A kind of auxiliary hoisting device for breaking and blocking arch rib for bridge demolition
By designing an auxiliary hoisting device with clamping structure, abutment component, and adjustment component, the problems of slippage and unstable posture during the hoisting of irregular arch ribs were solved, achieving safe and efficient arch rib hoisting and improving the reliability of bridge demolition operations.
Patent Information
- Application Number
- CN202522762312.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-12-26
- Publication Date
- 2026-11-10
- Estimated Expiration
- 2035-12-26
AI Technical Summary
In the existing technology, general-purpose clamps are difficult to stably hold irregular broken arch ribs, which can lead to slippage, center of gravity shift and unstable posture during hoisting, posing safety hazards.
An auxiliary hoisting device was designed, comprising a clamping structure, an abutment component, and an adjustment component. The clamping component provides multi-point rigid clamping, the abutment component applies a jacking force, and the adjustment component adjusts the posture, thereby achieving stable hoisting of irregular arch ribs.
It effectively prevents the arch ribs from slipping, stabilizes the posture of the components, improves the safety and efficiency of hoisting, adapts to the hoisting of broken arch ribs of various shapes, and enhances the reliability of bridge demolition operations.
Smart Images

Figure CN224954217U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of bridge dismantling technology, and in particular to an auxiliary hoisting device for breaking and segmenting arch ribs for bridge dismantling. Background Technology
[0002] In bridge demolition projects, especially for arch bridges, it is often necessary to break up and remove large arch rib structures in sections. These sections of arch rib are often huge, heavy, and irregular in shape, with uneven fracture surfaces, which poses a significant challenge to safe and efficient hoisting operations.
[0003] Currently, during bridge dismantling, a full-span scaffold is first erected to provide basic support for the arch ribs. Workers then break the arch ribs on the scaffold. Before the breaking process, a hoisting structure is used to connect the segmented arch ribs. After breaking, the segmented arch ribs are lifted away using the hoisting structure. This type of hoisting of segmented arch ribs often uses general-purpose clamps for direct gripping. However, general-purpose clamps have several limitations: First, their design is usually based on clamping flat or regular workpieces. The clamping surface for segmented arch ribs is often a broken, curved or inclined concrete surface, and the clamp jaws can only hold the two end faces of the segmented arch rib. Slippage is highly likely during lifting or dynamic movement. The rigid structure of the clamp itself cannot adapt to the irregular protrusions or depressions of the arch rib, resulting in extremely poor stability. Second, general-purpose clamps only provide unidirectional or bidirectional clamping force; their function is limited to "gripping" and they cannot actively adjust or stabilize the spatial posture of the component. When the segmented arch ribs are lifted off the support, their center of gravity may shift. The general-purpose clamps cannot provide lateral support or jacking force to correct and stabilize the posture of the components, which can easily cause the components to rotate and sway in the air, colliding with adjacent structures or hoisting equipment, making the operation highly dangerous. Utility Model Content
[0004] In view of the technical problems existing in the background art, the utility model provides an auxiliary hoisting device for breaking and segmenting arch ribs for bridge demolition, so as to solve the above-mentioned problems.
[0005] To achieve the above objectives, the technical solution provided by this utility model is as follows: An auxiliary hoisting device for breaking segmented arch ribs for bridge demolition includes an abutment component, an adjustment component, and a clamping structure on both sides that can move closer to or further away from each other. The segmented arch ribs are clamped by the clamping structure. The abutment component includes an abutment rod, which is located at the middle of the clamping structure. The abutment rod can move toward the segmented arch ribs, and its outer end face abuts against the segmented arch ribs. The adjustment component includes several adjustment plates, which are rotatably connected to the outside of the clamping structure. The adjustment plates have an L-shaped structure and are rotatable, with one end connected to the lower end of the segmented arch ribs.
[0006] Preferably, the clamping structure includes a guide rail and two gripper assemblies, the gripper assemblies being disposed in the middle of the guide rail and capable of sliding along the direction of the guide rail.
[0007] Preferably, the gripper assembly includes a connecting rod, a slider, and several gripper plates. Adjacent gripper plates are connected by a connecting rod, and the slider is fixedly disposed at the upper end of the connecting rod and connected to a guide rail.
[0008] Preferably, the guide rail is hollow, and the upper end of the slider is provided with at least two mounting plates. The gripper assembly also includes a first driving member with one end retractable. The first driving member is disposed inside the guide rail, and the retractable end of the first retractable member is connected to the mounting plate.
[0009] Preferably, the two ends of the connecting rod pass through the gripper plates on both sides, and a locking rod is provided at one end of the adjusting plate. The locking rod passes through the adjusting plate and connects to the end of the connecting rod. A shim is provided at the end of the locking rod that connects to the adjusting plate, and the diameter of the shim is larger than the diameter of the locking rod.
[0010] Preferably, the abutment assembly further includes a second drive member with one end retractable, the second drive member being fixedly disposed on the outside of the guide rail, and the retraction direction of the retractable end being perpendicular to the movement direction of the gripper plate.
[0011] Preferably, the abutment rod is provided with a connecting hole, and the telescopic end of the second drive member is connected to the connecting hole by a thread.
[0012] Preferably, the upper end of the guide rail is provided with a lifting ring for connecting to the crane.
[0013] Preferably, the gripper plate is arranged in an L-shape.
[0014] This utility model has the following advantages and beneficial effects: The abutment component applies a positive jacking force from the center, effectively preventing lateral slippage and stabilizing the component's posture. The adjustment component provides bottom support through a rotatable L-shaped plate and works in conjunction with the clamping structure to flexibly adapt to the contours of arch ribs with different curvatures, indirectly adjusting the effective clamping width of the entire device. This design not only solves the problem of traditional clamps easily slipping due to irregular contact surfaces, but also, through the combination of adjustable bottom support and active jacking from the center, endows the device with powerful posture adjustment and stability capabilities. It can safely and efficiently handle the hoisting of broken arch ribs of various shapes, greatly improving the reliability and efficiency of bridge demolition operations. Attached Figure Description
[0015] Figure 1 This is a structural schematic diagram of an auxiliary hoisting device for dismantling bridge ribs in this utility model. Figure 2A schematic diagram of the gripper assembly structure of an auxiliary hoisting device for breaking and segmenting arch ribs for bridge demolition proposed in this utility model; Figure 3 for Figure 1 A magnified view of a portion of the image; Figure 4 Exploded view of the adjustment component of the auxiliary hoisting device for breaking and segmenting arch ribs for bridge demolition proposed in this utility model; Figure 5 This is a schematic diagram of the hoisting state of a segmented arch rib with a small curvature, which is an auxiliary hoisting device for bridge demolition according to the present invention. Figure 6 This is a schematic diagram of the lifting state of a segmented arch rib with a large curvature, which is an auxiliary lifting device for bridge demolition based on the present invention.
[0016] Reference numerals: 1-clamping structure, 11-guide rail, 111-lifting ring, 12-gripper assembly, 121-connecting rod, 122-slider, 1221-mounting plate, 123-gripper plate, 124-first driving component, 2-abutting assembly, 21-abutting rod, 211-connecting hole, 22-second driving component, 3-adjusting assembly, 31-adjusting plate, 311-shaft hole, 32-locking rod, 33-shim, 4-segmented arch rib. Detailed Implementation
[0017] To make the objectives, technical solutions, and advantages of the embodiments of this utility model clearer, the technical solutions of the embodiments of this utility model will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are some embodiments of this utility model, but not all embodiments.
[0018] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the claimed invention, but merely to illustrate selected embodiments of the invention. All other embodiments obtained by those skilled in the art based on the embodiments of the present invention without inventive effort are within the scope of protection of the present invention.
[0019] Example An auxiliary hoisting device for dismantling bridge segmented arch ribs is specifically designed for the safe and stable hoisting of large, irregular concrete segmented arch ribs 4 broken off from arch bridges.
[0020] like Figures 1-6As shown, an auxiliary hoisting device for breaking up segmented arch ribs 4 for bridge demolition includes a clamping structure 1, an abutment assembly 2, and an adjusting assembly 3. The clamping structure 1 is responsible for providing the main clamping force on both sides of the segmented arch rib 4. The clamping structure 1 includes a long strip guide rail 11 and two gripper assemblies 12. The interior of the guide rail 11 is hollow, forming a sliding cavity. A lifting ring 111 is welded to or fixed to the top center of the guide rail 11 by high-strength bolts for direct connection to the crane hook.
[0021] Two identical gripper assemblies 12 are symmetrically arranged below the center of the guide rail 11 and can slide synchronously towards or away from each other along the length of the guide rail 11. Each gripper assembly 12 consists of a connecting rod 121, a slider 122, several gripper plates 123, and a first driving member 124. The connecting rod 121 is a rigid long rod, and multiple gripper plates 123 are equally spaced and sleeved on the connecting rod 121 and fixed by welding or other means to form a multi-point, rigid clamping surface. The gripper plates 123 are preferably L-shaped, with their vertical sections used to contact the sides of the arch rib, and their horizontal sections providing a certain downward support and serving as a connecting base. The two ends of the connecting rod 121 pass through the gripper plates 123 on both sides.
[0022] The slider 122 is fixedly connected to the top of the connecting rod 121. Specifically, a bracket is provided at the lower end of the slider 122, the connecting rod 121 is placed in the bracket and welded to the bracket, and the other end of the bracket is also connected to the slider 122 by welding.
[0023] The slider 122 has an overall T-shape. The guide rail 11 has a sliding cavity inside. The two sides of the slider 122 are respectively embedded in the sliding cavity of the guide rail 11, so that the entire gripper assembly 12 is suspended below the guide rail 11 and can slide along it. The first driving member 124 (such as a hydraulic cylinder or electric push rod) is disposed in the internal cavity of the guide rail 11. The mounting seat of the first driving member 124 is welded at the corresponding position in the guide rail 11, and the first driving member 124 is fixed to the mounting seat by bolts.
[0024] At least two mounting plates 1221 are welded to the upper end of the slider 122. The telescopic end of the first drive member 124 is aligned with the mounting plate 1221 and passes through the mounting plate 1221. The mounting plate 1221 is connected by welding. The at least two mounting plates 1221 are provided to ensure greater stability when the first drive member 124 and the slider 122 are connected. By controlling the telescopic extension of the first drive member 124, the gripper assemblies 12 on both sides can be driven to move precisely along the guide rail 11 to achieve clamping or releasing. In this utility model, a single-sided gripper assembly 12 can also be used for clamping, that is, one end of the gripper assembly 12 is fixed to the guide rail 11 by welding or other means, and the other end of the gripper assembly 12 moves closer to it to achieve the clamping function.
[0025] like Figure 1 , Figure 3 , Figure 5 , Figure 6 As shown, the abutment assembly 2 is installed on the outer middle of the guide rail 11 of the clamping structure 1. Its function is to apply an active pushing force to the arc-shaped end face of the segmented arch rib 4 from a direction perpendicular to the clamping direction. The abutment assembly 2 includes a second driving member 22 and an abutment rod 21. The second driving member 22 (which can also be a hydraulic cylinder or an electric push rod) is fixed to the side wall of the guide rail 11 by a mounting base, and the movement direction of its telescopic end is perpendicular to the clamping movement direction of the gripper plate 123. At least two sets of abutment assemblies 2 are provided, and they are respectively connected to both sides of the guide rail 11.
[0026] The abutment rod 21 is a rigid rod with a connecting hole 211 on its outer end face. The connecting hole 211 is a threaded hole. The telescopic end of the second drive member 22 is machined with external threads and can be directly screwed into the connecting hole 211 to achieve a detachable rigid connection. By driving the second drive member 22, the abutment rod 21 can be extended horizontally, so that its outer end face is tightly pressed against the arc-shaped surface of the segmented arch rib 4.
[0027] At least two symmetrically arranged components form a balanced jacking force on the middle of the arch rib, preventing component deflection. The second driving component 22 is threadedly connected to the abutment rod 21, which not only ensures the rigidity of force transmission but also facilitates the replacement or length adjustment of the abutment rod 21 to adapt to different arch rib concavity and convexity depths. This component is linked with the clamping structure 1 to form a two-way "clamping-jacking" constraint on the arch rib in the horizontal plane, greatly enhancing the ability to resist lateral slippage and actively correcting the slight tilting posture of the component.
[0028] like Figure 1 , Figure 2 , Figure 4 , Figure 5 , Figure 6 As shown, the adjustment assembly 3 is used to support the segmented arch rib 4 from below, further stabilizing its posture and distributing the load. This assembly includes multiple L-shaped adjustment plates 31. One end of each adjustment plate 31 has a shaft hole 311. The adjustment plate 31 is located at one end of the connecting rod 121, and the shaft hole 311 and the connecting rod 121 are concentrically arranged. However, the diameter of the shaft hole 311 is smaller than the diameter of the connecting rod 121. A locking rod 32 is provided at the location of the shaft hole 311. The locking rod 32 passes through this shaft hole 311 and connects to a pre-set hole at the end of the connecting rod 121, achieving a circumferentially rotatable and axially fixed connection between the adjustment plate 31 and the connecting rod 121.
[0029] At the end of the locking rod 32 located outside the adjusting plate 31, a shim 33 is fitted, the diameter of which is larger than the diameter of the locking rod 32, to provide a stable pressing surface. The hole on the connecting rod 121 is a threaded hole, and the section of the locking rod 32 that extends into the connecting rod 121 is a threaded section. When the position of the locking rod 32 is adjusted so that it moves toward the connecting rod 121, the locking rod 32 secures the adjusting plate 31 to the connecting rod 121 through the shim 33, preventing the adjusting plate 31 from rotating. Before hoisting, each adjusting plate 31 can be manually rotated according to the actual contour of the bottom of the segmented arch rib 4, so that its lower end can just support the bottom of the arch rib.
[0030] For the segmented arch rib 4 with a large curvature (steep arch shape), the required clamping width is small. In this case, the angle of the adjusting plate 31 can be adjusted to avoid contact with the bottom of the arch rib, and the device can operate at its basic width (e.g., Figure 6 (As shown). For the segmented arch rib 4 with a small curvature (gentle arch shape), a larger clamping width is required. In this case, the adjusting plate 31 can be rotated to extend its horizontal arm to support the bottom of the arch rib, thereby physically increasing the effective clamping span of the device (e.g., Figure 5 (As shown). The adjusting plate 31 is used in conjunction with the gripper assembly 12 to achieve flexible adaptation to arch ribs of different sizes and curvatures.
[0031] Working principle: The crane lifts and positions the device via lifting ring 111. The worker aligns the device with the section of arch rib 4 to be broken, and operates the first drive component 124 to clamp the claw assembly 12 onto both sides of the arch rib. The second drive component 22 is operated to press the abutment rod 21 against the central arc surface of the arch rib. Based on the curvature of the bottom of the arch rib, the locking rod 32 is released, the adjusting plate 31 is rotated to a suitable support angle, and then relocked. After checking that the force at each point is reliable, breaking and safe lifting can begin.
[0032] The above content is only a preferred embodiment of the present utility model and is not intended to limit the present utility model. For those skilled in the art, the present utility model can have various modifications and variations. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present utility model should be included within the protection scope of the present utility model.
Claims
1. An auxiliary hoisting device for breaking and segmenting arch ribs for bridge demolition, characterized in that: The device includes an abutment component, an adjustment component, and a clamping structure on both sides that can move closer to or further away from each other. The segmented arch ribs are clamped by the clamping structure. The abutment component includes an abutment rod, which is located in the middle of the clamping structure, with the segmented arch ribs located on the bottom side of the abutment component. The abutment rod can move towards the bottom segmented arch ribs, and its outer end face abuts against the top of the segmented arch ribs. The adjustment component includes several adjustment plates, which are rotatably connected to the outside of the clamping structure. The adjustment plates are L-shaped and can rotate, with one end connected to the lower end of the segmented arch ribs.
2. The auxiliary hoisting device for breaking and segmenting arch ribs for bridge demolition according to claim 1, characterized in that: The clamping structure includes a guide rail and two gripper assemblies. The gripper assemblies are located in the middle of the guide rail and can slide along the direction of the guide rail.
3. The auxiliary hoisting device for breaking and segmenting arch ribs for bridge demolition according to claim 2, characterized in that: The gripper assembly includes a connecting rod, a slider, and several gripper plates. Adjacent gripper plates are connected by a connecting rod. The slider is fixedly mounted on the upper end of the connecting rod and is connected to a guide rail.
4. An auxiliary hoisting device for breaking and segmenting arch ribs for bridge demolition according to claim 3, characterized in that: The guide rail is hollow, and the upper end of the slider is provided with at least two mounting plates. The gripper assembly also includes a first driving member that can extend and retract at one end. The first driving member is disposed inside the guide rail, and the extension end of the first extension member is connected to the mounting plate.
5. An auxiliary hoisting device for breaking and segmenting arch ribs for bridge demolition according to claim 2, characterized in that: Both ends of the connecting rod pass through the gripper plates on both sides. One end of the adjusting plate is provided with a locking rod. The locking rod passes through the adjusting plate and connects to the end of the connecting rod. A washer is provided at the end of the locking rod connected to the adjusting plate. The diameter of the washer is larger than the diameter of the locking rod.
6. An auxiliary hoisting device for breaking and segmenting arch ribs for bridge demolition according to claim 1, characterized in that: The abutment assembly also includes a second drive member with one end capable of extension and retraction. The second drive member is fixedly disposed on the outside of the guide rail, and the extension and retraction direction of the extension and retraction end is perpendicular to the movement direction of the gripper plate.
7. An auxiliary hoisting device for breaking and segmenting arch ribs for bridge demolition according to claim 6, characterized in that: The abutment rod is provided with a connecting hole, and the telescopic end of the second driving member is connected to the connecting hole by a thread.
8. An auxiliary hoisting device for breaking and segmenting arch ribs for bridge demolition according to claim 2, characterized in that: The upper end of the guide rail is provided with a lifting ring for connecting with the crane.
9. An auxiliary hoisting device for breaking and segmenting arch ribs for bridge demolition according to claim 3, characterized in that: The gripper plate is configured in an L-shape.