Large-span attachment wall connecting structure of construction hoist
By designing the L-shaped structure of the fixed seat and the rotating column and the connecting rod in the large-span attachment structure of the construction elevator, the problems of insufficient contact surfaces between the fixed seat and the standard section and inconvenient adjustment of the connecting rod angle are solved, and higher stability and diversity are achieved.
Patent Information
- Application Number
- CN202421967183.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-14
- Publication Date
- 2025-05-13
- Estimated Expiration
- 2034-08-14
AI Technical Summary
The existing construction lift large-span attachment structure has insufficient in the contact surface of the fixed seat and the standard section, resulting in a small contact surface, easy to shake, and inconvenient to adjust the angle between the connecting rod and the profile, and poor diversity and stability when used.
A construction elevator with a large span attached wall structure including standard sections, walls and fixed seats is designed. Through the cooperation of the fixed seats and rotating columns in the L-shaped structure and the connecting rod, multiple contact surfaces and angle adjustments are achieved to enhance stability.
Through the design of multiple contact surfaces and angle adjustment, the stability between the fixed seat and the standard section is improved, shaking is avoided, and the stability between the connecting rod and the profile is enhanced, and the diversity and stability during use is improved.
Smart Images

Figure CN222861012U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of elevator attachment structures, in particular to a large-span attachment wall connection structure for a construction elevator. Background Art
[0002] A construction elevator is a piece of equipment used to transport personnel and materials during construction. However, due to the limitations of the on-site installation environment and special conditions, sometimes the construction elevator is mounted on a wall far away from the building, resulting in the original factory attachment rod length of the construction elevator being unable to meet the attachment requirements.
[0003] China Utility Model Patent Publication No.: CN 219156224 U, discloses an extension structure for long-distance attachment of a construction elevator. When in a special environment, when the length of the original attachment rod of the elevator cannot meet the attachment requirements, the first support rod and the second support rod can be connected by a socket, and then the second limit member and the second limit pin are used to further limit the relative positions of the socket, the first support rod and the second support rod, thereby avoiding the second support rod from falling off due to the looseness of the socket. However, the extension structure for long-distance attachment of the construction elevator has some shortcomings. It does not improve the contact surface between the fixed seat and the standard section, which easily leads to a smaller contact surface and thus easy shaking; and the structure is not convenient for adjusting the angle between the connecting rod and the profile member, so that its angle is relatively fixed, and the diversity and stability are poor during use. Summary of the invention
[0004] The technical problem to be solved by the utility model is to provide a large-span attached wall connection structure for a construction elevator, which can effectively solve the problems in the prior art of not improving the contact surface between the fixed seat and the standard section, which easily leads to less contact surface, easy shaking, inconvenience in connecting the angle of the connecting rod and the profile, making the angle relatively fixed, resulting in poor diversity in use and easy poor stability.
[0005] The technical solution adopted by the utility model is: a large-span attached wall structure for a construction elevator, comprising a standard section, a wall and a fixed seat, a profile member is fixedly installed on the outside of the fixed seat, a connecting sleeve is fixedly installed on the inside of the profile member, a clamping block is fixedly installed inside the connecting sleeve, a fixed block 1 is fixedly installed on the bottom of the profile member, a rotating column 1 is rotatably installed on the outside of the fixed block 1, a connecting rod 1 is fixedly installed on the outside of the rotating column 1, a connecting seat 1 is fixedly installed on the other side of the connecting rod 1, a fixed block 2 is fixedly installed on the bottom of the profile member, a rotating column 2 is rotatably installed on the outside of the fixed block 2, a connecting rod 2 is fixedly installed on the outside of the rotating column 2, a connecting seat 2 is fixedly installed on the other side of the connecting rod 2, a limiting rod is arranged on the inside of the connecting sleeve, and a clamping groove is provided on the outside of the limiting rod.
[0006] Preferably, mounting sleeves are fixedly installed on the outer sides of the four sides of the standard section, and fixing bolts are arranged on the inner sides of the mounting sleeves. The standard section, mounting sleeves and fixing bolts are in one-to-one correspondence, and the fixing bolts at the connection between the two standard sections pass through the two mounting sleeves.
[0007] Through the above technical solution, through the design of the fixing bolt, the standard section can be fixedly installed on the ground through the fixing bolt at the bottom of the standard section, and when connecting multiple standard sections, the fixing bolt can be inserted into the installation sleeve to achieve connection between multiple standard sections.
[0008] Preferably, the cross-section of the fixing seat is in an "L"-shaped structure, and both sides of the fixing seat are fixedly mounted with standard sections by bolts.
[0009] Through the above technical solution, through the L-shaped structure of the fixing seat, it can be achieved that there are multiple contact surfaces between the fixing seat and the standard section, which can improve the stability between the fixing seat and the standard section and prevent them from shaking easily.
[0010] Preferably, the rotating column 1 is matched with the connecting rod 1, and the connecting seat 1 is fixedly installed with the standard section.
[0011] Through the above technical solution, by rotating the column 1 and the connecting rod 1, the angle between the connecting rod 1 and the profile can be adjusted according to actual conditions to improve its stability, and the cooperation between the other end of the connecting seat 1 and the standard section can enhance the stability between the two.
[0012] Preferably, a mounting seat is fixedly installed on the other side of the profile away from the fixing seat, the mounting seat is fixedly installed on the wall through bolts, and the second connecting seat is fixedly installed on the wall.
[0013] Through the above technical solution, the other end of the profile can be connected to the wall through the cooperation of the mounting seat and the wall. When it needs to be connected to the ground, the installation can be achieved by rotating the connecting seat 2 and then fixing it with bolts.
[0014] Preferably, the fixed seat, profile, fixed block 1, rotating column 1, connecting rod 1, connecting seat 1, fixed block 2, rotating column 2, connecting rod 2 and connecting seat 2 are provided in the same multiple groups, and each group of the fixed seat, profile, fixed block 1, rotating column 1, connecting rod 1, connecting seat 1, fixed block 2, rotating column 2, connecting rod 2 and connecting seat 2 is provided with the same two, and are symmetrically distributed about the center line of the standard node.
[0015] Through the above technical scheme, through the design of multiple sets of fixed seats, profiles, fixed block one, rotating column one, connecting rod one, connecting seat one, fixed block two, rotating column two, connecting rod two and connecting seat two, the stability of the overall standard section can be improved, avoiding the shaking of the standard section with a higher top.
[0016] Preferably, the card slot is adapted to the card block, and the limit rod connects the four connecting sleeves and the card block.
[0017] Through the above technical solution, through the cooperation of the slot and the block, when installing the limit rod, it can be inserted into the block through the slot, and then the limit rod can connect the two profiles, which can improve the stability between the two profiles and avoid displacement.
[0018] Compared with the prior art, the utility model provides a large-span attached wall structure for a construction elevator, which has the following beneficial effects:
[0019] 1. The large-span attached wall structure of the construction hoist can realize multiple contact surfaces between the fixed seat and the standard section through the L-shaped fixed seat, which can improve the stability between the fixed seat and the standard section and prevent it from shaking easily. By cooperating with the rotating column 1 and the connecting rod 1, the angle between the connecting rod 1 and the profile can be adjusted according to the actual situation to improve its stability, and the cooperation between the other end of the connecting seat 1 and the standard section can enhance the stability between the two;
[0020] 2. The large-span attached wall structure of the construction elevator can be installed by fitting the card slot and the card block. Then the limit rod can be connected to the two profiles, which can improve the stability between the two profiles and avoid displacement. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 The three-dimensional structure of the utility model is shown in FIG. Figure 1 ;
[0022] Figure 2 The three-dimensional structure of the utility model is shown in FIG. Figure 2 ;
[0023] Figure 3 This is a schematic diagram of the installation structure of the standard section and the connecting seat of the utility model;
[0024] Figure 4 This is a schematic diagram of the installation structure of the connecting seat and profile member of the utility model;
[0025] Figure 5 This is a schematic diagram of the installation structure of the limit rod and the card slot of the utility model.
[0026] Among them: 1. Standard section; 2. Installation sleeve; 3. Fixing bolt; 4. Wall; 5. Fixing seat; 6. Profile; 7. Installation seat; 8. Connecting sleeve; 9. Block; 10. Fixing block 1; 11. Rotating column 1; 12. Connecting rod 1; 13. Connecting seat 1; 14. Fixing block 2; 15. Rotating column 2; 16. Connecting rod 2; 17. Connecting seat 2; 18. Limiting rod; 19. Slot. DETAILED DESCRIPTION
[0027] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0028] Embodiment 1: Figure 1-2 As shown, the utility model provides a large-span attached wall structure for a construction elevator, comprising a standard section 1, a wall body 4 and a fixing seat 5, a profile member 6 is fixedly installed on the outside of the fixing seat 5, a connecting sleeve 8 is fixedly installed on the inside of the profile member 6, a clamping block 9 is fixedly installed inside the connecting sleeve 8, a fixing block 10 is fixedly installed on the bottom of the profile member 6, a rotating column 11 is rotatably installed on the outside of the fixing block 10, a connecting rod 12 is fixedly installed on the outside of the rotating column 11, and a connecting seat 13 is fixedly installed on the other side of the connecting rod 12, a fixing block 2 14 is fixedly installed on the bottom of the profile member 6, a rotating column 2 15 is rotatably installed on the outside of the fixing block 2 14, a connecting rod 2 16 is fixedly installed on the outside of the rotating column 2 15, and a connecting seat 2 17 is fixedly installed on the other side of the connecting rod 2 16, a limiting rod 18 is arranged on the inside of the connecting sleeve 8, and a clamping groove 19 is provided on the outside of the limiting rod 18.
[0029] Specifically, mounting sleeves 2 are fixedly installed on the outer sides of the four sides of the standard section 1, and a fixing bolt 3 is arranged on the inner side of the mounting sleeve 2. The standard section 1, the mounting sleeve 2 and the fixing bolt 3 are in one-to-one correspondence, and the fixing bolt 3 at the connection between the two standard sections 1 passes through the two mounting sleeves 2. The advantage is that, through the design of the fixing bolt 3, the fixing bolt 3 at the bottom of the standard section 1 can be used to achieve fixed installation of the standard section 1 and the ground, and when connecting multiple standard sections 1, the fixing bolt 3 can be inserted into the mounting sleeve 2 to achieve connection between multiple standard sections 1.
[0030] Specifically, the cross-section of the fixing seat 5 is an "L"-shaped structure, and both sides of the fixing seat 5 are fixed to the standard section 1 by bolts. The advantage is that through the L-shaped structure of the fixing seat 5, multiple contact surfaces can be provided between the fixing seat 5 and the standard section 1, which can improve the stability between the fixing seat 5 and the standard section 1 and prevent them from shaking easily.
[0031] Specifically, the rotating column 11 is matched with the connecting rod 12, and the connecting seat 13 and the standard section 1 are fixedly installed. The advantage is that, through the cooperation between the rotating column 11 and the connecting rod 12, the angle between the connecting rod 12 and the profile 6 can be adjusted according to actual conditions to improve its stability, and the cooperation between the other end of the connecting seat 13 and the standard section 1 can enhance the stability between the two.
[0032] Embodiment 2: Figure 2-5 As shown, as an improvement to the previous embodiment.
[0033] Specifically, a mounting seat 7 is fixedly installed on the other side of the profile member 6 away from the fixing seat 5. The mounting seat 7 is fixedly installed on the wall 4 by bolts, and the connecting seat 2 17 is fixedly installed on the wall 4. The advantage is that the other end of the profile member 6 can be connected to the wall 4 through the cooperation between the mounting seat 7 and the wall 4. When it needs to be connected to the ground, the installation can be achieved by rotating the connecting seat 2 17 and then fixing it with bolts.
[0034] Specifically, the fixed seat 5, the profile 6, the fixed block 10, the rotating column 11, the connecting rod 12, the connecting seat 13, the fixed block 14, the rotating column 15, the connecting rod 16 and the connecting seat 17 are provided with the same multiple groups, and each group of the fixed seat 5, the profile 6, the fixed block 10, the rotating column 11, the connecting rod 12, the connecting seat 13, the fixed block 2 14, the rotating column 2 15, the connecting rod 2 16 and the connecting seat 2 17 are provided with the same two, and are symmetrically distributed about the center line of the standard section 1. The advantage is that through the design of multiple groups of fixed seats 5, profiles 6, fixed blocks 10, rotating columns 11, connecting rods 12, connecting seats 13, fixed blocks 2 14, rotating columns 2 15, connecting rods 2 16 and connecting seats 2 17, the stability of the overall standard section 1 can be improved, and the shaking of the standard section 1 with a higher top can be avoided.
[0035] Specifically, the slot 19 is adapted to the block 9, and the limit rod 18 connects the four connecting sleeves 8 and the block 9. The advantage is that, through the cooperation between the slot 19 and the block 9, when the limit rod 18 is installed, it can be inserted into the block 9 through the slot 19, and then the limit rod 18 can be connected to the two profiles 6, which can improve the stability between the two profiles 6 and avoid displacement.
[0036] Working principle: When in use, through the design of the fixing bolt 3, the fixing bolt 3 at the bottom of the standard section 1 can be used to fix the standard section 1 to the ground, and when connecting multiple standard sections 1, the fixing bolt 3 can be inserted into the installation sleeve 2 to achieve connection between multiple standard sections 1. Through the L-shaped structure of the fixing seat 5, it can be achieved that there are multiple contact surfaces between the fixing seat 5 and the standard section 1, which can improve the stability between the fixing seat 5 and the standard section 1 and avoid it from shaking easily. By rotating the column 11 and the connecting rod 12, the angle between the connecting rod 12 and the profile 6 can be adjusted according to actual conditions to improve its stability, and the other end of the connecting seat 13 can be matched with the standard section 1 to enhance the stability between the two. Through the mounting seat 7 and the wall 4, the other end of the profile 6 can be connected to the wall 4. When it needs to be connected to the ground, it can be installed by rotating the connecting seat 2 17 and then fixing it with bolts. Through the design of multiple groups of fixing seats 5, profiles 6, fixing blocks 10, rotating columns 11, connecting rods 12, connecting seats 13, fixing blocks 2 14, rotating columns 2 15, connecting rods 2 16 and connecting seats 2 17, the stability of the overall standard section 1 can be improved to avoid the shaking of the standard section 1 with a higher top. Through the cooperation of the slot 19 and the block 9, when installing the limit rod 18, the slot 19 can be inserted into the block 9, and then the limit rod 18 can be connected to the two profiles 6, which can improve the stability between the two profiles 6 and avoid displacement.
[0037] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A large-span attached wall structure for a construction hoist, comprising a standard section (1), a wall (4) and a fixing seat (5), characterized in that: A profile member (6) is fixedly mounted on the outside of the fixed seat (5), a connecting sleeve (8) is fixedly mounted on the inside of the profile member (6), a clamping block (9) is fixedly mounted inside the connecting sleeve (8), a fixing block (10) is fixedly mounted on the bottom of the profile member (6), a rotating column (11) is rotatably mounted on the outside of the fixing block (10), a connecting rod (12) is fixedly mounted on the outside of the rotating column (11), a connecting seat (13) is fixedly mounted on the other side of the connecting rod (12), a fixing block (14) is fixedly mounted on the bottom of the profile member (6), a rotating column (15) is rotatably mounted on the outside of the fixing block (14), a connecting rod (16) is fixedly mounted on the outside of the rotating column (15), a connecting seat (17) is fixedly mounted on the other side of the connecting rod (16), a limiting rod (18) is arranged on the inside of the connecting sleeve (8), and a clamping groove (19) is arranged on the outside of the limiting rod (18).
2. A large-span attached wall structure for a construction elevator according to claim 1, characterized in that: The outer sides of the four sides of the standard section (1) are fixedly mounted with mounting sleeves (2), and the inner sides of the mounting sleeves (2) are provided with fixing bolts (3). The standard section (1), the mounting sleeves (2) and the fixing bolts (3) are in one-to-one correspondence, and the fixing bolts (3) at the connection of the two standard sections (1) penetrate the two mounting sleeves (2).
3. The large-span attachment wall structure for a construction elevator according to claim 2 is characterized in that: The cross section of the fixing seat (5) is in an "L"-shaped structure, and both sides of the fixing seat (5) are fixedly mounted with the standard section (1) by means of bolts.
4. The large-span attachment wall structure for a construction elevator according to claim 3 is characterized in that: The rotating column 1 (11) is matched with the connecting rod 1 (12), and the connecting seat 1 (13) is fixedly installed with the standard section (1).
5. The large-span attachment wall structure for a construction elevator according to claim 4 is characterized in that: A mounting seat (7) is fixedly mounted on the other side of the profile member (6) away from the fixing seat (5); the mounting seat (7) is fixedly mounted on the wall (4) via bolts; and the second connecting seat (17) is fixedly mounted on the wall (4).
6. The large-span attachment wall structure for a construction elevator according to claim 5, characterized in that: The fixing seat (5), the profile (6), the fixing block (10), the rotating column (11), the connecting rod (12), the connecting seat (13), the fixing block (14), the rotating column (15), the connecting rod (16) and the connecting seat (17) are provided in a plurality of identical groups, and each group of the fixing seat (5), the profile (6), the fixing block (10), the rotating column (11), the connecting rod (12), the connecting seat (13), the fixing block (14), the rotating column (15), the connecting rod (16) and the connecting seat (17) are provided in two identical groups, and are symmetrically distributed about the center line of the standard section (1).
7. The large-span attachment wall structure for a construction elevator according to claim 6, characterized in that: The clamping groove (19) is matched with the clamping block (9), and the limiting rod (18) connects the four connecting sleeves (8) and the clamping block (9).
Citation Information
Patent Citations
Lengthening structure for long-distance attachment of construction hoist
CN219156224U