Spliced temporary drainage chute
By designing spliced temporary drainage rapids, traditional drainage facilities have solved the problems of large engineering volume, high labor costs and inability to eliminate deep water during slope construction, and achieved synchronous drainage and convenient disassembly during slope construction, reducing costs and manpower consumption.
Patent Information
- Application Number
- CN202421123697.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-21
- Publication Date
- 2025-01-07
- Estimated Expiration
- 2034-05-21
AI Technical Summary
Traditional brickwork, stone or concrete drainage facilities have problems such as large project volume, high labor costs, inability to eliminate deep water, and difficulty in transition during slope construction.
A spliced temporary drainage rapids are designed, including concave grooves, edge ridges, joint tenons and grooves, seal strips, steel pipes, seal rings and top covers. Through splicing, a drainage system can be constructed on the slope. The water is drained simultaneously during the process and facilitates disassembly and transition.
Effective drainage during slope construction is achieved, the dismantling process is simplified, cost and labor consumption is reduced, production efficiency is improved, and material procurement and transportation costs are reduced.
Smart Images

Figure CN222314190U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of slope construction, and more specifically to a spliced temporary drainage rapids trough. Background Art
[0002] During the construction of the slope, drainage facilities are constructed simultaneously with the slope protection, and drainage facilities usually can only play a role after completion. Therefore, during the construction of the slope, if the drainage facilities fail to play a role, it is necessary to set up temporary drainage ditches and other drainage facilities.
[0003] Traditional brick, stone or concrete drainage facilities have the following disadvantages:
[0004] 1. The project is large in scale and requires a large amount of bricks, stone slabs, sand and other materials. It needs to be manually built, and the labor cost is also high; 2. During the slope construction process, when the fill fails to be compacted, the built drainage ditch is prone to uneven settlement and damage; 3. The built temporary drainage ditch can only drain the water on the surface of the slope, but cannot drain the deep water of the slope; 4. After the slope is completed, the built temporary drainage ditch cannot be transferred as a whole to the next slope construction location, and can only be dismantled and rebuilt. The transfer is very difficult, which increases the cost. Utility Model Content
[0005] In view of this, the utility model provides a spliced temporary drainage rapids trough, which can drain deep water from the slope and facilitate site transfer.
[0006] The utility model provides a spliced temporary drainage rapids trough, comprising: a trough body, the trough body is in a "concave" shape, and the edge of the trough body is connected with a side sill;
[0007] The bottom of the tank is provided with a plurality of holes;
[0008] Along the extension direction of the trough body, a joint tenon is arranged at one end of the trough body, and a joint groove is arranged at the other opposite end; the joint tenon of any trough body can be clamped in the joint groove of the other trough body.
[0009] In a possible implementation, a sealing strip is provided between the joint tenon and the joint groove.
[0010] In a possible implementation, a plurality of the trough bodies are sequentially connected end to end to form the spliced temporary drainage rapids trough.
[0011] In a possible implementation, it also includes a steel flower tube, a sealing ring and a top cover;
[0012] A plurality of steel flower tubes are opposite to the holes one by one and extend toward the bottom of the tank body;
[0013] The top cover extends downward from the top of the hole, and the top cover and the top of the steel flower tube are both embedded in the sealing ring.
[0014] In a possible implementation, the top cover is provided with a water outlet.
[0015] In a possible implementation, a plurality of water inlet holes are provided in the middle and lower portion of the steel flower tube.
[0016] In a possible implementation, the bottom of the steel flower tube is conical.
[0017] In a possible implementation, it also includes a hole cover;
[0018] A hole circular ridge is arranged along a circumference of the hole, the hole cover can be clamped in the hole circular ridge, and the sealing ring is arranged between the hole circular ridge and the hole cover.
[0019] In a possible implementation, the bottom surfaces of the trough body and the side sill are both provided with a plurality of anti-slip boots arranged in an array.
[0020] In a possible implementation, the tank body is made of aluminum alloy.
[0021] Compared with the prior art, the present invention provides at least the following beneficial effects:
[0022] In the embodiment provided by the utility model, by simply manually splicing the extended trough body, it is possible to achieve simultaneous construction and drainage. After the slope construction is completed, it is convenient to disassemble and transfer to the next place. The disassembly is simple, saving time and labor, improving production efficiency, reducing the cost of purchasing and transporting materials, and reducing costs.
[0023] Of course, any product implementing the present utility model does not necessarily need to achieve all of the above-mentioned technical effects at the same time.
[0024] Other features and advantages of the present invention will become apparent from the following detailed description of exemplary embodiments of the present invention with reference to the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] The accompanying drawings, which are incorporated in and constitute a part of the specification, illustrate embodiments of the present invention and, together with the description, serve to explain the principles of the present invention.
[0026] Figure 1 A schematic diagram of the structure of a tank provided by the utility model;
[0027] Figure 2 A schematic diagram of a splicing structure of a tank body provided by the utility model;
[0028] Figure 3 A schematic diagram of a local structure of a splicing of a tank body provided by the utility model;
[0029] Figure 4 A schematic diagram of the structure of another tank body provided by the utility model;
[0030] Figure 5 A structural schematic diagram of a steel flower tube provided by the utility model;
[0031] Figure 6 A schematic diagram of the structure of a top cover provided by the utility model;
[0032] Figure 7 A structural schematic diagram of a sealing ring provided by the utility model;
[0033] Figure 8 The present invention is a schematic structural diagram of an anti-skid boot provided by the utility model. DETAILED DESCRIPTION
[0034] Various exemplary embodiments of the present invention will now be described in detail with reference to the accompanying drawings. It should be noted that unless otherwise specifically stated, the relative arrangements of components and steps, numerical expressions and numerical values set forth in these embodiments do not limit the scope of the present invention.
[0035] The following description of at least one exemplary embodiment is merely illustrative in nature and is in no way intended to limit the present invention, its application, or uses.
[0036] Technologies, methods, and equipment known to ordinary technicians in the relevant art may not be discussed in detail, but where appropriate, the technologies, methods, and equipment should be considered as part of the specification.
[0037] In all examples shown and discussed herein, any specific values should be interpreted as merely exemplary and not limiting. Therefore, other examples of the exemplary embodiments may have different values.
[0038] It should be noted that like reference numerals and letters refer to similar items in the following figures, and therefore, once an item is defined in one figure, it need not be further discussed in subsequent figures.
[0039] The utility model embodiment provides a spliced temporary drainage rapids trough, referring to Figure 1As shown, the embodiment of the utility model provides a spliced temporary drainage rapids trough, including: a trough body 10, the trough body 10 is in a "concave" shape, and the edge of the trough body 10 is connected to a side sill 11; the concave shape of the groove 10 is conducive to the discharge of water flow and is convenient for being set up at a slope construction site. The trough body 10 is made of aluminum alloy, which is light in weight. Under the premise of ensuring rigidity, it is lighter and more convenient to turn around, has good corrosion resistance, good recyclability, and good sustainability and environmental protection.
[0040] Reference Figure 8 As shown, the bottom surfaces of the trough 10 and the side sill 11 are provided with a plurality of anti-skid boots 18 arranged in an array. The anti-skid boots 18 can be embedded in the roadbed and fixed to maintain the structural integrity and stability.
[0041] Along the extension direction of the trough body 10 , a joint tenon 13 is provided at one end of the trough body 10 , and a joint groove 14 is provided at the other opposite end; the joint tenon 13 of any trough body 10 can be clamped in the joint groove 14 of the other trough body 10 .
[0042] Reference Figure 2 As shown, several trough bodies 10 are connected end to end in sequence to form a spliced temporary drainage rapids trough. Compared with the prior art, this embodiment does not need to consume a large amount of bricks, stone slabs, sand and other materials. Manual assembly and disassembly are simple and easy, and can be assembled on demand. It can achieve simultaneous construction and drainage. After the slope construction is completed, it is convenient to disassemble and transfer to the next place, saving time and labor, improving production efficiency, reducing the cost of purchasing and transporting materials, and reducing costs.
[0043] Further, refer to Figure 3 As shown, a sealing strip 15 is provided between the joint tenon 13 and the joint groove 14. The design of the joint tenon 13 and the joint groove 14 being snap-fitted can adapt to a certain degree of deformation and is not easily damaged by uneven settlement of the slope. The specific assembly process includes: winding the wire, and before assembly, making sure that the joint groove 14 is clean and smooth. Then, lightly apply some lubricant to the outer surface of the sealing strip 15. This will help reduce the friction between the sealing strip 15 and the joint groove 14, making it easier to install. Gently insert the sealing strip 15 into the joint tenon 14 in the correct direction to ensure that it plays a firm sealing role, and then embed the joint tenon 13 into the joint groove 14 with the sealing strip 15 installed and assemble them together.
[0044] Furthermore, the spliced temporary drainage rapids trough of this embodiment can realize two drainage modes, which can be selected according to the specific conditions of the application site. Figure 2 As shown, the bottom of the tank body 10 is provided with a plurality of holes 12 . A hole cover 16 is also provided; a hole round ridge 17 is provided along the circumference of the hole 12 , the hole cover 16 can be clamped in the hole round ridge 17 , and a sealing ring 22 is provided between the hole round ridge 17 and the hole cover 16 .
[0045] When the slope material on site is hydrophobic, or other surfaces of the slope have been well protected, and there is no need for deep drainage, the drainage needs can be met only by the trough body 10 itself. At this time, the hole cover 16 is used to cover the holes 12 at the bottom of the trough body 10. Furthermore, a sealing ring 22 is provided between the hole 12 and the hole cover 16. A hole round ridge 17 is provided around the hole 12, which can better fit the sealing ring 22, ensure that the bottom of the trough body 10 will not leak, and the water flow can be fully discharged.
[0046] Reference Figure 4 and Figure 5 As shown, the spliced temporary drainage rapids trough also includes a steel flower pipe 20, a sealing ring 22 and a top cover 21;
[0047] A plurality of steel flower tubes 20 are opposite to the holes 12 one by one and extend toward the bottom of the tank body 10;
[0048] The top cover 21 extends downward from the top of the hole 12, and the top of the top cover 21 and the top of the steel flower tube 20 are both embedded in the sealing ring 22; the top cover 21 is provided with a water outlet 211. The middle and lower part of the steel flower tube 20 is provided with a plurality of water inlet holes 201. The bottom of the steel flower tube 20 is conical.
[0049] When deep drainage is required, remove the hole cover 16, and then put the sealing ring 22 on the top of the steel flower pipe 20. The bottom of the steel flower pipe 20 is conical, so it can be inserted downward into the slope soil through the hole 12. The top cover 21 covers from above the hole 12 and is also embedded in the sealing ring 22 for fixation. During the installation of the steel flower pipe 20, it is necessary to ensure that the steel flower pipe 20 is firmly embedded in the roadbed to avoid loosening or falling off that affects the drainage effect. After installation, place it where it is needed, and water flows in through the water inlet 201 of the steel flower pipe, and then is discharged through the water outlet 211 of the top cover 21, so that the deep water can be fully discharged.
[0050] In summary, the spliced temporary drainage rapids trough provided by the utility model achieves at least the following beneficial effects:
[0051] In the embodiment provided by the utility model, by simply manually splicing the extended trough body, it is possible to achieve simultaneous construction and drainage. After the slope construction is completed, it is convenient to disassemble and transfer to the next place. The disassembly is simple, saving time and labor, improving production efficiency, reducing the cost of purchasing and transporting materials, and reducing costs.
[0052] Although some specific embodiments of the present invention have been described in detail by way of examples, it should be understood by those skilled in the art that the above examples are for illustration only and are not intended to limit the scope of the present invention. It should be understood by those skilled in the art that the above embodiments may be modified without departing from the scope and spirit of the present invention. The scope of the present invention is defined by the appended claims.
Claims
1. A spliced temporary drainage rapids trough, characterized in that: The invention comprises: a trough body, the trough body is in a "concave" shape, and the edge of the trough body is connected with a side sill; The bottom of the tank is provided with a plurality of holes; Along the extension direction of the trough body, a joint tenon is arranged at one end of the trough body, and a joint groove is arranged at the other opposite end; the joint tenon of any trough body can be clamped in the joint groove of the other trough body.
2. The spliced temporary drainage rapids trough according to claim 1 is characterized in that: A sealing strip is provided between the joint tenon and the joint groove.
3. The spliced temporary drainage rapids trough according to claim 1 is characterized in that: A plurality of the trough bodies are connected end to end in sequence to form the spliced temporary drainage rapids trough.
4. The spliced temporary drainage rapids trough according to claim 1 is characterized in that: It also includes a steel flower tube, a sealing ring and a top cover; A plurality of steel flower tubes are opposite to the holes one by one and extend toward the bottom of the tank body; The top cover extends downward from the top of the hole, and the top cover and the top of the steel flower tube are both embedded in the sealing ring.
5. The spliced temporary drainage rapids trough according to claim 4 is characterized in that: The top cover is provided with a water outlet.
6. The spliced temporary drainage rapids trough according to claim 4, characterized in that: A plurality of water inlet holes are provided in the middle and lower part of the steel flower pipe.
7. The spliced temporary drainage rapids trough according to claim 4, characterized in that: The bottom of the steel flower tube is conical.
8. The spliced temporary drainage rapids trough according to claim 4, characterized in that: Also included are hole covers; A hole circular ridge is arranged along a circumference of the hole, the hole cover can be clamped in the hole circular ridge, and the sealing ring is arranged between the hole circular ridge and the hole cover.
9. The spliced temporary drainage rapids trough according to claim 1, characterized in that: The bottom surfaces of the trough body and the side sill are both provided with a plurality of anti-skid boots arranged in an array.
10. The spliced temporary drainage rapids trough according to claim 1, characterized in that: The tank body is made of aluminum alloy.