to be conical, it can clamp pipelines of different diameters. At the same time, the first clamp and the second clamp are detachably connected, which can be more convenient to replace.
[0025] 6. The utility model provides a rapid automatic painting system for pipelines. By providing a grinding device, the outer wall of the pipeline can be polished so as to better spray the outer wall of the pipeline. By providing a second motor, the first drum, the second drum and the third drum can be driven to rotate, so that the grinding piece can grind the outer wall of the pipeline; by arranging multiple grinding pieces in a circumferential array around the axis of the third drum and forming a circle, it can better adapt to the outer wall of the pipeline, so that the outer wall of the pipeline can be better and more efficiently polished; by providing a screw and a mounting plate, the screw can be screwed into the outer wall of the third drum and move toward the axis of the third drum, which can drive the grinding piece to move toward the axis of the third drum, so as to adapt to the grinding of pipelines of different diameters, making the grinding device more adaptable.
[0026] 7. The utility model provides a rapid automatic painting system for pipelines. By setting a spray gun and a telescopic part, the telescopic part can drive the spray gun to rise and fall vertically, so as to realize spraying of pipelines with different diameters and pipelines at different heights between the pipeline and the top of the first box body, thereby improving the efficiency of the spraying mechanism and making the spraying mechanism more adaptable. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 This is a schematic diagram of the structure of a spraying device of a pipeline rapid automatic coating system of the utility model;
[0028] Figure 2 It is a cross-sectional schematic diagram of a spraying device of a pipeline rapid automatic coating system of the utility model;
[0029] Figure 3 This is a schematic diagram of the structure of a grinding device for a pipeline rapid automatic coating system of the utility model;
[0030] Figure 4 It is a structural schematic diagram of a grinding mechanism of a pipeline rapid automatic coating system of the utility model;
[0031] Figure 5 for Figure 1 The enlarged structural diagram at A in the middle;
[0032] Figure 6 for Figure 5 The enlarged structural diagram at B in the middle;
[0033] Figure 7 It is a cross-sectional structural schematic diagram of a drying device of a pipeline rapid automatic coating system of the utility model;
[0034] Figure 8 The utility model is a schematic diagram of the cross-sectional structure of a drying device during paint spraying in a pipeline rapid automatic painting system.
[0035] [Description of Reference Numerals]
[0036] 1: spraying device; 11: first box; 111: first track; 12: first roller; 13: spraying mechanism; 131: spray gun; 132: telescopic member; 14: clamping device; 141: first clamping mechanism; 1411: first fixed seat; 1412: first lifting cylinder; 1413: first clamping member; 1414: first bearing; 142: second clamping mechanism; 1421: second fixed seat; 1422: second lifting cylinder; 1423: first motor; 1424: second clamping member; 1425: moving seat; 1426: second track; 1427: second oil cylinder; 2: drying device; 21: mounting seat; 22: UV lamp; 23: protective cover; 24: rotating mechanism; 241: gear; 242: roller; 243: latch; 244: first oil cylinder; 3: grinding device; 31: second box; 32: second roller; 33: grinding mechanism; 331: first rotating drum; 332: second rotating drum; 333: third rotating drum; 334: mounting plate; 335: grinding piece; 336: screw; 337: second motor; 4: pipeline. DETAILED DESCRIPTION
[0037] In order to better understand the above technical solution, exemplary embodiments of the present invention will be described in more detail with reference to the accompanying drawings. Although exemplary embodiments of the present invention are shown in the accompanying drawings, it should be understood that the present invention can be implemented in various forms and should not be limited by the embodiments described herein. On the contrary, these embodiments are provided to enable a clearer and more thorough understanding of the present invention and to fully convey the scope of the present invention to those skilled in the art.
[0038] Embodiment 1
[0039] like Figure 1-Figure 8 As shown, a pipeline 4 rapid automatic coating system of this embodiment includes a spraying device 1 and a drying device 2;
[0040] Specifically, the spraying device 1 includes a first box body 11, multiple first rollers 12, a spraying mechanism 13 and a clamping device 14. The first box body 11 has openings at the bottom and both ends. The multiple first rollers 12 are installed on the bottom wall of the first box body 11 at intervals and can be rotated. The pipeline 4 is placed flat on the multiple first rollers 12. The axial direction of the pipeline 4 is perpendicular to the axial direction of the first rollers 12. The friction force of the pipeline 4 when moving on the multiple rollers is smaller, which is more conducive to the movement of the pipeline 4 on the multiple rollers; the clamping device 14 can be raised and lowered into the first box body 11 or is located below the first box body 11, and the clamping device 14 can clamp the pipeline 4 and drive the pipeline 4 to rotate around the axis of the pipeline 4 when it is inside the first box body 11. By setting the clamping device 14, the pipeline 4 can be clamped. Since the clamping device 14 can rotate, it can drive the pipeline 4 to rotate around the axis of the pipeline 4, so that the spraying mechanism 13 can spray the pipeline 4 at various angles, avoiding that a certain part of the pipeline 4 is not sprayed by the spraying mechanism 13, thereby reducing the quality of the pipeline 4; a long through hole along the length direction of the first box body 11 is opened on the top wall of the first box body 11 located directly above the pipeline 4, and the spraying mechanism 13 is movably installed on the long rail 111 through the first rail 111. In the through hole, the spraying mechanism 13 can move back and forth on the first track 111, so as to realize the spraying of the pipeline 4; a plurality of drying devices 2 are installed at equal intervals on the upper part of the side walls on both sides of the first box body 11, and the drying device 2 can be opened or closed to immediately dry the pipeline 4 after spraying. After the spraying mechanism 13 completes the spraying of the pipeline 4, the drying mechanism can be immediately opened to dry the pipeline 4 after spraying, thereby realizing the integration of spraying and drying, improving work efficiency, and at the same time improving the production quality of the pipeline 4.
[0041] Furthermore, the spraying mechanism 13 includes a spray gun 131 and a telescopic member 132; the spray gun 131 is installed on the first rail 111 through the telescopic member 132, and the telescopic member 132 can drive the spray gun 131 to rise and fall vertically, thereby realizing the spraying of pipelines 4 of different diameters and pipelines 4 at different heights between the pipelines 4 and the top of the first box body 11, thereby improving the efficiency of the spraying mechanism 13 and making the spraying mechanism 13 more adaptable.
[0042] Furthermore, the clamping device 14 includes a first clamping mechanism 141 and a second clamping mechanism 142; the first clamping mechanism 141 and the second clamping mechanism 142 are relatively arranged in a direction perpendicular to the first roller 12 and the axes of the first clamping mechanism 141 and the second clamping mechanism 142 are always consistent during the lifting process, which can not only clamp the pipeline 4, but also avoid the angle change of the pipeline 4, thereby avoiding uneven spraying of the pipeline 4 during the spraying process and avoiding the reduction of the quality of the pipeline 4; the first clamping mechanism 141 is fixedly installed at the bottom of the first box body 11, and the second clamping mechanism 142 is movably installed at the bottom of the first box body 11. The second clamping mechanism 142 can move in a direction close to or away from the first clamping mechanism 141, thereby clamping pipelines 4 of different lengths, thereby improving the adaptability and practicality of the clamping device 14.
[0043] Specifically, the first clamping mechanism 141 includes a first fixed seat 1411, a first lifting cylinder 1412, a first clamping piece 1413 and a first bearing 1414; the first fixed seat 1411 is located below the first box body 11, the fixed end of the first lifting cylinder 1412 is connected to the top of the first fixed seat 1411, the protruding end of the first lifting cylinder 1412 is detachably connected to the first clamping piece 1413 through the first bearing 1414, and the axis of the first lifting cylinder 1412 is perpendicular to the axis of the first clamping piece 1413; the second clamping mechanism 142 includes The second fixing seat 1421, the second lifting cylinder 1422, the first motor 1423, the second clamping member 1424, the moving seat 1425, the second track 1426 and the second cylinder 1427 are both fixedly mounted below the first box 11, the moving seat 1425 is movably mounted on the second track 1426 and the tail end of the moving seat 1425 is connected to the protruding end of the second cylinder 1427, and the second lifting cylinder 1422 is mounted on the top of the moving seat 1425 through the second fixing seat 1421. By arranging the second cylinder 1427, the second track 1426 and the moving seat 1425, the second clamping member 1424 can be driven to move along the track, thereby adapting to clamping pipelines 4 of different lengths. The first motor 1423 is installed on the top of the second lifting cylinder 1422 and the motor is detachably connected to the second clamping member 1424. The axis of the second clamping member 1424 is perpendicular to the axis of the second lifting cylinder 1422. By providing the first motor 1423, the second clamping member 1424 can be driven to rotate. Since the first clamping member 1413 is connected to the first lifting cylinder 1412 through the first bearing 1414, the first clamping member 1413 can rotate with the rotation of the second clamping member 1424, thereby driving the pipeline 4 to rotate. By providing the first lifting cylinder 1412 and the second lifting cylinder 1422, the lifting and lowering of the first clamp 1413 and the second clamp 1424 are realized. In the initial state, the first clamp 1413 and the second clamp 1424 are lowered to the bottom of the first box 11, so that the pipeline 4 can quickly enter the first box 11 from the second box 31; when spraying, the first clamp 1413 and the second clamp 1424 rise to the inside of the first box 11, thereby clamping the pipeline 4. Preferably, the first clamp 1413 and the second clamp 1424 are both conical and the vertebral bodies of the first clamp 1413 and the second clamp 1424 are arranged relative to each other, which can realize the clamping of pipelines 4 of different diameters. At the same time, the first clamp 1413 and the second clamp 1424 are detachably connected, which can be more convenient for replacement.
[0044] Furthermore, if Figure 5-Figure 8As shown, the drying device 2 includes a mounting base 21, an ultraviolet lamp tube 22, a protective cover 23 and a rotating mechanism 24; one side of the mounting base 21 is connected to the upper part of the side wall of the first box body 11 and a groove is provided on the side wall of the mounting base 21 opposite to the side wall of the first box body 11, and both ends of the ultraviolet lamp tube 22 are connected to the side walls of the groove through a connecting rod, the protective cover 23 is placed in the groove and both ends of the protective cover 23 are sleeved on the connecting rod through a rotating mechanism 24, and the rotating mechanism 24 can drive the protective cover 23 to rotate around the axis of the connecting rod to turn on or off the drying of the pipeline 4. By providing the mounting base 21, the ultraviolet lamp tube 22, the protective cover 23 and the rotating mechanism 24, the rotating mechanism 24 can drive the protective cover 23 to rotate around the axis of the ultraviolet lamp tube 22, so that during spraying, the protective cover 23 covers the ultraviolet lamp tube 22 to avoid the paint being sprayed onto the outer wall of the ultraviolet lamp tube 22 during spraying, thereby avoiding the reduction of the drying efficiency of the ultraviolet lamp tube 22; after spraying, the rotating mechanism 24 can drive the protective cover 23 to rotate, so that the protective cover 23 is hidden in the groove, so that the ultraviolet lamp tube 22 can dry the paint film on the sprayed pipeline 4; because the rotating mechanism 24 is sleeved on the connecting rod, the protective cover 23 can rotate, but the ultraviolet lamp tube 22 is fixed. Preferably, the cross-sections of the groove and the protective cover 23 are both semicircular, wherein the shape of the groove is semi-cylindrical, the shape of the protective cover 23 is a semi-cylindrical hollow structure, and the inner contour of the groove is consistent with the outer contour of the protective cover 23, which can ensure that the protective cover 23 does not interfere with the mounting base 21 when rotating around the axis of the ultraviolet lamp tube 22.
[0045] Furthermore, if Figure 7 and Figure 8 As shown, the rotating mechanism 24 includes a gear 241, two rollers 242, a latch 243 and a first oil cylinder 244; the two rollers 242 are respectively mounted on two connecting rods and the outer walls of the two rollers 242 are respectively connected to the two ends of the protective cover 23, and the gear 241 is connected to one roller 242; the fixed end of the first oil cylinder 244 is installed on the side wall of the first box body 11, and the protruding end of the first oil cylinder 244 is connected to one end of the latch 243, and the latch 243 is meshed with the gear 241, so that the first oil cylinder 244 is extended or retracted, driving the latch 243 to move with the extension and retraction of the first oil cylinder 244, thereby driving the gear 241 to rotate, thereby driving the protective cover 23 to rotate around the axis of the ultraviolet lamp 22 to protect the ultraviolet lamp 22.
[0046] Furthermore, the rapid automatic painting system for pipelines 4 of the present embodiment further includes a grinding device 3 , which can grind the outer wall of the pipeline 4 so as to better spray the outer wall of the pipeline 4 .
[0047] Specifically, Figure 3 and Figure 4As shown, the grinding device 3 includes a second box 31, a plurality of second rollers 32 and a grinding mechanism 33; the second box 31 is provided with openings at the bottom and both ends, and the plurality of second rollers 32 are rotatably installed at the bottom of the second box 31 at intervals, so as to reduce the friction force of the pipeline 4 on the plurality of second rollers 32, so that the pipeline 4 moves more smoothly. The grinding mechanism 33 is placed inside the second box 31 and in the middle of the second box 31; the axis of the pipeline 4 is consistent with the axis of the grinding mechanism 33 and the pipeline 4 is placed flat on the plurality of second rollers 32, the axial direction of the pipeline 4 is perpendicular to the axial direction of the second rollers 32 and the pipeline 4 can pass through the grinding mechanism 33, so that the grinding mechanism 33 grinds the outer wall of the pipeline 4.
[0048] The grinding mechanism 33 includes a first rotating drum 331, a second rotating drum 332, a third rotating drum 333, a plurality of mounting plates 334, a plurality of grinding pieces 335, a plurality of screws 336 and a second motor 337; the first rotating drum 331, the second rotating drum 332 and the third rotating drum 333 are connected in sequence and have the same axis, and the output end of the second motor 337 is connected in series with the second rotating drum 332 through a belt or a chain to drive the first rotating drum 331, the second rotating drum 332 and the third rotating drum 333 to rotate simultaneously (it should be noted that the outer contours of the first rotating drum 331 and the third rotating drum 333 may not be circular, but may also be polygonal such as square or rhombus); a plurality of mounting plates 334, a plurality of grinding pieces 335 and Multiple screws 336 correspond to each other one by one and are arranged circumferentially around the axis of the third rotating cylinder 333. The side walls of the multiple grinding pieces 335 facing the axis of the third rotating cylinder 333 form a circle, which can better adapt to the outer wall of the pipeline 4, thereby being able to better and more efficiently grind the outer wall of the pipeline 4; the screw 336 passes through the outer wall of the third rotating cylinder 333 and the screw 336, the mounting plate 334 and the grinding piece 335 are connected in sequence. The screw 336 can be screwed into the outer wall of the third rotating cylinder 333 and move toward the axis of the third rotating cylinder 333. It can drive the grinding piece 335 to move toward the axis of the third rotating cylinder 333, thereby adapting to the grinding of pipelines 4 with different diameters, making the grinding device 3 more adaptable.
[0049] Through the above structure, the working principle of a pipeline 4 rapid automatic coating system of this embodiment is:
[0050] like Figure 1-Figure 8As shown, the system is first assembled, and then the pipeline 4 is stably placed on the multiple second rollers 32. The equipment pushes or rotates the pipeline 4 to move in a direction perpendicular to the multiple second rollers 32. At this time, the axis of the pipeline 4 is consistent with the axis of the grinding device 3; at the same time, the second motor 337 drives the second rotating drum 332 to rotate, and then drives the grinding mechanism 33 to rotate, and the grinding piece 335 in the grinding mechanism 33 also rotates around the axis of the third rotating drum 333, so that the pipeline 4 passes through the first rotating drum 331, the second rotating drum 332 and the third rotating drum 333. When the pipeline 4 passes through the third rotating drum 333, the outer wall of the pipeline 4 is polished by the multiple grinding pieces 335, so that the paint can be better adhered during subsequent painting. After the outer wall of the pipeline 4 is polished by the polishing mechanism 33 , the pipeline 4 enters the first box 11 from the second box 31 and moves along an axis perpendicular to the plurality of first rollers 12 . At this time, the first clamping mechanism 141 and the second clamping mechanism 142 are located below the first box 11 . When the pipeline 4 moves to a specific position, the first clamping member 1413 and the second clamping member 1424 are lifted due to the extension of the first lifting cylinder 1412 and the second lifting cylinder 1422, so that the tip of the cone of the first clamping member 1413 enters into the interior of the pipeline 4, and one end of the pipeline 4 is stuck on the outer wall of the first clamping member 1413. At the same time, the second clamping member 1424 is driven by the second cylinder 1427 to move along the second track 1426, driving the second clamping member 1424 to move in a direction close to the first clamping member 1413 (when the length of the pipeline 4 is too long, the second clamping member 1424 moves in a direction away from the first clamping member 1413), and the tip of the second clamping member 1424 enters into the interior of the pipeline 4, and the other end of the pipeline 4 is stuck on the outer wall of the second clamping member 1424, so that the pipeline 4 is stuck on the first clamping member 1413 and the second clamping member 1424. When the first clamping member 1413 and the second clamping member 1424 stably clamp the pipe 4, the first motor 1423 is driven to drive the second clamping member 1424 to rotate, thereby driving the pipe 4 to rotate around the axis of the pipe 4; at the same time, the spraying mechanism 13 starts to operate. According to the distance between the pipe 4 and the spray gun 131, the distance between the spray gun 131 and the pipe 4 is adjusted by the telescopic member 132, and then the pipe 4 is sprayed with paint by the spray gun 131; at the same time, the spraying mechanism is driven to reciprocate along the first track 111, so that the spraying mechanism can spray paint at various positions of the outer wall of the pipe 4 so that the paint is sprayed evenly.During the painting process, the protective cover 23 is in a state of protecting the ultraviolet lamp 22, that is, the protective cover 23 wraps the ultraviolet lamp 22; after the painting is completed, the first oil cylinder 244 extends (or retracts), driving the latch 243 to extend (or retract), thereby driving the gear 241 to rotate, and then driving the protective cover 23 to rotate around the axis of the ultraviolet lamp 22, so that the protective cover 23 is located in the groove, and the pipeline 4 is started to be dried at this time. After drying, the pipeline 4 is transported to the next working position.
[0051] In the description of the present utility model, it should be understood that the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of the present utility model, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.
[0052] In the present invention, unless otherwise clearly specified and limited, the terms "install", "connect", "connect", "fix" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium; it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0053] In the present utility model, unless otherwise clearly specified and limited, when a first feature is “on” or “below” a second feature, it may be that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, when a first feature is “above”, “above” or “above” a second feature, it may be that the first feature is directly above or obliquely above the second feature, or it may simply mean that the first feature is higher in level than the second feature. When a first feature is “below”, “below” or “below” a second feature, it may be that the first feature is directly below or obliquely below the second feature, or it may simply mean that the first feature is lower in level than the second feature.
[0054] In the description of this specification, the description of the terms "one embodiment", "some embodiments", "embodiment", "example", "specific example" or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the utility model. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, unless they are contradictory.
[0055] Although the embodiments of the present invention have been shown and described above, it can be understood that the above embodiments are illustrative and cannot be understood as limitations of the present invention. Ordinary technicians in the field can change, modify, replace and modify the above embodiments within the scope of the present invention.
Claims
1. A pipeline rapid automatic coating system, characterized in that: It comprises a spraying device (1) and a drying device (2); The spraying device (1) comprises a first housing (11), a plurality of first rollers (12), a spraying mechanism (13) and a clamping device (14). The first housing (11) has openings at the bottom and both ends. The plurality of first rollers (12) are rotatably installed on the bottom wall of the first housing (11) at intervals. The pipeline (4) is placed flat on the plurality of first rollers (12). The axial direction of the pipeline (4) is perpendicular to the axial direction of the first rollers (12). The clamping device can be raised and lowered into the first housing (11). The first box (11) is located inside or below the first box (11), and the clamping device (14) is capable of clamping the pipeline (4) and driving the pipeline (4) to rotate around the axis of the pipeline (4) when inside the first box (11). A long through hole along the length direction of the first box (11) is opened on the top wall of the first box (11) located directly above the pipeline (4), and the spraying mechanism (13) is movably installed in the long through hole through a first track (111); A plurality of drying devices (2) are installed at equal intervals on the upper parts of the side walls of both sides of the first box body (11); the drying devices (2) can be opened or closed to immediately dry the pipeline (4) after spraying.
2. A pipeline rapid automatic coating system as claimed in claim 1, characterized in that: The drying device (2) comprises a mounting base (21), an ultraviolet lamp tube (22), a protective cover (23) and a rotating mechanism (24); One side of the mounting seat (21) is connected to the upper part of the side wall of the first box body (11), and a groove is provided on the side wall of the mounting seat (21) opposite to the side wall of the first box body (11). The two ends of the ultraviolet lamp tube (22) are connected to the two side walls of the groove through a connecting rod. The protective cover (23) is placed in the groove, and the two ends of the protective cover (23) are sleeved on the connecting rod through the rotating mechanism (24). The rotating mechanism (24) can drive the protective cover (23) to rotate around the axis of the connecting rod to open or close the drying of the pipeline (4).
3. A pipeline rapid automatic coating system as claimed in claim 2, characterized in that: The cross sections of the groove and the protective cover (23) are both semicircular.
4. A pipeline rapid automatic coating system as claimed in claim 2, characterized in that: The rotating mechanism (24) comprises a gear (241), two rollers (242), a latching tooth (243) and a first oil cylinder (244); The two rollers (242) are respectively sleeved on the two connecting rods, and the outer walls of the two rollers (242) are respectively connected to the two ends of the protective cover (23), and the gear (241) is connected to one of the rollers (242); The fixed end of the first oil cylinder (244) is mounted on the side wall of the first box body (11), the protruding end of the first oil cylinder (244) is connected to one end of the latch tooth (243), and the latch tooth (243) is meshed with the gear (241).
5. The pipeline rapid automatic coating system according to claim 1, characterized in that: The clamping device (14) comprises a first clamping mechanism (141) and a second clamping mechanism (142); The first clamping mechanism (141) and the second clamping mechanism (142) are arranged opposite to each other in a direction perpendicular to the first roller (12), and the axes of the first clamping mechanism (141) and the second clamping mechanism (142) are always consistent during the lifting process; The first clamping mechanism (141) is fixedly installed below the first box body (11), and the second clamping mechanism (142) is movably installed below the first box body (11), and the second clamping mechanism (142) can move in a direction close to or away from the first clamping mechanism (141).
6. A pipeline rapid automatic coating system as claimed in claim 5, characterized in that: The first clamping mechanism (141) comprises a first fixing seat (1411), a first lifting cylinder (1412), a first clamping member (1413) and a first bearing (1414); The first fixing seat (1411) is located below the first box body (11), the fixing end of the first lifting cylinder (1412) is connected to the top of the first fixing seat (1411), the protruding end of the first lifting cylinder (1412) is detachably connected to the first clamping member (1413) via the first bearing (1414), and the axis of the first lifting cylinder (1412) is perpendicular to the axis of the first clamping member (1413); The second clamping mechanism (142) comprises a second fixed seat (1421), a second lifting cylinder (1422), a first motor (1423), a second clamping member (1424), a moving seat (1425), a second track (1426) and a second cylinder (1427); The fixed ends of the second rail (1426) and the second cylinder (1427) are both installed below the first box body (11); the movable seat (1425) is movably installed on the second rail (1426) and the tail end of the movable seat (1425) is connected to the protruding end of the second cylinder (1427); the second lifting cylinder (1422) is installed on the top of the movable seat (1425) through the second fixed seat (1421); the first motor (1423) is installed on the top of the second lifting cylinder (1422) and the motor is detachably connected to the second clamp (1424); the axis of the second clamp (1424) is perpendicular to the axis of the second lifting cylinder (1422).
7. A pipeline rapid automatic coating system as claimed in claim 6, characterized in that: The first clamping member (1413) and the second clamping member (1424) are both conical in shape, and the vertebral bodies of the first clamping member (1413) and the second clamping member (1424) are arranged opposite to each other.
8. The pipeline rapid automatic coating system according to claim 1, characterized in that: Also includes a grinding device (3); The grinding device (3) comprises a second box (31), a plurality of second rollers (32) and a grinding mechanism (33); The bottom and both ends of the second box (31) are provided with openings, the plurality of second rollers (32) are rotatably installed at intervals on the bottom of the second box (31), and the grinding mechanism (33) is placed inside the second box (31); The axis of the pipeline (4) is consistent with the axis of the grinding mechanism (33) and the pipeline (4) is placed flat on the plurality of second rollers (32). The axial direction of the pipeline (4) is perpendicular to the axial direction of the second rollers (32) and the pipeline (4) can pass through the grinding mechanism (33), so that the grinding mechanism (33) grinds the outer wall of the pipeline (4).
9. A pipeline rapid automatic coating system as claimed in claim 8, characterized in that: The grinding mechanism (33) comprises a first rotating drum (331), a second rotating drum (332), a third rotating drum (333), a plurality of mounting plates (334), a plurality of grinding members (335), a plurality of screw rods (336) and a second motor (337); The first rotating drum (331), the second rotating drum (332) and the third rotating drum (333) are connected in sequence and have the same axis; the output end of the second motor (337) is connected in series with the second rotating drum (332) through a belt or a chain to drive the first rotating drum (331), the second rotating drum (332) and the third rotating drum (333) to rotate simultaneously; The multiple mounting plates (334), the multiple grinding pieces (335) and the multiple screw rods (336) correspond to each other one by one and are arranged circumferentially around the axis of the third rotating cylinder (333); the side walls of the multiple grinding pieces (335) facing the axis of the third rotating cylinder (333) form a circle; the screw rod (336) passes through the outer wall of the third rotating cylinder (333); and the screw rod (336), the mounting plates (334) and the grinding pieces (335) are connected in sequence.
10. A pipeline rapid automatic coating system as claimed in claim 1, characterized in that: The spraying mechanism (13) comprises a spray gun (131) and a telescopic member (132); The spray gun (131) is installed on the first track (111) via the telescopic member (132), and the telescopic member (132) can drive the spray gun (131) to rise and fall vertically.