Subway construction pipeline suspension device

By designing a subway construction pipeline suspension device with combined structures such as gear rings, gears, and sleeve rings, the problem of inflexible installation of power cable pipelines in the existing technology is solved, convenient installation and height adjustment are achieved, and construction flexibility is improved. Practicality.

CN222282661UActive Publication Date: 2024-12-31ERCHU CO LTD OF CHINA RAILWAY TUNNEL GRP +3
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323315058.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-06
Publication Date
2024-12-31
Estimated Expiration
2033-12-06

AI Technical Summary

Technical Problem

The existing power cable pipeline installation methods for subway construction cannot be flexibly installed and disassembled, and the installation height cannot be adjusted, which affects use.

Method used

A subway construction pipeline suspension device is designed, using a combined structure of toothed ring, gear, collar, thread groove, bolt, plug rod, spring, plug block and connecting plate to realize the flexible installation and disassembly of cable pipelines, and can Adjust the installation height.

Benefits of technology

It realizes convenient installation and disassembly of cable pipelines, flexibly adjusts the installation height, and improves the flexibility and practicality of use.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222282661U_ABST
    Figure CN222282661U_ABST
Patent Text Reader

Abstract

The utility model discloses a subway construction pipeline suspension device which comprises a lantern ring, an annular groove is formed in the inner side of the lantern ring, a gear ring is arranged in the annular groove, a gear is arranged on the inner side of the lantern ring, the gear is meshed with the outer portion of the gear ring, a rotating handle is fixedly installed in the center of the outer portion of the gear, and the rotating handle is movably connected with the lantern ring. Threaded grooves are formed in the outer portions of the lantern ring and the gear ring in a penetrating mode, bolts are arranged in the threaded grooves, the lantern ring is connected with the gear ring in the mode that the bolts are matched with the threaded grooves, a sleeve rod is fixedly installed at the top of the lantern ring, a connecting rod is connected to the outer portion of the sleeve rod in a sleeving mode, a movable groove is formed in the front portion of the connecting rod in a penetrating mode, and an inserting rod is inserted into the movable groove. An inserting block is arranged at the tail end of the inserting rod, a spring is arranged outside the inserting rod, and one end of the spring is fixedly connected with the connecting rod. According to the subway construction pipeline hanging device, cables and pipelines can be flexibly installed, meanwhile, the height can be adjusted, and installation is convenient.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of subway construction tools, in particular to a subway construction pipeline hanging device. Background Art

[0002] Power cables are a type of subway pipeline. During subway construction, they are used to supply power to subway construction tools, platform lighting, ventilation equipment and other facilities. These power cables carry high voltage and high current to ensure the normal operation of subway construction. During construction, power cables usually need to be suspended so that they can transmit electricity without affecting subway construction.

[0003] However, the existing power cable pipelines are usually installed in a fixed manner during subway construction. Since the fixed installation method is usually a one-time installation, the cable pipelines cannot be flexibly installed and disassembled. At the same time, the installation height of the cable pipeline cannot be flexibly adjusted, which has a certain impact on the use of the cable pipeline. Therefore, a subway construction pipeline suspension device is proposed;

[0004] To this end, this case proposes a subway construction pipeline suspension device to address the above problems. Utility Model Content

[0005] The main purpose of the utility model is to provide a subway construction pipeline suspension device, which can effectively solve the technical problems in the background technology.

[0006] In order to achieve the above purpose, the technical solution adopted by the utility model is:

[0007] A subway construction pipeline suspension device comprises a collar, an annular groove is provided on the inner side of the collar, a gear ring is arranged in the annular groove, a gear is arranged on the inner side of the collar, and the gear is meshed with the outer side of the gear ring, a turning handle is fixedly installed at the center position of the outer side of the gear, and the turning handle and the collar are movably connected.

[0008] As a further solution of the utility model, a thread groove is opened through the outside of the collar and the gear ring, a bolt is arranged in the thread groove, and the collar is connected to the gear ring through the bolt and the thread groove.

[0009] As a further solution of the utility model, a sleeve rod is fixedly installed on the top of the sleeve ring, and a connecting rod is sleeved on the outside of the sleeve rod.

[0010] As a further solution of the utility model, a movable groove is opened through the front part of the connecting rod, an insertion rod is inserted into the movable groove, and an insertion block is arranged at the end of the insertion rod.

[0011] As a further solution of the utility model, a spring is arranged outside the insertion rod, one end of the spring is fixedly connected to the connecting rod, and the other end of the spring is fixedly connected to the insertion block.

[0012] As a further solution of the utility model, the rear portion of the insert block is provided with an inclined surface, and a plurality of slots matching the insert block are provided on the outside of the sleeve rod.

[0013] As a further solution of the utility model, a connecting plate is fixedly installed on the top of the connecting rod, and a plurality of installation grooves are opened through the upper and lower parts of the connecting plate.

[0014] The beneficial effects of the utility model are as follows:

[0015] By setting the gear ring and the gear matching the sleeve ring, the installation and removal of the cable pipeline are more convenient. When installing the cable pipeline, the gear rotates by turning the handle, and the gear rotates, and the rotation of the gear drives the meshing gear ring to rotate, and one end of the gear ring will be inserted into the sleeve ring. When the gear ring cannot rotate, the sleeve ring and the thread groove of the gear ring are aligned, and then the bolt is inserted into the thread groove to fix it. When disassembling, it is only necessary to remove the bolt, turn the handle, and then take out the cable pipeline, so that the cable can be installed flexibly, and the situation that the cable pipeline is inconvenient to disassemble due to being fixedly installed can be avoided;

[0016] By arranging an insertion rod, an insertion block, a spring, a slot, a sleeve rod and a connecting rod, the height of the device can be flexibly adjusted. When in use, the insertion rod is pulled, the spring contracts, and the insertion block also contracts into the movable slot. Then the sleeve rod is pulled out or contracted. After the length of the sleeve rod is adjusted to a suitable position, the pull rod is released, and the spring resets to drive the insertion block to pop out and insert it into the slot. In this way, the height of the cable pipeline installation can be flexibly adjusted, which is more practical. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is a schematic diagram of the overall structure of the utility model.

[0018] Figure 2 It is a front cross-sectional view of the sleeve ring of the present utility model.

[0019] Figure 3 This is a diagram of the internal structure of the sleeve ring of the present utility model.

[0020] Figure 4 This is a diagram of the gear ring of the present invention after rotation.

[0021] Figure 5 This is a diagram of the internal structure of the connecting rod of the utility model.

[0022] Figure 6 It is the front view of the utility model.

[0023] In the figure: 1, collar; 2, gear ring; 3, handle; 4, gear; 5, bolt; 6, threaded groove; 7, sleeve rod; 8, connecting rod; 9, plug rod; 10, slot; 11, spring; 12, plug block; 13, connecting plate. DETAILED DESCRIPTION

[0024] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further described below in conjunction with specific implementation methods.

[0025] like Figure 1-6 As shown, a subway construction pipeline suspension device includes a collar 1, an annular groove is provided on the inner side of the collar 1, a gear ring 2 is arranged in the annular groove, a gear 4 is arranged on the inner side of the collar 1, and the gear 4 is in meshing state with the outer side of the gear ring 2, a turning handle 3 is fixedly installed at the outer center position of the gear 4, and the turning handle 3 is movably connected to the collar 1.

[0026] In this embodiment, thread grooves 6 are provided on the outside of the collar 1 and the gear ring 2 , bolts 5 are provided in the thread grooves 6 , and the collar 1 is connected to the gear ring 2 through the bolts 5 and the thread grooves 6 .

[0027] When in use, the handle 3 is rotated, and the rotation of the handle 3 drives the meshed gear ring 2 to rotate, so that the cable pipeline can be placed therein.

[0028] In this embodiment, a sleeve rod 7 is fixedly mounted on the top of the sleeve ring 1 , and a connecting rod 8 is sleeved on the outside of the sleeve rod 7 .

[0029] By arranging the sleeve rod 7 and the connecting rod 8, the height of the device can be flexibly adjusted.

[0030] In this embodiment, a movable groove is formed through the front portion of the connecting rod 8 , an inserting rod 9 is inserted into the movable groove, and an inserting block 12 is provided at the end of the inserting rod 9 .

[0031] When in use, the insertion rod 9 is pulled, the spring 11 contracts, and the insertion block 12 also contracts into the movable groove.

[0032] In this embodiment, a spring 11 is disposed outside the insertion rod 9 , one end of the spring 11 is fixedly connected to the connecting rod 8 , and the other end of the spring 11 is fixedly connected to the insertion block 12 .

[0033] After the device is adjusted to a suitable height, the insertion rod 9 is released, and the spring 11 is reset to drive the insertion block 12 to pop out and insert into the slot 10, and its length can be fixed.

[0034] In this embodiment, the rear portion of the insert block 12 is arranged with an inclined surface, and a plurality of slots 10 adapted to the insert block 12 are arranged on the outside of the sleeve rod 7 .

[0035] When the sleeve rod 7 is pushed upward, the insert block 12 will automatically pop out and be inserted into the slot 10 when it passes through the slot 10 .

[0036] In this embodiment, a connecting plate 13 is fixedly mounted on the top of the connecting rod 8 , and a plurality of mounting grooves are formed through the upper and lower parts of the connecting plate 13 .

[0037] When in use, the device can be installed on the top of the wall of the subway construction through the installation groove of the connecting plate 13.

[0038] It should be noted that the utility model is a subway construction pipeline suspension device. When in use, the device is placed where it needs to be installed, and the device is fixedly connected to the top of the wall of the ground construction through the installation groove, and then the height is adjusted by adjusting the length of the sleeve rod 7. The insertion rod 9 can be pulled, the spring 11 contracts, and the insertion block 12 also enters the movable groove, pushing the sleeve rod 7 upward. When the length of the sleeve rod 7 is appropriate, the insertion rod 9 is loosened, the spring 11 resets and drives the insertion block 12 to pop out, and the insertion block 12 can be inserted into the slot 10. After the height adjustment is completed, the cable pipeline is placed in the collar 1, and the handle 3 is turned. The gear 4 rotates to drive the meshing gear ring 2 to rotate, and the handle 3 is continuously turned to insert the gear ring 2 into the collar 1. When the gear ring 2 cannot move, the thread grooves 6 of the collar 1 and the gear ring 2 have been aligned, and then the bolt 5 is aligned with the thread groove 6 and inserted and tightened.

[0039] When the cable needs to be removed, the bolt 5 can be directly loosened and removed, and the handle 3 can be turned again to make one end of the gear ring 2 rotate out of the ring 1, and then the cable can be removed.

[0040] The above shows and describes the basic principle and main features of the utility model and the advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments. The above embodiments and descriptions are only for explaining the principle of the utility model. Without departing from the spirit and scope of the utility model, the utility model may have various changes and improvements, which fall within the scope of the utility model to be protected. The scope of protection claimed by the utility model is defined by the attached claims and their equivalents.

Claims

1. A subway construction pipeline suspension device, characterized in that: The invention comprises a collar (1), wherein an annular groove is provided on the inner side of the collar (1), a gear ring (2) is arranged in the annular groove, a gear (4) is arranged on the inner side of the collar (1), and the gear (4) is in meshing state with the outer side of the gear ring (2), a turning handle (3) is fixedly installed at the center position of the outer side of the gear (4), and the turning handle (3) and the collar (1) are movably connected.

2. A subway construction pipeline suspension device according to claim 1, characterized in that: A thread groove (6) is provided on the outside of the collar (1) and the gear ring (2), a bolt (5) is arranged in the thread groove (6), and the collar (1) is connected to the gear ring (2) through the bolt (5) and the thread groove (6).

3. A subway construction pipeline suspension device according to claim 1, characterized in that: A sleeve rod (7) is fixedly mounted on the top of the sleeve ring (1), and a connecting rod (8) is sleeved on the outside of the sleeve rod (7).

4. A subway construction pipeline suspension device according to claim 3, characterized in that: A movable groove is provided through the front part of the connecting rod (8), an inserting rod (9) is inserted into the movable groove, and an inserting block (12) is provided at the end of the inserting rod (9).

5. A subway construction pipeline suspension device according to claim 4, characterized in that: A spring (11) is arranged outside the insertion rod (9); one end of the spring (11) is fixedly connected to the connecting rod (8), and the other end of the spring (11) is fixedly connected to the insertion block (12).

6. A subway construction pipeline suspension device according to claim 5, characterized in that: The rear part of the insert block (12) is arranged with an inclined surface, and a plurality of slots (10) matching with the insert block (12) are arranged on the outside of the sleeve rod (7).

7. The subway construction pipeline suspension device according to claim 5, characterized in that: A connecting plate (13) is fixedly mounted on the top of the connecting rod (8), and a plurality of mounting grooves are provided through the upper and lower parts of the connecting plate (13).