Steel pipe stack preset lifting appliance based on rotary swing type
By designing a preset spreader based on the rotary pendulum of steel pipe stacks, and using the combination of symmetrical structure and standard parts, the problem of difficult to find the center of gravity, easy to tilt and slide during the lifting process of steel pipes in the prior art, achieving a fast, safe and efficient lifting operation.
Patent Information
- Application Number
- CN202420649250.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-29
- Publication Date
- 2025-03-21
- Estimated Expiration
- 2034-03-29
AI Technical Summary
During the lifting process, existing steel pipe spreaders have problems such as difficulty in finding the center of gravity, easy tilt of the steel pipe, safety hazards of sliding down, and deviation of the suspender position, resulting in high lifting difficulty and low efficiency.
A preset steel pipe stacker based on a rotary pendulum is designed. Through the combination of symmetrical structure and screws, nuts, pads and screws, the relative setting and swing of the bracket are realized, thereby realizing the positioning preset of the sixth bracket and quickly lifting.
It improves the working efficiency of lifting, reduces the difficulty and time of operation, and ensures the safety and stability of the steel pipe.
Smart Images

Figure CN222647395U_ABST
Abstract
Description
Technical Field
[0001] This utility model belongs to the technical field of auxiliary lifting tools in hoisting equipment, specifically relating to a pre-set lifting tool for steel pipe stacks based on a swing-type mechanism. Background Technology
[0002] Currently, lifting slings are connecting devices used in lifting equipment to lift heavy objects. Steel pipe manufacturers need to lift bundles of steel pipes from stacks. Due to the large number and size of the bundles, lifting them presents a certain degree of difficulty. A common method is to use a hook and sling. First, the sling is passed through the bottom of the bundle, and then both ends of the sling are hooked onto the hook, thus lifting the steel pipes smoothly to the designated location. However, because the position of the sling is not fixed, this method has two problems: First, if the center of gravity is not accurately located, the bundle of steel pipes is prone to tilting, making it easy for them to collide with surrounding objects during transport, and posing a safety hazard of slipping. Second, if the sling's placement deviates, hooking it becomes difficult, and readjusting the sling's position is not only laborious but also extremely time-consuming, reducing lifting efficiency.
[0003] Patent document CN204125015 U discloses a steel pipe stack lifting device, which mainly includes a lifting beam, chain, lifting ring, hook, rubber-coated sling, chain adjuster, butterfly buckle, and pin. The pin inserts into the opening of the steel pipe to form a lifting point. Therefore, this device can prevent tilting during the lifting and transportation of the steel pipe stack, as well as large swings and twists. However, this device does not pre-set the placement position of the lifting device. Patent document CN 111661752 A discloses a heavy-duty automatic telescopic rotating lifting device for steel pipes, which mainly includes a main beam, hydraulic cylinder, distribution box, multi-way valve, gear plate, motor, main shaft, connector, hanger, pad, sub-beam, hook, positioning clamp, universal ball, and positioning plate. Because the centerline of the main beam is parallel to the centerline of the steel pipe, and the hooks are located at both ends of the steel pipe, the hydraulic rotating device can adjust the spacing between the hooks to accommodate steel pipes of different lengths. However, this device does not pre-set the placement position of the lifting device. Patent document CN 214611099 U discloses a steel pipe lifting attachment, which mainly includes a lifting chain, a lifting body, a top frame, outriggers, a rod, a star wheel, fins, a shaft, a ratchet, a pawl, and a stop pin. Due to the unidirectional rotation of the star wheel, the fins will prevent the steel pipe from rolling down. Moving the pawl can both unload the steel pipe individually and avoid collisions between the steel pipes. However, the device does not preset the placement position of the lifting attachment. Utility Model Content
[0004] To overcome one or more problems existing in the prior art, this utility model provides a pre-set lifting device for steel pipe stacks based on a swing-type mechanism. This utility model is designed based on a symmetrical structure. The combined use of the base plate, screw, and nut enables the relative setting of both the first and fourth supports; the combined use of the pad and screw enables the relative setting of both the first and third supports, as well as the relative setting of both the fourth and fifth supports; the combined use of the first, third, fourth, and fifth supports and the rolling bearing enables the swing of the second support, thereby achieving the pre-set positioning of the sixth support, thus enabling rapid lifting. Therefore, the working efficiency of this utility model device is relatively high.
[0005] The technical solution adopted by this utility model to solve its technical problem is as follows.
[0006] The pre-installed lifting device for steel pipe stacks based on a gyratory type provided by this utility model includes: four first supports, eight second supports, four third supports, two fourth supports, two fifth supports, four sixth supports, a base plate, eight pads, sixty-four screws, sixteen rolling bearings, thirty-two threaded rods, and thirty-two nuts;
[0007] The first bracket is composed of a first body, a first boss, a second boss, and a third boss connected together. The first body, the first boss, the second boss, and the third boss are all symmetrical cuboid structures. The first boss is located on the upper end face of the first body, the second boss is located on the upper end face of the first boss, and the third boss is located on the right end face of the second boss. The first body has four cylindrical first through holes symmetrically opened, and the screw passes through the first through holes. The second boss has four cylindrical second through holes symmetrically opened, and the screw passes through the second through holes. The upper end face of the third boss has a cylindrical first groove, and the rolling bearing passes through the first groove. A cylindrical third through hole is opened at the axial position of the first groove, and the bearing section of the second bracket passes through the third through hole.
[0008] The second bracket is composed of a second body, two fourth protrusions, and two bearing segments connected together. The second body and the fourth protrusions are both symmetrical cuboid structures. The two fourth protrusions are located on the right end face of the second body, and the two bearing segments are located on the upper and lower end faces of the second body, respectively. The bearing segments are symmetrical cylindrical structures used to carry the rolling bearings. A cuboid through groove can be formed between the two fourth protrusions, and the sixth body of the sixth bracket is carried through the through groove.
[0009] The third bracket is composed of a third body and a fifth boss connected together. Both the third body and the fifth boss are symmetrical rectangular parallelepiped structures. The fifth boss is located on the right end face of the third body. The third body has four cylindrical sixth through holes symmetrically opened, and the screws are inserted into the sixth through holes. The lower end face of the fifth boss has a cylindrical second groove, and the rolling bearing is inserted into the second groove. A cylindrical seventh through hole is opened at the axial position of the second groove, and the bearing section of the second bracket is inserted into the seventh through hole.
[0010] The fourth bracket is composed of a fourth body, two sixth protrusions, a seventh protrusion, and two eighth protrusions connected together. The fourth body, the sixth protrusions, the seventh protrusion, and the eighth protrusion are all symmetrical cuboid structures. The two sixth protrusions are simultaneously located on the upper end face of the fourth body, the seventh protrusion is located on the upper end face of the two sixth protrusions, and the two eighth protrusions are simultaneously located on the right end face of the seventh protrusion. The fourth body symmetrically has two sets, totaling eight cylindrical through holes, with the screw passing through each through hole. The seventh protrusion symmetrically has two sets, totaling eight cylindrical through holes, with the screw passing through each through hole. The upper end face of the eighth protrusion has a cylindrical third groove, with the rolling bearing passing through each groove. A cylindrical tenth through hole is located at the axial position of the third groove, with the bearing section of the second bracket passing through each tenth through hole.
[0011] The fifth bracket is composed of a fifth body and two ninth protrusions connected together. Both the fifth body and the ninth protrusions are symmetrical rectangular parallelepiped structures. The two ninth protrusions are located on the right end face of the fifth body. The fifth body has two sets of eight cylindrical eleventh through holes symmetrically opened, and the screws are inserted into the eleventh through holes. A cylindrical fourth groove is opened on the lower end face of the ninth protrusion, and the rolling bearing is inserted into the fourth groove. A cylindrical twelfth through hole is opened at the axial position of the fourth groove, and the bearing section of the second bracket is inserted into the twelfth through hole.
[0012] The sixth bracket is composed of a sixth body, a tenth protrusion, and an eleventh protrusion connected together. The sixth body, the tenth protrusion, and the eleventh protrusion are all symmetrical rectangular parallelepiped structures. The tenth protrusion is located on the upper end face of the sixth body, and the eleventh protrusion is located on the lower end face of the sixth body. The tenth protrusion has a thirteenth through hole in the shape of a rectangular parallelepiped, which is used to thread a hook. The eleventh protrusion has a fourteenth through hole in the shape of a rectangular parallelepiped, which is used to thread a sling.
[0013] In some embodiments, the base plate has a symmetrical rectangular parallelepiped structure, and the base plate has four sets of sixteen cylindrical fourth through holes symmetrically opened, with the screw passing through the fourth through holes; the base plate also has four sets of sixteen cylindrical fifth through holes symmetrically opened, with the screw passing through the fifth through holes.
[0014] In some embodiments, the pad is a symmetrical rectangular parallelepiped structure, and the pad has four symmetrically opened screw holes, in which the screws are screwed.
[0015] In some embodiments, the nut is screwed onto the threaded end of the screw.
[0016] In some embodiments, the screw, the rolling bearing, the threaded rod, and the nut are all standard parts.
[0017] The beneficial effects of this utility model are as follows:
[0018] 1) The pre-installed lifting device for steel pipe stacks based on the swing type provided by this utility model includes four first supports, eight second supports, four third supports, two fourth supports, two fifth supports, four sixth supports, a base plate, eight pads, sixty-four screws, sixteen rolling bearings, thirty-two screws and thirty-two nuts. Since the materials are common and easy to process and form, the manufacturing cost of this utility model device is relatively low.
[0019] 2) When using this utility model, initially all eight second supports are positioned on the left and right. The sixth bodies of the four sixth supports are inserted into the through slots of the eight second supports. Two lifting straps are passed through the bottom of the bundled steel pipes, and the two ends of the two lifting straps are respectively inserted into the fourteenth through holes of the four sixth supports. Four hooks are respectively inserted into the thirteenth through holes of the four sixth supports. The eight second supports are rotated in the opposite direction so that the sixth bodies of the four sixth supports can be pulled out from the through slots of the eight second supports, and the four sixth supports can be lifted without obstruction. Therefore, the operation of this utility model device is relatively simple.
[0020] 3) This utility model is designed based on a symmetrical structure. The combined use of the base plate, screw, and nut can achieve the relative setting of the first support and the fourth support; the combined use of the pad and screw can achieve the relative setting of the first and third supports, as well as the relative setting of the fourth and fifth supports; the combined use of the first, third, fourth, and fifth supports and the rolling bearing can realize the swing of the second support, thereby realizing the positioning preset of the sixth support, thus achieving the purpose of rapid lifting. Therefore, the working efficiency of this utility model device is relatively high.
[0021] The pre-set lifting device for steel pipe stacks based on the swing-type structure provided by this utility model can pre-set the positions of the four sixth supports in order to achieve the purpose of rapid lifting. This utility model device has the characteristics of low manufacturing cost, simple operation and high work efficiency. Attached Figure Description
[0022] Figure 1 This is a front view schematic diagram of the pre-installed lifting device for steel pipe stacks based on the swing type of the present invention when the second support is set in front and behind;
[0023] Figure 2 This is a left-side structural schematic diagram of the pre-installed lifting device for steel pipe stacks based on a gyratory type according to this utility model when the second support is positioned in the front and rear positions.
[0024] Figure 3 This is a top view of the pre-installed lifting device for steel pipe stacks based on a gyratory type, when the second support is positioned in the front and rear positions.
[0025] Figure 4 This is a front view structural diagram of the pre-installed lifting device for steel pipe stacks based on a gyratory type according to this utility model when the second support is positioned on the left and right sides.
[0026] Figure 5 This is a left-side view of the pre-installed lifting device for steel pipe stacks based on a gyratory type, when the second support is positioned on the left and right sides.
[0027] Figure 6 This is a top view of the pre-installed lifting device for steel pipe stacks based on a gyratory type, when the second support is positioned to the left and right.
[0028] Figure 7 This is a schematic diagram of the front view of the first support structure of this utility model;
[0029] Figure 8 This is a cross-sectional view of the first support of this utility model along the MM plane.
[0030] Figure 9 This is a top view of the first support structure of this utility model;
[0031] Figure 10 This is a top view of the base plate of this utility model.
[0032] Figure 11 This is a top view of the pad block of this utility model;
[0033] Figure 12 This is a schematic diagram of the front view of the second support structure of this utility model;
[0034] Figure 13 This is a top view of the second support structure of this utility model;
[0035] Figure 14 This is a schematic diagram of the main structure of the third support of this utility model;
[0036] Figure 15 This is a bottom view of the third support structure of this utility model;
[0037] Figure 16 This is a schematic diagram of the main structure of the fourth bracket of this utility model;
[0038] Figure 17 This is a cross-sectional view of the fourth support of this utility model along the NN plane.
[0039] Figure 18 This is a top view of the fourth support structure of this utility model;
[0040] Figure 19 This is a schematic diagram of the front view of the fifth bracket of this utility model;
[0041] Figure 20 This is a bottom view of the fifth support structure of this utility model;
[0042] Figure 21 This is a schematic diagram of the main structure of the sixth bracket of this utility model;
[0043] Figure 22 This is a schematic diagram of the left-side structure of the sixth bracket of this utility model;
[0044] Figure 23 This is a schematic diagram of the second support of this utility model rotating in the forward direction when the second support is changed from a front-to-back arrangement to a left-to-right arrangement;
[0045] Figure 24 This is a schematic diagram of the second support of this utility model rotating in the opposite direction when the second support is changed from a left-right arrangement to a front-back arrangement.
[0046] Explanation of reference numerals in the attached drawings: 1-First bracket; 101-First body; 102-First boss; 103-Second boss; 104-Third boss; 105-First through hole; 106-Second through hole; 107-First groove; 108-Third through hole; 2-Base plate; 201-Fourth through hole; 202-Fifth through hole; 3-Padded block; 301-Screw hole; 4-Second bracket; 401-Second body; 402-Fourth boss; 403-Bearing section; 404-Through groove; 5-Third bracket; 501-Third body; 502-Fifth boss; 503-Sixth through hole; 504-Second groove; 505-Seventh through hole; 6-Fourth bracket; 601-Fourth body; 602-Sixth boss; 603-Seventh boss; 604-Eighth boss; 605-Eighth through hole; 606-Ninth through hole; 607-Third groove; 608-Tenth through hole; 7-Fifth bracket; 701-Fifth body; 702-Ninth boss; 703-Eleventh through hole; 704-Fourth groove; 705-Twelfth through hole; 8-Sixth bracket; 801-Sixth body; 802-Tenth boss; 803-Eleventh boss; 804-Thirteenth through hole; 805-Fourteenth through hole; 9-Screw; 10-Rolling bearing; 11-Threaded rod; 12-Nut. Detailed Implementation
[0047] The present invention will be described in detail below with reference to the embodiments and accompanying drawings. The embodiments are only for understanding the present invention and are not intended to limit the content of the present invention.
[0048] Combination Figures 1 to 6As shown, this utility model provides a pre-installed lifting device for steel pipe stacks based on a gyratory type, which includes four first supports 1, eight second supports 4, four third supports 5, two fourth supports 6, two fifth supports 7, four sixth supports 8, a base plate 2, eight pads 3, sixty-four screws 9, sixteen rolling bearings 10, thirty-two screws 11, and thirty-two nuts 12; wherein, the four first supports 1 are arranged in pairs opposite each other on the base plate 2 and connected by the sixteen screws 11 and the sixteen nuts 12; four rolling bearings 10 are inserted into the four first grooves 107 of the four first supports 1, and four bearing sections 403 of the four second supports 4 are inserted into the four rolling bearings 10; the other four bearing sections 403 of the four second supports 4 are inserted into the four rolling bearings 10, and the four rolling bearings 10 are inserted into the four second grooves 504 of the four third supports 5; the four second protrusions 103 of the four first supports 1 and the four second protrusions 107 of the four second supports 4 ... second Four pads 3 are inserted between the four third bodies 501 of the three supports 5 and connected by thirty-two screws 9; two fourth supports 6 are arranged opposite each other on the base plate 2 and connected by sixteen screws 11 and sixteen nuts 12; four rolling bearings 10 are inserted into the four third grooves 607 of the two fourth supports 6, and four bearing segments 403 of the four second supports 4 are inserted into the four rolling bearings 10; the other four bearing segments 403 of the four second supports 4 are inserted into the four rolling bearings 10, and the four rolling bearings 10 are inserted into the four fourth grooves 704 of the two fifth supports 7; four pads 3 are inserted between the two seventh bosses 603 of the two fourth supports 6 and the two fifth bodies 701 of the two fifth supports 7 and connected by thirty-two screws 9; four sixth bodies 801 of the four sixth supports 8 are inserted into the eight through slots 404 of the eight second supports 4.
[0049] The assembly process of the pre-set lifting device for steel pipe stacks based on a gyratory type provided by this utility model
[0050] Combination Figures 1 to 22 As shown, firstly, four rolling bearings 10 are installed in the four first grooves 107 of the four first brackets 1. Then, the four first brackets 1 are arranged opposite each other in pairs. Then, the four bearing segments 403 of the four second brackets 4 are inserted into the four rolling bearings 10. In this way, the four first brackets 1, the four rolling bearings 10 and the four second brackets 4 can be assembled.
[0051] Then, the base plate 2 is placed on the mounting platform, and the four first brackets 1 are simultaneously placed on the base plate 2. The sixteen first through holes 105 of the four first brackets 1 and the sixteen fifth through holes 202 of the base plate 2 are aligned. Then, sixteen screws 11 are inserted into the sixteen sets of aligned through holes, and sixteen nuts 12 are screwed onto the threaded ends of the sixteen screws 11. In this way, the four first brackets 1 and the base plate 2 can be assembled.
[0052] Then, four rolling bearings 10 are installed in the four second grooves 504 of the four third brackets 5, and then the four third brackets 5 are arranged opposite each other in pairs. Then, the other four bearing segments 403 of the four second brackets 4 are inserted into the four rolling bearings 10. In this way, the four third brackets 5, the four rolling bearings 10 and the four second brackets 4 can be assembled.
[0053] Then, the four pads 3 are inserted between the four second protrusions 103 of the four first brackets 1 and the four third bodies 501 of the four third brackets 5, and the sixteen screw holes 301 of the four pads 3 are aligned with the sixteen second through holes 106 of the four first brackets 1 and the sixteen sixth through holes 503 of the four third brackets 5. Then, the thirty-two screws 9 are passed through the sixteen second through holes 106 and the sixteen sixth through holes 503 and screwed into the sixteen screw holes 301. In this way, the four first brackets 1, the four pads 3 and the four third brackets 5 can be assembled.
[0054] Then, four rolling bearings 10 are installed in the four third grooves 607 of the two fourth brackets 6, and the two fourth brackets 6 are arranged opposite each other. Then, the four bearing segments 403 of the other four second brackets 4 are inserted into the four rolling bearings 10. In this way, the two fourth brackets 6, the four rolling bearings 10 and the other four second brackets 4 can be assembled.
[0055] Then, the two fourth brackets 6 are simultaneously placed on the base plate 2, and the sixteen eighth through holes 605 of the two fourth brackets 6 are aligned with the sixteen fourth through holes 201 of the base plate 2. Then, sixteen screws 11 are inserted into the sixteen sets of aligned through holes, and sixteen nuts 12 are screwed onto the threaded ends of the sixteen screws 11. In this way, the two fourth brackets 6 and the base plate 2 can be assembled.
[0056] Then, four rolling bearings 10 are installed in the four fourth grooves 704 of the two fifth brackets 7, and the two fifth brackets 7 are arranged opposite each other. Then, the other four bearing segments 403 of the other four second brackets 4 are inserted into the four rolling bearings 10. In this way, the two fifth brackets 7, the four rolling bearings 10 and the other four second brackets 4 can be assembled.
[0057] Then, the other four pads 3 are inserted between the two seventh protrusions 603 of the two fourth brackets 6 and the two fifth bodies 701 of the two fifth brackets 7, and the sixteen screw holes 301 of the four pads 3, the sixteen ninth through holes 606 of the two fourth brackets 6, and the sixteen eleventh through holes 703 of the two fifth brackets 7 are aligned. Then, the thirty-two screws 9 are passed through the sixteen ninth through holes 606 and the sixteen eleventh through holes 703 and screwed into the sixteen screw holes 301. In this way, the two fourth brackets 6, the other four pads 3, and the two fifth brackets 7 can be assembled.
[0058] Then, by rotating the sixteen bearing segments 403 of the eight second supports 4, the eight second supports 4 are positioned to the left and right. Finally, the four sixth bodies 801 of the four sixth supports 8 are inserted into the eight through slots 404 of the eight second supports 4. In this way, the entire device is assembled and can be put into use.
[0059] The principle for setting the swing direction of the second support of the pre-set lifting device for a swing-type steel pipe stack provided by this utility model.
[0060] like Figure 3 and Figure 6 As shown in the top view of the device of this utility model, for ease of description, the eight second supports 4 can be defined as ①, ②, ③, ④, ⑤, ⑥, ⑦ and ⑧, wherein the sixteen bearing segments 403 of the eight second supports 4 are all swing shafts;
[0061] like Figure 3 As shown, assuming that initially all eight second supports 4 are positioned front and back, the simplified version is as follows: Figure 23 As shown, ①, ④, ⑤ and ⑧ simultaneously rotate 90 degrees clockwise, and ②, ③, ⑥ and ⑦ simultaneously rotate 90 degrees counterclockwise. Thus, all eight second supports 4 are positioned to the left and right. We can define this rotation direction of the second supports 4 as positive.
[0062] like Figure 6 As shown, assuming that initially all eight second supports 4 are positioned on the left and right, after simplification as follows: Figure 24As shown, ①, ④, ⑤ and ⑧ simultaneously rotate 90 degrees counterclockwise, and ②, ③, ⑥ and ⑦ simultaneously rotate 90 degrees clockwise. Thus, all eight second supports 4 are arranged in a front-to-back configuration. We can define this rotation direction of the second supports 4 as reverse.
[0063] The present invention provides a method for using a pre-set lifting device for steel pipe stacks based on a gyratory type.
[0064] Combination Figures 1 to 22 As shown, assuming that initially all eight second supports 4 are positioned left and right, and the four sixth bodies 801 of the four sixth supports 8 are inserted into the eight through slots 404 of the eight second supports 4, firstly, two lifting straps are passed through the bottom of the bundled steel pipes located within the steel pipe stack, and then the two ends of the two lifting straps are respectively inserted into the fourteenth through holes 805 of the four sixth supports 8. At this time, the four sixth supports 8 can be directly aligned with the four hooks of the crane. Then, the four hooks are respectively inserted into the four thirteenth through holes 804 of the four sixth supports 8. Then, the eight second supports 4 are rotated in the opposite direction so that all eight second supports 4 are positioned front and back. At this time, the four sixth bodies 801 of the four sixth supports 8 can be pulled out from the eight through slots 404 of the eight second supports 4. In this way, the crane can lift the four sixth supports 8 without obstruction.
[0065] Additional explanation: The pre-installed lifting device for steel pipe stacks based on the gyratory type provided by this utility model adopts a symmetrical structure design. First, according to the interval between the four hooks of the crane, the setting width and setting height of the steel pipe stack, multiple specifications of this utility model device should be designed and manufactured to match it.
[0066] As can be seen from the embodiments, the pre-set lifting device for steel pipe stacks based on the swing type provided by this utility model can pre-set the positions of the four sixth supports in order to achieve the purpose of rapid lifting. This utility model device has the characteristics of low manufacturing cost, simple operation and high work efficiency.
[0067] Finally, it should be noted that the above description is only a preferred embodiment of the present utility model and is not intended to limit the present utility model. Although the present utility model has been described in detail with reference to the foregoing embodiments, those skilled in the art can still modify the technical solutions described in the foregoing embodiments or make equivalent substitutions for some of the technical features.
Claims
1. A pre-set hanger for steel pipe stack based on a rotary swing type, characterized in that: The swing-type steel pipe stack preset hanger comprises: four first brackets (1), eight second brackets (4), four third brackets (5), two fourth brackets (6), two fifth brackets (7), four sixth brackets (8), a bottom plate (2), eight cushion blocks (3), sixty-four screws (9), sixteen rolling bearings (10), thirty-two screw rods (11) and thirty-two nuts (12), wherein: The first bracket (1) is composed of a first body (101), a first boss (102), a second boss (103) and a third boss (104) connected together; the first body (101), the first boss (102), the second boss (103) and the third boss (104) are all rectangular parallelepiped symmetrical structures; the first boss (102) is located on the upper end surface of the first body (101), the second boss (103) is located on the upper end surface of the first boss (102), and the third boss (104) is located on the right end surface of the second boss (103); the first body (101) is symmetrically provided with four cylindrical The first through hole (105) is symmetrically provided with four cylindrical second through holes (106), and the screw (9) is passed through the second through holes (106); the upper end surface of the third boss (104) is provided with a cylindrical first groove (107), and the rolling bearing (10) is passed through the first groove (107); the first groove (107) is provided with a cylindrical third through hole (108) at the axial position, and the bearing section (403) of the second bracket (4) is passed through the third through hole (108); The second bracket (4) is composed of a second body (401), two fourth bosses (402) and two bearing segments (403) connected together; the second body (401) and the fourth boss (402) are both rectangular parallelepiped symmetrical structures; the two fourth bosses (402) are simultaneously located on the right end surface of the second body (401); the two bearing segments (403) are respectively located on the upper and lower end surfaces of the second body (401); the bearing segments (403) are cylindrical symmetrical structures and are used to pass the rolling bearing (10); a rectangular parallelepiped through groove (404) can be formed between the two fourth bosses (402), and the sixth body (801) of the sixth bracket (8) is passed through the through groove (404); The third bracket (5) is composed of a third body (501) and a fifth boss (502) connected together, the third body (501) and the fifth boss (502) are both rectangular parallelepiped symmetrical structures, and the fifth boss (502) is located on the right end surface of the third body (501); the third body (501) is symmetrically provided with four cylindrical sixth through holes (503), and the screws (9) are penetrated through the sixth through holes (503); the lower end surface of the fifth boss (502) is provided with a cylindrical second groove (504), and the rolling bearing (10) is penetrated through the second groove (504); the axial position of the second groove (504) is provided with a cylindrical seventh through hole (505), and the bearing section (403) of the second bracket (4) is penetrated through the seventh through hole (505); The fourth bracket (6) is composed of a fourth body (601), two sixth bosses (602), a seventh boss (603) and two eighth bosses (604) connected together; the fourth body (601), the sixth boss (602), the seventh boss (603) and the eighth boss (604) are all rectangular parallelepiped symmetrical structures; the two sixth bosses (602) are simultaneously located on the upper end surface of the fourth body (601); the seventh boss (603) is located on the upper end surface of the two sixth bosses (602); and the two eighth bosses (604) are simultaneously located on the right end surface of the seventh boss (603); the fourth body (601) is symmetrically provided with two groups, A total of eight cylindrical eighth through holes (605) are provided, and the screw rod (11) is inserted into each of the eighth through holes (605); the seventh boss (603) is symmetrically provided with two groups of eight cylindrical ninth through holes (606), and the screw (9) is inserted into each of the ninth through holes (606); a cylindrical third groove (607) is provided on the upper end surface of the eighth boss (604), and the rolling bearing (10) is inserted into the third groove (607); a cylindrical tenth through hole (608) is provided at the axial position of the third groove (607), and the bearing section (403) of the second bracket (4) is inserted into the tenth through hole (608); The fifth bracket (7) is composed of a fifth body (701) and two ninth bosses (702) connected together. The fifth body (701) and the ninth boss (702) are both rectangular parallelepiped symmetrical structures. The two ninth bosses (702) are simultaneously located on the right end surface of the fifth body (701); the fifth body (701) is symmetrically provided with two groups of eight cylindrical eleventh through holes (703) in total, and the screws (9) are penetrated through the eleventh through holes (703); the lower end surface of the ninth boss (702) is provided with a cylindrical fourth groove (704), and the rolling bearing (10) is penetrated through the fourth groove (704); the axial position of the fourth groove (704) is provided with a cylindrical twelfth through hole (705), and the bearing section (403) of the second bracket (4) is penetrated through the twelfth through hole (705); The sixth bracket (8) is composed of a sixth body (801), a tenth boss (802) and an eleventh boss (803) connected together; the sixth body (801), the tenth boss (802) and the eleventh boss (803) are all rectangular parallelepiped symmetrical structures; the tenth boss (802) is located on the upper end surface of the sixth body (801), and the eleventh boss (803) is located on the lower end surface of the sixth body (801); the tenth boss (802) is provided with a thirteenth through hole (804) in the shape of a rectangular parallelepiped, and the thirteenth through hole (804) is used for passing a hook; the eleventh boss (803) is provided with a fourteenth through hole (805) in the shape of a rectangular parallelepiped, and the fourteenth through hole (805) is used for passing a sling.
2. The swing-type steel pipe stack preset hanger according to claim 1 is characterized in that: The bottom plate (2) is a rectangular parallelepiped symmetrical structure. The bottom plate (2) is symmetrically provided with four groups of sixteen cylindrical fourth through holes (201), and the screw rods (11) are inserted into the fourth through holes (201). The bottom plate (2) is also symmetrically provided with four groups of sixteen cylindrical fifth through holes (202), and the screw rods (11) are inserted into the fifth through holes (202).
3. The swing-type steel pipe stack preset hanger according to claim 1 or 2, characterized in that: The cushion block (3) is a rectangular parallelepiped symmetrical structure. The cushion block (3) is symmetrically provided with four screw holes (301), and the screws (9) are screwed into the screw holes (301).
4. The swing-type steel pipe stack preset hanger according to claim 1 or 2, characterized in that: The threaded end of the screw rod (11) is screwed with the nut (12).
5. The swing-type steel pipe stack preset hanger according to claim 1 or 2, characterized in that: The screw (9), the rolling bearing (10), the screw rod (11) and the nut (12) are all standard parts.
Citation Information
Patent Citations
Heavy-duty steel pipe automatic telescopic rotating hanger
CN111661752A
Steel pipe pile sling
CN204125015U
Steel pipe hoisting accessory
CN214611099U