Pier column cylinder construction platform
By using bolts and nuts to connect and snap plate slides in the pier cylindrical construction platform, the problems of insufficient stability and cumbersome installation of the traditional platform are solved, and higher construction efficiency and safety are achieved.
Patent Information
- Application Number
- CN202421007206.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-10
- Publication Date
- 2025-01-14
- Estimated Expiration
- 2034-05-10
AI Technical Summary
The structural stability of the traditional pier cylindrical construction platform is insufficient, the installation is cumbersome, which affects the construction efficiency and poses safety hazards.
Two cylindrical construction platforms connected to the first nut are adopted by the first bolt, the bracket is welded to the fixed pedal, and the snap plate connecting plate is installed with the snap plate slider through the second bolt and the second nut, which simplifies the installation process instead. Rotating operation increases overall rigidity and stability.
It has achieved simple structure, convenient installation, high safety and improved construction efficiency, eliminated safety hazards, simplified operating procedures, and enhanced wind resistance resistance.
Smart Images

Figure CN222350188U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of pier column and cylindrical construction, in particular to a pier column and cylindrical construction platform. Background Art
[0002] During the construction of bridge pier columns, it is necessary to set up a pier column construction platform for construction. However, the traditional pier column construction platform has the following shortcomings: 1. The bracket and the platform channel are set separately, resulting in insufficient structural stability of the pier column construction platform and certain safety hazards. 2. The structure is complex, and the construction platform adopts four platform channels for docking. There are many bolts, insufficient overall rigidity, cumbersome processing, and waste of materials and manpower. 3. The installation is cumbersome, which affects the construction efficiency. 4. The previous product used a screw to be screwed to the lower flange, and the steel formwork was fixed by rotating it. Because the rotation stroke is long, the construction personnel may not install the standard operation, and this protection measure has safety hazards. Therefore, in order to avoid the shortcomings existing in the prior art, it is necessary to improve the prior art. Utility Model Content
[0003] The utility model aims to overcome the shortcomings and deficiencies in the prior art and provide a pier column construction platform which has a simple structure and is easy to install.
[0004] The utility model is realized by the following technical solutions:
[0005] A pier column cylindrical construction platform comprises two cylindrical construction platforms connected by a first bolt and a first nut, a bracket is provided at the bottom of the cylindrical construction platform, a plurality of fixed pedals are welded to the top of the bracket, a plurality of snap plate connecting plates are provided on the inner side of the bracket, a snap plate slider is installed on the snap plate connecting plate through a second bolt and a second nut, the snap plate slider is provided with a long strip slide groove extending inward and outward for installing the second bolt, and a plurality of protective nets are inserted on the outer side of the top of the bracket.
[0006] Furthermore, a connecting plate is welded on one side of the protective net, and corresponding bolt mounting holes are provided on the connecting plate and the other side of the protective net. The protective nets are connected by a third bolt and a third nut.
[0007] Furthermore, the protective net is provided with a plug-in support tube, and the outer side of the top of the bracket is provided with a sleeve for plugging the plug-in support tube.
[0008] Furthermore, the sleeve is welded with a skirting board.
[0009] Furthermore, the sleeve is threadedly connected with a locking screw that presses against the plug-in support tube, and the sleeve and the plug-in support tube are connected via a fourth bolt and a fourth nut.
[0010] Furthermore, a plurality of movable pedals are installed on the top of the bracket via hinges.
[0011] Furthermore, a plurality of handles are provided on the top of the cylindrical construction platform.
[0012] Furthermore, both ends of the cylindrical construction platform are provided with connecting flange plates for installing the first bolt and the first nut.
[0013] Furthermore, a semi-annular flange panel is provided on the inner side of the top of the bracket, and a semi-annular flange bottom plate is provided on the inner side of the bottom of the bracket.
[0014] Furthermore, the bracket is provided with a plurality of triangular brackets.
[0015] Compared with the prior art, the utility model comprises two cylindrical construction platforms connected by a first bolt and a first nut through the pier column cylindrical construction platform, the bracket and the fixed pedal are welded together, and the snap plate connecting plate is installed with a snap plate slider through the second bolt and the second nut, and the snap plate slider is provided with a long strip slide groove extending along the inward and outward directions for the installation of the second bolt, so that the structure of the pier column cylindrical construction platform is simple, and the installation of the two cylindrical construction platforms can be completed by operating the bolt and nut connection once. The construction is simple, the lifting is convenient, the operation process is simplified, the installation is simple, the structure is stable, the overall rigidity is increased, the safety is good, the stability is good, the wind resistance is strong, and the safety hazards are eliminated. After the snap plate slider slides, it is locked and positioned with bolts and nuts instead of the original rotation operation. The snap plate slider supports the steel formwork to fix the cylindrical construction platform, which is simple and quick, more conducive to on-site construction and installation, and improves construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] In order to more clearly illustrate the embodiments of the utility model or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0017] Figure 1 It is a schematic diagram of the first direction structure of the pier column cylindrical construction plane of the utility model;
[0018] Figure 2 It is a schematic diagram of the second direction structure of the pier column cylindrical construction plane of the utility model;
[0019] Figure 3 This is a structural exploded view of the pier column construction plane of the utility model;
[0020] Figure 4 for Figure 3 Enlarged view of part A.
[0021] In the figure: 1-cylindrical construction platform; 2-bracket; 3-fixed pedal; 4-clip plate connecting plate; 5-clip plate slider; 6-long strip slide; 7-protective net; 8-connecting plate; 9-plug-in support pipe; 10-sleeve; 11-skirting board; 12-locking screw; 13-hinge; 14-movable pedal; 15-handle; 16-connecting flange plate; 17-flange panel; 18-flange bottom plate; 19-triangular bracket. DETAILED DESCRIPTION
[0022] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0023] like Figures 1 to 4 The utility model shown is a pier column cylindrical construction platform, comprising two cylindrical construction platforms 1 connected by a first bolt and a first nut, a bracket 2 is provided at the bottom of the cylindrical construction platform 1, a plurality of fixed pedals 3 are welded to the top of the bracket 2, a plurality of snap plate connecting plates 4 are provided on the inner side of the bracket 2, a snap plate connecting plate 4 is installed with a snap plate slider 5 through a second bolt and a second nut, the snap plate slider 5 is provided with a long strip slide groove 6 extending along the inward and outward direction for the installation of the second bolt, and a plurality of protective nets 7 are inserted on the outer side of the top of the bracket 2. The pier column cylindrical construction platform includes two cylindrical construction platforms 1 connected by a first bolt and a first nut, the bracket 2 and the fixed pedal 3 are welded together, and the snap plate connecting plate 4 is installed with a snap plate slider 5 through the second bolt and the second nut. The snap plate slider 5 is provided with a long strip slide groove 6 extending along the inward and outward directions for the installation of the second bolt, so that the structure of the pier column cylindrical construction platform is simple, and the installation of the two cylindrical construction platforms 1 can be completed by operating the bolts and nuts once. The construction is simple, the lifting is convenient, the operation process is simplified, the installation is simple, the structure is stable, the overall rigidity is increased, the safety is good, the stability is good, the wind resistance is strong, and the safety hazards are eliminated. After the snap plate slider slides, it is locked and positioned with bolts and nuts instead of the original rotation operation. The snap plate slider supports the steel formwork to fix the cylindrical construction platform, which is simple and fast, more conducive to on-site construction and installation, and improves construction efficiency.
[0024] A connecting plate 8 is welded on one side of the protective net 7, and corresponding bolt mounting holes are provided on the other side of the connecting plate 8 and the protective net 7. The protective nets 7 are connected by a third bolt and a third nut, which improves the safety of use and facilitates the connection and disassembly of the protective nets 5.
[0025] The protection net 7 is provided with a plug-in support tube 9, and the outer side of the top of the bracket 2 is provided with a sleeve 10 for plugging the plug-in support tube 9, which facilitates the rapid plug-in installation of the protection net 7.
[0026] The sleeve 10 is welded with a kick plate 11 to prevent materials from falling from the outside of the top of the bracket 2.
[0027] The sleeve 10 is threadedly connected with a locking screw 12 which presses against the plug-in support tube 9, so as to facilitate the quick locking installation of the protection net 7. The sleeve 10 and the plug-in support tube 9 are connected by a fourth bolt and a fourth nut, so that the installation of the protection net 7 is more stable and the disassembly and assembly are more convenient.
[0028] A plurality of movable pedals 14 are mounted on the top of the bracket 2 via hinges 13. The movable pedals 14 can be opened to facilitate the upward and downward conveyance of materials.
[0029] A plurality of handles 15 are provided on the top of the cylindrical construction platform 1 to facilitate the hoisting of the cylindrical construction platform 1 and to make installation more convenient.
[0030] Both ends of the cylindrical construction platform 1 are provided with the connecting flange plate 16 for installing the first bolt and the first nut, so as to facilitate the stable locking between the two cylindrical construction platforms 1.
[0031] A semi-circular flange panel 17 is provided on the inner side of the top of the bracket 2, and a semi-circular flange base plate 18 is provided on the inner side of the bottom of the bracket 2, which facilitates the connection of the inner support of the bracket 2 and makes the structure of the cylindrical construction platform 1 more stable.
[0032] The bracket 2 is provided with a plurality of triangular brackets 19, so that the supporting structure of the cylindrical construction platform 1 is simple, the support is stable, and the manufacturing cost is low.
[0033] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A pier column construction platform, characterized in that: It comprises two cylindrical construction platforms connected by a first bolt and a first nut, a bracket is provided at the bottom of the cylindrical construction platform, a plurality of fixed pedals are welded to the top of the bracket, a plurality of snap plate connecting plates are provided on the inner side of the bracket, a snap plate slider is installed on the snap plate connecting plate through a second bolt and a second nut, the snap plate slider is provided with a long strip slide groove extending inward and outward directions for installing the second bolt, and a plurality of protective nets are inserted on the outer side of the top of the bracket.
2. The pier column construction platform according to claim 1, characterized in that: A connecting piece is welded on one side of the protective net, and corresponding bolt mounting holes are provided on the connecting piece and the other side of the protective net. The protective nets are connected by a third bolt and a third nut.
3. The pier column construction platform according to claim 1, characterized in that: The protective net is provided with a plug-in support pipe, and the outer side of the top of the bracket is provided with a sleeve for plugging the plug-in support pipe.
4. The pier column construction platform according to claim 3, characterized in that: The sleeve is welded with a skirting board.
5. The pier column construction platform according to claim 3, characterized in that: The sleeve is threadedly connected with a locking screw that presses against the plug-in support tube, and the sleeve and the plug-in support tube are connected through a fourth bolt and a fourth nut.
6. The pier column construction platform according to claim 1, characterized in that: A plurality of movable pedals are installed on the top of the bracket through hinges.
7. The pier column construction platform according to claim 1, characterized in that: A plurality of handles are arranged on the top of the cylindrical construction platform.
8. The pier column construction platform according to claim 1, characterized in that: Both ends of the cylindrical construction platform are provided with connecting flange plates for installing the first bolt and the first nut.
9. The pier column construction platform according to claim 1, characterized in that: A semi-annular flange panel is arranged on the inner side of the top of the bracket, and a semi-annular flange bottom plate is arranged on the inner side of the bottom of the bracket.
10. The pier column construction platform according to claim 1, characterized in that: The bracket is provided with a plurality of triangular brackets.