High-temperature steam steel jacket steel nano aerogel thermal insulation pipeline
By designing anti-blocking mechanisms and filtering mechanisms in high-temperature steam steel-sheathed steel insulation pipes, the power of water flow and the filtering function of the filter net are used to solve the problems of substances attached to the inner wall of the pipeline and the poor cleaning, and efficient cleaning and long-term stability of the pipeline are achieved.
Patent Information
- Application Number
- CN202421529739.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-01
- Publication Date
- 2025-03-21
- Estimated Expiration
- 2034-07-01
AI Technical Summary
The existing high-temperature steam steel sleeve steel insulation pipes are prone to internal wall rust and impurities in long-term high-temperature environments, which affects the insulation quality, and the cleaning device cannot be effectively cleaned when the water flow remains unchanged.
A high-temperature steam steel sleeve steel nano-aerogel insulation pipe is designed, using anti-blocking mechanism and filtering mechanism. The anti-blocking mechanism uses the combination of spiral torsion and scraping rod to generate disturbance and shear force by using the power of the water flow to prevent the adhesion of easily sticky substances; the filtering mechanism passes through the filter mesh and scraper to pre-filter and clean impurities in the water flow.
It effectively prevents the adhesion of easily sticky substances on the inner wall of the insulation pipe, maintains the unobstructed and cleanliness of the pipe, extends the service life, and improves the insulation effect.
Smart Images

Figure CN222650855U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of heat-insulated pipelines, in particular to a high-temperature steam steel jacketed steel nano-aerogel heat-insulated pipeline. Background Art
[0002] The steel-in-steel steam insulated pipe is composed of an outer protective steel pipe, a steel pipe anti-corrosion and insulation layer, and an inner working steel pipe. The steel-in-steel high-temperature steam insulated pipe is exposed to high-temperature gas for a long time, which causes rust and impurities on the inner wall, affecting the normal insulation quality. Therefore, a high-temperature steam steel-in-steel nano-aerogel insulated pipe is needed.
[0003] According to the description of the steel-in-steel high-temperature steam insulated pipeline disclosed on the patent website (authorization announcement number: CN 208816974U), "The utility model discloses a steel-in-steel high-temperature steam insulated pipeline, including a pipeline body, and mounting grooves are provided on the inner walls on both sides of the left and right sides of the pipeline body. The inner surfaces of the two mounting grooves on the side away from each other are fixedly connected with mounting bearing seats, and the inner surfaces of the two mounting bearing seats on the side close to each other are fixedly connected with a rotating rod, and the outer surface of the rotating rod is fixedly connected with an impeller, and the outer surface of the rotating rod is fixedly connected with an active tooth block located on the side of the impeller close to the mounting groove. The utility model sets an impeller to play the role of pulling the rotating rod to rotate during the high-temperature steam transportation, and the rotation of the impeller controls the rotating rod to pull the active tooth block to rotate. The driven tooth plate and the cleaning plate are set to play the role of cleaning the inner wall of the insulation pipeline with the transportation of high-temperature steam as the power, and then the inner wall of the insulation pipeline is cleaned in a timely and effective manner to improve the quality and service life."
[0004] In view of the above description, the applicant believes that there are the following problems:
[0005] During use, the utility model sets an impeller to pull the rotating rod to rotate when high-temperature steam is transported, and the rotation of the impeller controls the rotating rod to pull the active gear block to rotate. The driven gear plate and the cleaning plate are set to clean the inner wall of the insulation pipe with the transportation of high-temperature steam as the power. However, in actual use, the rotation of the impeller of the device controls the rotating rod to pull the active gear block to rotate, and the rotation of the active gear block pulls the driven gear plate to change its position. However, when the flow direction of water remains unchanged, the driven gear plate will not move after moving to a certain position, thereby failing to drive the cleaning plate to clean the inner wall of the pipe body. When cleaning, the water flow direction needs to be alternately changed so that the cleaning plate can move up and down to clean the inner wall of the pipe body. When cleaning, the device cannot transport the liquid to be transported, so it is necessary to improve a high-temperature steam steel-jacketed steel nano-aerogel insulation pipe to solve the above problems. Utility Model Content
[0006] The utility model aims to provide a high-temperature steam steel jacketed steel nano-aerogel insulation pipeline to solve the problems raised in the above background technology.
[0007] To achieve the above-mentioned purpose, the utility model provides the following technical solution: a high-temperature steam steel-jacketed steel nano-aerogel insulated pipeline, comprising an insulation pipe, a mounting pipe A is arranged on the right side of the insulation pipe, a mounting pipe B is arranged inside the insulation pipe, a mounting pipe C is arranged on the left side of the mounting pipe B, an anti-blocking mechanism is arranged inside the insulation pipe, and a filtering mechanism is arranged outside the mounting pipe C.
[0008] The anti-blocking mechanism comprises a power component and an anti-blocking component, and the anti-blocking component is arranged outside the power component.
[0009] Preferably, the power assembly includes three limiting cross rods, and the three limiting cross rods are respectively fixedly installed inside the mounting tube A, the mounting tube B and the mounting tube C; the three limiting cross rods are internally rotatably installed with a rotating shaft A, the interior of the rotating shaft A is provided with a spiral twisting piece, the internal thread of the rotating shaft A is threaded with a bolt A, and the outside of the rotating shaft A is fixedly installed with an impeller, which drives the rotating shaft A to rotate under the action of water flow, and uses water flow as a power source, which is more convenient.
[0010] Preferably, the number of the rotating shafts A is two, and the spiral twisted pieces are arranged inside the two rotating shafts A. The number of the bolts A is four, and the bolts A are threadedly installed inside the spiral twisted pieces. The spiral twisted pieces are arranged inside the insulation pipe, so that the water flow is disturbed, and the water flow is close to a fully turbulent state, making it difficult for easily sticky substances in the water to adhere to the inner wall of the insulation pipe.
[0011] Preferably, the anti-blocking component includes two rotating rods, which are respectively fixedly installed on the outside of two rotating shafts A, and two springs are fixedly installed inside the two rotating rods. A mounting block is fixedly installed on the end of the spring away from the rotating rod, and sliders are fixedly installed on the left and right of the mounting block. A scraper rod is fixedly installed on the side of the mounting block away from the rotating rod to scrape off trace amounts of easily sticky substances that may adhere to the inner wall of the insulation pipe.
[0012] Preferably, the scraper rod contacts the inner wall of the insulation pipe, the mounting block is slidably mounted inside the rotating rod, and the slider is slidably mounted inside the rotating rod to limit the movement of the mounting block.
[0013] Preferably, the filtering mechanism includes a flange A, which is fixedly mounted on the outside of a mounting tube C. A filter tube is provided on the left side of the mounting tube C. A flange B is fixedly mounted on the outside of the filter tube. A filter screen is fixedly mounted on the inside of the filter tube. A rotating shaft B is rotatably mounted on the inside of the filter screen. A scraper is fixedly mounted on the left end of the rotating shaft B. Two sealing rings are provided on the outside of the flange B. Bolts B are installed on the internal threads of the sealing rings. The two sealing rings are installed on the outside of flange B and flange A.
[0014] Preferably, the number of the bolts B is two, and the two bolts B are threadedly installed inside two sealing rings, the two sealing rings are arranged outside the filter tube, and the end of the rotating shaft B away from the scraper is fixedly installed on the rotating shaft A, and the scraper is in contact with the filter screen to scrape off impurities adhered to the surface of the filter screen.
[0015] Compared with the prior art, the utility model provides a high-temperature steam steel jacketed steel nano-aerogel insulation pipeline, which has the following beneficial effects:
[0016] 1. The high-temperature steam steel-jacketed steel nano-aerogel insulated pipe has an anti-clogging mechanism. During use, the spiral twisting piece rotates to disturb the water flow. The strongly rotating water flow generates friction and shear force on the inner wall of the insulation pipe, which destroys the adhesion mechanism of sticky substances in the water on the inner wall of the insulation pipe, making it difficult for sticky substances in the water to adhere to the inner wall of the insulation pipe. The scraper rod always adheres to the inner wall of the insulation pipe under the action of the spring, scrapes off the trace sticky substances that may adhere to the inner wall of the insulation pipe, and discharges them with the water flow, so that the inside of the insulation pipe remains unobstructed.
[0017] 2. The high-temperature steam steel-jacketed steel nano-aerogel insulated pipe has a filtering mechanism set up. During use, the filter screen pre-filters the water to make the water cleaner and the inside of the insulation pipe tidier. The rotating shaft A drives the rotating shaft B to rotate, so that the scraper rotates to scrape off the impurities adhered to the surface of the filter screen to avoid clogging. The two sealing rings seal the flange B and the flange A, so that the filter pipe is installed. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative labor:
[0019] Figure 1 This is a schematic diagram of the appearance structure of the utility model;
[0020] Figure 2This is a schematic diagram of the exploded structure of the utility model;
[0021] Figure 3 This is a schematic diagram of the exploded structure of the anti-blocking mechanism of the utility model;
[0022] Figure 4 This is a schematic diagram of the exploded structure of the anti-blocking component of the utility model;
[0023] Figure 5 It is a schematic diagram of the decomposition structure of the filtering mechanism of the utility model.
[0024] In the figure: 1. Insulation pipe; 2. Mounting pipe A; 3. Mounting pipe B; 4. Mounting pipe C; 5. Anti-blocking mechanism; 51. Power assembly; 511. Limiting cross rod; 512. Rotating shaft A; 513. Spiral twisting piece; 514. Bolt A; 515. Impeller; 52. Anti-blocking assembly; 521. Rotating rod; 522. Spring; 523. Mounting block; 524. Sliding block; 525. Scraper rod; 6. Filter mechanism; 61. Flange A; 62. Filter tube; 63. Flange B; 64. Filter net; 65. Rotating shaft B; 66. Scraper; 67. Sealing ring; 68. Bolt B. DETAILED DESCRIPTION
[0025] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0026] In the present invention, unless otherwise clearly specified and limited, the terms "install", "connect", "connect", "fix" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0027] Embodiment 1:
[0028] See also Figure 1-4 The utility model provides a technical solution: a high-temperature steam steel jacketed steel nano-aerogel insulated pipeline, comprising an insulation pipe 1, a mounting pipe A2 is arranged on the right side of the insulation pipe 1, a mounting pipe B3 is arranged inside the insulation pipe 1, a mounting pipe C4 is arranged on the left side of the mounting pipe B3, an anti-blocking mechanism 5 is arranged inside the insulation pipe 1, and a filtering mechanism 6 is arranged outside the mounting pipe C4.
[0029] The anti-blocking mechanism 5 includes a power assembly 51 and an anti-blocking assembly 52 , and the anti-blocking assembly 52 is arranged outside the power assembly 51 .
[0030] Furthermore, the power assembly 51 includes three limiting cross rods 511, and the three limiting cross rods 511 are respectively fixedly installed inside the mounting tube A2, the mounting tube B3 and the mounting tube C4. The three limiting cross rods 511 are internally rotatably installed with a rotating shaft A512, the interior of the rotating shaft A512 is provided with a spiral twisting piece 513, the internal thread of the rotating shaft A512 is installed with a bolt A514, and the outside of the rotating shaft A512 is fixedly installed with an impeller 515, which drives the rotating shaft A512 to rotate under the action of water flow, and uses water flow as a power source, which is more convenient.
[0031] Furthermore, there are two rotating shafts A512, and the spiral twisted pieces 513 are arranged inside the two rotating shafts A512. There are four bolts A514, and the bolts A514 are threadedly installed inside the spiral twisted pieces 513. The spiral twisted pieces 513 are arranged inside the insulation pipe 1, so that the water flow is disturbed, and the water flow is close to a fully turbulent state, making it difficult for easily sticky substances in the water to adhere to the inner wall of the insulation pipe 1.
[0032] Furthermore, the anti-blocking component 52 includes two rotating rods 521, which are respectively fixedly installed on the outside of the two rotating shafts A512, and two springs 522 are fixedly installed inside the two rotating rods 521. A mounting block 523 is fixedly installed on one end of the spring 522 away from the rotating rod 521, and sliders 524 are fixedly installed on the left and right of the mounting block 523. A scraper rod 525 is fixedly installed on the side of the mounting block 523 away from the rotating rod 521 to scrape off trace amounts of easily sticky substances that may adhere to the inner wall of the insulation pipe 1.
[0033] Furthermore, the scraper rod 525 contacts the inner wall of the insulation pipe 1 , the mounting block 523 is slidably installed inside the rotating rod 521 , and the slider 524 is slidably installed inside the rotating rod 521 to limit the movement of the mounting block 523 .
[0034] Embodiment 2:
[0035] See also Figure 5, and combined with Example 1, it is further obtained that the filtering mechanism 6 includes a flange A61, the flange A61 is fixedly installed on the outside of the mounting tube C4, a filter tube 62 is arranged on the left side of the mounting tube C4, a flange B63 is fixedly installed on the outside of the filter tube 62, a filter screen 64 is fixedly installed inside the filter tube 62, a rotating shaft B65 is rotatably installed inside the filter screen 64, a scraper 66 is fixedly installed on the left end of the rotating shaft B65, two sealing rings 67 are arranged on the outside of the flange B63, and a bolt B68 is installed on the internal thread of the sealing ring 67, and the two sealing rings 67 are installed on the flange B63 and the outside of the flange A61.
[0036] Furthermore, there are two bolts B68, and both bolts B68 are threadedly installed inside two sealing rings 67. The two sealing rings 67 are arranged on the outside of the filter tube 62. The end of the rotating shaft B65 away from the scraper 66 is fixedly installed with the rotating shaft A512. The scraper 66 contacts the filter screen 64 to scrape off impurities adhered to the surface of the filter screen 64.
[0037] In actual operation, when the device is used, water enters the filter tube 62, and the filter screen 64 pre-filters the water, making the water cleaner and the inside of the insulation tube 1 tidier. The filtered water passes through the filter mechanism 6 and the installation tube C4 and enters the installation tube B3. The impact of the water flow causes the impeller 515 to rotate, and the impeller 515 drives the rotating shaft A512 to rotate, thereby driving the spiral twisted blade 513 to rotate, causing the water flow to be disturbed, making the water flow close to a fully turbulent state. The strongly rotating water flow generates friction and shear force against the inner wall of the insulation tube 1, destroying the adhesion mechanism of the easily sticky substances in the water on the inner wall of the insulation tube 1, making it difficult for the easily sticky substances in the water to adhere to the inner wall of the insulation tube 1. The rotating shaft A512 drives the rotating shaft B65 to rotate, and the rotating shaft B65 drives the scraper 66 to rotate, and the scraper 66 scrapes off the impurities adhered to the surface of the filter screen 64 to prevent the impurities from clogging the filter screen 64. The two sealing rings 67 seal the flange B63 and the flange A61 under the action of the two bolts B68, so that the filter tube 62 can be installed more compactly to prevent water leakage. The rotating shaft A512 drives the rotating rod 521 to rotate, so that the mounting block 523 drives the scraper rod 525 to rotate, and the scraper rod 525 scratches the inner wall of the insulation tube 1. The spring 522 always exerts a force on the mounting block 523 toward the inner wall of the insulation tube 1, so that the scraper rod 525 always fits the inner wall of the insulation tube 1. The slider 524 limits the movement of the mounting block 523, and the scraper rod 525 scrapes off the trace amount of easily sticky substances that may adhere to the inner wall of the insulation tube 1.
[0038] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the statement "comprise a ..." do not exclude the presence of other identical elements in the process, method, article or device including the elements.
Claims
1. A high-temperature steam steel jacketed steel nano-aerogel insulated pipeline, comprising an insulated pipe (1), characterized in that: A mounting tube A (2) is arranged on the right side of the thermal insulation tube (1), a mounting tube B (3) is arranged inside the thermal insulation tube (1), a mounting tube C (4) is arranged on the left side of the mounting tube B (3), an anti-blocking mechanism (5) is arranged inside the thermal insulation tube (1), and a filtering mechanism (6) is arranged outside the mounting tube C (4); The anti-blocking mechanism (5) comprises a power component (51) and an anti-blocking component (52), and the anti-blocking component (52) is arranged outside the power component (51).
2. The high-temperature steam steel jacketed steel nano-aerogel insulation pipeline according to claim 1 is characterized in that: The power assembly (51) comprises three limiting cross rods (511), the three limiting cross rods (511) are respectively fixedly mounted inside the mounting tube A (2), the mounting tube B (3) and the mounting tube C (4), a rotating shaft A (512) is rotatably mounted inside the three limiting cross rods (511), a spiral twisting piece (513) is arranged inside the rotating shaft A (512), a bolt A (514) is threadedly mounted inside the rotating shaft A (512), and an impeller (515) is fixedly mounted outside the rotating shaft A (512).
3. The high-temperature steam steel jacketed nano-aerogel insulated pipeline according to claim 2 is characterized by: The number of the rotating shafts A (512) is two, and the spiral twisted plates (513) are arranged inside the two rotating shafts A (512). The number of the bolts A (514) is four, and the bolts A (514) are threadedly installed inside the spiral twisted plates (513). The spiral twisted plates (513) are arranged inside the insulation pipe (1).
4. The high-temperature steam steel jacketed nano-aerogel insulated pipeline according to claim 2 is characterized by: The anti-blocking assembly (52) comprises two rotating rods (521), the two rotating rods (521) are respectively fixedly mounted on the outside of two rotating shafts A (512), two springs (522) are fixedly mounted inside the two rotating rods (521), a mounting block (523) is fixedly mounted on one end of the spring (522) away from the rotating rod (521), sliding blocks (524) are fixedly mounted on the left and right of the mounting block (523), and a scraper rod (525) is fixedly mounted on one side of the mounting block (523) away from the rotating rod (521).
5. The high-temperature steam steel jacketed steel nano-aerogel insulation pipeline according to claim 4 is characterized by: The scraper rod (525) contacts the inner wall of the thermal insulation pipe (1), the mounting block (523) is slidably mounted inside the rotating rod (521), and the slider (524) is slidably mounted inside the rotating rod (521).
6. The high-temperature steam steel jacketed steel nano-aerogel insulation pipeline according to claim 1 is characterized by: The filtering mechanism (6) comprises a flange A (61), wherein the flange A (61) is fixedly mounted on the outside of a mounting tube C (4), a filtering tube (62) is arranged on the left side of the mounting tube C (4), a flange B (63) is fixedly mounted on the outside of the filtering tube (62), a filtering screen (64) is fixedly mounted on the inside of the filtering tube (62), a rotating shaft B (65) is rotatably mounted on the inside of the filtering screen (64), a scraper (66) is fixedly mounted on the left end of the rotating shaft B (65), two sealing rings (67) are arranged on the outside of the flange B (63), and a bolt B (68) is threadedly mounted on the inside of the sealing ring (67).
7. The high-temperature steam steel jacketed steel nano-aerogel insulation pipeline according to claim 6 is characterized by: The number of the bolts B (68) is two, and the two bolts B (68) are both threadedly installed inside the two sealing rings (67). The two sealing rings (67) are arranged outside the filter tube (62). The end of the rotating shaft B (65) away from the scraper (66) is fixedly installed with the rotating shaft A (512), and the scraper (66) is in contact with the filter screen (64).
Citation Information
Patent Citations
Steel-in-steel high-temperature steam heat preservation pipeline
CN208816974U