A bridge structure with externally mounted prefabricated flower beds

By setting up a fence base and cantilever beams on top of the flower bed, combined with the design of a lifting mechanism and drainage pipes, the problems of installation stability, maintenance convenience, and drainage efficiency of the external prefabricated flower bed bridge structure were solved. This achieved stable support and rapid drainage of the flower bed, enhancing the aesthetics and ecological benefits of the bridge.

CN224982033UActive Publication Date: 2026-11-17GUANGZHOU MUNICIPAL ENG DESIGN & RES INST CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522421918.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-11-14
Publication Date
2026-11-17
Estimated Expiration
2035-11-14

AI Technical Summary

Technical Problem

The external precast flower bed bridge structure has problems in terms of installation stability, ease of maintenance and drainage efficiency, especially in the maintenance and replacement process, where stability and efficiency are difficult to achieve.

Method used

Design a bridge structure for externally mounted prefabricated flower beds. By opening a first pool at the top of the flower bed and setting a fence seat to divide it into a drainage channel and a second pool, the flower bed is stably supported and moved by cantilever beams and a lifting mechanism. Combined with the design of drainage pipes and connecting pipes, the smoothness of the drainage system and the convenience of flower bed maintenance are ensured.

Benefits of technology

The stable installation of the flower beds was achieved, which improved the aesthetics and ecological benefits of the bridge, ensured rapid drainage in severe weather, facilitated the maintenance and replacement of the flower beds, and improved work efficiency and structural stability.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224982033U_ABST
    Figure CN224982033U_ABST
Patent Text Reader

Abstract

This utility model relates to a bridge structure with an externally mounted prefabricated flower bed. The flower bed is located on the outside of a steel box girder. A railing at the top of the flower bed divides a first pool into a drainage channel and a second pool. Multiple cantilever beams are bolted to the outside of the steel box girder. A support plate is provided at the top of the cantilever beams. Multiple rollers are bolted to the bottom of the flower bed. A first guide rail that mates with the rollers is fixed at the top of the support plate. A lifting mechanism is mounted on the cantilever beams and includes multiple first electric push rods and a moving component. The moving component drives the multiple first electric push rods to move. The output end of the first electric push rods is provided with a pulley for lifting the flower bed. A drainage pipe is fixedly connected to the top of the multiple cantilever beams. Multiple first connecting pipes are provided through the top of the flower bed and are connected to the drainage pipe. This externally mounted prefabricated flower bed bridge structure achieves stable installation, convenient maintenance, and efficient drainage of the bridge, improving its aesthetics, ecological benefits, and environmental adaptability.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model belongs to the field of bridge construction technology and relates to a bridge structure with an externally attached precast flower bed. Background Technology

[0002] With the acceleration of urbanization, bridges, as vital transportation infrastructure, are undergoing continuous development and innovation in design and construction technology. Bridge structures with externally mounted precast flower beds are a novel type of bridge structure. By precasting and attaching flower beds to the outside of the bridge, it not only enhances the bridge's aesthetics but also improves its ecological benefits and environmental adaptability. This design approach is gaining increasing attention in modern urban landscape design because it effectively integrates with the urban environment, elevates the city's image, and provides more green space for urban residents.

[0003] The design and construction technology of precast flower bed bridge structures involves multiple aspects. During construction, the maintenance and replacement of the flower beds also need to be considered. Since the flower beds are located on the outside of the bridge, their maintenance and replacement are relatively difficult; therefore, a structural system that facilitates maintenance and replacement needs to be designed. Utility Model Content

[0004] In view of this, in order to solve the problems of installation stability, maintenance convenience and drainage efficiency of external precast flower bed bridges, this utility model provides a bridge structure with external precast flower beds, which realizes stable installation, convenient maintenance and efficient drainage of the bridge, and improves the aesthetics, ecological benefits and environmental adaptability of the bridge.

[0005] To achieve the above objectives, this utility model provides the following technical solution:

[0006] A bridge structure with an externally mounted prefabricated flower bed, wherein the flower bed is located on the outside of a steel box girder, and a first pool trough is provided on the top of the flower bed. A railing seat is provided inside the first pool trough, and the railing seat divides the first pool trough into a drainage channel and a second pool trough.

[0007] Multiple cantilever beams are bolted to the outside of the steel box girder. The top of the cantilever beams is equipped with a support plate. The bottom of the flower bed is bolted to multiple rollers. The top of the support plate is fixed with a first guide rail that mates with the rollers.

[0008] The lifting mechanism is installed on the cantilever beam and includes multiple first electric push rods and a moving component. The moving component drives the multiple first electric push rods to move. The output end of the first electric push rod is provided with a pulley for lifting the flower bed.

[0009] The drainage pipe is fixedly connected to the top of multiple cantilever beams, and multiple first connecting pipes are provided through the top of the flower bed, which are connected to the drainage pipe.

[0010] The lifting mechanism can drive the flower bed to move and lift along the first guide rail, which is convenient for maintenance. The water in the second pool is discharged into the drain pipe through the first connecting pipe.

[0011] Furthermore, multiple second guide rails are fixedly installed on the top of the cantilever beam. These second guide rails are vertically connected to the outside of the steel box beam by bolts, and a sliding groove is provided on one side of the flower bed to slide with the second guide rails.

[0012] Furthermore, two third guide rails are welded to the top of multiple cantilever beams. The outer wall of one of the third guide rails is slidably fitted with a first slider corresponding to the cantilever beam. A first electric push rod is mounted on the first slider. The output end of the first electric push rod is fixedly mounted with a rotating shaft. The outer wall of the rotating shaft is rotatably mounted with two pulleys via bearings.

[0013] Furthermore, a second slider corresponding to the first slider is slidably sleeved on another third guide rail. A second rotating seat is bolted to one side of the second slider. A second electric push rod is rotatably mounted inside the second rotating seat via a pin. A first rotating seat is bolted to one side of the first slider. The first electric push rod is rotatably mounted inside the first rotating seat via a pin. A connecting seat is fixedly sleeved on the outer wall of the first electric push rod. The output end of the second electric push rod is rotatably mounted inside the connecting seat via a pin.

[0014] Furthermore, the moving assembly includes two winding cabinets located below the steel box girder. A winding roller is rotatably installed inside the winding cabinet. A motor is bolted to the winding cabinet, and the output end of the motor is fixedly connected to the winding roller. A steel wire rope is fixedly installed on the outer wall of one of the winding rollers. The other end of the steel wire rope is fixed and wound around the other winding roller. Multiple first sliders are fixedly sleeved on the steel wire rope. A waist-shaped hole for accommodating the steel wire rope is opened on the outer side of the winding cabinet.

[0015] Furthermore, two pads are fixedly installed at the top of the cantilever beam to support the support plate, and the pads are used to reserve installation space for the first electric push rod.

[0016] Furthermore, multiple guide rods are fixedly installed at the bottom of the support plate, and the guide rods are slidably connected to the corresponding pads and cantilever beams.

[0017] Furthermore, a second connecting pipe corresponding to the first connecting pipe is fixedly installed through the top of the support plate, and an insertion hole for insertion into the second connecting pipe is opened on the top of the drain pipe.

[0018] The beneficial effects of this utility model are as follows:

[0019] 1. The bridge structure of the prefabricated flower bed disclosed in this utility model provides suitable growth space for plants by opening a first trough on the top of the flower bed. This allows the bridge to not only meet traffic functions but also beautify the environment and improve ecological benefits. The fence seat set in the first trough divides it into a drainage channel and a second trough, realizing the separation of planting and drainage. The drainage channel can quickly collect and drain excess water from the road surface. The first connecting pipe on the top of the flower bed is connected to the drainage pipe fixed on the top of the cantilever beam. A second connecting pipe corresponding to the first connecting pipe is set on the top of the support plate. The top of the drainage pipe has a plug hole for insertion into the second connecting pipe, which ensures the smoothness and reliability of the drainage system. Even in severe weather conditions such as heavy rain, the accumulated water can be drained quickly, avoiding potential threats to the bridge structure from the accumulated water.

[0020] 2. The bridge structure of the precast flower bed disclosed in this utility model has multiple cantilever beams bolted to the outside of the steel box girder. The bottom of the cantilever beams is welded with support beams connected to the steel box girder, which enhances the load-bearing capacity of the cantilever beams and enables them to stably support the weight of the flower bed and its internal plants and soil. The support plate set on the top of the cantilever beams provides a reliable support platform for the flower bed. Multiple rollers bolted to the bottom of the flower bed cooperate with the first guide rail on the top of the support plate, allowing the flower bed to slide smoothly when it needs to be moved, reducing resistance during the movement process and ensuring the stability of the flower bed during the movement. In addition, multiple second guide rails fixedly set on the top of the cantilever beams are slidably connected to the sliding groove on one side of the flower bed, further enhancing the guidance and stability of the flower bed movement, preventing the flower bed from shifting or shaking during the movement, and ensuring the overall stability of the bridge structure.

[0021] 3. The bridge structure of the externally mounted precast flower bed disclosed in this utility model includes a lifting mechanism comprising multiple first electric push rods and a moving component. The moving component drives the multiple first electric push rods to start simultaneously. After moving to the designated position, the flower bed is lifted by the first electric push rods, allowing the flower bed to be lifted according to actual needs. For example, during bridge maintenance, the flower bed can be lifted to a certain height, facilitating inspection and repair of the bridge bottom by staff. When it is necessary to replace the plants or soil in the flower bed, it can also be easily lifted for related operations. In the moving component, a motor drives a winding roller to rotate, which in turn drives the wire rope to wind up and down, thereby causing multiple first sliders fixedly sleeved on the wire rope to move on a third guide rail, realizing the synchronous movement of the first electric push rods. This allows the first electric push rods to be moved to the designated position quickly, improving work efficiency. At the same time, the rotating shaft and pulley set at the output end of the first electric push rod, as well as the connection method between the second electric push rod and the first slider, make the lifting process more stable and reliable, reducing the impact on the flower bed and bridge structure during the lifting process.

[0022] 4. The bridge structure of the external precast flower bed disclosed in this utility model has two pads fixedly installed on the top of the cantilever beam for supporting the support plate. These not only provide stable support for the support plate, but also reserve installation space for the first electric push rod, making the overall structural layout more reasonable and compact. Multiple guide rods fixed at the bottom of the support plate are slidably connected to the corresponding pads and cantilever beam, further enhancing the stability of the support plate during the lifting process, preventing the support plate from shifting or tilting, and ensuring the safety and reliability of the flower bed lifting.

[0023] Other advantages, objectives, and features of this invention will be set forth in part in the description which follows, and in part will be apparent to those skilled in the art from the following examination and study, or may be learned from practice of this invention. The objectives and other advantages of this invention can be realized and obtained through the following description. Attached Figure Description

[0024] To make the objectives, technical solutions, and advantages of this utility model clearer, the preferred embodiments of this utility model will be described in detail below with reference to the accompanying drawings, wherein:

[0025] Figure 1 This is a three-dimensional structural diagram of the bridge structure of the externally mounted prefabricated flower bed of this utility model.

[0026] Figure 2 This utility model Figure 1 Schematic diagram of the central support plate and flower bed structure;

[0027] Figure 3 This utility model Figure 1 Schematic diagram of the central flower bed structure;

[0028] Figure 4 This utility model Figure 1 Schematic diagram of the cantilever beam structure;

[0029] Figure 5 This utility model Figure 1 Schematic diagram of the central lifting mechanism;

[0030] Figure 6 This utility model Figure 1 Schematic diagram of the take-up roll structure;

[0031] Figure 7 This utility model Figure 1 Schematic diagram of the drainage pipe structure.

[0032] Reference numerals: 1. Steel box girder; 2. Flower bed; 3. First pool trough; 4. Cantilever beam; 5. Support plate; 6. Guide rod; 7. Roller; 8. Drainage pipe; 9. Steel wire rope; 10. Rewinding cabinet; 11. First guide rail; 12. Pad block; 13. Slide groove; 14. Fence seat; 15. Drainage ditch; 16. Second pool trough; 17. First connecting pipe; 18. Support beam; 19. Second guide rail; 20. Third guide rail; 21. First slider; 22. First rotating seat; 23. First electric push rod; 24. Connecting seat; 25. Rotating shaft; 26. Pulley; 27. Second electric push rod; 28. Second rotating seat; 29. ​​Second slider; 30. Rewinding roller; 31. Motor; 32. Waist-shaped hole; 33. Second connecting pipe; 34. Insertion hole. Detailed Implementation

[0033] The following specific examples illustrate the implementation of this utility model. Those skilled in the art can easily understand other advantages and effects of this utility model from the content disclosed in this specification. This utility model can also be implemented or applied through other different specific embodiments, and various details in this specification can also be modified or changed based on different viewpoints and applications without departing from the spirit of this utility model.

[0034] like Figure 1 The bridge structure shown is an externally mounted prefabricated flower bed. This structure mainly consists of a steel box girder 1, flower beds 2, cantilever beams 4, a lifting mechanism, and drainage pipes 8. The steel box girder 1 serves as the main load-bearing structure of the bridge, providing the installation foundation for the flower beds 2 and other auxiliary components. The flower beds 2 are located outside the steel box girder 1, and their tops have a first planting trough 3. Figure 3 As shown, a fence seat 14 is provided on one side of the first pond 3, dividing the first pond 3 into a drainage channel 15 and a second pond 16. A gap is left between the fence seat 14 and the first pond 3 to allow excess water from the potted plants in the second pond 16 to overflow and drain through the drainage channel 15 along the gap between the fence seat 14 and the first pond 3. In practical applications, the fence seat 14 can be made of a metal material with sufficient strength and corrosion resistance, such as stainless steel. Its height can be designed according to the height requirements of the plants planted in the flower bed 2 to ensure effective separation of the drainage channel 15 and the second pond 16 without affecting plant growth.

[0035] like Figure 2The cantilever beams 4 shown are bolted to the outside of the steel box girder 1. Multiple cantilever beams 4 are evenly distributed to provide stable support. A support plate 5 is provided at the top of the cantilever beams 4 to guide the flower bed 2. Multiple rollers 7 are bolted to the bottom of the flower bed 2. A first guide rail 11 is fixed to the top of the support plate 5 to cooperate with the rollers 7. The rollers 7 can roll on the first guide rail 11, thereby realizing the movement of the flower bed 2 on the cantilever beams 4. A positioning block for positioning the outer rollers 7 is also welded inside the first guide rail 11. In actual installation, the diameter of the rollers 7 is approximately 20 cm. The first guide rail 11 can be made of wear-resistant steel, and its surface is smoothed to reduce the rolling resistance of the rollers 7. Figure 4 As shown, a support beam 18 is welded to the bottom of the cantilever beam 4, and the other side of the support beam 18 is welded to the steel box girder 1 to enhance the stability of the cantilever beam 4. The support beam 18 can be made of the same I-beam as the cantilever beam 4.

[0036] To further enhance the stability of the flower bed 2 during movement, multiple second guide rails 19 are fixedly installed on the top of the cantilever beam 4. These second guide rails 19 are vertically connected to the outside of the steel box beam 1 by bolts. One side of the flower bed 2 is provided with a sliding groove 13 that slides in connection with the second guide rails 19. The clearance between the second guide rails 19 and the sliding groove 13 should be controlled at approximately 2 mm to ensure that the flower bed 2 does not wobble during movement.

[0037] like Figure 5 The lifting mechanism shown is mounted on the cantilever beam 4 and is used to lift the flower bed 2. The lifting mechanism includes multiple first electric push rods 23 and a moving assembly. A drive assembly simultaneously activates the multiple first electric push rods 23, and after moving into position, the flower bed 2 is lifted via the first electric push rods 23. Two third guide rails 20 are welded to the top of the cantilever beam 4. A first slider 21 corresponding to the cantilever beam 4 is slidably fitted onto the outer wall of one of the third guide rails 20, and the first electric push rod 23 is mounted on the first slider 21. A rotating shaft 25 is fixedly mounted through the output end of the first electric push rod 23. Two pulleys 26 are rotatably mounted on the outer wall of the rotating shaft 25 via bearings, reducing friction between the first electric push rod 23 and the support plate 5.

[0038] A second slider 29, corresponding to the first slider 21, is slidably mounted on another third guide rail 20. A second rotating seat 28 is bolted to one side of the second slider 29, and a second electric push rod 27 is rotatably mounted inside the second rotating seat 28 via a pin. A first rotating seat 22 is bolted to one side of the first slider 21, and a first electric push rod 23 is rotatably mounted inside the first rotating seat 22 via a pin. A connecting seat 24 is fixedly mounted on the outer wall of the first electric push rod 23, and the output end of the second electric push rod 27 is rotatably mounted inside the connecting seat 24 via a pin. The extension and retraction of the second electric push rod 27 drives the first electric push rod 23 to rotate within the first rotating seat 22. During rotation, this drives the support plate 5 to move upwards. Furthermore, the extension of the first electric push rod 23 drives the support plate 5 to move upwards again, thus achieving a secondary movement of the support plate 5 and ensuring that the flower bed 2 is completely pushed out within a limited space.

[0039] like Figure 6 The movable assembly shown includes two winding cabinets 10 located below the steel box girder 1. A winding roller 30 is rotatably mounted inside each winding cabinet 10. A motor 31 is bolted to the inside of each winding cabinet 10, and the output end of the motor 31 is fixedly connected to the winding roller 30. A steel wire rope 9 is fixedly mounted on the outer wall of one of the winding rollers 30. The other end of the steel wire rope 9 is fixed and wound around the other winding roller 30. Multiple first sliders 21 are fixedly sleeved on the steel wire rope 9. A slotted hole 32 for accommodating the steel wire rope 9 is provided on the outer side of the winding cabinet 10. When the motor 31 starts, it drives the winding roller 30 to rotate, thereby realizing the winding and unwinding of the steel wire rope 9, allowing the steel wire rope 9 to move. During this movement, the first sliders 21 move on the third guide rail 20, realizing the movement of the first electric push rod 23, which can lift the corresponding flower bed 2 as needed.

[0040] Two pads 12 are fixedly installed at the top of the cantilever beam 4 to support the support plate 5, and the pads 12 are used to reserve installation space for the first electric push rod 23. Multiple guide rods 6 are fixedly installed at the bottom of the support plate 5, and the guide rods 6 are slidably connected to the corresponding pads 12 and the cantilever beam 4. The guide rods 6 ensure that the support plate 5 remains stable during the lifting process and does not shift.

[0041] Drainage pipe 8 is fixedly connected to the top of multiple cantilever beams 4. Multiple first connecting pipes 17 are threaded through the top of the flower bed 2. A second connecting pipe 33, corresponding to the first connecting pipe 17, is fixedly threaded through the top of the support plate 5. After the flower bed 2 is moved into position, the first connecting pipe 17 and the second connecting pipe 33 align, and the top of the second connecting pipe 33 is equipped with a sealing gasket to ensure that water does not leak out through the gap between the first and second connecting pipes 33. Figure 7As shown, the top of the drain pipe 8 has a socket 34 for insertion into the second connecting pipe 33. When the water in the flower bed 2 reaches a certain height, it can flow into the drain pipe 8 through the first connecting pipe 17 and the second connecting pipe 33, thereby realizing the drainage function. In addition, the support plate 5 can drive the second connecting pipe 33 to move in the socket 34 during the lifting and moving process, so that it can be easily connected.

[0042] When the bridge structure of the external prefabricated flower bed is in use, the motor 31 on one side is started to rotate forward, driving the winding roller 30 to rotate. The rotation of the winding roller 30 can wind up the wire rope 9. At the same time, the motor 31 on the other side is started to rotate in reverse, driving the winding roller 30 to rotate and unwinding the wire rope 9, which can drive the wire rope 9 to move.

[0043] During the movement of the wire rope 9, the first slider 21 can be driven to move on the third guide rail 20, so that it moves to the bottom of the corresponding flower bed 2. During the movement of the third guide rail 20, the second slider 29 can be driven to move on another third guide rail 20 through the connecting seat 24 and the second electric push rod 27.

[0044] After being moved into place, the second electric push rod 27 is activated to extend. During the extension of the second electric push rod 27, the first electric push rod 23 can be driven to swing upward. During the swing, the pulley 26 can be used to abut against the support plate 5 to move upward. The upward movement of the support plate 5 can drive the flower bed 2 to move upward.

[0045] When the second electric push rod 27 extends to its position, it continues to drive the first electric push rod 23 to extend, which can drive the support plate 5 to continue to move upward until the bottom of the flower bed 2 is flush with the top of the steel box beam 1. At this time, the flower bed 2 is disengaged from the second guide rail 19.

[0046] Pull the flower bed 2 onto the steel box beam 1, and then manually plant the flowers in the second pool trough 16 or place the potted plants directly in the second pool trough 16.

[0047] After planting, push the flower bed 2 onto the support plate 5 and move the roller 7 into the first guide rail 11 until the outer roller 7 touches the first guide rail 11. At this time, the first connecting pipe 17 and the second connecting pipe 33 correspond to each other.

[0048] When the first electric push rod 23 is activated and retracted, the support plate 5 can move downward under the gravity of the flower bed 2, and drive the second electric push rod 27 to retract. During the downward movement of the flower bed 2, it can be positioned by the second guide rail 19, and at the same time, it can drive the second connecting pipe 33 to be inserted into the corresponding socket 34.

[0049] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of this utility model and are not intended to limit it. Although this utility model has been described in detail with reference to preferred embodiments, those skilled in the art should understand that modifications or equivalent substitutions can be made to the technical solution of this utility model without departing from the spirit and scope of this technical solution, and all such modifications or substitutions should be covered within the scope of the claims of this utility model.

Claims

1. A bridge structure with externally mounted precast planters, characterized by, include: A steel box girder (1) and a flower bed (2) set on the outside of the steel box girder (1). A first pool trough (3) is opened on the top of the flower bed (2). A fence seat (14) is provided in the first pool trough (3). The fence seat (14) divides the first pool trough (3) into a drainage ditch (15) and a second pool trough (16) for planting plants. Multiple cantilever beams (4) are fixedly connected to the outside of the steel box beam (1) by bolts. The top of the cantilever beams (4) is provided with a support plate (5). The bottom of the flower bed (2) is connected with multiple rollers (7) by bolts. The top of the support plate (5) is fixedly provided with a first guide rail (11) that cooperates with the rollers (7). The lifting mechanism is installed on the cantilever beam (4) and includes multiple first electric push rods (23) and a moving component. The moving component drives the multiple first electric push rods (23) to move. The output end of the first electric push rod (23) is provided with a pulley (26) for lifting the flower bed (2). The drain pipe (8) is fixedly connected to the top of the multiple cantilever beams (4). The top of the flower bed (2) is provided with multiple first connecting pipes (17), and the first connecting pipes (17) are connected to the drain pipe (8). The lifting mechanism can drive the flower bed (2) to move and lift along the first guide rail (11) for easy maintenance. The water in the second pool (16) is discharged into the drain pipe (8) through the first connecting pipe (17).

2. The bridge structure with prefabricated flowerbeds as claimed in claim 1, characterized in that The top of the cantilever beam (4) is fixed with multiple second guide rails (19), which are vertically connected to the outside of the steel box beam (1) by bolts. The flower bed (2) is provided with a sliding groove (13) that is slidably connected to the second guide rails (19) on one side.

3. The precast planter add-on bridge structure of claim 1, wherein, Two third guide rails (20) are welded to the top of multiple cantilever beams (4). The outer wall of one of the third guide rails (20) is slidably fitted with a first slider (21) corresponding to the cantilever beam (4). A first electric push rod (23) is rotatably connected to the first slider (21). The output end of the first electric push rod (23) is fixedly connected to a rotating shaft (25). The outer wall of the rotating shaft (25) is rotatably connected to a pulley (26) through a bearing. Another third guide rail (20) is slidably fitted with a second slider (29) corresponding to the first slider (21). The second slider (29) is rotatably connected to a second electric push rod (27). The outer wall of the first electric push rod (23) is fixedly fitted with a connecting seat (24). The output end of the second electric push rod (27) is rotatably located in the connecting seat (24) through a pin.

4. The bridge structure with prefabricated flowerbeds according to claim 3, characterized in that, The first slider (21) is connected to a first rotating seat (22) by bolts on one side, and the first electric push rod (23) is rotatably disposed in the first rotating seat (22) by a pin. The second slider (29) is connected to a second rotating seat (28) by bolts on one side, and the second electric push rod (27) is rotatably disposed in the second rotating seat (28) by a pin.

5. The bridge structure with prefabricated flowerbeds according to claim 3, characterized in that, The moving assembly includes two winding cabinets (10) located below the steel box girder (1). A winding roller (30) is rotatably installed inside the winding cabinet (10). A motor (31) is bolted to the winding cabinet (10). The output end of the motor (31) is fixedly connected to the winding roller (30). A steel wire rope (9) is fixedly installed on the outer wall of one of the winding rollers (30). The other end of the steel wire rope (9) is fixed and wound around the other winding roller (30). Multiple first sliders (21) are fixedly sleeved on the steel wire rope (9). A waist-shaped hole (32) for accommodating the steel wire rope (9) is opened on the outer side of the winding cabinet (10).

6. The precast planter add-on bridge structure of claim 1, wherein, The top of the cantilever beam (4) is fixed with two pads (12) for supporting the support plate (5), and the pads (12) are used to reserve the installation space for the first electric push rod (23).

7. The bridge structure with prefabricated flowerbeds according to claim 6, characterized in that The bottom of the support plate (5) is fixedly provided with multiple guide rods (6), and the guide rods (6) are slidably connected to the corresponding pads (12) and cantilever beams (4).

8. The precast planter add-on bridge structure of claim 1, wherein, The top of the support plate (5) is fixedly provided with a second connecting pipe (33) corresponding to the first connecting pipe (17), and the top of the drain pipe (8) is provided with an insertion hole (34) for insertion into the second connecting pipe (33).