Water mill drilling machine lifting transport vehicle platform

By designing a water grinding drill rig lifting transport vehicle platform that can be lifted and conveniently transported, the problem of water grinding drill rigs in the prior art cannot adjust the height and unstable construction is solved, rapid height adjustment and convenient transportation are achieved, and construction efficiency and safety are improved.

CN222698381UActive Publication Date: 2025-04-01CHINA RAILWAY 11TH BUREAU GRP CORP LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202422122659.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-08-30
Publication Date
2025-04-01
Estimated Expiration
2034-08-30

AI Technical Summary

Technical Problem

The existing water grinding drilling rig lifting platform cannot be adjusted, resulting in the need to stack the discarded slag-raising platform every time the step section is excavated, which is troublesome and dangerous, affects the construction progress, and lacks stability and safety during construction.

Method used

A water grinding drill rig lifting transport vehicle platform is designed, including a transport vehicle and a lifting platform. The lifting platform can be lifted and lowered by hydraulic components and is equipped with adjustable installation holes and pins for locking and fixing. The bottom of the transport vehicle is equipped with telescopic legs and ground screws to ensure the stable fixation of the platform at different heights.

Benefits of technology

It realizes rapid height adjustment and convenient transportation of the water grinding drill rig, improves construction efficiency, ensures construction safety, and reduces the time for the drill rig to be transferred to the next hole position, and improves the construction progress.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222698381U_ABST
    Figure CN222698381U_ABST
Patent Text Reader

Abstract

The utility model discloses a water mill drilling machine lifting transport vehicle platform which comprises a transport vehicle and a lifting platform, the lifting platform is installed on the top face of the transport vehicle, each supporting leg of the lifting platform is provided with a row of adjustable installation holes, and the lifting platform is provided with plug pins used for locking and fixing the lifting platform at different height positions. After being parked in place, the drilling machine is fixed to the lifting platform through the fixing assembly. Telescopic supporting legs are arranged at the bottom of the transport vehicle, and when the transport vehicle loaded with the drilling machine arrives at a working place, the telescopic supporting legs extend downwards to be supported on the ground. The lifting assembly is additionally arranged on the transport vehicle, the position of the water mill drilling machine can be rapidly adjusted, transportation is convenient, meanwhile, the construction height of the water mill drilling machine is adjusted through the lifting assembly, operation is convenient and fast, construction efficiency can be improved, and construction safety of the water mill drilling machine in a tunnel is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of tunnel construction, in particular to a water-mill drilling rig lifting and transporting vehicle platform. Background Art

[0002] Due to the restrictions of the surrounding environment, more and more tunnel constructions choose to use non-explosive excavation technology. In the excavation process of cross passages and pilot tunnels, water-grinding drills are often used to drill holes and core along the periphery of the face, thereby providing an open surface for subsequent static splitting or static crushing construction and improving the surrounding rock crushing effect.

[0003] The water-mill drill enters the tunnel and reaches the face, where it performs core drilling. During operation, the motor drives the drill bit to rotate through the transmission device, while the grouting system injects cement slurry into the borehole. The water spraying system plays a role in cooling and cleaning, and the coring system can quickly remove the core. The existing water-mill drill lifting platform uses a transport vehicle to carry the drill into the tunnel for work, and the height is fixed after entering the tunnel section, so it is impossible to excavate a higher section. Every time the upper step section is excavated, it is necessary to pile up the waste slag to raise the platform, which is troublesome and dangerous. It is difficult to quickly change the position of the drill, which results in a lot of time spent on transferring the drill to the next hole position, seriously affecting the construction progress. In addition, the water-mill drill frame is often connected with a simple scaffolding during construction, and its stability and safety cannot be guaranteed. Utility Model Content

[0004] In view of the defects of the above-mentioned prior art, the technical problem to be solved by the utility model is to provide a water-mill drilling rig lifting and transport vehicle platform which is easy to operate, convenient to transport and capable of adjusting the construction height of the water-mill drilling rig at any time.

[0005] In order to solve the above technical problems, the utility model adopts the following technical solutions: a water-mill drilling rig lifting transport vehicle platform, comprising a transport vehicle and a lifting platform, the lifting platform being installed on the top surface of the transport vehicle, each leg of the lifting platform being provided with a row of adjustable mounting holes, and being equipped with latches for locking and fixing the lifting platform at different heights, and when the drilling rig is parked in place, being fixed to the lifting platform through a fixing assembly; telescopic legs are provided at the bottom of the transport vehicle, and when the transport vehicle loaded with the drilling rig arrives at the work site, the telescopic legs are extended downward and supported on the ground.

[0006] Preferably, the lifting platform is lifted and lowered by a hydraulic assembly, and when lifted into place, the lifting platform is fixed by inserting a pin into an adjustable mounting hole.

[0007] Preferably, the telescopic legs are telescopically extended by ground-supporting screw rods.

[0008] Preferably, the fixing assembly includes an anti-skid lock and a wedge-shaped anti-skid pad, and the two wedge-shaped anti-skid pads are respectively clamped on the front and rear ends of the tire of the drilling rig and fixed by the anti-skid lock.

[0009] Preferably, a side wall screw rod is provided on the side of the lifting platform to prevent lateral shaking.

[0010] Preferably, the outer side surface of each telescopic leg is obliquely provided with a screw support for auxiliary support.

[0011] Preferably, in the tunnel, two water-mill drilling rig lifting and transport vehicle platforms are symmetrically connected side by side on the left and right, and the two lifting platforms are connected by an intermediate connecting screw. The outer sides of the two lifting platforms are each equipped with a side wall screw connected to the side wall of the tunnel, and the end of the side wall screw connected to the side wall is higher than the end connected to the lifting platform.

[0012] Preferably, the drilling rig travels to the lifting platform via a movable inclined bridge, the top of the movable inclined bridge is flush with the lifting platform, and the inclination angle of the movable inclined bridge is 20°.

[0013] The beneficial effects of the utility model are as follows: by adding a lifting component to the transport vehicle, the position of the water-mill drilling rig can be quickly adjusted, and transportation is convenient; at the same time, the construction height of the water-mill drilling rig can be adjusted by the lifting component, which is convenient to operate, can improve construction efficiency, and ensure the safety of the water-mill drilling rig in the tunnel. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 It is the loading diagram of the drilling rig of the present utility model;

[0015] Figure 2 This is a schematic diagram of the drilling rig loading;

[0016] Figure 3 It is a working schematic diagram of the utility model;

[0017] Figure 4 It is a right view of the utility model;

[0018] In the figure: 1-transport vehicle, 2-drilling rig, 3-telescopic legs, 4-lifting platform, 5-anti-skid lock, 6-wedge-shaped anti-skid pad, 7-latch, 8-ground support screw, 9-side wall screw, 10-connecting screw. DETAILED DESCRIPTION

[0019] In order to better understand the improvements made by the present invention relative to the prior art, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments.

[0020] like Figure 1As shown in FIG. 4 , a water-grinding drilling rig lifting and transporting vehicle platform is mainly composed of a transporting vehicle 1 and a lifting platform 4. The lifting platform 4 is installed on the top surface of the transporting vehicle 1.

[0021] Each leg of the lifting platform 4 is provided with a row of adjustable mounting holes and is equipped with a latch 7 for locking and fixing the lifting platform 4 at different height positions. The lifting platform 4 is lifted and lowered by a hydraulic assembly. When lifted into place, the lifting platform 4 is fixed by inserting the latch 7 into the adjustable mounting hole.

[0022] The drilling rig 2 travels to the lifting platform 4 via the movable inclined bridge, the top of the movable inclined bridge is flush with the lifting platform 4, and the tilt angle of the movable inclined bridge is preferably 20°. When the drilling rig 2 is parked in place, it is fixed on the lifting platform 4 through the fixing assembly, and the drilling rig 2 is parked in the middle of the lifting platform 4. The fixing assembly is mainly composed of an anti-skid lock 5 and a wedge-shaped anti-skid pad 6. The two wedge-shaped anti-skid pads 6 are respectively clamped on the front and rear ends of the tires of the drilling rig 2 and fixed by the anti-skid lock 5.

[0023] A telescopic leg 3 is provided at the bottom of the transport vehicle 1. When the transport vehicle 1 loaded with the drilling rig 2 arrives at the work site, the telescopic leg 3 is extended downward and supported on the ground. The telescopic leg 3 is telescopically extended by a ground-supporting screw rod 8, and a screw support is obliquely provided on the outer side of each telescopic leg 3 for auxiliary support.

[0024] The side of the lifting platform 4 is preferably provided with a side wall screw 9 to prevent lateral shaking. In the tunnel, two water mill drilling rig lifting and transport vehicle platforms are symmetrically connected side by side, and the two lifting platforms 4 are connected by an intermediate connecting screw 10. The outer sides of the two lifting platforms 4 are each equipped with a side wall screw 9 connected to the tunnel side wall, and the end of the side wall screw 9 connected to the side wall is higher than the end connected to the lifting platform 4.

[0025] The two transport vehicles back up into the working area of ​​the face. After they are in place, the telescopic legs 3 are extended, the ground support screws are installed and fixed, and the drilling rig 2 on the lifting platform 4 is checked again to see if it is firmly fixed. After it is correct, the hydraulic assembly is started, the cylinder is extended, and it is raised to the specified position. The height is determined according to the tunnel section. During the ascent of the lifting platform 4, it is observed whether it is stable. After reaching the appropriate height, the maximum height from the ground is 3.5m. After the lifting platform 4 is checked to meet the requirements, the legs are inserted into the pins 7 to fix it. The side wall screw 9 is extended and supported on the side wall of the tunnel to fix the lifting platform 4 laterally. At the same time, the two lifting platforms 4 are connected by the connecting screw 10 to further prevent lateral shaking.

[0026] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes within the technical scope disclosed by the present invention according to the technical scheme and the utility model concept of the present invention, which should be covered by the protection scope of the present invention.

Claims

1. A water-mill drilling rig lifting and transporting vehicle platform, comprising a transporting vehicle (1) and a lifting platform (4), characterized in that: The lifting platform (4) is installed on the top surface of the transport vehicle (1). Each leg of the lifting platform (4) is provided with a row of adjustable mounting holes and is equipped with a latch (7) for locking and fixing the lifting platform (4) at different heights. When the drilling rig (2) is parked in place, it is fixed on the lifting platform (4) through a fixing assembly. The bottom of the transport vehicle (1) is provided with a telescopic leg (3). When the transport vehicle (1) loaded with the drilling rig (2) arrives at the work site, the telescopic leg (3) is extended downward to support the ground.

2. A water-mill drilling rig lifting and transporting vehicle platform according to claim 1, characterized in that: The lifting platform (4) is lifted and lowered by a hydraulic assembly. When lifted into place, the lifting platform (4) is fixed by inserting a latch (7) into an adjustable mounting hole.

3. The water-mill drilling rig lifting and transporting vehicle platform according to claim 1 is characterized in that: The telescopic legs (3) are telescopically extendable using a ground-supporting screw rod (8).

4. The water-mill drilling rig lifting and transporting vehicle platform according to claim 1 is characterized in that: The fixing assembly comprises an anti-skid lock (5) and a wedge-shaped anti-skid pad (6), wherein the two wedge-shaped anti-skid pads (6) are respectively clamped on the front and rear ends of the tire of the drilling rig (2) and fixed by the anti-skid lock (5).

5. The water-mill drilling rig lifting and transporting vehicle platform according to claim 1 is characterized by: The side of the lifting platform (4) is provided with a side wall screw rod (9) for preventing lateral shaking.

6. The water-mill drilling rig lifting and transporting vehicle platform according to claim 1, characterized in that: The outer side surface of each telescopic leg (3) is obliquely provided with a lead screw support for auxiliary support.

7. The water-mill drilling rig lifting and transporting vehicle platform according to claim 1 is characterized by: In the tunnel, two water-mill drilling rig lifting and transport vehicle platforms are symmetrically connected side by side, and the two lifting platforms (4) are connected via an intermediate connecting screw rod (10). The outer sides of the two lifting platforms (4) are each equipped with a side wall screw rod (9) connected to the tunnel side wall, and the end of the side wall screw rod (9) connected to the side wall is higher than the end connected to the lifting platform (4).

8. The water-mill drilling rig lifting and transporting vehicle platform according to claim 1, characterized in that: The drilling rig (2) travels to the lifting platform (4) via a movable inclined bridge, the top of the movable inclined bridge is flush with the lifting platform (4), and the inclination angle of the movable inclined bridge is 20°.