Downward lighting type photovoltaic module test equipment

By designing the under-lighting photovoltaic module test equipment, the photovoltaic module is supported by the conveyor device and pallet mechanism to realize the under-lighting test, solving the problems of low testing complexity and efficiency in the existing technology, and improving production efficiency and adaptability Compatibility.

CN222464565UActive Publication Date: 2025-02-11SUZHOU SHENGCHENG SOLAR EQUIP CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202420171422.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-24
Publication Date
2025-02-11
Estimated Expiration
2034-01-24

AI Technical Summary

Technical Problem

Existing photovoltaic module testing equipment cannot directly test the power of the module during testing, and needs to be converted through the simulator before testing, which increases the test complexity, reduces efficiency and increases costs.

Method used

设计一种下打光式光伏组件测试设备,采用输送装置和托板机构将光伏组件托起,利用推动模组使输送模组相互远离,实现下打光测试,并通过可调节的测试机构适配不同方向的接线盒。

Benefits of technology

The problem of the transmission line blocking the amount of light entering the bottom edge of the assembly during lighting is solved, and automatic testing of the photovoltaic assembly is realized, which improves production efficiency, reduces production costs, and enhances the adaptability and flexibility of the test device.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222464565U_ABST
    Figure CN222464565U_ABST
Patent Text Reader

Abstract

The utility model discloses a lower lighting type photovoltaic module test device. The photovoltaic module testing device comprises a rack, a conveying device for conveying a photovoltaic module, a plurality of supporting plate mechanisms which are arranged above the conveying device and used for hooking and supporting the photovoltaic module on the conveying device from the upper part, and a testing device which is arranged above the conveying device and used for testing the photovoltaic module supported by the supporting plate mechanisms, the conveying device comprises two conveying modules and a pushing module, wherein the two conveying modules are arranged in parallel at the same height and used for conveying photovoltaic modules, and the pushing module is arranged on the conveying modules and used for driving the two conveying modules to be close to each other or away from each other. According to the utility model, the problem that the conveying line shields the light incoming quantity of the bottom edge of the assembly during downward polishing is solved, and the testing device can adapt to the layout of the photovoltaic assembly junction box in different directions, so that the production efficiency is improved, and the production cost is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The utility model belongs to the technical field of solar energy component testing, in particular to a downward-lighting photovoltaic component testing device. [Background technology]

[0002] During the photovoltaic module testing process, the module needs to be illuminated. In order to ensure the reliability and accuracy of the test results, the light source is irradiated on the photovoltaic module without any obstruction in the middle. Since the photovoltaic module is generally placed on a conveyor line for testing, if the tester illuminates the conveyor line from below, the amount of light entering the bottom edge of the module will be blocked. Therefore, in the prior art, IV testing of photovoltaic modules generally uses a light source to illuminate from above the photovoltaic module, and the test probe detects the electrical connection from below or above the photovoltaic module. For example, a photovoltaic module power tester disclosed in patent publication number CN 111323620 A adopts the method of illuminating from above and detecting from below. The conveyor line transports the solar module to the top of the floating test platform. After the alignment mechanism corrects the position of the solar module, the lifting cylinder of the floating test platform lifts the detection module to the set position of the test junction box, and the tester illuminates from above to perform a power test. However, the following problems still exist for the power test equipment of top lighting: during the test, the power of the photovoltaic module cannot be tested directly, but it must be converted through a simulator before the test, which increases the complexity of the test process, reduces the efficiency of the test, and increases the cost of the test.

[0003] Therefore, it is necessary to provide a down-lighting photovoltaic module testing device to solve the above technical problems. [Utility Model Content]

[0004] The main purpose of the utility model is to provide a bottom-lighting photovoltaic module testing device, which solves the problem that the conveyor line will block the amount of light entering the bottom edge of the module when the bottom light is on, realizes the automatic testing of the photovoltaic module, and the testing device can adapt to the layout of the photovoltaic module junction box in different directions, thereby improving production efficiency and reducing production costs.

[0005] The utility model achieves the above-mentioned purpose through the following technical scheme: a bottom-lit photovoltaic module testing equipment, which includes a frame, a conveying device for conveying photovoltaic modules, a plurality of support plate mechanisms arranged above the conveying device and hooking up and supporting the photovoltaic modules on the conveying device from above, and a testing device arranged above the conveying device and testing the photovoltaic modules supported by the support plate mechanisms; the conveying device includes two conveying modules arranged in parallel and at the same height and conveying the photovoltaic modules, and a pushing module arranged on the conveying modules and driving the two conveying modules to move closer to or away from each other.

[0006] Furthermore, the conveying modules include a first transmission assembly and a second transmission assembly arranged at both ends of the frame, a conveyor belt mounted on the first transmission assembly and the second transmission assembly, a first driving member for driving the first transmission assembly to rotate, a connecting beam arranged between the first transmission assembly and the second transmission assembly, a support bar fixed to the lower groove on the inner side surface of the connecting beam and used to support the conveyor belt, an angle steel fixed to the upper groove on the inner side surface of the connecting beam, and a plurality of side guide wheels arranged in a straight line under the angle steel and guiding the side edges of the photovoltaic components.

[0007] Furthermore, the pushing module includes a second driving member and a first support plate driven by the second driving member to move forward or backward, the first transmission assembly and the second transmission assembly are both fixed on the first support plate, a first slide rail is provided on the frame, and the first support plate is mounted on the first slide rail through the first slider.

[0008] Furthermore, a stopping module for stopping the photovoltaic component being transported is provided at one end of the conveying module, and the stopping module includes a mounting frame fixed on the connecting beam, a third driving member fixed on the mounting frame and on the relatively inner side of the conveying module, and a stop rod driven by the third driving member to rotate around a horizontal axis; a second slide rail is provided on the connecting beam, and the stop module is installed on the second slide rail through a second slider.

[0009] Furthermore, the support plate mechanism includes a first support plate mechanism that supports the inner side of the frame on one side of the photovoltaic component and a second support plate mechanism that supports the inner side of the frame on the other opposite side of the photovoltaic component and is symmetrically arranged with respect to the first support plate mechanism.

[0010] Furthermore, the first support plate mechanism and the second support plate mechanism both include a fourth driving member, a second support plate driven by the fourth driving member to move forward and backward, a fifth driving member fixed on the second support plate, and a support plate driven by the fifth driving member to move up and down.

[0011] Furthermore, the testing device includes a plurality of first testing mechanisms for testing a plurality of junction boxes arranged transversely on the photovoltaic module and arranged transversely corresponding to the plurality of junction boxes, and a plurality of second testing mechanisms for testing a plurality of junction boxes arranged longitudinally on the photovoltaic module and arranged longitudinally corresponding to the plurality of junction boxes.

[0012] Furthermore, the first testing mechanism and the second testing mechanism have the same structure and both include a sixth driving member fixed on the frame, a plane adjustment assembly that is moved up and down by the sixth driving member, a fixture assembly fixed below the plane adjustment assembly, and a test assembly fixed below the plane adjustment assembly and located above the fixture assembly.

[0013] Furthermore, the fixture assembly includes a seventh driving member and a pair of jaws driven by the seventh driving member to open or clamp the junction box; the test assembly includes an eighth driving member, a third support plate driven by the eighth driving member to move up and down, a probe box fixed on the third support plate, and a plurality of probes arranged on the probe box and extending out from the lower surface of the probe box.

[0014] Furthermore, a plurality of installation beams arranged at intervals are provided above the rack, each installation beam is provided with a third slide rail, and the support plate mechanism and the testing device are respectively installed on the installation beams through a third slide block; a plurality of fourth slide rails are provided above the rack, and a plurality of the installation beams are installed on the fourth slide rails through a fourth slide block.

[0015] Compared with the prior art, the beneficial effects of the bottom-lighting photovoltaic module testing equipment of the utility model are as follows: (1) the conveying device includes two conveying modules arranged in parallel and at the same height for conveying photovoltaic modules, and a pushing module arranged at both ends of the conveying module for driving the two conveying modules to move closer to or away from each other, and a supporting plate mechanism for lifting the photovoltaic modules on the conveying device is arranged above the conveying device. When the photovoltaic modules are transported to the right place, the supporting plate mechanism lifts the photovoltaic modules, and the pushing module pushes the two conveying modules away from each other. The supporting plate mechanism holds the photovoltaic modules for testing. When the bottom-lighting method is adopted, the conveying line will not block the light from shining on the photovoltaic modules, and the test value is more accurate and close to the real value.

[0016] (2) The testing device includes a plurality of first testing mechanisms for testing a plurality of junction boxes arranged horizontally on a photovoltaic module and arranged horizontally corresponding to the plurality of junction boxes, and a plurality of second testing mechanisms for testing a plurality of junction boxes arranged vertically on a photovoltaic module and arranged vertically corresponding to the plurality of junction boxes. The first testing mechanisms and the second testing mechanisms are adapted to junction boxes arranged in different directions. The first testing mechanism or the second testing mechanism can be selected for testing according to the arrangement of the junction boxes of the photovoltaic module. One testing device can test photovoltaic modules with junction boxes arranged in different ways, has strong adaptability and high flexibility, high testing efficiency, and low production cost.

[0017] Therefore, the downward-lit photovoltaic module testing equipment provided by this solution solves the problem that the conveyor line will block the amount of light entering the bottom edge of the module when downward lighting is used, realizes automatic testing of photovoltaic modules, and the testing device can adapt to the layout of photovoltaic module junction boxes in different directions, thereby improving production efficiency and reducing production costs.

Brief Description of the Drawings

[0018] Figure 1This is a schematic diagram of the three-dimensional structure of the lighting-type photovoltaic module testing equipment according to the embodiment of the utility model;

[0019] Figure 2 This is a schematic diagram of the top view of the structure of the lighting type photovoltaic module testing equipment according to the embodiment of the utility model;

[0020] Figure 3 This is a schematic diagram of the partial structure of the conveying device of the utility model embodiment;

[0021] Figure 4 This is a schematic diagram of the three-dimensional structure of the support plate mechanism of the embodiment of the utility model;

[0022] Figure 5 This is a schematic diagram of the three-dimensional structure of the test device of the utility model embodiment;

[0023] The numbers in the figure represent:

[0024] 100- Downward lighting photovoltaic module testing equipment;

[0025] 1-frame, 11-first slide rail, 12-mounting beam, 121-third slide rail, 13-fourth slide rail;

[0026] 2-conveying device, 21-conveying module, 211-first transmission assembly, 212-second transmission assembly, 213-conveying belt, 214-connecting beam, 2141-second slide rail, 215-support bar, 216-angle steel, 217-side guide wheel, 218-first driving member, 22-pushing module, 221-second driving member, 222-first supporting plate, 223-first sliding block, 23-stopping module, 231-mounting frame, 232-third driving member, 233-gear lever;

[0027] 3- support plate mechanism, 31- first support plate mechanism, 32- second support plate mechanism, 33- fourth driving member, 34- second support plate, 35- fifth driving member, 36- support plate;

[0028] 4-testing device, 41-first testing mechanism, 42-second testing mechanism, 43-sixth driving member, 44-plane adjustment assembly, 45-clamp assembly, 451-seventh driving member, 452-clamping jaw, 46-testing assembly, 461-eighth driving member, 462-third supporting plate, 463-probe box, 464-probe. [Specific implementation method]

[0029] Please refer to Figure 1-Figure 5The present embodiment is a downward-lit photovoltaic module testing device. The downward-lit photovoltaic module testing device 100 includes a frame 1, a conveying device 2 installed in the middle of the frame 1 and used to convey photovoltaic modules, a plurality of support mechanisms 3 arranged above the conveying device 2 and used to hook and lift the photovoltaic modules on the conveying device 2 from above, and a testing device 4 arranged above the conveying device 2 and used to perform power testing on the photovoltaic modules held by the support mechanisms 3.

[0030] The conveying device 2 comprises two conveying modules 21 which are arranged in parallel and at the same height and are used to convey the photovoltaic components, and a driving module 22 which is arranged at both ends of the conveying modules 21 and drives the two conveying modules 21 to move closer to or away from each other.

[0031] The two conveying modules 21 each include a first transmission assembly 211 and a second transmission assembly 212 arranged at both ends of the frame 1, a conveyor belt 213 sleeved on the first transmission assembly 211 and the second transmission assembly 212, a first driving member 218 driving the first transmission assembly 211 to rotate, a connecting beam 214 arranged between the first transmission assembly 211 and the second transmission assembly 212, a support bar 215 fixed to the lower groove of the inner side surface of the connecting beam 214 and used to support the conveyor belt 213, an angle steel 216 fixed to the upper groove of the inner side surface of the connecting beam 214, and a plurality of side guide wheels 217 arranged in a straight line below the angle steel 216 and guiding the side edges of the photovoltaic module, the side guide wheels 217 all rotate around a vertical axis and are located on the outside of the conveyor belt 213, the angle steel 216 has a vertical surface fixed to the connecting beam 214 and a horizontal surface perpendicular to the vertical surface, and the plurality of side guide wheels 217 are arranged in a straight line below the horizontal surface.

[0032] The connecting beam 214 is an aluminum profile with a square cross-section and two grooves on each side. The structure has good bending resistance in four directions: up, down, left and right. The inner side surfaces of the connecting beam 214 are used to fix the support bar 215 and the angle steel 216 respectively. The support bar 215 can maintain the horizontality so that the upper section of the conveyor belt 213 can have sufficient contact with the edge area of ​​the lower surface of the plate. The angle steel 216 itself also has deformation resistance in two vertical directions, and the side guide wheels 217 arranged on the angle steel 216 can move the photovoltaic module on the conveyor belt 213 under low resistance to prevent the photovoltaic module from deviating from the middle.

[0033] The pushing module 22 includes a second driving member 221 and a first support plate 222 driven by the second driving member 221 to move forward or backward. The first transmission assembly 211 and the second transmission assembly 212 are both fixed on the first support plate 222. A first slide rail 11 is provided on the frame 1, and the first support plate 222 is installed on the first slide rail 11 through a first slider 223.

[0034] A stop module 23 for stopping the photovoltaic module being transported is provided at one end of the conveying module 21. The stop module 23 includes a mounting frame 231 fixed on the connecting beam 214, a third driving member 232 fixed on the mounting frame 231 and on the relatively inner side of the conveying module 21, and a stop rod 233 driven by the third driving member 232 to rotate around a horizontal axis. A second slide rail 2141 is provided on the connecting beam 214, and the stop module 23 is installed on the second slide rail 2141 through a second slider to facilitate adaptation to photovoltaic modules of different sizes. The initial state of the stop rod 233 is in a horizontal state. When a stop action is required, the third driving member 232 drives the stop rod 233 to rotate from a horizontal state to a vertical state to block one end of the photovoltaic module being transported forward.

[0035] The support mechanism 3 is arranged above the frame 1, and the support mechanism 3 includes a first support mechanism 31 for supporting the inner side of the frame on one side of the photovoltaic component and a second support mechanism 32 for supporting the inner side of the frame on the other opposite side of the photovoltaic component and arranged symmetrically with the first support mechanism 31. The first support mechanism 31 and the second support mechanism 32 both include a fourth driving member 33, a second support plate 34 driven by the fourth driving member 33 to move forward and backward, a fifth driving member 35 fixed on the second support plate 34, and a support plate 36 driven by the fifth driving member 35 to move up and down. The support plates 36 of the first support mechanism 31 and the second support mechanism 32 simultaneously extend into the inner side of the frames on both sides of the photovoltaic component to lift the photovoltaic component.

[0036] After the conveying device 2 is in place, the fifth driving member 35 simultaneously drives the pallet 36 to move downward, and the fourth driving member 33 of the front first pallet mechanism 31 drives the second support plate 34 to move forward so that the pallet 36 extends into the inner side of the frame on one side of the photovoltaic component. At the same time, the fourth driving member 33 of the rear second pallet mechanism 32 drives the second support plate 34 to move backward so that the pallet 36 extends into the inner side of the frame on the other side of the photovoltaic component. At the same time, the fifth driving member drives the pallet 36 to move upward to lift the photovoltaic component.

[0037] The testing device 4 includes a plurality of first testing mechanisms 41 for testing a plurality of junction boxes arranged horizontally on the photovoltaic module and arranged horizontally corresponding to the plurality of junction boxes, and a plurality of second testing mechanisms 42 for testing a plurality of junction boxes arranged vertically on the photovoltaic module and arranged vertically corresponding to the plurality of junction boxes. The first testing mechanisms 41 and the second testing mechanisms can be adapted to junction boxes with different arrangement directions. The first testing mechanism 41 or the second testing mechanism 42 can be selected for testing according to the arrangement of the junction boxes of the photovoltaic module. One testing device can test photovoltaic modules with junction boxes of different arrangements, has strong adaptability and high flexibility, high testing efficiency, and low production cost.

[0038] The first testing mechanism 41 and the second testing mechanism 42 have the same structure and both include a sixth driving member 43 fixed on the frame 1, a plane adjustment assembly 44 that is moved up and down by the sixth driving member 43, a clamp assembly 45 fixed below the plane adjustment assembly 44, and a testing assembly 46 fixed below the plane adjustment assembly 44 and located above the clamp assembly 45.

[0039] The clamp assembly 45 includes a seventh driving member 451 and a pair of clamping jaws 452 driven by the seventh driving member 451 to open or clamp the junction box.

[0040] The test assembly 46 includes an eighth driving member 461 , a third support plate 462 driven by the eighth driving member 461 to move up and down, a probe box 463 fixed on the third support plate 462 , and a plurality of probes 464 disposed on the probe box 463 and extending out from the lower surface of the probe box 463 .

[0041] The plane adjustment component 44 can simultaneously adjust the fixture component 45 and the test component 46 in the front-to-back and left-to-right directions, so that the probe 464 of the test component 46 completely matches the test point of the junction box, which can improve the accuracy of the test.

[0042] A plurality of installation beams 12 arranged at intervals are arranged above the rack 1, and the support plate mechanism 3 and the test device 4 are respectively arranged on the installation beams 12, and the installation beams 12 are both provided with third slide rails 121, and the support plate mechanism 3 and the test device 4 are respectively installed on the installation beams 12 through third sliders; a plurality of fourth slide rails 13 are arranged above the rack 1, and a plurality of installation beams 12 are installed on the fourth slide rails 13 through fourth sliders. By moving the support plate mechanism 3 or the test device 4 on the installation beam 12, or directly moving the installation beam 12, different sizes of photovoltaic modules or junction boxes at different positions can be adapted, and the installation method is simple and convenient, and the production efficiency is high.

[0043] When the test equipment provided by the present solution is used, the photovoltaic components are placed on the conveyor belt 213 and conveyed forward. The side guide wheels 217 on both sides guide the two sides of the photovoltaic components to avoid deviation. After being conveyed to the right position, the third driving member 232 drives the gear lever 233 to rotate from a horizontal state to a vertical state to block the photovoltaic components conveyed forward. The fifth driving member 35 of the support plate mechanism 3 simultaneously drives the support plate 36 to move downward. The fourth driving member 33 of the first support plate mechanism 31 in front drives the second support plate 34 to move forward so that the support plate 36 extends into the inner side of the frame on one side of the photovoltaic component. At the same time, the fourth driving member 33 of the second support plate mechanism 32 at the rear drives the second support plate 34 to move backward so that the support plate 36 extends into the inner side of the frame on the other side of the photovoltaic component. At the same time, the fifth driving member drives the support plate 36 to move upward so as to lift the photovoltaic component. The pushing modules 2 at both ends of the two conveying devices 2 2 act simultaneously, the second driving member 221 drives the first supporting plate 222 to drive the conveying module 21 to move away from each other, and the fifth driving member 35 of the supporting plate mechanism 3 drives the supporting plate 36 to move downward to restore to the initial position. The bottom lighting method is adopted. According to the arrangement and distribution of the junction boxes on the photovoltaic module, the first test mechanism 41 or the second test mechanism 42 is selected for testing. The sixth driving member 43 drives the clamp assembly 45 to descend and clamp the junction box. At the same time, the probe 464 of the test assembly 46 is located above the test point of the junction box. The plane adjustment assembly 44 adjusts the clamp assembly 45 and the test assembly 46 in the front-to-back and left-to-right directions so that the probe 464 matches the position of the junction box. After the position is adjusted, the eighth driving member 461 of the test assembly 46 drives the third supporting plate 462 to drive the probe 464 to move downward so as to contact the test point of the junction box to complete the test of the photovoltaic module.

[0044] The present invention provides a bottom-lighting photovoltaic module testing device, wherein (1) a conveying device 2 includes two conveying modules 21 arranged in parallel and at the same height for conveying photovoltaic modules, and a pushing module 22 arranged at both ends of the conveying module 21 for driving the two conveying modules 21 to move closer to or away from each other, and a supporting plate mechanism 3 for lifting the photovoltaic modules on the conveying device 2 is arranged above the conveying device 2. When the photovoltaic modules are transported to the right place, the supporting plate mechanism 3 lifts the photovoltaic modules, and the pushing module 22 pushes the two conveying modules 21 away from each other. The supporting plate mechanism 3 holds the photovoltaic modules for testing. When the bottom-lighting method is adopted, the conveying line will not block the light from shining on the photovoltaic modules, and the test value is more accurate and close to the real value; (2 ) The testing device 4 includes a plurality of first testing mechanisms 41 for testing a plurality of junction boxes arranged horizontally on the photovoltaic module and arranged horizontally corresponding to the plurality of junction boxes, and a plurality of second testing mechanisms 42 for testing a plurality of junction boxes arranged vertically on the photovoltaic module and arranged vertically corresponding to the plurality of junction boxes. The first testing mechanism 41 and the second testing mechanism can be adapted to junction boxes arranged in different directions. The first testing mechanism 41 or the second testing mechanism 42 can be selected for testing according to the arrangement of the junction boxes of the photovoltaic module. One testing device can test photovoltaic modules with junction boxes arranged in different ways, with strong adaptability and high flexibility, high testing efficiency and low production cost. Therefore, compared with the prior art, the down-lighting photovoltaic module testing device 100 provided by the present solution solves the problem that the conveyor line will block the amount of light entering the bottom edge of the module when down-lighting is applied, realizes the automatic testing of the photovoltaic module, and the testing device can adapt to the layout of the junction boxes of the photovoltaic module in different directions, thereby improving production efficiency and reducing production costs.

[0045] The above are only some embodiments of the present invention. For those skilled in the art, several modifications and improvements can be made without departing from the inventive concept of the present invention, which all belong to the protection scope of the present invention.

Claims

1. A downlighting photovoltaic module testing device, characterized in that: It includes a frame, a conveying device for conveying photovoltaic components, a plurality of support plate mechanisms arranged above the conveying device and hooking up and supporting the photovoltaic components on the conveying device from above, and a testing device arranged above the conveying device and testing the photovoltaic components supported by the support plate mechanisms; the conveying device includes two conveying modules arranged in parallel and at the same height and conveying the photovoltaic components, and a pushing module arranged on the conveying modules and driving the two conveying modules to move closer to or away from each other.

2. A downlighting photovoltaic module testing device as claimed in claim 1, characterized in that: The conveying modules include a first transmission assembly and a second transmission assembly arranged at both ends of the frame, a conveyor belt mounted on the first transmission assembly and the second transmission assembly, a first driving member that drives the first transmission assembly to rotate, a connecting beam arranged between the first transmission assembly and the second transmission assembly, a support bar fixed to the lower groove on the inner side surface of the connecting beam and used to support the conveyor belt, an angle steel fixed to the upper groove on the inner side surface of the connecting beam, and a plurality of side guide wheels arranged in a straight line below the angle steel and guiding the side edges of the photovoltaic components.

3. A downlighting photovoltaic module testing device as claimed in claim 2, characterized in that: The pushing module includes a second driving member and a first supporting plate driven by the second driving member to move forward or backward, the first transmission assembly and the second transmission assembly are both fixed on the first supporting plate, a first slide rail is provided on the frame, and the first supporting plate is mounted on the first slide rail through a first slider.

4. A downlighting photovoltaic module testing device as claimed in claim 2, characterized in that: A stopping module for stopping the photovoltaic component being transported is provided at one end of the conveying module, and the stopping module includes a mounting frame fixed on the connecting beam, a third driving member fixed on the mounting frame and on the relatively inner side of the conveying module, and a stop rod driven by the third driving member to rotate around a horizontal axis; a second slide rail is provided on the connecting beam, and the stopping module is installed on the second slide rail through a second slider.

5. The downlighting photovoltaic module testing device according to claim 1, characterized in that: The support plate mechanism comprises a first support plate mechanism supporting the inner side of the frame on one side of the photovoltaic component and a second support plate mechanism supporting the inner side of the frame on the other opposite side of the photovoltaic component and arranged symmetrically with the first support plate mechanism.

6. A downlighting photovoltaic module testing device as claimed in claim 5, characterized in that: The first support plate mechanism and the second support plate mechanism both include a fourth driving member, a second support plate driven by the fourth driving member to move forward and backward, a fifth driving member fixed on the second support plate, and a support plate driven by the fifth driving member to move up and down.

7. The downlighting photovoltaic module testing device according to claim 1, characterized in that: The testing device includes a plurality of first testing mechanisms for testing a plurality of junction boxes arranged transversely on the photovoltaic module and arranged transversely corresponding to the plurality of junction boxes, and a plurality of second testing mechanisms for testing a plurality of junction boxes arranged longitudinally on the photovoltaic module and arranged longitudinally corresponding to the plurality of junction boxes.

8. The downlighting photovoltaic module testing device according to claim 7, characterized in that: The first testing mechanism and the second testing mechanism have the same structure and both include a sixth driving member fixed on the frame, a plane adjustment assembly that is moved up and down by the sixth driving member, a fixture assembly fixed below the plane adjustment assembly, and a test assembly fixed below the plane adjustment assembly and located above the fixture assembly.

9. A downlighting photovoltaic module testing device as claimed in claim 8, characterized in that: The clamp assembly includes a seventh driving member and a pair of jaws driven by the seventh driving member to open or clamp the junction box; the test assembly includes an eighth driving member, a third support plate driven by the eighth driving member to move up and down, a probe box fixed on the third support plate, and a plurality of probes arranged on the probe box and extending out from the lower surface of the probe box.

10. The downlighting photovoltaic module testing device according to claim 1, characterized in that: A plurality of installation beams arranged at intervals are arranged above the rack, and a third slide rail is arranged on each of the installation beams. The support plate mechanism and the test device are respectively installed on the installation beams through third sliders; a plurality of fourth slide rails are arranged above the rack, and a plurality of the installation beams are installed on the fourth slide rails through fourth sliders.

Citation Information

Patent Citations

  • Photovoltaic module power testing machine

    CN111323620A