Automatic silicone adhesive filling device

By designing an automated glue filling device, using mobile components and material storage components, the existing glue filling machine has solved the problem of glue filling errors caused by workpiece movement or position deviation, and achieved higher glue filling accuracy and flexibility.

CN222469550UActive Publication Date: 2025-02-14WEIFANG KEHUA PACKAGING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420356557.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-27
Publication Date
2025-02-14
Estimated Expiration
2034-02-27

AI Technical Summary

Technical Problem

During the processing process, existing glue filling machines may cause glue filling errors due to movement or position deviation of the workpiece to be processed.

Method used

An automated glue filling device including mobile components, glue filling components and material storage components is designed. The mobile components drive the glue filling components to move in multiple directions to ensure the accuracy of glue filling. The storage components are responsible for the storage and supply of glue.

Benefits of technology

It improves the flexibility and accuracy of the glue filling device, reduces the possibility of glue filling errors, and ensures the supply of glue filling components.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222469550U_ABST
    Figure CN222469550U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of glue filling, in particular to an automatic silicone glue filling device, and aims to solve the problems that although a glue filling machine in the prior art is relatively accurate in control, the glue filling machine cannot be used for filling silicone glue automatically. However, in the machining process, glue filling errors are possibly caused by movement or position deviation of the workpiece to be machined. The glue filling device comprises a workbench, a moving assembly is arranged at the top of the workbench, a glue filling assembly is arranged in the moving assembly, and a storage assembly is arranged on the left side of the workbench; the moving assembly is used for driving the glue filling assembly to move in multiple directions; the glue pouring assembly is used for pouring glue into the machined part on the workbench; the material storage assembly is used for storing and conveying rubber materials; the glue filling assembly can be driven to move in multiple directions through the moving assembly, the glue filling accuracy of the glue filling device is improved, and meanwhile supply of the glue filling assembly can be completed through the material storage assembly.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of glue pouring, in particular to an automatic silicone glue pouring device. Background Art

[0002] At present, glue dispensing machines are also called glue coating machines, glue dripping machines, glue spraying machines, glue filling machines, etc. They are specially used to control fluids; they are automated machines that drip and apply fluids on the surface or inside of products, and can achieve three-dimensional and four-dimensional path glue dispensing, precise positioning, precise glue control, no drawing, no glue leakage, and no glue dripping; glue dispensing machines are mainly used for the precise dot, injection, coating, and dripping of glue, paint and other liquids in product processes to the precise position of each product;

[0003] Although the glue dispensing machine in the related art has relatively accurate control over the glue dispensing machine itself, glue dispensing errors may still occur during the processing process due to the movement or position deviation of the workpiece to be processed.

[0004] Therefore, it is particularly important to improve the existing glue pouring device and design a new glue pouring device to change the above technical defects and improve the practicability of the overall glue pouring device. Utility Model Content

[0005] The purpose of the utility model is to provide an automatic silicone glue filling device to solve the problems raised in the above background technology.

[0006] In order to achieve the above purpose, the utility model provides the following technical solutions:

[0007] An automatic silicone glue pouring device comprises a workbench, a moving component is arranged on the top of the workbench, a glue pouring component is arranged inside the moving component, and a material storage component is arranged on the left side of the workbench;

[0008] The moving component is used to drive the glue filling component to move in multiple directions;

[0009] The glue pouring assembly is used to pour glue on the workpiece on the workbench;

[0010] The material storage component is used for storing and transporting rubber material.

[0011] As a preferred solution of the utility model, the moving assembly includes two groups of moving frames, a first linear slide rail, a sliding frame, a second linear slide rail, a storage barrel, a mounting frame, a first drag chain and a second drag chain, and the two groups of moving frames are fixedly connected to the left and right sides of the top of the workbench.

[0012] As a preferred solution of the utility model, the tops of the two groups of movable frames are fixedly connected with a first linear slide rail, a sliding frame is provided between the two groups of the first linear slide rails, the tops of the sliding frames are fixedly connected with two groups of second linear slide rails, and the tops of the two groups of the second linear slide rails are provided with a storage barrel.

[0013] As a preferred solution of the utility model, a mounting frame is fixedly connected to the top of one group of the movable frames and located above the sliding frame, a first drag chain is provided on the top of the mounting frame, and a second drag chain is provided on the top of the sliding frame and located behind the second linear slide rail.

[0014] As a preferred solution of the utility model, the glue pouring assembly includes a support seat, a screw motor, a third linear slide rail, a connecting seat and a glue pouring device. The support seat is fixedly connected to the front side of the storage barrel, the screw motor is fixedly installed on the bottom of the support seat, the third linear slide rail is fixedly connected to the top of the support seat, the front side of the third linear slide rail is slidably connected to the connecting seat, and the glue pouring device is installed on the front side of the connecting seat.

[0015] As a preferred solution of the utility model, the material storage assembly includes a support table, a storage tank, a conveying pipe and a control box. The support table is arranged on the left side of the workbench. The top of the support table is provided with a storage tank, and the storage tank is connected to the storage barrel through the conveying pipe.

[0016] As a preferred solution of the utility model, a control box is fixedly connected to the top of the support table and in front of the storage tank, a regulating valve is provided on the top of the storage tank, a support frame is provided at the bottom of the workbench, and the conveying pipeline is a corrugated pipe.

[0017] Compared with the prior art, the beneficial effects of the utility model are:

[0018] In the utility model, through the design of the moving component, the glue pouring component and the material storage component, the moving component can drive the glue pouring component to move in multiple directions, so that the glue pouring component can be accurately moved to any position on the top of the workbench, thereby improving the flexibility of the glue pouring device and making it less likely to make glue pouring mistakes; improving the accuracy of glue pouring by the glue pouring device, and at the same time, the supply of the glue pouring component can be completed through the material storage component. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] Figure 1 It is a schematic diagram of the overall three-dimensional structure of the utility model;

[0020] Figure 2 It is a schematic diagram of a partial three-dimensional structure of the utility model;

[0021] Figure 3 It is a schematic diagram of the three-dimensional structure of the mobile component of the utility model.

[0022] In the figure: 1. workbench; 101. support frame; 2. moving assembly; 201. moving frame; 202. first linear slide; 203. sliding frame; 204. second linear slide; 205. storage barrel; 206. mounting frame; 207. first drag chain; 208. second drag chain; 3. glue pouring assembly; 301. support seat; 302. screw motor; 303. third linear slide; 304. connecting seat; 305. glue pouring equipment; 4. storage assembly; 401. support table; 402. storage tank; 403. conveying pipeline; 404. control box. DETAILED DESCRIPTION

[0023] The technical solutions in the embodiments of the utility model will be clearly and completely described below in conjunction with the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, rather than all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the utility model. Example

[0024] In view of the shortcomings of the prior art, the purpose of the utility model is to provide an automatic silicone glue pouring device, which aims to solve the technical problem that although the control of the glue pouring machine itself is relatively accurate, it may still cause glue pouring errors during the processing due to the movement or position deviation of the workpiece to be processed.

[0025] See also Figure 1-Figure 3 , the utility model provides a technical solution:

[0026] A silicone glue automatic glue pouring device comprises a workbench 1, a moving component 2 is arranged on the top of the workbench 1, a glue pouring component 3 is arranged inside the moving component 2, and a material storage component 4 is arranged on the left side of the workbench 1;

[0027] Wherein, a support frame 101 is provided at the bottom of the workbench 1 .

[0028] Specifically, first, the support frame 101 is placed at the specified position, and then the workbench 1 is placed on the support frame 101. When in use, the glue pouring component 3 is driven to move by the moving component 2. At this time, the glue pouring component 3 is loaded through the material storage component 4. After the glue pouring component 3 is moved above the workpiece to be processed, the workpiece on the workbench 1 is then glued through the glue pouring component 3, which improves the flexibility of the glue pouring device and makes it less likely to make glue pouring mistakes; improves the accuracy of glue pouring by the glue pouring component 3, and at the same time, the supply of the glue pouring component 3 can be guaranteed through the material storage component 4.

[0029] Also, see Figure 1-Figure 3A moving component 2 is provided on the top of the workbench 1.

[0030] The moving component 2 is used to drive the glue filling component 3 to move in multiple directions. The specific structure of the moving component 2 is as follows:

[0031] The moving assembly 2 includes two groups of moving frames 201, a first linear slide 202, a sliding frame 203, a second linear slide 204, a storage barrel 205, a mounting frame 206, a first drag chain 207 and a second drag chain 208. The two groups of moving frames 201 are fixedly connected to the left and right sides of the top of the workbench 1. The tops of the two groups of moving frames 201 are fixedly connected with the first linear slide 202. A sliding frame 203 is arranged between the two groups of first linear slides 202. The tops of the sliding frames 203 are fixedly connected with two groups of second linear slides 204. The tops of the two groups of second linear slides 204 are provided with a storage barrel 205. The top of one group of moving frames 201 and located above the sliding frame 203 is fixedly connected with a mounting frame 206. The top of the mounting frame 206 is provided with a first drag chain 207. The top of the sliding frame 203 and located behind the second linear slide 204 is provided with a second drag chain 208.

[0032] Specifically, a telescopic cylinder is provided at the top of the workbench 1 and at a position corresponding to the movable frame 201. The telescopic cylinder drives the sliding frame 203 to move on the two groups of sliding frames 203. At this time, the two groups of first linear slides 202 reduce the friction between the sliding frame 203 and the first linear slides 202. At this time, the first drag chain 207 on the top of the mounting frame 206 can protect the wires in the movable frame 201. At the same time, the telescopic cylinder can be used to drive the storage barrel 205 to move on the sliding frame 203. The second linear slide 204 reduces the friction between the storage barrel 205 and the sliding frame 203. The second drag chain 208 can protect the wires in the sliding frame 203.

[0033] Then, see Figure 1-Figure 3 A glue pouring component 3 is provided inside the moving component 2, and a material storage component 4 is provided on the left side of the workbench 1.

[0034] The glue pouring component 3 is used to pour glue on the workpiece on the workbench 1, and the material storage component 4 is used to store and transport the glue. The specific structures of the glue pouring component 3 and the material storage component 4 are as follows:

[0035] The glue pouring assembly 3 includes a support seat 301, a screw motor 302, a third linear slide rail 303, a connecting seat 304 and a glue pouring device 305. The support seat 301 is fixedly connected to the front of the storage barrel 205, the screw motor 302 is fixedly installed on the bottom of the support seat 301, the third linear slide rail 303 is fixedly connected to the top of the support seat 301, the front of the third linear slide rail 303 is slidably connected to the connecting seat 304, and the glue pouring device 305 is installed on the front of the connecting seat 304.

[0036] The material storage assembly 4 includes a support platform 401, a material storage tank 402, a conveying pipe 403 and a control box 404. The support platform 401 is arranged on the left side of the workbench 1. The material storage tank 402 is arranged on the top of the support platform 401. The material storage tank 402 is connected to the material storage barrel 205 through the conveying pipe 403. The control box 404 is fixedly connected to the top of the support platform 401 and located in front of the material storage tank 402. A regulating valve is arranged on the top of the material storage tank 402, and the conveying pipe 403 is a bellows.

[0037] Specifically, by installing the support seat 301 on the front side of the storage barrel 205, a screw is provided inside the support seat 301 and at a position corresponding to the screw motor 302 and the connecting seat 304. When in use, the screw is driven to rotate by the screw motor 302, and then the connecting seat 304 is driven to rise and fall on the support seat 301 through the rotation of the screw. The third linear slide rail 303 reduces the friction between the connecting seat 304 and the support seat 301, and then the glue pouring device 305 is driven to rise and fall through the connecting seat 304, so that the glue pouring device 305 is moved above the workpiece to be processed, and the workpiece is processed by the glue pouring device 305. At the same time, the control box 404 conveys the glue in the storage tank 402 to the storage barrel 205 through the conveying pipe 403, and the workpiece is processed by the glue pouring device 305. At this time, the support platform 401 supports the storage tank 402.

[0038] The working process of the utility model is as follows: when using the glue pouring device, firstly, the support frame 101 is placed at the specified position, and then the workbench 1 is placed on the support frame 101. When in use, the glue pouring component 3 is driven to move by the moving component 2. At this time, the glue pouring component 3 is loaded through the material storage component 4. After the glue pouring component 3 is moved above the workpiece to be processed, the workpiece on the workbench 1 is then glued through the glue pouring component 3, which improves the flexibility of the glue pouring device and makes it less likely to make mistakes in glue pouring; improves the accuracy of glue pouring by the glue pouring component 3, and at the same time, the supply of the glue pouring component 3 can be guaranteed by the material storage component 4. Compared with the existing glue pouring device, the utility model improves the overall practicality of the glue pouring device through design.

[0039] The above embodiments are preferred implementation schemes of the present invention. In addition, the present invention can also be implemented in other ways. Any obvious replacement without departing from the concept of the present technical solution is within the protection scope of the present invention.

Claims

1. A silicone glue automatic glue pouring device, comprising a workbench (1), characterized in that: A moving component (2) is provided on the top of the workbench (1), a glue pouring component (3) is provided inside the moving component (2), and a material storage component (4) is provided on the left side of the workbench (1); The moving component (2) is used to drive the glue pouring component (3) to move in multiple directions; The glue pouring component (3) is used to pour glue on the workpiece on the workbench (1); The material storage component (4) is used for storing and transporting rubber material.

2. The automatic silicone glue pouring device according to claim 1, characterized in that: The moving assembly (2) comprises two groups of moving frames (201), a first linear slide rail (202), a sliding frame (203), a second linear slide rail (204), a material storage barrel (205), a mounting frame (206), a first drag chain (207) and a second drag chain (208), and the two groups of moving frames (201) are fixedly connected to the left and right sides of the top of the workbench (1).

3. The automatic silicone glue pouring device according to claim 2, characterized in that: The tops of the two groups of movable frames (201) are fixedly connected to first linear slide rails (202), a sliding frame (203) is provided between the two groups of the first linear slide rails (202), the tops of the sliding frames (203) are fixedly connected to two groups of second linear slide rails (204), and the tops of the two groups of the second linear slide rails (204) are provided with storage barrels (205).

4. The automatic silicone glue pouring device according to claim 3, characterized in that: A mounting frame (206) is fixedly connected to the top of one group of the mobile frames (201) and located above the sliding frame (203); a first drag chain (207) is provided on the top of the mounting frame (206); and a second drag chain (208) is provided on the top of the sliding frame (203) and located behind the second linear slide rail (204).

5. The automatic silicone glue pouring device according to claim 3, characterized in that: The glue pouring assembly (3) comprises a support seat (301), a screw motor (302), a third linear slide rail (303), a connecting seat (304) and a glue pouring device (305); the support seat (301) is fixedly connected to the front of the material storage barrel (205); the screw motor (302) is fixedly mounted on the bottom of the support seat (301); the third linear slide rail (303) is fixedly connected to the top of the support seat (301); the front of the third linear slide rail (303) is slidably connected to the connecting seat (304); and the glue pouring device (305) is mounted on the front of the connecting seat (304).

6. The automatic silicone glue pouring device according to claim 3, characterized in that: The material storage assembly (4) comprises a support platform (401), a material storage tank (402), a delivery pipeline (403) and a control box (404); the support platform (401) is arranged on the left side of the workbench (1); a material storage tank (402) is arranged on the top of the support platform (401); and the material storage tank (402) is connected to a material storage barrel (205) via a delivery pipeline (403).

7. The automatic silicone glue pouring device according to claim 6, characterized in that: A control box (404) is fixedly connected to the top of the support platform (401) and located in front of the storage tank (402); a regulating valve is provided on the top of the storage tank (402); a support frame (101) is provided at the bottom of the workbench (1); and the delivery pipeline (403) is a corrugated pipe.