Highway roadbed structure capable of preventing roadbed softening

By using components such as connecting pipes, rectangular rings, drainage pipes and water absorption stones in the highway subgrade structure, combined with the setting of bases and support columns, the problem of softening of the highway subgrade in the rainy air humidity environment is solved, and the road surface stability is achieved Improvement of sexual and safety.

CN222477132UActive Publication Date: 2025-02-14陕西省交通规划设计研究院有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420726446.1
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-09
Publication Date
2025-02-14
Estimated Expiration
2034-04-09

AI Technical Summary

Technical Problem

The existing highway subgrade structure is prone to softening in a rainy environment with high humidity, resulting in unstable road surfaces and even some road surfaces collapse, affecting the safety and stability of the expressway.

Method used

The roadbed structure is adopted, including connecting pipes, rectangular rings, drain pipes and water-absorbing stones. The road moisture is collected through the connecting pipes, the drain pipe discharges rainwater, and the water-absorbing stones absorb internal moisture and prevent the structure from being soft. At the same time, the arrangement of the base, the first support column, the storage plate, the insertion rod and the second support column enhances the stability of the roadbed.

Benefits of technology

It effectively prevents softening of the roadbed, improves the stability of the road surface, prevents deformation and collapse of the road surface, and enhances the safety and service life of the expressway.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222477132U_ABST
    Figure CN222477132U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of expressways, in particular to an expressway roadbed structure capable of preventing roadbed softening, which comprises a roadbed layer, the top end of the roadbed layer is fixedly connected with a connecting pipe, the top end of the connecting pipe is fixedly connected with a rectangular ring, the bottom end of the connecting pipe is fixedly connected with a drainage pipe, and the outer surface of the connecting pipe is provided with a plurality of slotted holes. Through the arrangement of the connecting pipe, the rectangular ring, the drainage pipe and the water absorption stone, during use, the rectangular ring is fixed to the top end of the connecting pipe, and the interior of the rectangular ring is arranged in a big-end-up mode, so that water on the road surface can be collected and drained conveniently; the drainage pipe is used for draining rainwater collected by the connecting pipe and can guide a route to be drained outwards, finally, through installation of the water absorption stone, the water absorption stone can absorb internal water vapor, internal moisture is prevented from forming a water source and causing the internal structure to be soft, the pavement can be prevented from being soft and deformed after the water is drained, and therefore the effect of preventing the roadbed from being softened is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of expressways, in particular to an expressway roadbed structure that prevents roadbed softening. Background Art

[0002] Expressways, or highways for short, are roads designed for high-speed driving of cars. Expressways have different regulations in different countries, regions, eras, and scientific research fields. According to China's Highway Engineering Technical Standards (JTG B01-2014), expressways are multi-lane roads designed for cars to drive in different directions and lanes, with full access control. The existing expressways use roadbeds for bottom support, and different materials are used for structural connections in different regions.

[0003] However, the existing technology lacks the function of preventing the road surface from softening. In actual use, in a rainy and humid environment, the road surface will be unstable, soften, and partially collapse, which will cause great harm when the speed of the car on the highway is high.

[0004] In addition, the existing technology lacks the function of support and fixation. In actual use, highways need to have good toughness and strength due to their long sections and large number of vehicles. The unstable installation structure of the roadbed material will cause the road surface to deform and the material to become loose. Utility Model Content

[0005] The utility model aims to provide a highway roadbed structure for preventing roadbed softening, so as to solve the problems raised in the above-mentioned background technology.

[0006] In order to achieve the above purpose, the utility model provides the following technical solutions:

[0007] A highway roadbed structure for preventing roadbed softening, comprising:

[0008] A roadbed layer, the top of the roadbed layer is fixedly connected with a connecting pipe, the top of the connecting pipe is fixedly connected with a rectangular ring, the bottom of the connecting pipe is fixedly connected with a drainage pipe, the outer surface of the connecting pipe is provided with a plurality of slots, the inner walls of the slots are fixedly connected with absorbent stones, the top of the roadbed layer is fixedly connected with a base on both sides, the top of the base is fixedly connected with a plurality of first support columns, the top of the first support column is fixedly connected with a storage plate, the top of the base is provided with a circular slot, the inner wall of the circular slot is clamped with a plug rod, and the bottom of the storage plate is fixedly connected with a plurality of second support columns.

[0009] Preferably, a connecting groove is provided on the top of the road base layer, and a water-blocking layer is fixedly connected to the inner wall of the connecting groove.

[0010] Preferably, a slot is provided at the top of the water-blocking layer, and a barrier layer is fixedly connected to the inner wall of the slot.

[0011] Preferably, a rectangular slot is opened at the top of the barrier layer, and the inner wall of the rectangular slot is fixedly connected to the asphalt pavement.

[0012] Preferably, a square slot is opened at the top of the asphalt pavement, and a coating is fixedly connected to the inner wall of the square slot.

[0013] Preferably, rectangular holes are opened on both sides of the top of the asphalt pavement, and the inner walls of the rectangular holes are fixedly connected to the outer surface of the rectangular ring.

[0014] Compared with the prior art, the beneficial effects of the utility model are:

[0015] 1. A highway subgrade structure for preventing subgrade softening is provided with a connecting pipe, a rectangular ring, a drainage pipe and a water-absorbing stone. When in use, the rectangular ring is fixed at the top of the connecting pipe, and the interior of the rectangular ring is arranged to be larger at the top and smaller at the bottom, so that moisture on the road surface can be collected and discharged. Then, the drainage pipe is installed, and the drainage pipe is used to discharge rainwater collected by the connecting pipe and guide the route to be discharged outward. Finally, the water-absorbing stone is installed, and the water-absorbing stone can absorb the water vapor inside to prevent the internal moisture from forming a water source and causing the internal structure to become loose. After the water is discharged, the road surface can be prevented from becoming loose and deformed, thereby achieving the effect of preventing subgrade softening.

[0016] 2. This highway roadbed structure for preventing roadbed softening is provided with a base, a first support column, a storage plate, an insertion rod and a second support column. When in use, the first support column is fixed to the top of the base through the installation of the base, and the first support column is used to fix the storage plate at the top, and then the insertion rod is inserted into the base to fix the entire device to stabilize the structure. By installing more second support columns, the entire structure is supported, the overall stability is enhanced, and the road deformation caused by the loose road structure is prevented, thereby achieving the effect of enhanced fixation. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 It is an overall schematic diagram of the utility model;

[0018] Figure 2 It is a schematic diagram showing the road base, connecting pipe, rectangular ring, drainage pipe and water-absorbing stone of the utility model;

[0019] Figure 3 It is a schematic diagram showing the base, the first support column, the storage plate, the insertion rod and the second support column of the utility model;

[0020] Figure 4 This is a schematic diagram of the separation of the barrier layer and the asphalt pavement of the utility model;

[0021] Figure 5 It is a schematic internal cross-sectional view of the utility model.

[0022] In the figure: 1. road base; 2. connecting pipe; 3. rectangular circle; 4. drainage pipe; 5. water-absorbing stone; 6. base; 7. first support column; 8. storage plate; 9. insertion rod; 10. second support column; 11. water-blocking layer; 12. barrier layer; 13. asphalt pavement; 14. coating. DETAILED DESCRIPTION

[0023] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0024] See also Figure 1-Figure 5 As shown, a technical solution provided by the utility model:

[0025] A highway roadbed structure for preventing roadbed softening, comprising:

[0026] A roadbed 1 is provided, the top of the roadbed 1 is fixedly connected with a connecting pipe 2, the top of the connecting pipe 2 is fixedly connected with a rectangular ring 3, the bottom of the connecting pipe 2 is fixedly connected with a drainage pipe 4, a plurality of slots are provided on the outer surface of the connecting pipe 2, and a water-absorbing stone 5 is fixedly connected to the inner wall of the slot. A base 6 is fixedly connected to both sides of the top of the roadbed 1, a plurality of first supporting columns 7 are fixedly connected to the top of the base 6, a storage plate 8 is fixedly connected to the top of the first supporting column 7, a circular slot is provided on the top of the base 6, a plug rod 9 is clamped on the inner wall of the circular slot, and a plurality of second supporting columns 10 are fixedly connected to the bottom of the storage plate 8. Through the arrangement of the connecting pipe 2, the rectangular ring 3, the drainage pipe 4 and the water-absorbing stone 5, when in use, through the rectangular ring 3 fixed on the top of the connecting pipe 2, the interior of the rectangular ring 3 is arranged to be large at the top and small at the bottom, which can be convenient for collecting moisture from the road surface for discharge, and then through the installation of the drainage pipe 4, the drainage The water pipe 4 is used to discharge the rainwater collected by the connecting pipe 2 and can be guided to be discharged outward. Finally, by installing the absorbent stone 5, the absorbent stone 5 can absorb the water vapor inside to prevent the internal moisture from forming a water source, causing the internal structure to become loose. After the water is discharged, the road surface can be prevented from becoming loose and deformed, thereby achieving the effect of preventing the roadbed from softening. Through the arrangement of the base 6, the first support column 7, the storage plate 8, the insertion rod 9 and the second support column 10, when in use, through the installation of the base 6, the first support column 7 is fixed to the top of the base 6. The first support column 7 is used to fix the storage plate 8 at the top, and then the insertion rod 9 is inserted into the base 6 to fix the overall device to stabilize the structure. By installing more second support columns 10, the overall structure is supported, the overall stability is enhanced, and the road surface structure is prevented from being loosened and causing deformation of the road surface, thereby achieving the effect of enhanced fixation.

[0027] In this embodiment, preferably, a connection groove is provided at the top of the roadbed layer 1, and a water-blocking layer 11 is fixedly connected to the inner wall of the connection groove. By setting the water-blocking layer 11, when in use, the water-blocking layer 11 is installed to prevent the water source left at the top from penetrating into the surface of the roadbed layer 1, and prevent the roadbed layer 1 from softening, thereby achieving the effect of water blocking and waterproofing;

[0028] In this embodiment, preferably, a card slot is provided at the top of the water-blocking layer 11, and a barrier layer 12 is fixedly connected to the inner wall of the card slot. By setting the barrier layer 12, when in use, the barrier layer 12 is installed, and the barrier layer 12 is used to block the upper and lower surface layers, so that the internal and external temperatures are different, and external weather or air factors are prevented from affecting the bottom structure, thereby achieving the effect of blocking temperature;

[0029] In this embodiment, preferably, a rectangular slot is provided at the top of the barrier layer 12, and an asphalt pavement 13 is fixedly connected to the inner wall of the rectangular slot. By setting the asphalt pavement 13, when in use, the asphalt pavement 13 can resist drying, and the rough surface increases friction, so that the tires of the car can run normally on the surface without slipping, thereby achieving the effect of increasing friction and facilitating the driving of the car;

[0030] In this embodiment, preferably, a square slot is provided at the top of the asphalt pavement 13, and a coating 14 is fixedly connected to the inner wall of the square slot. By setting the coating 14, when in use, the coating 14 is installed, and the coating 14 is used to guide the vehicle to travel, and guides it following the curvature of the pavement, thereby achieving the function of guiding the vehicle to travel forward;

[0031] In this embodiment, preferably, rectangular holes are opened on both sides of the top of the asphalt pavement 13 , and the inner walls of the rectangular holes are fixedly connected to the outer surface of the rectangular ring 3 .

[0032] When the highway subgrade structure of the present embodiment is used to prevent the softening of the subgrade, the water-blocking layer 11 is installed. The water-blocking layer 11 is used to prevent the water source left on the top from penetrating into the surface of the subgrade 1 and preventing the subgrade 1 from softening, thereby achieving the effect of water-blocking and waterproofing. The barrier layer 12 is installed. The barrier layer 12 is used to block the upper and lower surface layers to make the internal and external temperatures different, thereby preventing external weather or air factors from affecting the bottom structure, thereby achieving the effect of blocking temperature. The asphalt pavement 13 is installed. The asphalt pavement 13 is resistant to drying, and the rough surface increases the friction, so that the tires of the car can run normally on the surface without slipping, thereby achieving the effect of increasing friction and facilitating the driving of the car. The coating 14 is installed. The coating 14 is used to guide the driving of the vehicle and guides it by following the bending changes of the road surface, thereby achieving the effect of guiding the forward direction of the vehicle. The top of the connecting pipe 2 is fixed The rectangular circle 3 has a larger upper part and a smaller lower part inside, which can collect moisture from the road surface for discharge. Then, through the installation of the drain pipe 4, the drain pipe 4 is used to discharge the rainwater collected by the connecting pipe 2 and can guide the route to be discharged outward. Finally, through the installation of the absorbent stone 5, the absorbent stone 5 can absorb the internal water vapor to prevent the internal moisture from forming a water source, causing the internal structure to become loose. After the moisture is discharged, the road surface can be prevented from becoming soft and deformed, thereby achieving the effect of preventing the roadbed from softening. Through the installation of the base 6, the first support column 7 is fixed to the top of the base 6. The first support column 7 is used to fix the storage plate 8 at the top, and then the base 6 is inserted through the insertion rod 9 to fix the overall device to stabilize the structure. By installing more second support columns 10, the overall structure is supported, the overall stability is enhanced, and the road surface structure is prevented from becoming soft and causing deformation of the road surface, thereby achieving the effect of enhancing fixation.

[0033] The above shows and describes the basic principle, main features and advantages of the utility model. Those skilled in the art should understand that the utility model is not limited by the above embodiments. The above embodiments and descriptions are only preferred examples of the utility model and are not used to limit the utility model. Without departing from the spirit and scope of the utility model, the utility model may have various changes and improvements, which fall within the scope of the utility model to be protected. The scope of protection of the utility model is defined by the attached claims and their equivalents.

Claims

1. A highway roadbed structure for preventing roadbed softening, characterized in that: include A roadbed (1), wherein a connecting pipe (2) is fixedly connected to the top of the roadbed (1), a rectangular ring (3) is fixedly connected to the top of the connecting pipe (2), a drainage pipe (4) is fixedly connected to the bottom of the connecting pipe (2), a plurality of slots are provided on the outer surface of the connecting pipe (2), a water-absorbing stone (5) is fixedly connected to the inner wall of the slot, a base (6) is fixedly connected to both sides of the top of the roadbed (1), a plurality of first support columns (7) are fixedly connected to the top of the base (6), a storage plate (8) is fixedly connected to the top of the first support column (7), a circular slot is provided on the top of the base (6), a plug rod (9) is clamped on the inner wall of the circular slot, and a plurality of second support columns (10) are fixedly connected to the bottom of the storage plate (8).

2. The highway roadbed structure for preventing roadbed softening according to claim 1, characterized in that: A connection groove is provided at the top of the road base layer (1), and a water-blocking layer (11) is fixedly connected to the inner wall of the connection groove.

3. The highway subgrade structure for preventing subgrade softening according to claim 2, characterized in that: A slot is provided at the top of the water-blocking layer (11), and a barrier layer (12) is fixedly connected to the inner wall of the slot.

4. The highway subgrade structure for preventing subgrade softening according to claim 3, characterized in that: A rectangular slot is provided at the top of the barrier layer (12), and an asphalt pavement (13) is fixedly connected to the inner wall of the rectangular slot.

5. The highway subgrade structure for preventing subgrade softening according to claim 4, characterized in that: A square slot is provided at the top of the asphalt pavement (13), and a coating (14) is fixedly connected to the inner wall of the square slot.

6. The highway subgrade structure for preventing subgrade softening according to claim 5, characterized in that: Rectangular holes are provided on both sides of the top of the asphalt pavement (13), and the inner walls of the rectangular holes are fixedly connected to the outer surface of the rectangular ring (3).