Uneven load energy storage container hoisting tool
By designing a lifting fixture for energy storage containers under uneven loads, and utilizing a combination structure of main lifting rods, auxiliary lifting rods, and support lifting rods, the problems of tilting and rope breakage during the lifting of energy storage containers were solved, achieving stability and safety in the lifting process.
Patent Information
- Application Number
- CN202522503540.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-11-26
- Publication Date
- 2026-11-03
- Estimated Expiration
- 2035-11-26
AI Technical Summary
In existing technologies, the feasibility and convenience of equipment installation and maintenance are often compromised when hoisting energy storage containers. Asymmetrical layouts are frequently used, which can lead to tilting or rope breakage during hoisting.
Design a lifting fixture for uneven load energy storage containers, including a main lifting boom, an auxiliary lifting boom, and a support lifting boom. By combining adjustment holes, shackles, and wire ropes, the lifting points can be flexibly adjusted to adapt to lifting frames of different weights, ensuring stable lifting.
It achieves stability and safety during hoisting under uneven loads, avoids slippage of the hoisting frame and breakage of the hoisting ropes, and has a simple structure and strong versatility.
Smart Images

Figure CN224930144U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of logistics and transportation technology, specifically to a hoisting fixture for an energy storage container with uneven load. Background Technology
[0002] Through a containerized "kit" design, energy storage systems can be pre-packaged and transported, requiring only overall hoisting for deployment on-site. This modular approach significantly reduces on-site construction chaos and shortens mechanical completion time.
[0003] When designing the layout of energy storage containers for various systems, the feasibility and convenience of equipment installation and maintenance are often considered. This often results in an asymmetrical layout relative to the container itself, meaning the center of the energy storage container is not on the longitudinal centerline. If the lifting points are arranged according to experience, the container may tilt during crane lifting. Firstly, severe tilting can cause battery packs or other electrical equipment to slip off. Secondly, uneven stress on the lifting ropes can lead to breakage. Therefore, we propose a lifting fixture for energy storage containers with uneven loads. Utility Model Content
[0004] To address the problems in the existing technology, this utility model provides a lifting fixture for non-uniform load energy storage containers.
[0005] The technical solution adopted by this utility model to solve its technical problem is a lifting tool for an uneven load energy storage container, including a main lifting rod. The top and bottom ends of the main lifting rod are integrally constructed with adjustment holes. Both sides of the main lifting rod are fixedly connected to main splicing flanges. The holes of the adjustment holes are fastened with shackles, and steel wire ropes are assembled inside the rings of the shackles.
[0006] By adopting the above technical solution, during hoisting, the position of the adjustment hole at the bottom of the main hoisting rod is adjusted according to the different weights of the hoisting frame, so that the center of gravity of the hoisting frame can be found quickly and the hoisting operation can be carried out. The overall structure is simple, highly versatile, and widely applicable.
[0007] Specifically, the main lifting rod is connected to the secondary splicing flange by a main splicing flange, the secondary splicing flange is fixedly connected to both ends of the secondary lifting rod, and the top and bottom ends of the secondary lifting rod are integrally constructed with the same adjustment holes as the top and bottom ends of the main lifting rod.
[0008] By adopting the above technical solution, the main splicing flanges on both sides of the main lifting rod are aligned with and screwed together with the secondary splicing flanges on the side wall of the secondary lifting rod to form a splicing lifting rod. This allows for lifting operations to be carried out with the help of shackles and wire ropes, and can flexibly handle lifting frames of different weights.
[0009] Specifically, the bottom ends of the main lifting rod and the auxiliary lifting rod are equipped with lifting supports via adjustment holes, shackles, and wire ropes.
[0010] By adopting the above technical solution, the lifting rod is supported by shackles and wire ropes and suspended below the main lifting rod and auxiliary lifting rod, thereby achieving a combined lifting structure. By combining the corresponding lifting frames to adjust the position of the shackles, it can adapt to various lifting environments. The structure is simple and highly versatile.
[0011] Specifically, the main lifting rod, auxiliary lifting rod, and support lifting rod are equipped with a lifting frame through multiple adjustment holes, shackles, and wire ropes.
[0012] By adopting the above technical solution, a lifting structure consisting of a main lifting rod, an auxiliary lifting rod, and a support lifting rod is used in conjunction with lifting equipment to lift a container carrying multiple energy storage containers with different gravity.
[0013] Compared with the prior art, the present invention has the following beneficial effects:
[0014] 1. The center of gravity of the lifting frame can be determined by the digital model of the energy storage container. The force on the two longitudinal beams can be determined by the balance of force and torque and the center position of each piece of equipment. The lifting points can be finely adjusted according to the obtained force to ensure that the lifting is stable and reliable.
[0015] 2. It can be used alone or in combination to adapt to various hoisting environments. It has a simple structure and strong versatility. Attached Figure Description
[0016] The present invention will be further described below with reference to the accompanying drawings and embodiments.
[0017] Figure 1 This is an isometric view of the present invention;
[0018] Figure 2 This is a schematic diagram of the connection structure at the main hoisting rod of this utility model;
[0019] Figure 3 This is a schematic diagram of the combined structure of the main lifting rod, auxiliary lifting rod, and support lifting rod of this utility model;
[0020] In the diagram: 1. Main lifting rod; 2. Adjustment hole; 3. Main splicing flange; 4. Shackle; 5. Wire rope; 6. Secondary splicing flange; 7. Secondary lifting rod; 8. Support lifting rod; 9. Lifting frame. Detailed Implementation
[0021] To make the technical means, creative features, objectives and effects of this utility model easier to understand, the present utility model will be further described below in conjunction with specific embodiments.
[0022] Please see Figure 1-3This utility model provides a technical solution: a lifting fixture for an uneven load energy storage container, including a main lifting rod 1. The top and bottom ends of the main lifting rod 1 are integrally constructed with adjustment holes 2. The two sides of the main lifting rod 1 are fixedly connected with main splicing flanges 3. The holes of the adjustment holes 2 are fastened with shackles 4, and the rings of the shackles 4 are fitted with wire ropes 5.
[0023] During use, when hoisting, the position of the shackle 4 fastened to the adjustment hole 2 at the bottom of the main hoisting rod 1 is adjusted according to the different weights of the hoisting frame 9, so that the center of gravity of the hoisting frame 9 can be quickly found and the hoisting operation can be carried out. The overall structure is simple, highly versatile, and widely applicable.
[0024] like Figure 3 As shown, the main lifting rod 1 is connected to the auxiliary splicing flange 6 by the main splicing flange 3. The auxiliary splicing flange 6 is fixedly connected to both ends of the auxiliary lifting rod 7, and the top and bottom ends of the auxiliary lifting rod 7 are integrally constructed with the same adjustment holes 2 as the top and bottom ends of the main lifting rod 1.
[0025] In use, by aligning and screwing the main splicing flanges 3 on both sides of the main lifting rod 1 with the secondary splicing flanges 6 on the side wall of the secondary lifting rod 7, a splicing lifting rod is formed. With the cooperation of the shackles 4 and the wire ropes 5, the lifting operation can be carried out, which can flexibly cope with the lifting frame 9 of different weights.
[0026] like Figure 3 As shown, the bottom ends of the main lifting rod 1 and the auxiliary lifting rod 7 are equipped with a support lifting rod 8 through the adjustment hole 2, shackle 4 and wire rope 5.
[0027] In use, the lifting rod 8 is supported by the shackle 4 and the wire rope 5 and is suspended below the supporting lifting rod 8 and the auxiliary lifting rod 7, thereby achieving a combined lifting structure. The position of the shackle 4 can be adjusted by combining the corresponding lifting frame 9 to adapt to various lifting environments.
[0028] like Figure 3 As shown, the main lifting rod 1, the auxiliary lifting rod 7, and the support lifting rod 8 are equipped with a lifting frame 9 through multiple adjustment holes 2, shackles 4, and wire ropes 5.
[0029] In use, the lifting structure consisting of the main lifting rod 1, the auxiliary lifting rod 7 and the support lifting rod 8 is used in conjunction with the lifting equipment to lift the container containing multiple energy storage containers with different gravity.
[0030] The working principle and usage process of this utility model are as follows: During hoisting, the position of the shackle 4 fastened to the adjustment hole 2 at the bottom of the main hoisting rod 1 is adjusted according to the different weights of the hoisting frame 9, so that the center of gravity of the hoisting frame 9 can be quickly found and hoisting operations can be carried out. The overall structure is simple, highly versatile, and widely applicable. By aligning and screwing the main splicing flange 3 on both sides of the main hoisting rod 1 with the secondary splicing flange 6 on the side wall of the secondary hoisting rod 7, a splicing hoisting rod is formed. Hoisting operations are carried out with the cooperation of the shackle 4 and the wire rope 5. It can flexibly cope with hoisting frames 9 of different weights. The hoisting rod 8 is supported by the shackle 4 and the wire rope 5 and hoisted below the support hoisting rod 8 and the secondary hoisting rod 7, thereby achieving a combined hoisting structure. By adjusting the position of the shackle 4 according to the corresponding hoisting frame 9, it can adapt to various hoisting environments. The structure is simple and highly versatile.
[0031] The foregoing has shown and described the basic principles, main features, and advantages of this utility model. Those skilled in the art should understand that this utility model is not limited to the above embodiments. The descriptions of the above embodiments and specifications are merely illustrative of the principles of this utility model. Various changes and modifications can be made to this utility model without departing from its spirit and scope, and all such changes and modifications fall within the scope of protection claimed by this utility model. The scope of protection of this utility model is defined by the appended claims and their equivalents.
Claims
1. A lifting fixture for an energy storage container under non-uniform load, characterized in that, Includes a main lifting rod (1), the top and bottom of the main lifting rod (1) are integrally constructed with adjustment holes (2), the two sides of the main lifting rod (1) are fixedly connected with main splicing flanges (3), the holes of the adjustment holes (2) are fastened with shackles (4), and the rings of the shackles (4) are fitted with wire ropes (5).
2. The non-uniform load energy storage container lifting fixture according to claim 1, characterized in that, The main lifting rod (1) is connected to the secondary splicing flange (6) by the main splicing flange (3). The secondary splicing flange (6) is fixedly connected to both ends of the secondary lifting rod (7). The top and bottom ends of the secondary lifting rod (7) are integrally constructed with the same adjustment holes (2) as the top and bottom ends of the main lifting rod (1).
3. The non-uniform load energy storage container lifting fixture according to claim 1, characterized in that, The bottom ends of the main lifting rod (1) and the auxiliary lifting rod (7) are equipped with a support lifting rod (8) through the adjustment hole (2), shackle (4) and wire rope (5).
4. The non-uniform load energy storage container lifting fixture according to claim 3, characterized in that, The main lifting rod (1), the auxiliary lifting rod (7) and the support lifting rod (8) are equipped with a lifting frame (9) through multiple adjustment holes (2), shackles (4) and wire ropes (5).