A prefabricated system suitable for connecting rigid composite piles to foundations
By integrating precast core-filled components with precast inner core piles through precast curing and molding, and combining buffer fillers and anchoring connection structures, the problems of complicated procedures, long construction period, high cost, and difficult quality control in connecting rigid composite piles with foundations are solved, achieving efficient and reliable connection results.
Patent Information
- Application Number
- CN202620069807.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2026-01-20
- Publication Date
- 2026-11-10
- Estimated Expiration
- 2036-01-20
AI Technical Summary
The existing process of connecting rigid composite piles to the foundation is complicated by cumbersome procedures, long construction period, high cost and difficulty in quality control. In particular, after cement and soil flow into the hollow part of the core pile, the drilling and core filling operations are difficult and affect the reliability of the connection.
The precast core-filled components and inner core precast piles are precast and cured in one piece, combined with buffer fillers and anchoring connection structures, eliminating the need for welding of closed steel plates and on-site core-filling processes, thus ensuring the stability and reliability of the connection area.
It achieves an efficient and reliable connection between the rigid composite pile and the foundation, reduces the construction period and cost, improves the reliability and quality of the connection, and is adaptable to various geological conditions.
Smart Images

Figure CN224955082U_ABST
Abstract
Description
Technical Field
[0001] This utility model relates to the field of pile foundation engineering technology, and in particular to a prefabricated system suitable for connecting rigid composite piles to foundations. Background Technology
[0002] In various engineering construction projects, pile foundations serve as crucial components that bear the loads of the superstructure and transfer them to the deep soil layer; their performance directly affects the safety and stability of the entire project. Currently, commonly used pile types in engineering mainly include PHC precast piles, cast-in-place piles, and reinforced composite piles.
[0003] Precast PHC piles (prestressed high-strength concrete pipe piles) have significant advantages such as standardized factory production, stable and controllable quality, high construction efficiency, strong durability, and economical cost. They are widely used in geological conditions such as soft soil and cohesive soil. However, this type of pile is difficult to drive in complex geological scenarios such as dense sand and gravel layers, and its application is significantly limited. Cast-in-place piles, on the other hand, are adaptable to various geological conditions, and the pile diameter and length can be flexibly adjusted according to project requirements. However, their on-site construction is greatly affected by weather and environmental factors, and quality control during pile formation is difficult, easily leading to quality defects such as necking and pile breakage. In addition, the pile formation speed is slow, the construction period is long, and a large amount of mud is generated that needs to be treated, bringing significant environmental pressure. The project cost is also relatively high.
[0004] As a new type of composite pile, rigid composite piles adopt a combination of "cement-soil pile body (outer core) + PHC precast pile (core pile)". Its composite section has a more reasonable stress distribution. It inherits the high strength and high durability of PHC precast piles and has the good adaptability of cast-in-place piles to geological conditions. Its construction efficiency is higher than that of traditional cast-in-place piles, and its cost is between that of precast piles and cast-in-place piles. It can be successfully driven into complex geological conditions such as dense sand, so it has a wide range of application prospects.
[0005] However, traditional construction methods for reinforced composite piles have several technical drawbacks: Reinforced composite pile construction requires first mixing cement and soil to form the pile, then implanting the PHC precast pile. After curing, the core pile needs to be excavated and grouted to ensure a reliable connection between the reinforced composite pile and the foundation. During the implantation of the core pile into the outer cement-soil pile, cement and soil can easily seep from the top and bottom of the core pile into the hollow part of the pipe pile. The hardened cement-soil has extremely high strength, making subsequent excavation and grooving operations difficult and inefficient. Incomplete excavation may even affect the quality of grooving, thus reducing the reliability of the pile-foundation connection.
[0006] To address these issues, the current conventional approach is to weld sealing steel plates to both ends of the core pile before implantation to prevent cement and soil from seeping in. These sealing steel plates are then removed before the final core grouting. However, this method not only adds extra steps for welding and removing the steel plates, extending the construction period, but also increases project costs. Furthermore, the stability of the welding quality can affect the overall performance of the pile. In addition, on-site core grouting is greatly affected by factors such as the construction environment and operator skill, making it difficult to guarantee the density and strength of the grouting concrete. This can easily lead to quality problems such as voids and cracks, further affecting the connection between the reinforced composite pile and the foundation, as well as the structural safety.
[0007] Therefore, there is an urgent need for a technical solution that can solve the problems of complicated procedures, long construction period, high cost and difficult quality control in the connection process between existing rigid composite piles and foundations, so as to achieve efficient and reliable connection between rigid composite piles and foundations and meet the requirements of engineering construction for construction efficiency, quality and economy. Utility Model Content
[0008] To address the problems of cumbersome procedures, long construction periods, high costs, and difficulty in quality control in the existing connection process between rigid composite piles and foundations, this utility model provides a prefabricated system suitable for connecting rigid composite piles and foundations. This system achieves efficient and reliable connection between rigid composite piles and foundations, meeting the requirements of engineering construction for construction efficiency, quality, and economy.
[0009] The technical solution adopted by this utility model for a prefabricated system for connecting rigid composite piles to foundations is as follows: A prefabricated system for connecting rigid composite piles to foundations includes precast core-filled components, rigid composite pile bodies, and anchoring connection structures; wherein, the rigid composite pile body includes an outer core pile and a coaxially arranged inner core precast pile, the precast core-filled components are embedded in the hollow cavity of the inner core precast pile, and are precast and cured integrally with the inner core precast pile. The top of the precast core pile has a reserved connection area, which is filled with a removable buffer filler. The top of the precast core component extends into the connection area and has a reserved connection part. The anchoring connection structure is used to connect the reserved connection part of the precast core component to the reinforcing steel in the foundation.
[0010] A further improvement of this utility model is that: the concrete strength grade of the precast core-filling component is not lower than the concrete strength grade of the foundation; the outer diameter of the precast core-filling component is adapted to the diameter of the hollow cavity of the inner core precast pile; the precast core-filling component is provided with longitudinal reinforcement; the reserved connection part is an extension of the longitudinal reinforcement extending upward to the top of the precast core-filling component; and the length of the extension is 80mm-120mm.
[0011] A further improvement of this utility model is that the top of the precast core-filling component is 180mm-220mm lower than the top of the inner core precast pile, forming the connection area.
[0012] A further improvement of the present invention is that the buffer filling material includes at least one of foam block, sponge, flexible rubber or biodegradable polymer material, the buffer filling material completely fills the internal space of the connection area and abuts against the top of the precast core component, and the outer surface of the buffer filling material is in contact with the inner wall of the inner core precast pile.
[0013] A further improvement of this utility model is that the diameter of the outer core pile is larger than the outer diameter of the inner core precast pile, and the radial distance between the outer core pile and the inner core precast pile is 150mm-200mm.
[0014] A further improvement of the present invention is that the anchoring connection structure includes a foundation anchoring steel bar, and the foundation anchoring steel bar and the reserved connection part are fixedly connected by welding or mechanical connection.
[0015] The technological advancements achieved by this utility model due to the adoption of the above technical solution are as follows: This utility model integrates the precast core-filling component with the inner core precast pile for precast curing, eliminating the need to weld closed steel plates at both ends of the core pile, and also saving the tedious process of removing the steel plates and filling the core on site later, thus reducing the amount of on-site construction work and shortening the construction period.
[0016] This utility model precast core-filled component is produced in the factory using standardized processes. By controlling the concrete mix ratio, reinforcement parameters, and centrifugal curing conditions, its strength, density, and other performance indicators are ensured to be stable and controllable. At the same time, the precast core-filled component and the inner core precast pile are centrifugally cured simultaneously, which can form a strong bonding surface, avoiding quality defects such as voids, cracks, and insufficient strength that may occur during on-site core filling. It also eliminates the problem of cement and soil flowing into the hollow cavity of the core pile, thereby improving the structural reliability of the connection between the rigid composite pile and the foundation.
[0017] This invention eliminates the material costs of the sealing steel plate, the labor costs of welding and removal, and the costs of using machinery. On the other hand, it reduces the input of concrete materials, construction equipment, and labor required for on-site core grouting. At the same time, the shortened construction period reduces project management costs and equipment rental costs.
[0018] The precast core-filled component of this utility model has a reserved connection part at the top, which facilitates quick connection with the foundation anchoring steel bars in the later stage. The connection method can be flexibly selected by welding or mechanical connection, and the operation is simple. The buffer filling part filled in the connection area at the top of the inner core precast pile can effectively protect the reserved connection part from damage during the pile driving process, and the subsequent cleaning is convenient. A reasonable radial spacing is set between the outer core pile and the inner core precast pile to ensure that the inner core precast pile can be driven smoothly and adapt to various geological conditions. Attached Figure Description
[0019] Figure 1 This is a structural schematic diagram of a prefabricated system for connecting rigid composite piles and foundations according to this utility model.
[0020] In the attached diagram: 1. Inner core precast pile; 2. Outer core pile; 3. Precast core-filled component; 4. Reinforcing steel bar; 5. Anchorage connection structure; 6. Foundation. Detailed Implementation
[0021] To make the objectives, technical solutions, and advantages of this utility model clearer, the present utility model will be further described in detail below with reference to specific embodiments and accompanying drawings. In the following description, descriptions of well-known structures and technologies are omitted to avoid unnecessarily obscuring the concept of this utility model.
[0022] like Figure 1 As shown, this utility model provides an assembled system suitable for connecting rigid composite piles to foundations, including a precast core-filled component 3, a rigid composite pile body, and an anchoring connection structure 5.
[0023] The aforementioned rigid composite pile body includes an outer core pile 2 and a coaxially arranged inner core precast pile 1. A precast core-filled component 3 is embedded in the hollow cavity of the inner core precast pile 1 and is integrally precast and cured with the inner core precast pile 1. The centrifugal curing speed of the precast core-filled component 3 and the inner core precast pile 1 is 800 r / min-1200 r / min, the curing temperature is 40℃-60℃, and the curing time is not less than 4 hours; ensuring that the bond strength between the precast core-filled component 3 and the inner core precast pile 1 is not less than 1.5 MPa.
[0024] The concrete strength grade of the precast core-filling component 3 is not lower than that of the foundation 6, and the outer diameter of the precast core-filling component 3 is compatible with the diameter of the hollow cavity of the inner core precast pile 1.
[0025] The top of the precast core pile 1 has a reserved connection area, which is filled with a removable buffer filler. The top of the precast core grouting component 3 extends into the connection area and has a reserved connection part. The precast core grouting component 3 has longitudinal reinforcement, and the reserved connection part is an extension of the longitudinal reinforcement extending upward to the top of the precast core grouting component 3. The length of the extension is 80mm-120mm.
[0026] The inner wall of the connection area is provided with an anti-corrosion coating, which can be an epoxy resin coating or a polyvinyl chloride coating, with a coating thickness of 0.5mm-1.0mm.
[0027] The top of the precast core-filling component 3 is 180mm-220mm lower than the top of the inner core precast pile 1, forming a connection area; the precast core-filling component 3 is inserted into the production mold of the inner core precast pile 1 as an inner mold, and is centrifugally cured synchronously with the inner core precast pile 1, with the reserved connection part facing upward.
[0028] The aforementioned buffer filler is at least one of foam block, sponge, flexible rubber or biodegradable polymer material. The buffer filler completely fills the internal space of the connection area and abuts against the top of the precast core component 3. At the same time, the outer surface of the buffer filler is in contact with the inner wall of the inner core precast pile 1.
[0029] The anchoring connection structure 5 is used to detachably connect the reserved connection part of the precast core-filling component 3 to the stressed steel bar 4 in the foundation 6, so as to realize the prefabricated fixing of the rigid composite pile body and the foundation 6.
[0030] The anchorage connection structure 5 includes foundation anchorage reinforcement. The diameter and length of the foundation anchorage reinforcement meet the requirements of the "Technical Specification for Reinforced Composite Piles" JGJ / T 327-2014. The foundation anchorage reinforcement is fixed to the reserved connection part by welding or mechanical connection. The mechanical connection can be one of sleeve connection, binding connection or extrusion connection.
[0031] In this embodiment, the outer core pile 2 is a cement-soil pile, the inner core precast pile 1 is a PHC precast pile, the radial distance between the outer core pile 2 and the inner core precast pile 1 is 150mm-200mm, and the diameter of the outer core pile 2 is larger than the outer diameter of the inner core precast pile 1.
[0032] In this embodiment, the outer core pile 2 is formed by a single-axis mixing process, a double-axis mixing process, or a triple-axis mixing process. During the pile formation process, the water-cement ratio of the cement-soil is controlled to be 0.8-1.2. The inner core precast pile 1 is driven to the preset depth of the outer core pile 2 by a hammering process or a static pressure process. During the pile driving process, the pile driving rate is controlled to be 0.5m / min-1.5m / min.
[0033] In this embodiment, the number of longitudinal reinforcements in the precast core-filled component 3 is 4-12, and the longitudinal reinforcements are evenly distributed along the circumference of the precast core-filled component 3; the length of the precast core-filled component 3 is determined according to the design bearing capacity of the rigid composite pile and the "Technical Specification for Rigid Composite Piles" JGJ / T 327-2014.
[0034] In the above embodiments, a prefabricated system suitable for connecting rigid composite piles to foundations is provided. This invention integrates the precast core-filled component with the inner core precast pile through prefabrication and curing, eliminating the need to weld sealing steel plates at both ends of the core pile and saving the tedious process of removing the steel plates and on-site core filling later, thus reducing on-site construction work and shortening the construction period. The precast core-filled component is produced in a factory using standardized processes. By controlling the concrete mix ratio, reinforcement parameters, and centrifugal curing conditions, its strength, density, and other performance indicators are ensured to be stable and controllable. Simultaneously, the precast core-filled component and the inner core precast pile are centrifuged together, forming a strong bonding surface, avoiding quality defects such as voids, cracks, and insufficient strength that may occur during on-site core filling, and also preventing the problem of cement and soil flowing into the hollow cavity of the core pile, thus improving... This invention enhances the structural reliability of the connection between the reinforced composite pile and the foundation. On one hand, it eliminates the material costs of the enclosed steel plate, the labor costs for welding and removal, and the machinery usage costs. On the other hand, it reduces the input of concrete materials, construction equipment, and labor required for on-site core grouting. Simultaneously, the shortened construction period reduces project management costs and equipment rental costs. The pre-reserved connection portion at the top of the precast core component facilitates rapid connection with the foundation anchoring reinforcement. The connection method can be flexibly selected as welding or mechanical connection, and the operation is simple. The buffer filling material in the connection area at the top of the inner core precast pile effectively protects the reserved connection portion from damage during pile driving and facilitates subsequent cleaning. A reasonable radial spacing is set between the outer core pile and the inner core precast pile to ensure smooth pile driving of the inner core precast pile, adapting to various geological conditions.
[0035] The embodiments described above are merely preferred embodiments of the present invention and are not intended to limit the concept and scope of the present invention. Various modifications and improvements made to the technical solutions of the present invention by those skilled in the art without departing from the design concept of the present invention should fall within the protection scope of the present invention. The technical content for which protection is sought in the present invention has been fully described in the claims.
Claims
1. A prefabricated system suitable for connecting rigid composite piles to foundations, characterized in that: It includes precast core-filling components (3), rigid composite piles and anchoring connection structures (5); wherein, the rigid composite piles include an outer core pile (2) and an inner core precast pile (1) arranged coaxially, the precast core-filling components (3) are embedded in the hollow cavity of the inner core precast pile (1) and are precast and cured in an integrated manner with the inner core precast pile (1); The top of the precast core pile (1) has a reserved connection area, which is filled with a removable buffer filler. The top of the precast core grouting component (3) extends into the connection area and is provided with a reserved connection part. The anchoring connection structure (5) is used to connect the reserved connection part of the precast core grouting component (3) to the reinforcing steel bar (4) in the foundation (6).
2. The prefabricated system for connecting rigid composite piles to foundations according to claim 1, characterized in that: The concrete strength grade of the precast core-filling component (3) is not lower than that of the foundation (6). The outer diameter of the precast core-filling component (3) is matched with the diameter of the hollow cavity of the inner core precast pile (1). The precast core-filling component (3) is provided with longitudinal reinforcement. The reserved connection part is an extension of the longitudinal reinforcement extending upward to the top of the precast core-filling component (3), and the length of the extension is 80mm-120mm.
3. The prefabricated system for connecting rigid composite piles to foundations according to claim 1, characterized in that: The top of the precast core-filling component (3) is 180mm-220mm lower than the top of the inner core precast pile (1), forming the connection area.
4. The prefabricated system for connecting rigid composite piles to foundations according to claim 1, characterized in that: The buffer filler includes at least one of foam block, sponge, flexible rubber or biodegradable polymer material. The buffer filler completely fills the internal space of the connection area and abuts against the top of the precast core component (3). At the same time, the outer surface of the buffer filler is in contact with the inner wall of the inner core precast pile (1).
5. The prefabricated system for connecting rigid composite piles to foundations according to claim 1, characterized in that: The diameter of the outer core pile (2) is greater than the outer diameter of the inner core precast pile (1), and the radial distance between the outer core pile (2) and the inner core precast pile (1) is 150mm-200mm.
6. The prefabricated system for connecting rigid composite piles to foundations according to claim 1, characterized in that: The anchoring connection structure (5) includes a foundation anchoring steel bar, which is fixedly connected to the reserved connection part by welding or mechanical connection.