A two-to-one combined cycle steam turbine shaft seal steam supply system

By adopting a two-drive-one-shaft-seal steam supply system in the combined cycle steam turbine, steam is directly supplied to the turbine shaft seal using the reheat cold section. This simplifies the pipeline layout and allows for the rapid discharge of cold air using the air vent valve, solving the problem of excessively long turbine start-up time and improving the unit's start-up speed and peak-shaving response capability.

CN224955787UActive Publication Date: 2026-11-10POWERCHINA HEBEI ELECTRIC POWER SURVEY & DESIGN INST CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522345933.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-11-05
Publication Date
2026-11-10
Estimated Expiration
2035-11-05

AI Technical Summary

Technical Problem

The combined cycle unit has a long start-up time, which is limited by the preheating time of the turbine shaft seal system, resulting in a slow overall start-up speed.

Method used

The two-to-one combined cycle turbine shaft seal steam supply system is adopted, which directly supplies steam to the turbine shaft seal system through the reheat cold section, simplifies the pipeline layout, eliminates the need for a start-up boiler, and uses an air vent valve to quickly discharge cold air and low-parameter steam, reducing preheating time.

Benefits of technology

It shortens the steam transmission path, reduces engineering construction costs and operating energy consumption, and improves the unit's start-up speed and peak-shaving response capability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224955787U_ABST
    Figure CN224955787U_ABST
Patent Text Reader

Abstract

This utility model discloses a steam supply system for the shaft seal of a two-to-one combined cycle steam turbine, belonging to the field of gas turbine power generation technology. It includes two sets of waste heat boiler groups. Each set includes a waste heat boiler superheater connected to the turbine inlet via a steam pipeline and a waste heat boiler reheater connected to the turbine outlet via a reheat cold pipeline. The steam pipeline at the outlet of the waste heat boiler superheater in the same group is connected to the reheat cold pipeline at the inlet of the waste heat boiler superheater in the same group via a bypass pipeline, and a bypass valve is installed on the bypass pipeline. Simultaneously, the reheat cold pipeline at the inlet of the waste heat boiler superheater is also connected to the turbine shaft seal system via a connecting pipeline. This utility model increases the pipeline supplying the reheat cold section to the shaft seal, reduces the preheating time of the shaft seal system, and improves the start-up speed of the combined cycle unit.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of gas turbine power generation technology, and in particular to a shaft seal steam supply system for a two-to-one combined cycle steam turbine. Background Technology

[0002] In the thermal power generation sector, combined cycle units occupy an important position due to their high efficiency and low emissions. Their rapid start-up and shutdown capabilities give them an advantage in the power peak-shaving market. To simplify system layout, an increasing number of power plants are eliminating start-up boilers during the design phase, instead relying on existing steam systems to meet various steam demands during unit startup.

[0003] However, the start-up progress of combined cycle units is often limited by the steam turbine rather than the gas turbine. The steam turbine needs to meet two key conditions for start-up: the reliable establishment of the shaft sealing system and the stable formation of the vacuum environment. It also has strict requirements on the superheat and pressure stability of the steam at the shaft seal inlet. It can only be put into operation after the steam parameters meet the standards.

[0004] In conventional designs, turbine shaft sealing steam is typically supplied by an auxiliary steam system, which draws its steam source from main steam or reheat cold section steam. Before the shaft sealing steam is officially put into operation, the main steam pipeline, the pipeline from the main steam (or reheat cold section) to the auxiliary steam system, the auxiliary steam pipeline, and the pipeline from the auxiliary steam to the shaft sealing steam must be fully preheated. Steam can only enter the turbine after all pipeline temperatures reach the set standard. This type of pipeline layout is lengthy and the preheating process is cumbersome, resulting in excessively long turbine start-up delays, directly restricting the overall start-up speed of the combined cycle unit. Utility Model Content

[0005] To address the issue of slow start-up time in existing combined cycle turbine units, this invention provides a two-to-one combined cycle turbine shaft seal steam supply system. This system adds a pipeline from the reheat cold section to the shaft seal, reducing the preheating time of the shaft seal system and improving the start-up speed of the combined cycle unit.

[0006] The technical solution adopted by this utility model for a shaft seal steam supply system for a two-to-one combined cycle steam turbine is as follows: A two-to-one combined cycle steam turbine shaft seal steam supply system includes two sets of waste heat boiler groups. Each set of waste heat boiler groups includes a waste heat boiler superheater connected to the turbine inlet via a steam pipeline and a waste heat boiler reheater connected to the turbine outlet via a reheat cold pipeline. The steam pipeline at the outlet of the waste heat boiler superheater in the same set is connected to the reheat cold pipeline at the inlet of the waste heat boiler superheater in the same set via a bypass pipeline, and a bypass valve is installed on the bypass pipeline. At the same time, the reheat cold pipeline at the inlet of the waste heat boiler superheater is also connected to the turbine shaft seal system via a connecting pipeline.

[0007] A further improvement of the present invention is that: one waste heat boiler group includes a #1 waste heat boiler superheater and a #1 waste heat boiler reheater, and another waste heat boiler group includes a #2 waste heat boiler superheater and a #2 waste heat boiler reheater; wherein, the #1 waste heat boiler superheater and the #2 waste heat boiler superheater, and the #1 waste heat boiler reheater and the #2 waste heat boiler reheater operate in parallel.

[0008] A further improvement of this utility model is that: the outlets of the superheater of the #1 waste heat boiler and the superheater of the #2 waste heat boiler are both connected to main steam pipeline branch pipes, and the two main steam pipeline branch pipes are connected to the turbine inlet through a main steam pipeline header; the inlets of the reheater of the #1 waste heat boiler and the reheater of the #2 waste heat boiler are both connected to reheat cold pipeline branch pipes, and the two reheat cold pipeline branch pipes are connected to the turbine outlet through a reheat cold pipeline header.

[0009] A further improvement of the present invention is that: a first isolation door is provided on the main steam pipe branch corresponding to the #1 waste heat boiler superheater, a second isolation door is provided on the main steam pipe branch corresponding to the #2 waste heat boiler superheater, and a third isolation door is provided on the main steam pipe near the turbine.

[0010] A further improvement of this utility model is that: a fourth isolation door is provided on the reheat cold pipe branch corresponding to the #1 waste heat boiler reheater, a fifth isolation door is provided on the reheat cold pipe branch corresponding to the #2 waste heat boiler reheater, and a check valve is provided on the reheat cold pipe main pipe.

[0011] A further improvement of this utility model is that: the main steam pipe branch corresponding to the superheater of the #1 waste heat boiler is connected to the reheat cold pipe branch corresponding to the reheater of the #1 waste heat boiler through a first bypass pipe, and a first bypass valve is provided on the first bypass pipe; the main steam pipe branch corresponding to the superheater of the #2 waste heat boiler is connected to the reheat cold pipe branch corresponding to the reheater of the #2 waste heat boiler through a second bypass pipe, and a second bypass valve is provided on the second bypass pipe.

[0012] A further improvement of the present invention is that: the reheat cold pipe branch corresponding to the #1 waste heat boiler reheater is connected to a first connecting pipe, the reheat cold pipe branch corresponding to the #2 waste heat boiler reheater is connected to a second connecting pipe, and the first connecting pipe and the second connecting pipe are connected to the turbine shaft sealing system through a connecting pipe header.

[0013] A further improvement of this utility model is that: a sixth isolation valve and a first check valve are sequentially arranged on the first connecting pipe along the steam flow direction; a seventh isolation valve and a second check valve are sequentially arranged on the second connecting pipe along the steam flow direction; and an eighth isolation valve and an electric regulating valve are sequentially arranged on the main connecting pipe along the steam flow direction.

[0014] A further improvement of this utility model is that: the main connecting pipe is located in front of the eighth isolation door and is connected to an air vent pipe, and an air vent valve is provided on the air vent pipe.

[0015] The technological advancements achieved by this utility model due to the adoption of the above technical solution are as follows: This invention eliminates the need for a start-up boiler, directly supplying steam to the turbine shaft seal system via the reheat cold section. This eliminates the need for an additional start-up boiler and supporting facilities, reducing construction costs while also decreasing boiler maintenance and operating energy consumption. Furthermore, this invention simplifies the steam supply pipeline layout, eliminating the lengthy pipelines from main steam to auxiliary steam and from auxiliary steam to the shaft seal in traditional systems. Instead, it directly connects to the turbine shaft seal system via a reheat cold section branch pipe and the main pipe, shortening the steam transmission path. Finally, the air vent valve in this invention can quickly discharge cold air and low-parameter steam during the pipeline preheating stage, accelerating the pipeline heating rate, reducing preheating time, and improving unit start-up speed and peak-shaving response capabilities. Attached Figure Description

[0016] Figure 1 This is a connection structure diagram of a shaft seal steam supply system for a two-to-one combined cycle steam turbine according to this utility model.

[0017] In the attached diagram: 1. Superheater of #1 waste heat boiler; 2. Superheater of #2 waste heat boiler; 3. Reheater of #1 waste heat boiler; 4. Reheater of #2 waste heat boiler; 5. Steam turbine; 6. Main steam pipeline branch pipe; 7. Main steam pipeline header; 8. Reheat cold pipeline branch pipe; 9. Reheat cold pipeline header; 10. First isolation valve; 11. Second isolation valve; 12. Third isolation valve; 13. Fourth isolation valve; 14. Fifth isolation valve; 15. Check valve; 16. First bypass pipe; 17. First bypass valve; 18. Second bypass pipe; 19. Second bypass valve; 20. First connecting pipe; 21. Second connecting pipe; 22. Main connecting pipe; 23. Sixth isolation valve; 24. First check valve; 25. Seventh isolation valve; 26. Second check valve; 27. Eighth isolation valve; 28. Electric regulating valve; 29. ​​Air vent pipe; 30. Air vent valve; 31. Turbine shaft sealing system. Detailed Implementation

[0018] To make the objectives, technical solutions, and advantages of this utility model clearer, the present utility model will be further described in detail below with reference to specific embodiments and accompanying drawings. In the following description, descriptions of well-known structures and technologies are omitted to avoid unnecessarily obscuring the concept of this utility model.

[0019] This utility model provides a shaft seal steam supply system for a two-to-one combined cycle steam turbine, such as... Figure 1 As shown, it includes two sets of waste heat boilers. One set of waste heat boilers includes waste heat boiler superheater 1 and waste heat boiler reheater 3, and the other set of waste heat boilers includes waste heat boiler superheater 2 and waste heat boiler reheater 4. At the same time, waste heat boiler superheater 1 and waste heat boiler superheater 2, waste heat boiler reheater 3 and waste heat boiler reheater 4 operate in parallel.

[0020] The outlets of the superheater 1 of the #1 waste heat boiler and the superheater 2 of the #2 waste heat boiler are both connected to main steam pipeline branch pipes 6. The two main steam pipeline branch pipes 6 are merged into a main steam pipeline header 7, which is connected to the inlet of the turbine 5. A first isolation door 10 is provided on the main steam pipeline branch pipe 6 corresponding to the superheater 1 of the #1 waste heat boiler, a second isolation door 11 is provided on the main steam pipeline branch pipe 6 corresponding to the superheater 2 of the #2 waste heat boiler, and a third isolation door 12 is provided on the main steam pipeline header 7 near the turbine 5.

[0021] The inlet of reheater 3 of waste heat boiler #1 and the inlet of reheater 4 of waste heat boiler #2 are both connected to reheat cold pipe branch pipes 8. The two reheat cold pipe branch pipes 8 are merged into a reheat cold pipe main pipe 9, which is connected to the outlet of turbine 5. Among them, the reheat cold pipe branch pipe 8 corresponding to reheater 3 of waste heat boiler #1 is equipped with a fourth isolation valve 13, the reheat cold pipe branch pipe 8 corresponding to reheater 4 of waste heat boiler #2 is equipped with a fifth isolation valve 14, and the reheat cold pipe main pipe 9 is equipped with a check valve 15.

[0022] In this utility model, the main steam pipe branch 6 corresponding to the superheater 1 of the #1 waste heat boiler is connected to the reheat cold pipe branch 8 corresponding to the reheater 3 of the #1 waste heat boiler through the first bypass pipe 16, and a first bypass valve 17 is provided on the first bypass pipe 16; the main steam pipe branch 6 corresponding to the superheater 2 of the #2 waste heat boiler is connected to the reheat cold pipe branch 8 corresponding to the reheater 4 of the #2 waste heat boiler through the second bypass pipe 18, and a second bypass valve 19 is provided on the second bypass pipe 18.

[0023] Meanwhile, in this utility model, the reheat cold pipe branch 8 corresponding to the #1 waste heat boiler reheater 3 is connected to the first connecting pipe 20. The first connecting pipe 20 is provided with a sixth isolation valve 23 and a first check valve 24 in sequence along the steam flow direction; the reheat cold pipe branch 8 corresponding to the #2 waste heat boiler reheater 4 is connected to the second connecting pipe 21. The second connecting pipe 21 is provided with a seventh isolation valve 25 and a second check valve 26 in sequence along the steam flow direction; the first connecting pipe 20 and the second connecting pipe 21 are combined into a connecting pipe main pipe 22 and connected to the turbine shaft sealing system 31. The connecting pipe main pipe 22 is provided with an eighth isolation valve 27 and an electric regulating valve 28 in sequence along the steam flow direction. The connecting pipe main pipe 22 is located in front of the eighth isolation valve 27 and is connected to an air vent pipe 29. An air vent valve 30 is provided on the air vent pipe 29.

[0024] When starting up a two-to-one combined cycle unit, taking Unit 1 as the first unit to start up, the first isolation valve 10 at the outlet of the superheater of the No. 1 waste heat boiler is closed, the third isolation valve 12 at the inlet of turbine 5 is closed, and the first bypass valve 17 at the outlet of the No. 1 waste heat boiler superheater is opened. Steam is connected to the reheat cold pipe branch 8 corresponding to the reheater of the No. 1 waste heat boiler through the first bypass pipe. At this time, the fourth isolation valve 13 is opened, and steam enters the reheater of the No. 1 waste heat boiler.

[0025] The sixth isolation valve 23 of the first connecting pipe 20 is opened, and the eighth isolation valve 27 on the main connecting pipe 22 is closed. Steam preheats the pipes through the shaft sealing system pipes and is discharged to the atmosphere through the air vent valve 30, increasing the preheating rate of the pipes. When the steam parameters meet the requirements of the turbine 5 for shaft sealing steam, the eighth isolation valve 27 and the electric regulating valve 28 are opened, and the turbine shaft sealing system 31 is put into operation. Subsequently, a vacuum is established, the parameters of the main steam pipes are gradually increased, and the air vent valve 30 is gradually closed and the first isolation valve 10 is opened as the pressure increases, preheating the pipes at the inlet of the turbine 5. When the parameters meet the requirements of the turbine inlet steam temperature, steam enters the turbine 5.

[0026] In the above embodiments, a two-to-one combined cycle turbine shaft seal steam supply system is provided. This invention eliminates the need for a start-up boiler, directly supplying steam to the turbine shaft seal system via the reheat cold section. This eliminates the need for an additional start-up boiler and supporting facilities, reducing both construction investment costs and boiler maintenance workload and operating energy consumption. The invention also simplifies the steam supply pipeline layout, eliminating the lengthy pipelines from main steam to auxiliary steam and from auxiliary steam to the shaft seal in traditional systems. Instead, it directly connects the turbine shaft seal system via a reheat cold section branch pipe and the main pipe, shortening the steam transmission path. Furthermore, the air vent valve in this invention can quickly discharge cold air and low-parameter steam during the pipeline preheating stage, accelerating the pipeline heating rate, reducing preheating time, and improving unit start-up speed and peak-shaving response capability.

[0027] The embodiments described above are merely preferred embodiments of the present invention and are not intended to limit the concept and scope of the present invention. Various modifications and improvements made to the technical solutions of the present invention by those skilled in the art without departing from the design concept of the present invention should fall within the protection scope of the present invention. The technical content for which protection is sought in the present invention has been fully described in the claims.

Claims

1. A shaft seal steam supply system for a two-to-one combined cycle steam turbine, characterized in that: It includes two sets of waste heat boiler groups. Each set of waste heat boiler groups includes a waste heat boiler superheater connected to the inlet of the steam turbine (5) via a steam pipe and a waste heat boiler reheater connected to the outlet of the steam turbine (5) via a reheat cold pipe. The steam pipe at the outlet of the waste heat boiler superheater in the same set is connected to the reheat cold pipe at the inlet of the waste heat boiler superheater in the same set via a bypass pipe, and a bypass valve is installed on the bypass pipe. At the same time, the reheat cold pipe at the inlet of the waste heat boiler superheater is also connected to the steam turbine shaft seal system (31) via a connecting pipe.

2. The shaft seal steam supply system for a two-drive-one combined cycle steam turbine according to claim 1, characterized in that: One group of waste heat boilers includes a #1 waste heat boiler superheater (1) and a #1 waste heat boiler reheater (3), and the other group of waste heat boilers includes a #2 waste heat boiler superheater (2) and a #2 waste heat boiler reheater (4); wherein, the #1 waste heat boiler superheater (1) and the #2 waste heat boiler superheater (2), the #1 waste heat boiler reheater (3) and the #2 waste heat boiler reheater (4) operate in parallel.

3. The shaft seal steam supply system for a two-drive-one combined cycle steam turbine according to claim 2, characterized in that: The outlets of the #1 waste heat boiler superheater (1) and the #2 waste heat boiler superheater (2) are both connected to main steam pipeline branch pipes (6), and the two main steam pipeline branch pipes (6) are connected to the turbine (5) inlet through a main steam pipeline header (7); the inlets of the #1 waste heat boiler reheater (3) and the #2 waste heat boiler reheater (4) are both connected to reheat cold pipeline branch pipes (8), and the two reheat cold pipeline branch pipes (8) are connected to the turbine (5) outlet through a reheat cold pipeline header (9).

4. The shaft seal steam supply system for a two-drive-one combined cycle steam turbine according to claim 3, characterized in that: A first isolation door (10) is provided on the main steam pipe branch (6) corresponding to the #1 waste heat boiler superheater (1), a second isolation door (11) is provided on the main steam pipe branch (6) corresponding to the #2 waste heat boiler superheater (2), and a third isolation door (12) is provided on the main steam pipe (7) near the turbine (5).

5. A shaft seal steam supply system for a two-drive-one combined cycle steam turbine according to claim 3, characterized in that: A fourth isolation door (13) is provided on the reheat cold pipe branch (8) corresponding to the #1 waste heat boiler reheater (3), a fifth isolation door (14) is provided on the reheat cold pipe branch (8) corresponding to the #2 waste heat boiler reheater (4), and a check valve (15) is provided on the reheat cold pipe main pipe (9).

6. The shaft seal steam supply system for a two-drive-one combined cycle steam turbine according to claim 3, characterized in that: The main steam pipe branch (6) corresponding to the superheater (1) of the #1 waste heat boiler is connected to the reheat cold pipe branch (8) corresponding to the reheater (3) of the #1 waste heat boiler through the first bypass pipe (16), and a first bypass valve (17) is provided on the first bypass pipe (16); the main steam pipe branch (6) corresponding to the superheater (2) of the #2 waste heat boiler is connected to the reheat cold pipe branch (8) corresponding to the reheater (4) of the #2 waste heat boiler through the second bypass pipe (18), and a second bypass valve (19) is provided on the second bypass pipe (18).

7. The shaft seal steam supply system for a two-drive-one combined cycle steam turbine according to claim 3, characterized in that: The reheat cold pipe branch (8) corresponding to the #1 waste heat boiler reheater (3) is connected to a first connecting pipe (20), and the reheat cold pipe branch (8) corresponding to the #2 waste heat boiler reheater (4) is connected to a second connecting pipe (21). The first connecting pipe (20) and the second connecting pipe (21) are connected to the turbine shaft sealing system (31) through a connecting pipe main pipe (22).

8. A shaft seal steam supply system for a two-drive-one combined cycle steam turbine according to claim 7, characterized in that: The first connecting pipe (20) is provided with a sixth isolation valve (23) and a first check valve (24) in sequence along the steam flow direction; the second connecting pipe (21) is provided with a seventh isolation valve (25) and a second check valve (26) in sequence along the steam flow direction; the main pipe (22) of the connecting pipe is provided with an eighth isolation valve (27) and an electric regulating valve (28) in sequence along the steam flow direction.

9. A shaft seal steam supply system for a two-drive-one combined cycle steam turbine according to claim 8, characterized in that: The main pipe (22) of the connecting pipeline is located in front of the eighth isolation door (27) and is connected to the air vent pipe (29), and an air vent valve (30) is provided on the air vent pipe (29).