Hot galvanizing hanger
By designing splicable fixed disks and convenient disassembly and assembly components, the existing hot-dip galvanized hangers cannot work multiple simultaneously and the hook deformation and disassembly are solved, and the efficient effect of multi-hangers working at the same time and quickly replacing them is achieved.
Patent Information
- Application Number
- CN202421279523.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-05
- Publication Date
- 2025-03-21
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The existing hot-dip galvanized hangers can only perform hot-dip galvanization work in a single one, and cannot be performed at the same time, which affects the use effect, and is inconvenient to disassemble when the hook is deformed, affecting the use effect.
A hot-dip galvanized hanging tool is designed, including a fixed disk and a splicing assembly. Through the splicing assembly, it can be spliced easily and conveniently to achieve the use of multiple hanging tools at the same time. At the same time, by disassembling and assembling the assembly, the hook can be easily removed and the deformed part can be replaced separately.
Multiple hanging tools are realized to perform hot-dip galvanizing at the same time, which improves work efficiency and can be quickly disassembled and replaced when the hook is deformed, avoiding the risk of hot-dip galvanizing parts falling into the pool and reducing the inconvenience of fishing.
Smart Images

Figure CN222648064U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of hot-dip galvanizing hangers, in particular to a hot-dip galvanizing hanger. Background Art
[0002] Hot-dip galvanizing is also called hot-dip galvanizing and hot-dip galvanizing: the rust-removed steel parts are immersed in molten zinc liquid at about 500°C to make a zinc layer adhere to the surface of the steel components, thereby achieving the purpose of corrosion protection. Hot-dip galvanizing is an effective metal corrosion protection method, mainly used in metal structural facilities in various industries.
[0003] Patent publication number "CN220619064U" discloses "a hot-dip galvanizing hanger, comprising a bracket and a gap adjustment structure, wherein the gap adjustment structure has a drive shaft that can be controlled to rotate by a driver and a plurality of movable ends for the hanger to be installed and cooperate with the drive shaft; when the drive shaft rotates forward, the movable ends approach each other; when the drive shaft rotates reversely, the movable ends separate from each other; the utility model can control the movable ends to make the workpieces suspended on the movable ends approach or move away from each other, so as to achieve the purpose of adjusting the gap between adjacent workpieces."
[0004] In view of the above-mentioned related problems, the existing hangers can only be hot-dip galvanized individually, and multiple hangers cannot be hot-dip galvanized simultaneously, which will affect the use effect. In addition, it is inconvenient to remove the hook when it is deformed, which will affect the use effect.
[0005] Therefore, the utility model provides a hot-dip galvanizing hanger to solve the above problems. Utility Model Content
[0006] In view of the deficiencies in the prior art, the utility model provides a hot-dip galvanizing hanger, which solves the problem that the existing hangers can only perform hot-dip galvanizing work individually, but cannot perform hot-dip galvanizing between multiple hangers at the same time, which affects the use effect.
[0007] To achieve the above purpose, the utility model is implemented through the following technical solutions: a hot-dip galvanizing hanger, comprising a fixed plate 1 and a fixed plate 2, the side walls of the fixed plate 1 and the fixed plate 2 are respectively fixedly installed with a disassembly assembly, the bottom of the fixed plate 1 and the top of the fixed plate 2 are respectively fixedly installed with a splicing assembly, and the fixed plate 2 and the fixed plate 1 are connected through the splicing assembly; the splicing assembly comprises a connecting frame 1 and a circular groove 3, the connecting frame 1 is fixedly installed at the bottom of the fixed plate 1, the circular groove 3 is opened on both sides of the connecting frame 1, the bottom of the connecting frame 1 is provided with a rectangular groove, the top of the fixed plate 2 is fixedly installed with a connecting frame 2, the connecting frame 2 and the rectangular groove are clamped, the inner side wall of the connecting frame 2 is provided with a steel ball, the steel ball and the circular groove 3 are clamped, the inner side wall of the connecting frame 2 is fixedly installed with a limit plate 2, the limit plate 2 is located on both sides of the steel ball, the top of the connecting frame 2 is connected with a threaded rod by threading, and the bottom end of the threaded rod is connected with a rectangular plate by a bearing.
[0008] Furthermore, the disassembly and assembly component includes a fixed block and a circular groove 1, the fixed block is fixedly installed on the side walls of the fixed plate 1 and the fixed plate 2, the circular groove 1 is opened at the top of the fixed block, the inner side wall of the circular groove 1 is clamped with a hook, a circular groove 2 is opened on one side of the hook, a fixed frame is fixedly installed on one side of the fixed block, a sliding rod 1 is slidably connected to one side of the fixed frame, the sliding rod 1 is clamped with the circular groove 2, a spring is sleeved on the side wall of the sliding rod 1, and a limiting plate 1 is fixedly connected to the side wall of the sliding rod 1.
[0009] By adopting the technical solution, disassembly and assembly can be carried out, and the disassembly and assembly is convenient.
[0010] Furthermore, the disassembly and assembly component also includes a pull plate, and the pull plate is fixedly connected to one end of the sliding rod.
[0011] By adopting the technical solution, the pull plate is used to conveniently pull the slide bar one.
[0012] Furthermore, one side of the fixed block and the hook is provided with a positioning assembly, the positioning assembly includes a positioning block and a positioning groove, the positioning block is fixedly connected to one side of the hook, the inner side wall of the fixed block is provided with a positioning groove, and the positioning block and the positioning groove are snap-connected.
[0013] The above technical solution can be used to perform positioning work, making installation more convenient.
[0014] Furthermore, a U-shaped frame is fixedly installed on the top of the fixed plate 1, and an arc groove is opened on one side of the U-shaped frame.
[0015] By adopting the above technical solution, the whole can be conveniently connected with the lifting equipment to facilitate hot-dip galvanizing work.
[0016] Furthermore, a second slide bar is fixedly installed on the top of the rectangular plate, and the second slide bar is slidably connected to the second connecting frame.
[0017] By adopting the above technical solution, the rectangular plate can be moved more stably.
[0018] Furthermore, the splicing assembly also includes a knob, and the knob is fixedly connected to the top end of the threaded rod.
[0019] By adopting the above technical solution, the threaded rod can be conveniently rotated by using the knob, making the rotation of the threaded rod easier.
[0020] Beneficial Effects
[0021] The utility model provides a hot-dip galvanizing hanger. Compared with the prior art, it has the following beneficial effects:
[0022] 1. The hot-dip galvanizing hanger can perform splicing work between the fixed plate 1 and the fixed plate 2 through the splicing components, and the splicing is simple and convenient. When there are many parts that need hot-dip galvanizing, they can be spliced and used in time, so that the hot-dip galvanizing work can be completed in a single time, and the work efficiency will also increase accordingly, effectively ensuring the use effect.
[0023] 2. The hot-dip galvanizing hanger can disassemble the hook through the disassembly and assembly components, and the disassembly is simple and convenient. When it is deformed, it can be replaced in time to prevent the hot-dip galvanized parts from falling into the hot-dip galvanizing pool due to deformation, and reduce the inconvenience of fishing it out, so that the use effect will be better. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] In order to more clearly illustrate the implementation scheme of the utility model or the technical scheme in the prior art, the drawings required for use in the implementation scheme or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some implementation schemes of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.
[0025] Figure 1 It is a schematic diagram of the overall structure of the utility model;
[0026] Figure 2 This utility model Figure 1 A magnified view of the structure at center A;
[0027] Figure 3 It is a side view of the overall structure of the utility model;
[0028] Figure 4 This utility model Figure 3 A magnified view of the structure at B in the middle.
[0029] In the figure: 1. Fixed plate 1; 2. Disassembly and assembly component; 21. Fixed block; 22. Circular groove 1; 23. Hook; 24. Circular groove 2; 25. Fixed frame; 26. Slide bar 1; 27. Spring; 28. Limit plate 1; 29. Pull plate; 3. Positioning component; 31. Positioning block; 32. Positioning groove; 4. Fixed plate 2; 5. Splicing component; 51. Connecting frame 1; 52. Circular groove 3; 53. Rectangular groove; 54. Connecting frame 2; 55. Steel ball; 56. Limit plate 2; 57. Threaded rod; 58. Rectangular plate; 59. Knob; 6. Slide bar 2; 7. U-shaped frame; 8. Arc groove. DETAILED DESCRIPTION
[0030] It should be noted that in the description of the embodiments of the present application, the terms "front, rear", "left, right", "up, down", etc. indicating directions or positional relationships are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as a limitation on the present application. The terms "install", "connect", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be a connection between the two elements. For those of ordinary skill in the art, the specific meanings of the above terms in the present application can be understood according to specific circumstances.
[0031] The present application is further described in detail below through drawings and examples.
[0032] Reference Figures 1 to 4The embodiment of the present application provides a hot-dip galvanizing hanger, including a fixed plate 1 and a fixed plate 2 4, the side walls of the fixed plate 1 and the fixed plate 2 4 are respectively fixedly installed with a disassembly assembly 2, the bottom of the fixed plate 1 and the top of the fixed plate 2 4 are respectively fixedly installed with a splicing assembly 5, and the fixed plate 2 4 and the fixed plate 1 are connected through the splicing assembly 5; the splicing assembly 5 includes a connecting frame 1 51 and a circular groove 3 52, the connecting frame 1 51 is fixedly installed at the bottom of the fixed plate 1, the circular groove 3 52 is opened on both sides of the connecting frame 1 51, the bottom of the connecting frame 1 51 is opened with a rectangular groove 53, the top of the fixed plate 2 4 is fixedly installed with a connecting frame 1 The second connecting frame 54 is snap-fitted with the rectangular groove 53, the inner side wall of the second connecting frame 54 is provided with a steel ball 55, the steel ball 55 is snap-fitted with the circular groove three 52, the inner side wall of the second connecting frame 54 is fixedly installed with a limit plate 56, the limit plate 56 is located on both sides of the steel ball 55, the top of the second connecting frame 54 is connected with a threaded rod 57 through a thread, the bottom end of the threaded rod 57 is connected with a rectangular plate 58 through a bearing, the top of the rectangular plate 58 is fixedly installed with a slide rod 6, the slide rod 6 is slidably connected to the second connecting frame 54, and the splicing component 5 also includes a knob 59, which is fixedly connected to the top of the threaded rod 57.
[0033] In this embodiment, first, the connecting frame 2 54 is inserted into the interior of the rectangular groove 53, and then the knob 59 is rotated to drive the threaded rod 57 to rotate, so that the rectangular plate 58 can squeeze the steel ball 55 out of the inner third of the connecting frame 2 54, so that the steel ball 55 can be clamped together with the circular groove 3 52 to complete the splicing work. The splicing is simple and convenient, and the splicing can be carried out in time when necessary, so that the use effect will be better.
[0034] Reference Figures 1 to 4 In one aspect of the present embodiment, the disassembly assembly 2 includes a fixed block 21 and a circular groove 22. The fixed block 21 is fixedly mounted on the side walls of the fixed disk 1 and the fixed disk 24. The circular groove 22 is opened at the top of the fixed block 21. The inner side wall of the circular groove 22 is clamped with a hook 23. A circular groove 24 is opened on one side of the hook 23. A fixed frame 25 is fixedly mounted on one side of the fixed block 21. A sliding rod 26 is slidably connected to one side of the fixed frame 25. The sliding rod 26 is clamped with the circular groove 24. A spring 27 is sleeved on the side wall of the sliding rod 26. A limiting plate 28 is fixedly connected to the side wall of the sliding rod 26. The disassembly assembly 2 also includes a pull plate 29, which is fixedly connected to one end of the sliding rod 26.
[0035] In this embodiment, when the hook 23 needs to be replaced, the pull plate 29 is first pulled to drive the slide bar 26 to move, so that the slide bar 26 can squeeze the spring 27 through the limit plate 28, so that the slide bar 26 can be separated from the circular groove 24, so that the hook 23 can be disassembled and replaced. The hook 23 can be replaced alone, which reduces the cost of replacing all of them and has a better effect.
[0036] Reference Figures 1 to 4 In one aspect of the present embodiment, a positioning assembly 3 is provided on one side of the fixed block 21 and the hook 23. The positioning assembly 3 includes a positioning block 31 and a positioning groove 32. The positioning block 31 is fixedly connected to one side of the hook 23. The inner side wall of the fixed block 21 is provided with a positioning groove 32, and the positioning block 31 and the positioning groove 32 are clamped together.
[0037] In this embodiment, the positioning block 31 and the positioning groove 32 can position the hook 23, making its installation more convenient.
[0038] Reference Figures 1 to 4 In one aspect of the present embodiment, a U-shaped frame 7 is fixedly mounted on the top of the fixed plate 1, and an arc-shaped groove 8 is opened on one side of the U-shaped frame 7.
[0039] In this embodiment, the whole body can be hoisted, which is convenient for lifting and lowering, and also convenient for lowering the whole body into the hot-dip galvanizing pool.
[0040] Working principle: first, insert the connecting frame 2 54 into the rectangular groove 53, and then rotate the knob 59 to drive the threaded rod 57 to rotate, so that the rectangular plate 58 can squeeze the steel ball 55 out of the inner third of the connecting frame 2 54, so that the steel ball 55 can be clamped together with the circular groove 3 52 to complete the splicing work.
[0041] When the hook 23 needs to be replaced, first pull the pull plate 29 to drive the slide bar 26 to move, so that the slide bar 26 can squeeze the spring 27 through the limit plate 28, so that the slide bar 26 can be separated from the circular groove 24, so that the hook 23 can be disassembled and replaced. The hook 23 can be replaced alone, which also reduces the cost of replacing all of them.
[0042] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0043] Although the embodiments of the present application have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present application, and that the scope of the present application is defined by the appended claims and their equivalents.
Claims
1. A hot dip galvanizing rack, comprising a first fixing plate (1) and a second fixing plate (4), characterized in that: The side walls of the fixed plate 1 (1) and the fixed plate 2 (4) are respectively fixedly mounted with disassembly and assembly components (2); the bottom of the fixed plate 1 (1) and the top of the fixed plate 2 (4) are respectively fixedly mounted with splicing components (5); and the fixed plate 2 (4) is connected to the fixed plate 1 (1) via the splicing components (5); The splicing assembly (5) comprises a connecting frame (51) and a circular groove (52), wherein the connecting frame (51) is fixedly mounted on the bottom of the fixing plate (1), the circular groove (52) is provided on both sides of the connecting frame (51), a rectangular groove (53) is provided on the bottom of the connecting frame (51), a connecting frame (54) is fixedly mounted on the top of the fixing plate (4), and the connecting frame (54) and the rectangular groove (53) are locked together. The inner side wall of the second connecting frame (54) is provided with a steel ball (55), and the steel ball (55) is clamped with the circular groove three (52). The inner side wall of the second connecting frame (54) is fixedly installed with a limit plate (56), and the limit plate (56) is located on both sides of the steel ball (55). The top of the second connecting frame (54) is connected with a threaded rod (57) through a thread, and the bottom end of the threaded rod (57) is connected with a rectangular plate (58) through a bearing.
2. A hot dip galvanizing rack according to claim 1, characterized in that: The disassembly assembly (2) comprises a fixed block (21) and a circular groove one (22). The fixed block (21) is fixedly mounted on the side walls of the fixed disk one (1) and the fixed disk two (4). The circular groove one (22) is provided at the top of the fixed block (21). The inner side wall of the circular groove one (22) is clamped with a hook (23). A circular groove two (24) is provided on one side of the hook (23). A fixed frame (25) is fixedly mounted on one side of the fixed block (21). A sliding rod one (26) is slidably connected to one side of the fixed frame (25). The sliding rod one (26) is clamped with the circular groove two (24). A spring (27) is sleeved on the side wall of the sliding rod one (26). A limiting plate one (28) is fixedly connected to the side wall of the sliding rod one (26).
3. A hot dip galvanizing rack according to claim 2, characterized in that: The disassembly and assembly component (2) also includes a pull plate (29), and the pull plate (29) is fixedly connected to one end of the sliding rod (26).
4. A hot dip galvanizing rack according to claim 2, characterized in that: A positioning assembly (3) is provided on one side of the fixing block (21) and the hook (23), and the positioning assembly (3) comprises a positioning block (31) and a positioning groove (32). The positioning block (31) is fixedly connected to one side of the hook (23), and a positioning groove (32) is provided on the inner side wall of the fixing block (21), and the positioning block (31) and the positioning groove (32) are clamped together.
5. The hot dip galvanizing rack according to claim 1, characterized in that: A U-shaped frame (7) is fixedly mounted on the top of the fixed plate 1 (1), and an arc-shaped groove (8) is provided on one side of the U-shaped frame (7).
6. The hot dip galvanizing rack according to claim 1, characterized in that: A second sliding rod (6) is fixedly mounted on the top of the rectangular plate (58), and the second sliding rod (6) is slidably connected to the second connecting frame (54).
7. The hot dip galvanizing rack according to claim 1, characterized in that: The splicing assembly (5) further comprises a knob (59), wherein the knob (59) is fixedly connected to the top end of the threaded rod (57).
Citation Information
Patent Citations
Hot galvanizing hanger
CN220619064U