Vertical transport device for fire protection pipeline installation
By designing a vertical transport device for fire-fighting pipelines with multi-stage lifting components, the complexity and safety issues of transporting fire-fighting pipelines in high-rise buildings and underground utility tunnels have been solved, achieving efficient and safe pipeline transport.
Patent Information
- Application Number
- CN202522340853.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-11-04
- Publication Date
- 2026-11-10
- Estimated Expiration
- 2035-11-04
AI Technical Summary
Existing vertical transport tools for fire protection pipelines are complex to operate and time-consuming in high-rise buildings and underground utility tunnels. In particular, the frequent adjustment of lifting points due to building structure limitations and pipeline length affects the construction progress.
A vertical transport device comprising a primary lifting component and a secondary lifting component was designed. It utilizes a combination of a rectangular frame, a carrying rack, guide wheels, an electric winch, and pulleys to achieve multi-stage lifting and adapt to flexible transport in different floors and spaces.
It significantly reduces labor costs and intensity, improves operational safety, avoids accidents, and adapts to the rapid transportation needs in complex spaces.
Smart Images

Figure CN224954295U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of fire protection engineering construction equipment technology, specifically a vertical transportation device for fire protection pipeline installation suitable for high-rise buildings, underground pipe corridors and other scenarios. Background Technology
[0002] In fire protection engineering construction, the vertical transportation of fire protection pipelines (such as DN50-DN200 galvanized steel pipes) is usually achieved using simple hoists or traditional mobile platforms. When using a simple hoist to lift fire protection pipelines, it needs to work in conjunction with temporary fixed pulleys. Firstly, since fire protection pipelines are generally 6 meters or longer, the lifting points of a single fixed pulley may not cover the entire transportation range of the pipeline, requiring multiple lifting points to be set up at different locations for segmented transportation. Secondly, due to the limitations of the building structure, different floors have different heights, and the presence of beams, columns, and other structural elements within the building can obstruct the vertical transportation path. To avoid these obstacles, the positions of the lifting points need to be adjusted to ensure the pipeline can pass smoothly. Therefore, a significant amount of time is spent fixing the pulleys during the operation, resulting in a large workload.
[0003] When using traditional mobile platforms to lift fire hydrants, these platforms typically have a fixed lifting height, making it impossible to adjust the height according to actual construction needs. This necessitates frequent changes or adjustments to the platform's position in different floor or height-dependent construction scenarios, increasing operational complexity and time costs. The aforementioned problems have made the vertical transportation of fire-fighting pipelines a bottleneck restricting the construction progress, and there is an urgent need for a vertical transportation device that is compact, safe, reliable, and adaptable to complex spaces. Utility Model Content
[0004] In view of the problems existing in the vertical transportation tools for fire protection pipelines, this utility model proposes a vertical transportation device for fire protection pipeline installation.
[0005] The present invention relates to a vertical transportation device for fire pipeline installation, characterized in that the device comprises a primary lifting assembly and a secondary lifting assembly, wherein: The primary lifting assembly consists of a rectangular frame and a carrying rack. The rectangular frame has opposing channel steel sections on both sides. The carrying rack comprises a vertical frame and a horizontal frame, which are welded together. Two pairs of guide wheels are installed on the vertical frame, with one end of the bearing of each guide wheel fixed to the side of the vertical frame. The guide wheels drive the carrying rack to slide vertically along the flanges of the channel steel sections on both sides of the rectangular frame. The horizontal frame supports the fire-fighting pipes. A first pulley is installed on the bottom surface of the rectangular frame, a second pulley is installed below the top surface of the rectangular frame, and a third pulley is installed on the vertical frame of the carrying rack. A wire rope fixing point is also provided at the top of the rectangular frame. The secondary lifting assembly consists of a bottom base and a column. Limiting units are provided on both the column and the rectangular frame, allowing the rectangular frame to slide vertically along the column. A fixing rod is provided on the rear side of the top of the column, and a fourth pulley is provided on the fixing rod. The trajectory of the fixing rod and the fourth pulley is staggered from that of the rectangular frame. An electric winch is fixed on the bottom base. The wire rope of the electric winch passes through the fourth pulley, the first pulley, the second pulley, and the third pulley in sequence, and the end of the wire rope is locked at the wire rope fixing point.
[0006] More specifically, the limiting unit includes two structures. One structure uses two channel steels, which are welded to the inner edges of both sides of the column. Guide wheels are installed in the channel steels, and the bearings of the guide wheels are fixed to the wing plates on both sides of the channel steels, so that the guide wheels hold the rectangular frame. The other structure uses two channel steels, which are welded to the outer edges of both sides of the rectangular frame. Guide wheels are installed in the channel steels, and the bearings of the guide wheels are fixed to the wing plates on both sides of the channel steels, so that the guide wheels hold the column.
[0007] More specifically, the bottom base includes long support legs, short support legs, and a crossbeam, all of which are made of square tubing. The long and short support legs overlap and are fixed with bolts, with the short support legs positioned inside the outer support legs. The crossbeam is located between the two short support legs. A column is welded and fixed to the crossbeam between the short support legs of the bottom base, and diagonal braces are installed between the column and the short support legs. The diagonal braces, short support legs, and column form a stable triangular support structure with excellent stability. The bottom base, as the support frame of the entire transport device, provides stable mechanical performance through its unique design. Its shape not only conforms to the laws of mechanical distribution, dispersing and bearing vertical loads from the column to a certain extent, but also provides horizontal support, enhancing the anti-tipping ability of the transport device. Furthermore, the bolted fixing of the long and short support legs allows for quick disassembly and installation, facilitating rapid handling and deployment in narrow spaces such as stairwells and pipe gallery access points. Its compact size after disassembly facilitates vehicle transport.
[0008] More specifically, a limiting block is provided on the rectangular frame. The limiting block is fixed to the channel steel on both sides of the rectangular frame to adjust and limit the lifting height of the rack, while preventing the second pulley from being squeezed by the rack.
[0009] More specifically, a connecting piece is provided on the rear side of the rectangular frame. The connecting piece is made of flat steel to prevent the rectangular frame from deforming.
[0010] More specifically, the horizontal frame of the storage rack is vertically equipped with two pairs of safety guardrails. Each safety guardrail has a sleeve at its bottom, which is fitted onto the horizontal frame of the storage rack and locked in place with bolts. During use, the fire-fighting pipes are positioned between the safety guardrails to prevent them from rolling and to facilitate construction.
[0011] More specifically, the bottom base is equipped with rollers and the back of the column is equipped with a handle to facilitate the movement of the entire fire pipeline installation vertical transport device.
[0012] The advantages of this utility model are: First, it significantly reduces labor costs and labor intensity, replacing a large number of manual vertical transport tasks, especially in buildings with high ceilings.
[0013] Second, it effectively improves operational safety and avoids accidents such as slipping, falling, and being crushed when workers are carrying heavy pipes on the mobile platform. Attached Figure Description
[0014] Figure 1 This is a front view of the present invention.
[0015] Figure 2 This is a side view of the present invention.
[0016] Figure 3 This is a top view of the present invention.
[0017] Figure 4 Schematic diagram of the limiting unit The components include: rectangular frame 1, shelf 2, first pulley 3, second pulley 4, third pulley 5, wire rope fixing point 6, bottom base 7, column 8, limiting unit 9, fixing rod 10, fourth pulley 11, electric winch 12, limiting block 13, connecting piece 14, and safety guard rod 15. Detailed Implementation
[0018] Example 1: A vertical transport device for fire pipeline installation, characterized in that the device includes a primary lifting assembly and a secondary lifting assembly, wherein: the primary lifting assembly consists of a rectangular frame and a carrying rack, the rectangular frame has opposing channel steels on both sides, the carrying rack consists of a vertical frame and a horizontal frame, the vertical frame and the horizontal frame are welded together, and two pairs of guide wheels are provided on the vertical frame, with one end of the bearing of the guide wheel fixed to the side of the vertical frame. The guide wheels drive the load-bearing frame to slide vertically along the flanges of the channel steel on both sides of the rectangular frame; the horizontal frame is used to support fire-fighting pipes; a first pulley is installed on the bottom surface of the rectangular frame, a second pulley is installed below the top surface of the rectangular frame, and a third pulley is installed on the vertical frame of the load-bearing frame; a wire rope fixing point is also installed at the top of the rectangular frame; the secondary lifting assembly consists of a bottom base and a column, and both the column and the rectangular frame are equipped with limiting units to allow the rectangular frame to slide vertically along the column; a fixing rod is installed on the rear side of the top of the column, and a fourth pulley is installed on the fixing rod. The trajectory of the fixing rod and the fourth pulley is staggered from that of the vertical sliding of the rectangular frame; an electric winch is fixed on the bottom base, and the wire rope of the electric winch passes through the fourth pulley, the first pulley, the second pulley, and the third pulley in sequence, with the end of the wire rope locked to the wire rope fixing point. A connecting piece is installed on the rear side of the rectangular frame. Two pairs of safety guardrails are vertically installed on the horizontal frame of the load-bearing frame, and sleeves are installed at the bottom of the safety guardrails. The sleeves are fitted onto the horizontal frame of the load-bearing frame and locked with bolts. Rollers are installed under the base, and handles are installed at the rear of the column to facilitate the movement of the entire fire pipeline installation vertical transport device.
[0019] The electric winch achieves multi-stage lifting through pulley blocks: when the conveyor is performing lifting operations, the wire rope fixing point and the first pulley are subjected to a tension force of equal magnitude and opposite direction, and the load frame is subjected to an upward tension force. At this time, the load frame moves upward along the rectangular frame to below the fixed connecting rod, realizing the first stage of lifting; When the rack rises to the position of the limit block of the rectangular frame, the rectangular frame and the rack are relatively fixed. At this time, the first pulley, the second pulley, the third pulley and the wire rope fixing point form a whole. When the lifting operation continues, the rectangular frame and the rack are lifted synchronously along the column until they are lifted to below the fourth pulley, thus achieving the second stage of lifting.
Claims
1. A vertical transport device for fire pipeline installation, characterized in that... The device includes a primary lifting assembly and a secondary lifting assembly. The primary lifting assembly consists of a rectangular frame and a carrying rack. The rectangular frame has opposing channel steel on both sides. The carrying rack consists of a vertical frame and a horizontal frame, which are welded together. Two pairs of guide wheels are installed on the vertical frame, and one end of the bearing of each guide wheel is fixed to the side of the vertical frame. The guide wheel drives the load-bearing frame to slide vertically along the flanges of the channel steel on both sides of the rectangular frame; the horizontal frame is used to support the fire-fighting pipes; a first pulley is set on the bottom surface of the rectangular frame, a second pulley is set below the top surface of the rectangular frame, a third pulley is set on the vertical frame of the load-bearing frame, and a wire rope fixing point is also set at the top of the rectangular frame; the secondary lifting assembly consists of a bottom base and a column, and both the column and the rectangular frame are equipped with limiting units to allow the rectangular frame to slide vertically along the column; a fixing rod is set on the rear side of the top of the column, and a fourth pulley is set on the fixing rod, and the trajectory of the fixing rod and the fourth pulley is staggered from that of the vertical sliding of the rectangular frame; an electric winch is fixed on the bottom base, and the wire rope of the electric winch passes through the fourth pulley, the first pulley, the second pulley and the third pulley in sequence, and the end of the wire rope is locked at the wire rope fixing point.
2. The vertical transport device for fire pipeline installation as described in claim 1, characterized in that... The limiting unit includes two structures. One structure uses two channel steels, which are welded to the inner edges of both sides of the column. Guide wheels are installed in the channel steels, and the bearings of the guide wheels are fixed to the wing plates on both sides of the channel steels, so that the guide wheels hold the rectangular frame. The other structure uses two channel steels, which are welded to the outer edges of both sides of the rectangular frame. Guide wheels are installed in the channel steels, and the bearings of the guide wheels are fixed to the wing plates on both sides of the channel steels, so that the guide wheels hold the column.
3. The vertical transport device for fire pipeline installation as described in claim 1, characterized in that... The base consists of long legs, short legs, and a crossbeam, all of which are made of square tubing. The long and short legs overlap and are fixed with bolts, with the short legs positioned inside the outer legs. The crossbeam is located between the two short legs. The uprights are welded and fixed to the crossbeam between the short legs of the base, and diagonal bracing is provided between the uprights and the short legs.
4. The vertical transport device for fire pipeline installation as described in claim 1, characterized in that... Limiting blocks are provided on the rectangular frame, and the limiting blocks are fixed to the channel steel on both sides of the rectangular frame.
5. The vertical transport device for fire pipeline installation as described in claim 1, characterized in that... A connecting piece is installed on the back of the rectangular frame.
6. The vertical transportation device for fire pipeline installation as described in claim 1, characterized in that... Two pairs of safety guards are vertically installed on the horizontal frame of the shelf. The bottom of the safety guards is provided with a sleeve, which is fitted onto the horizontal frame of the shelf and locked with bolts.