Auxiliary ladder assembly for large-diameter pipeline operation
By designing a U-shaped large-diameter pipeline operation auxiliary ladder, the problem that workers cannot get close to the working point is solved, and the effect of improving operation safety and efficiency is achieved. It is suitable for the installation and construction of large-diameter pipelines.
Patent Information
- Application Number
- CN202420695286.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-07
- Publication Date
- 2025-04-25
- Estimated Expiration
- 2034-04-07
AI Technical Summary
During the installation and construction of large-diameter pipelines, workers cannot directly approach the working point, and the existing solutions have problems such as high cost, long construction cycle, large safety risks and low efficiency.
A U-shaped large-diameter pipeline operation auxiliary ladder frame is designed, including the main frame, support feet and platform board. The main frame is supported on the top of the pipeline. The platform board can be removable and snapped to the flat panel connecting frame to provide climbing and standing support, and to prevent rolling through the large-diameter pipeline support.
It realizes that workers quickly approach the working points, improves operation safety and efficiency, reduces construction costs and time, and is suitable for outdoor construction under various weather conditions.
Smart Images

Figure CN222797450U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to an auxiliary ladder frame for large-diameter pipeline operations, belonging to the technical field of large-diameter pipeline installation operations. Background Art
[0002] At present, in the installation and construction of large-diameter pipelines, there is often a problem that the pipeline diameter is too large and the operators cannot directly approach the work point, but the construction of pipeline connection, grinding, welding, etc. must ensure that the operators can approach the work point. The most commonly used domestic solutions are to use three temporary solutions.
[0003] Option 1: Set up scaffolding at the location where the pipeline needs to be constructed.
[0004] Option 2: Use a ladder to lean against the pipeline, and workers climb the ladder to carry out construction.
[0005] Option three: Use wooden boxes to build steps, and workers stand on the steps to carry out construction.
[0006] However, the above conventional solutions have the following problems:
[0007] (1) Plan 1 requires the erection of scaffolding, which requires a large amount of scaffolding materials and professional scaffolding workers. In addition, in general pipeline construction areas, material transportation is difficult due to excavation and other reasons. This plan is costly and has a long construction period, and cannot meet actual needs in a timely manner.
[0008] (2) Option 2: Ladders are prone to slipping when leaning against the pipe, so a fixed solution is required. The coverage of the ladder is limited, and workers need to climb up and down the ladder repeatedly when adjusting the construction position. This increases safety risks and construction time. To ensure safety, special personnel need to be arranged to support the ladder, which increases labor. In addition, outdoor construction is inconvenient in adverse weather such as rain, snow, and strong winds. This solution is rarely used at present.
[0009] (3) Option 3 is less efficient and labor-intensive. Since the materials for building the steps are often locally sourced, the stability of the steps is difficult to control, which increases safety risks. In addition, during outdoor construction, in adverse weather such as rain, snow, and strong winds, temporary steps cannot be protected, making construction inconvenient. Currently, this option is only applicable to some situations where the amount of construction work is small.
[0010] In summary, the three solutions all have their own shortcomings, so it is quite necessary to design a large-diameter pipeline operation auxiliary equipment with a simple structure, easy installation, and both safety and improved operation efficiency. Utility Model Content
[0011] The utility model provides a large-diameter pipeline operation auxiliary ladder frame, which assists workers to quickly approach the operation point. The auxiliary ladder frame has a simple structure and is easy to set up on the large-diameter pipeline. It can provide standing and climbing support for workers approaching the operation point during large-diameter pipeline installation operations, and uses the large-diameter pipeline to support the auxiliary ladder frame to prevent the auxiliary ladder frame from tipping over and over, thereby improving operation safety. It can both ensure safety and improve operation efficiency, and is highly practical.
[0012] In order to achieve the above purpose, the technical solution adopted by the utility model is:
[0013] The auxiliary ladder for large-diameter pipeline operations is U-shaped and is erected across the large-diameter pipeline. It is characterized in that it includes a U-shaped main frame supported on the top of the large-diameter pipeline, supporting feet and a platform plate fixed to the bottom of the main frame and in contact with the ground, flat plate connecting frames are evenly spaced on the main frame, ladder rods are arranged between adjacent flat plate connecting frames, and the platform plate is detachably snapped onto the flat plate connecting frame.
[0014] Preferably, the main frame includes four U-shaped steel pipes distributed in a rectangular shape, the flat plate connecting frame is rectangular, and the U-shaped steel pipes are respectively welded to the corners of the flat plate connecting frame.
[0015] Preferably, the ladder rod is welded between two U-shaped steel pipes and is located on the inner side of the main frame opposite to the large-diameter pipe, and a ladder rod is arranged between adjacent flat plate connection frames.
[0016] Preferably, the main frame has an isolation support rod extending from the inner side of the main frame and contacting the top of the large-diameter pipe, and the isolation support rod separates the main frame from the large-diameter pipe by 10 to 30 centimeters.
[0017] Preferably, the isolation support rod is integrally formed with the platform connecting frame located at the top of the main frame, and the two sides of the platform connecting frame are extended downward to form the isolation support rod. The number of the isolation support rods is four to eight, and they are symmetrically arranged on the front and rear sides of the main frame.
[0018] Preferably, a universal wheel with a brake is installed at the bottom of the supporting foot.
[0019] The beneficial effects of the utility model are:
[0020] The large-diameter pipeline operation auxiliary ladder frame of the utility model is U-shaped and is erected across the large-diameter pipeline. The supporting feet are in contact with the ground, the main frame is supported on the top of the large-diameter pipeline, and the platform plate can be snap-connected and overlapped on the flat plate connecting frame. During operation, the operator can climb to the position of the flat plate connecting frame with the help of the ladder rod, and snap-connect the platform plate to the flat plate connecting frame with the help of the ladder rod, and the operator can stand on the platform plate to operate on the large-diameter pipeline, or climb to the top of the large-diameter pipeline with the help of the ladder rod and the flat plate connecting frame to operate on it, so that the auxiliary operator can quickly approach the operation point. The auxiliary ladder frame has a simple structure and is easy to be erected on the large-diameter pipeline. It can provide standing and climbing support for the operator to approach the operation point during the large-diameter pipeline installation operation, and use the large-diameter pipeline to support the auxiliary ladder frame to prevent the auxiliary ladder frame from tipping over and tipping over, thereby improving the safety of operation, ensuring safety and improving operation efficiency, and having high practicality. In rainy, snowy and windy weather, a rainproof cloth can be covered on the auxiliary ladder frame to improve the convenience of outdoor construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 It is a schematic diagram of an auxiliary ladder for large-diameter pipeline operations in a specific implementation method.
[0022] Figure 2 This is a schematic diagram of an auxiliary ladder frame for large-diameter pipeline operations installed across a large-diameter pipeline. DETAILED DESCRIPTION
[0023] Combine the following Figure 1~2 The embodiments of the utility model are described in detail.
[0024] The auxiliary ladder frame for large-diameter pipeline operations is U-shaped and is erected across the large-diameter pipeline 100. It is characterized in that it includes a U-shaped main frame 1 supported on the top of the large-diameter pipeline, support feet 2 and a platform plate 3 fixed to the bottom of the main frame and in contact with the ground, flat plate connecting frames 4 are evenly spaced on the main frame 1, ladder rods 5 are arranged between adjacent flat plate connecting frames 4, and the platform plate 3 is detachably snap-connected to the flat plate connecting frame 4.
[0025] The large-diameter pipeline operation auxiliary ladder frame described above is erected across the large-diameter pipeline 100, the supporting feet 2 are in contact with the ground, the main frame 1 is supported on the top of the large-diameter pipeline 100, and the platform plate 3 can be snap-connected to the flat plate connection frame. During operation, the operator can climb to the position of the flat plate connection frame 4 with the help of the ladder rod 5, and snap-connect the platform plate 3 to the flat plate connection frame 1. The operator can stand on the platform plate 3 to operate the large-diameter pipeline, or climb to the top of the large-diameter pipeline with the help of the ladder rod 5 and the flat plate connection frame 4 to operate it, so as to assist the operator to quickly approach the operation point. The auxiliary ladder frame has a simple structure and is easy to be erected on the large-diameter pipeline 100. It can provide standing and climbing support for the operator to approach the operation point during the large-diameter pipeline installation operation, and use the large-diameter pipeline 100 to support the auxiliary ladder frame to prevent the auxiliary ladder frame from tipping over and tipping over, thereby improving the safety of the operation, ensuring safety and improving the operation efficiency. It is highly practical, and a rainproof cloth can be covered on the auxiliary ladder frame in rainy, snowy and windy weather to improve the convenience of outdoor construction.
[0026] The main frame 1 includes four U-shaped steel pipes 11 distributed in a rectangular shape, the flat plate connection frame 4 is rectangular, and the U-shaped steel pipes 11 are welded to the corners of the flat plate connection frame 4. The U-shaped steel pipes 11 are welded to form a whole through the flat plate connection frame 4, and the flat plate connection frame 4 is evenly spaced on the main frame 1 to ensure the strength of the main frame 1. The four U-shaped steel pipes 11 are connected to the flat plate connection frame 4 to form a main frame 1 with a hollow channel structure, which is convenient for operators to be in the hollow channel structure when climbing and standing, and acts as a fence around the operators, which can effectively prevent the operators from falling off and improve safety.
[0027] The ladder rod 5 is welded between two U-shaped steel pipes 11 and is located on the inner side of the main frame 1 opposite to the large-diameter pipe. A ladder rod 5 is provided between adjacent flat plate connection frames 4. The ladder rod 5 is used for climbing by the operator. When the flat plate connection frame 4 is buckled with the overlapping platform plate 3, the operator can stand and work. When the overlapping platform plate 3 is not buckled, the operator can climb, and the operator is assisted to quickly climb to the top of the large-diameter pipe. When climbing and standing, the main frame 1 is supported on the top of the large-diameter pipe 100, and the support foot 2 is supported on the ground, so the auxiliary ladder frame will not tilt and overturn, and the safety is high.
[0028] The main frame 1 has an isolation support rod 6 extending from the inside of the main frame and contacting the top of the large-diameter pipe 100. The isolation support rod 6 separates the main frame 1 from the large-diameter pipe 100 by 10 to 30 centimeters. The isolation support rod 6 supports the main frame 1 on the top of the large-diameter pipe and separates the large-diameter pipe from the main frame 1 to form a working space, which is convenient for operators to work and go up and down.
[0029] The isolation support rod 3 is integrally formed with the platform connection frame 4 located at the top of the main frame 1. The two sides of the platform connection frame 4 are extended downward to form isolation support rods 6. The number of isolation support rods 6 is four to eight, and they are symmetrically arranged on the front and rear sides of the main frame 1. As shown in the accompanying drawings, the number of isolation support rods 6 is eight, which are formed by the two sides of four platform connection frames 4 extending downward respectively. The eight isolation support rods 6 are symmetrically arranged on the front and rear sides of the main frame 1, which stably supports the main frame 1 on the large-diameter pipe 100, reduces the shaking of the main frame 1 during operation, and forms an operating space between the auxiliary ladder frame and the large-diameter pipe 100, which improves the stability of the auxiliary ladder frame and improves the safety of operation.
[0030] The bottom of the support foot 2 is provided with a universal wheel with a brake, which facilitates the movement of the auxiliary ladder frame along the large-diameter pipeline 100. The universal wheel is positioned with a brake to position the auxiliary ladder frame on the ground, thereby ensuring the stability of the auxiliary ladder frame during operation.
[0031] The above is a complete description of the technical solutions of the embodiments of the utility model in combination with the accompanying drawings. It should be noted that the described embodiments are only part of the embodiments of the utility model. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the utility model.
Claims
1. Auxiliary ladder for large-diameter pipeline operation, which is U-shaped and erected across the large-diameter pipeline, is characterized by: It includes a U-shaped main frame supported on the top of a large-diameter pipe, support feet and a platform plate fixed to the bottom of the main frame and in contact with the ground, flat plate connecting frames are evenly spaced on the main frame, ladder rods are arranged between adjacent flat plate connecting frames, and the platform plate is detachably connected to the flat plate connecting frames by snaps.
2. The large-diameter pipeline operation auxiliary ladder according to claim 1 is characterized in that: The main frame comprises four U-shaped steel pipes distributed in a rectangular shape, the flat plate connection frame is rectangular, and the U-shaped steel pipes are respectively welded to the corners of the flat plate connection frame.
3. The large-diameter pipeline operation auxiliary ladder according to claim 2 is characterized in that: The ladder rod is welded between two U-shaped steel pipes and is located on the inner side of the main frame opposite to the large-diameter pipe. A ladder rod is arranged between adjacent flat plate connection frames.
4. The large-diameter pipeline operation auxiliary ladder according to claim 3 is characterized in that: The main frame is provided with an isolation support rod extending from the inner side of the main frame and contacting the top of the large-diameter pipeline. The isolation support rod separates the main frame from the large-diameter pipeline by 10 to 30 centimeters.
5. The large-diameter pipeline operation auxiliary ladder according to claim 4 is characterized in that: The isolation support rods are integrally formed with the platform connection frame located at the top of the main frame. The two sides of the platform connection frame extend downward to form isolation support rods. The number of isolation support rods is four to eight and they are symmetrically arranged on the front and rear sides of the main frame.
6. The large-diameter pipeline operation auxiliary ladder according to claim 1 is characterized by: Universal wheels with brakes are installed at the bottom of the supporting feet.