Flare tower foundation of frame structure
By adopting the torch tower foundation with a frame structure, the design of reinforced concrete frame structure and rigid joint nodes, the elevation of the torch tower foundation is adjusted, and the problem of torch tower foundation support in complex terrain and elevation difference undulating sites is solved, and the adaptability of torch tower elevation and optimization of plant planning is achieved.
Patent Information
- Application Number
- CN202421897116.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-07
- Publication Date
- 2025-06-03
- Estimated Expiration
- 2034-08-07
AI Technical Summary
The prior art is difficult to effectively support the foundation of the elevated torch tower in complex terrain and elevation fluctuations, resulting in the elevation of the torch tower that cannot meet the requirements of process layout.
The torch tower foundation with a frame structure is used to adjust the elevation of the torch tower foundation through the frame structure bracket, and the reinforced concrete frame structure and rigid joint node design are used to form a multi-layer frame beam and column structure to support the torch cylinder and tower column.
The height adjustment of the torch tower foundation is realized, adapting to complex terrain and undulating sites, improving the height of the torch foundation, meeting the requirements of process layout, and optimizing the factory planning and layout.
Smart Images

Figure CN222936024U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the field of petrochemical engineering, and particularly relates to a flare tower foundation with a frame structure. Background Art
[0002] An elevated flare is one of the iconic structures in petrochemical enterprises. It is a special facility in petrochemical plants for burning and treating waste gas and toxic gas. It usually consists of an automatic control system, an ignition system and a flare cylinder, which can make the flame burn at a high altitude far from the ground, thus protecting the personnel on the ground and the factory equipment. A flare tower is a common high-rise structure in petrochemical plants, which is used to support the flare cylinder and ensure its stability. Generally, a flare tower is composed of multiple flare tower columns. The flare tower not only has to support the weight of the flare cylinder, but also needs to bear the influence of natural actions such as wind load and earthquake. The foundation of the flare tower is the key part to ensure the stability and safety of the flare tower. At present, generally, the foundation of the flare tower is set at the ground level, and the common foundation forms include: reinforced concrete independent foundation, pile raft foundation, etc. The corresponding design ideas and construction schemes are relatively simple and conventional.
[0003] In order to strictly control the building safety distance and improve the site utilization rate in the plant layout of petrochemical enterprises, the exhaust stack and the elevated flare are usually arranged in a position far from the core area or in a marginal area that is difficult to utilize. The common foundation forms (such as reinforced concrete independent foundation, pile raft foundation, etc.) are all large monolithic concrete foundations, and the ground height at the foundation is usually within 1m. The application scenario is limited to setting the foundation elevation of the flare tower at the ground elevation. When the construction site has complex terrain and large height differences, the conventional foundation forms cannot meet the actual use requirements according to local conditions. Summary of the Utility Model
[0004] Aiming at the problems existing in the prior art, the utility model provides a flare tower foundation with a frame structure, which uses a frame structure support to adjust the elevation of the flare tower foundation, so as to break through the terrain limitation in the process layout and reasonably optimize the plant layout.
[0005] The technical scheme adopted by the utility model is as follows:
[0006] A flare tower foundation with a frame structure, which includes a frame structure support and a flare foundation arranged on the top of the frame structure support. The frame structure support includes a plurality of frame columns and frame beams for connecting the frame columns. The flare foundation includes a flare cylinder foundation for supporting the flare cylinder and a plurality of flare tower column foundations for supporting the flare tower columns and surrounding the flare cylinder foundation. The flare cylinder foundation and the flare tower column foundations are both formed by extending upward from the top ends of the corresponding frame columns.
[0007] Furthermore, the frame structure support is a reinforced concrete frame structure, and the nodes between the frame columns and the frame beams are all rigidly connected.
[0008] Furthermore, the frame columns include a first frame column arranged below the flare barrel foundation and a second frame column arranged below the flare tower column foundation. The number of the second frame columns is 3 or 4, and the plurality of second frame columns are distributed in a regular polygon. The second frame columns are arranged at the corners of the regular polygon, and the first frame column is arranged at the centroid of the regular polygon formed by the second frame columns. The top end of the first frame column extends upward to form the flare barrel foundation, and the top end of the second frame column extends upward to form the flare tower column foundation. The height of the extension of the top end of the first frame column and the second frame column meets the anchorage requirement for the longitudinal reinforcement of the column.
[0009] Furthermore, third frame columns are arranged on both sides of one of the second frame columns, the positions of the two third frame columns correspond to the positions of the other two second frame columns respectively, and the third frame columns and the corresponding second frame columns form a rectangle.
[0010] Furthermore, the frame beam includes a first frame beam and a second frame beam, the first frame beam is connected between the second frame column and the first frame column, the second frame beam is connected between the second frame columns or between the second frame column and the third frame column, the frame beam is generally multi-layered, such as 2, 3 or 4 layers, and is arranged in sequence in the vertical direction, the second frame beam of each layer connects the second frame columns at a certain height, the first frame beam of each layer is radially connected between the second frame column and the first frame column at a certain height, the second frame beam of the top layer connects the top of each second frame column, and the first frame beam of the top layer is connected between the top of the second frame column and the top of the first frame column.
[0011] Furthermore, secondary beams or floor slabs for arranging the foundation of the torch auxiliary equipment are connected between the second frame beams at the top layer.
[0012] Furthermore, the cross-sectional area of the flare tower column foundation is larger than the cross-sectional area of the second frame column, so that the flare tower column foundation meets the structural requirements of the flare tower column foot, and a first shear groove is reserved at the top of the flare tower column foundation for inserting the flare tower column foot. After the flare tower column foot is installed in the first shear groove, secondary grouting is performed to form a secondary grouting layer after the grouting is completed.
[0013] Furthermore, a plurality of first anchor bolts are pre-embedded inside the flare tower column foundation outside the first shear groove, and the plurality of first anchor bolts are evenly distributed around the circumference of the first shear groove. The number of the first anchor bolts may be, for example, 4 to 8, preferably 6. The top of the first anchor bolt extends out of the flare tower column foundation, and the first anchor bolt is used to connect to the flare tower column.
[0014] Furthermore, the cross-sectional area of the torch cylinder foundation is larger than that of the first frame column. A second shear groove for inserting the torch cylinder is reserved at the top of the torch cylinder foundation. After the torch cylinder is installed in the second shear groove, secondary grouting is carried out, and a secondary grouting layer is formed after the grouting is completed.
[0015] Furthermore, a plurality of second anchor bolts are embedded inside the torch cylinder foundation outside the second shear groove. The plurality of second anchor bolts are evenly distributed around the circumference of the second shear groove. The number of the second anchor bolts can be, for example, 10 - 15, preferably 12. The tops of the second anchor bolts protrude from the torch cylinder foundation, and the second anchor bolts are used to connect with the torch cylinder.
[0016] Furthermore, the frame structure support is provided with a staircase for workers to go up and down, and a landing is provided between the staircases.
[0017] Advantages of the present utility model:
[0018] For the torch tower rack foundation with a frame structure provided by the present utility model, the torch foundation is arranged on the frame structure support, the torch tower rack and the torch cylinder are arranged on the torch foundation, and the height of the frame structure support determines the elevation of the torch tower rack. Therefore, the foundation height of the torch tower rack is determined according to the process requirements and is not restricted by the height of the natural terrain, thus adapting to complex terrains and large height differences. After construction, the top of the column of the frame structure is the top of the torch foundation, and the height of the torch foundation is the height of the lower frame structure support. Therefore, the foundation height is greatly increased. The torch tower rack foundation with a frame structure of the present utility model provides a new idea and solution for optimizing the plant layout and solving practical engineering problems. Description of the Drawings
[0019] Figure 1 It is an elevation view of a torch tower rack foundation with a frame structure of the present utility model.
[0020] Figure 2 It is a distribution diagram of frame columns and frame beams.
[0021] Figure 3 It is a top view of the torch tower column foundation.
[0022] Figure 4 It is a cross-sectional view of the torch tower column foundation.
[0023] Figure 5 It is a top view of the torch cylinder foundation.
[0024] Figure 6 It is a cross-sectional view of the torch cylinder foundation.
[0025] Reference Signs:
[0026] 1 - Frame structure support, 101 - Frame column, 1011 - First frame column, 1012 - Second frame column, 1013 - Third frame column, 102 - Frame beam, 1021 - First frame beam, 1022 - Second frame beam,
[0027] 2 - Torch foundation, 201 - Torch barrel foundation, 202 - Torch tower column foundation,
[0028] 3 - Torch barrel, 4 - Torch tower column, 5 - Secondary beam, 6 - Floor slab, 7 - First shear groove, 8 - Secondary grouting layer, 9 - First anchor bolt, 10 - Second shear groove, 11 - Second anchor bolt, 12 - Stairs, 13 - Torch auxiliary equipment foundation, 14 - Slope protection, 15 - Factory road, 16 - Torch tower. Specific implementation mode
[0029] The present utility model will be further described below in conjunction with the drawings and embodiments.
[0030] As Figures 1-6 shown, a torch tower foundation of a frame structure includes a frame structure support 1 and a torch foundation 2 provided on the top of the frame structure support 1. The frame structure support 1 includes a plurality of frame columns 101 and frame beams 102 for connecting the frame columns 101. The torch foundation 2 includes a torch barrel foundation 201 for supporting the torch barrel 3 and a plurality of torch tower column foundations 202 for supporting the torch tower column 4 and surrounding the torch barrel foundation 201. The torch barrel foundation 201 and the torch tower column foundations 202 are both formed by extending upward from the top ends of the corresponding frame columns 101.
[0031] In an embodiment, the frame structure support 1 is a reinforced concrete frame structure, and the joints of the frame columns 101 and the frame beams 102 all adopt a rigid connection method. The frame columns 101 are of reinforced concrete structure, and the column section sizes of the frame columns 101 should meet both the structural calculation and seismic design requirements. Initially, a trial calculation can be carried out according to 1 / 15 of the storey height. The foundation form and foundation treatment method of the frame structure are determined according to the actual situation of the site, and natural foundation, pile foundation or rock anchor can be adopted. The frame beams 102 are also of reinforced concrete structure, and the section sizes should meet both the structural calculation and seismic design requirements. Initially, the general beam height can be taken as 1 / 10 of the span for trial calculation.
[0032] In another embodiment, the frame column 101 includes a first frame column 1011 disposed below the flare column foundation 201 and a second frame column 1012 disposed below the flare tower column foundation 202. There are 3 or 4 second frame columns 1012, and the multiple second frame columns 1012 are distributed in a regular polygon. The second frame columns 1012 are disposed at the corners of the regular polygon, and the first frame column 1011 is disposed at the centroid of the regular polygon formed by the second frame columns 1012. The top end of the first frame column 1011 extends upward to form the flare column foundation 201, and the top end of the second frame column 1012 extends upward to form the flare tower column foundation 202. The upward extension height of the top ends of the first frame column 1011 and the second frame column 1012 satisfies the anchorage of the longitudinal steel bars of the columns.
[0033] In yet another embodiment, third frame columns 1013 are disposed on both sides of one of the second frame columns 1012, and the positions of the two third frame columns 1013 correspond to the positions of the other two second frame columns 1012 respectively. The third frame column 1013 and the corresponding second frame column 1012 form a rectangle.
[0034] In yet another embodiment, the frame beam 102 includes a first frame beam 1021 and a second frame beam 1022. The first frame beam 1021 is connected between the second frame column 1012 and the first frame column 1011, and the second frame beam 1022 is connected between the second frame columns 1012 or between the second frame column 1012 and the third frame column 1013. The frame beam 102 is generally multi-layered, such as 2, 3 or 4 layers, and is arranged at intervals in the vertical direction. The height of the first layer of the frame beam 102 from the ground (the bottom of the first frame column 1011 or the second frame column 1012) (or the height of each layer) can be flexibly allocated as needed. Considering the overall economy, it is advisable to take 4 - 6 meters. The second frame beam 1022 of each layer connects the second frame columns 1012 at a certain height, and the first frame beam 1021 of each layer is connected between the second frame column 1012 and the first frame column 1011 at a certain height. The second frame beam 1022 of the top layer connects the tops of the frame columns 101, and the first frame beam 1021 of the top layer is connected between the top of the second frame column 1012 and the top of the first frame column 1011.
[0035] In yet another embodiment, secondary beams 5 or floor slabs 6 for arranging the flare accessory equipment foundation 13 are connected between the second frame beams 1022 of the topmost layer.
[0036] In another embodiment, the cross-sectional area of the flare tower column foundation 202 is greater than the cross-sectional area of the second frame column 1012, so that the flare tower column foundation 202 meets the structural requirements of the column foot of the flare tower column 4, and a first shear groove 7 is reserved at the top of the flare tower column foundation 202 for inserting the column foot of the flare tower column 4. After the column foot of the flare tower column 4 is installed in the first shear groove 7, secondary grouting is performed, and the secondary grouting layer 8 is formed after the grouting is completed.
[0037] In another embodiment, a plurality of first anchor bolts 9 are pre-embedded inside the flare tower column foundation 202 outside the first shear groove 7, and the plurality of first anchor bolts 9 are evenly distributed around the circumference of the first shear groove 7. The number of the first anchor bolts 9 may be, for example, 4 to 8, preferably 6. The top of the first anchor bolt 9 extends out of the flare tower column foundation 202, and the first anchor bolt 9 is used to connect to the flare tower column 4.
[0038] In another embodiment, the cross-sectional area of the flare barrel foundation 201 is larger than the cross-sectional area of the first frame column 1011, and a second shear groove 10 for inserting the flare barrel 3 is reserved at the top of the flare barrel foundation 201. After the flare barrel 3 is installed in the second shear groove 10, secondary grouting is performed to form a secondary grouting layer 8.
[0039] In another embodiment, a plurality of second anchor bolts 11 are pre-embedded inside the flare barrel foundation 201 outside the second shear groove 10, and the plurality of second anchor bolts 11 are evenly distributed around the circumference of the second shear groove 10. The number of the second anchor bolts 11 may be, for example, 10-15, preferably 12, and the top of the second anchor bolt 11 extends out of the flare barrel foundation 201, and the second anchor bolt 11 is used to connect to the flare barrel 3.
[0040] In yet another embodiment, the frame structure support 1 is provided with stairs 12 for workers to go up and down, and a stair rest platform is provided between the stairs 12 .
[0041] The first frame beam 1021 at the top of the frame column 101 and the topmost layer, the second frame beam 1022 and the secondary beam 5 or the floor slab 6 form a platform for supporting the flare tower column 4, the flare barrel 3 and its ancillary equipment. The height of the entire frame structure support 1 is preferably determined according to the process layout requirements, and the plane size is determined according to the equipment layout range. The top of the frame structure support 1 is arranged with a torch foundation 2 and a matching torch ancillary equipment foundation 13. The torch foundation 2 is arranged at the top of the frame column 101, and other torch ancillary equipment foundations 13 are arranged on the secondary beam 5 or the floor slab 6.
[0042] The top of the frame column of the frame structure support 1 is the top of the torch foundation, and the height of the torch foundation 2 is the height of the lower frame structure support 1, so the height of the torch foundation 2 can be greatly improved. Example 1
[0043] likeFigure 1 As shown in the figure, a flare tower 16 is arranged in a low-lying area. If a conventional reinforced concrete independent foundation or a pile foundation raft foundation is directly constructed on the bottom surface of the pit, the elevation of the flare tower 16 cannot meet the requirements of the process layout. By using the flare tower foundation with a frame structure of the present utility model, the elevation of the flare tower 16 is determined by the height of the frame structure support 1. The top of the frame column of the frame structure support 1 is the top of the flare foundation. The height of the flare foundation 2 is the height of the lower frame structure support 1. By increasing the height of the flare foundation 2, the elevation of the flare tower 16 is not restricted by the natural terrain of the site. The specific implementation plan is as follows:
[0044] As Figures 1-6 As shown in the figure, a flare tower foundation with a frame structure includes a frame structure support 1 and a flare foundation 2 arranged on the top of the frame structure support 1. The frame structure support 1 includes a plurality of frame columns 101 and frame beams 102 for connecting the frame columns 101. The flare foundation 2 includes a flare cylinder foundation 201 for supporting the flare cylinder 3 and a plurality of flare tower column foundations 202 for supporting the flare tower column 4 and surrounding the flare cylinder foundation 201. The flare cylinder foundation 201 and the flare tower column foundations 202 are both formed by extending upward from the top ends of the corresponding frame columns 101.
[0045] The frame structure support 1 is a reinforced concrete frame structure. The joints of the frame columns 101 and the frame beams 102 all adopt a rigid connection method. The frame columns 101 and the frame beams 102 are of reinforced concrete structure. The cross-sectional dimensions of the frame columns 101 are calculated by trial according to 1 / 15 of the storey height. The foundation form and foundation treatment method of the frame structure adopt pile foundations. The initial beam height of the frame beams 102 is calculated by trial taking 1 / 10 of the span.
[0046] The frame columns 101 include a first frame column 1011 arranged below the flare cylinder foundation 201 and a second frame column 1012 arranged below the flare tower column foundations 202. There are 3 second frame columns 1012, and the 3 second frame columns 1012 are distributed in an equilateral triangle. The second frame columns 1012 are arranged at the corners of the equilateral triangle. The first frame column 1011 is arranged at the centroid of the equilateral triangle formed by the second frame columns 1012. The top end of the first frame column 1011 extends upward to form the flare cylinder foundation 201. The top ends of the second frame columns 1012 extend upward to form the flare tower column foundations 202. The upward extension heights of the top ends of the first frame column 1011 and the second frame columns 1012 meet the anchorage requirements of the longitudinal steel bars of the columns.
[0047] Third frame columns 1013 are arranged on both sides of one of the second frame columns 1012. The positions of the two third frame columns 1013 correspond to the positions of the other two second frame columns 1012 respectively. The third frame columns 1013 and the corresponding second frame columns 1012 form a rectangle.
[0048] The frame beam 102 includes a first frame beam 1021 and a second frame beam 1022. The first frame beam 1021 is radially connected between the second frame column 1012 and the first frame column 1011. The second frame beam 1022 is connected between the second frame columns 1012 or between the second frame column 1012 and the third frame column 1013. The frame beam 102 has three layers and is arranged at intervals in the vertical direction, with each interval being 5 meters.
[0049] Between the second frame beams 1022 on the topmost layer, there are secondary beams 5 or floor slabs 6 for arranging the foundation 13 of the torch auxiliary equipment.
[0050] The cross-sectional area of the torch tower column foundation 202 is larger than that of the second frame column 1012, so that the torch tower column foundation 202 meets the structural requirements of the column feet of the torch tower column 4. A first shear key groove 7 for inserting the column foot of the torch tower column 4 is reserved at the top of the torch tower column foundation 202. After the column foot of the torch tower column 4 is installed in the first shear key groove 7, secondary grouting is carried out, and after the grouting is completed, a secondary grouting layer 8 is formed.
[0051] Six first anchor bolts 9 are embedded inside the torch tower column foundation 202 around the first shear key groove 7. The multiple first anchor bolts 9 are evenly distributed circumferentially around the first shear key groove 7. The top of the first anchor bolt 9 extends out of the torch tower column foundation 202, and the first anchor bolt 9 is used to connect with the torch tower column 4.
[0052] The cross-sectional area of the torch barrel foundation 201 is larger than that of the first frame column 1011. A second shear key groove 10 for inserting the torch barrel 3 is reserved at the top of the torch barrel foundation 201. After the torch barrel 3 is installed in the second shear key groove 10, secondary grouting is carried out, and after the grouting is completed, a secondary grouting layer 8 is formed.
[0053] Twelve second anchor bolts 11 are embedded inside the torch barrel foundation 201 around the second shear key groove 10. The multiple second anchor bolts 11 are evenly distributed circumferentially around the second shear key groove 10. The top of the second anchor bolt 11 extends out of the torch barrel foundation 201, and the second anchor bolt 11 is used to connect with the torch barrel 3.
[0054] The frame structure support 1 is provided with a staircase 12 for workers to go up and down, and there is a staircase landing between the staircases 12.
[0055] The torch tower rack foundation of the frame structure in this embodiment is designed according to relevant structural specifications, the designed finished product passes the engineering review, and the actual engineering project is in good condition after being put into use, indicating the feasibility of using the frame structure as the foundation for the elevated torch tower rack and its related auxiliary facilities.
[0056] The preferred embodiments of the present utility model have been described above. However, the above description is not for the purpose of limitation. Those of ordinary skill in the art can make many changes or modifications to the present utility model without departing from the gist and scope of the present utility model. Such changes or modifications should be included within the scope of the appended claims.
Claims
1. A flare stack foundation of a frame structure, characterized in that: The invention comprises a frame structure support (1), a flare foundation (2) arranged on the top of the frame structure support (1), the frame structure support (1) comprising a plurality of frame columns (101), and a frame beam (102) for connecting the frame columns (101), the flare foundation (2) comprising a flare barrel foundation (201) for supporting a flare barrel (3) and a plurality of flare tower column foundations (202) for supporting a flare tower column (4) and surrounding the flare barrel foundation (201), the flare barrel foundation (201) and the flare tower column foundation (202) both being formed by extending upward from the top of the frame columns (101) at corresponding positions.
2. The flare stack foundation according to claim 1, characterized in that: The frame structure support (1) is a reinforced concrete frame structure, and the nodes between the frame columns (101) and the frame beams (102) are all rigidly connected.
3. The flare stack foundation according to claim 1 or 2, characterized in that: The frame column (101) includes a first frame column (1011) arranged below the flare barrel foundation (201) and a second frame column (1012) arranged below the flare tower column foundation (202). The number of the second frame columns (1012) is 3 or 4, and the plurality of second frame columns (1012) are distributed in the form of a regular polygon. The second frame columns (1012) are arranged at the corners of the regular polygon. The first frame column (1011) is arranged at the centroid of the regular polygon formed by the second frame columns (1012). The top end of the first frame column (1011) extends upward to form the flare barrel foundation (201), and the top end of the second frame column (1012) extends upward to form the flare tower column foundation (202).
4. The flare stack foundation according to claim 3, characterized in that: A third frame column (1013) is arranged on both sides of one of the second frame columns (1012), and the positions of the two third frame columns (1013) respectively correspond to the positions of the other two second frame columns (1012), and the third frame column (1013) and the corresponding second frame column (1012) form a rectangle.
5. The flare stack foundation according to claim 4, characterized in that: The frame beam (102) comprises a first frame beam (1021) and a second frame beam (1022), wherein the first frame beam (1021) is radially connected between the second frame column (1012) and the first frame column (1011), and the second frame beam (1022) is connected between the second frame columns (1012) or between the second frame column (1012) and the third frame column (1013), and the frame beams (102) are arranged in sequence and spaced apart in the vertical direction.
6. The flare stack foundation according to claim 5, characterized in that: A secondary beam (5) or floor slab (6) for arranging the foundation (13) of the torch auxiliary equipment is connected between the second frame beams (1022) at the top layer.
7. The flare stack foundation according to claim 1, characterized in that: The cross-sectional area of the flare tower column foundation (202) is larger than the cross-sectional area of the second frame column (1012), and a first shear-resistant groove (7) is reserved at the top of the flare tower column foundation (202) for inserting the column foot of the flare tower column (4).
8. The flare stack foundation according to claim 7, characterized in that: A plurality of first anchor bolts (9) are pre-buried inside the flare tower column foundation (202) outside the first shear-resistant groove (7). The plurality of first anchor bolts (9) are evenly distributed around the circumference of the first shear-resistant groove (7). There are 4 to 8 first anchor bolts (9). The top of the first anchor bolt (9) extends out of the flare tower column foundation (202). The first anchor bolt (9) is used to connect to the flare tower column (4).
9. The flare stack foundation according to claim 1, characterized in that: The cross-sectional area of the flare barrel foundation (201) is larger than the cross-sectional area of the first frame column (1011), and a second shear-resistant groove (10) for inserting the flare barrel (3) is reserved at the top of the flare barrel foundation (201).
10. The flare stack foundation according to claim 9, characterized in that: A plurality of second anchor bolts (11) are pre-buried inside the flare barrel foundation (201) outside the second shear groove (10). The plurality of second anchor bolts (11) are evenly distributed around the circumference of the second shear groove (10). There are 10 to 15 second anchor bolts (11). The top of the second anchor bolt (11) extends out of the flare barrel foundation (201). The second anchor bolt (11) is used to connect to the flare barrel (3).