Permanent and temporary combined support pile retaining wall structure
By designing a permanent and temporary combined retaining pile retaining wall structure, which combines retaining piles, capping beams, and cantilever retaining walls, and using a tie structure to balance the eccentricity of the cantilever retaining wall, the construction obstacles caused by asynchronous construction progress were solved, the permanent transformation and safety of the retaining structure were achieved, and the project delivery requirements were met.
Patent Information
- Application Number
- CN202522793830.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2025-12-29
- Publication Date
- 2026-11-17
- Estimated Expiration
- 2035-12-29
AI Technical Summary
When the construction progress of adjacent plots is not synchronized, the foundation of the traditional wall cannot be implemented at the same time, which means that the support structure cannot play its retaining function in time during the foundation pit construction, affecting the delivery and use of the project. At the same time, there are also construction deformation and cost issues.
A combined temporary and permanent retaining wall structure is designed, including retaining piles, capping beams, cantilever retaining walls, and tie structures. By connecting the cantilever retaining wall with the main structure of the basement in the foundation pit through tie connections, the eccentricity problem of the cantilever retaining wall is balanced, realizing the combination of temporary support and permanent enclosure wall, and solving the problems of construction technology limitations and uneven stress distribution.
This enabled the direct conversion of the support system into a permanent structure, eliminating construction obstacles, saving time and costs, ensuring the safety and stability of the structure, allowing backfilling of earthwork before the foundation pit is backfilled, advancing the time for the work process, and meeting the project delivery requirements.
Smart Images

Figure CN224982201U_ABST
Abstract
Description
Technical Field
[0001] This utility model belongs to the field of slope protection technology, and specifically relates to a permanent and temporary combined support pile retaining wall structure. Background Technology
[0002] With the acceleration of urbanization and the increasing scarcity of construction land, urban buildings are generally designed with basements, and basement projects typically employ deep foundation pits close to the building's boundary line. When adjacent plots experience asynchronous construction progress due to differences in building nature, function, and delivery goals, the traditional retaining wall foundations between adjacent plots cannot be implemented simultaneously. According to relevant specifications and design requirements, loads cannot be placed on the pit top before backfilling is completed, thus preventing the construction of retaining walls and unilateral backfilling on the pit top, ultimately affecting project delivery. Due to the construction characteristics of the support structure, there is a certain distance between the support structure and the boundary line, preventing the retaining wall foundation from resting on support piles; underground pipelines that cannot be relocated may exist between plots, placing high demands on the support deformation during foundation pit construction. Utility Model Content
[0003] The purpose of this utility model is to overcome the shortcomings of the existing technology and provide a permanent and temporary combined support pile retaining wall structure. A cantilever retaining wall is set on the support pile cap beam structure of the foundation pit support to solve the problems of retaining wall foundation and pit edge surcharge. By setting tie structures in the backfill soil of the foundation pit bottom slab, the outer wall of the foundation pit basement and the top slab of the basement, the eccentricity problem of the cantilever retaining wall is balanced, and the lateral pressure of the backfill soil is avoided from affecting the support structure of the adjacent plot.
[0004] The technical solution of this utility model is a permanent and temporary combined support pile retaining wall structure, including:
[0005] Support piles are vertically installed at the edge of the foundation pit, with the bottom of the piles embedded in the bearing layer of the foundation.
[0006] The cap beam is cast and connected to the top of the support piles;
[0007] The cantilever retaining wall, as the foundation of the permanent enclosure wall, is fixed at its bottom to the capping beam through a cantilever structure and cantilevered outward from the foundation pit, and its wall body is provided with drainage holes;
[0008] A tie structure is connected between the support piles, capping beam, and cantilever retaining wall and the main structure of the basement in the foundation pit, and is used to balance the lateral pressure and overturning moment generated by the backfill soil on the cantilever retaining wall.
[0009] Preferably, the cantilever structure includes a cantilever plate connecting the cap beam and the cantilever retaining wall, and an upper stiffening plate and a lower stiffening plate disposed at the connection between the cantilever plate and the cantilever retaining wall.
[0010] Preferably, the pull structure includes at least one of the following:
[0011] The external wall tie assembly includes a first anchor embedded in the cap beam, a second anchor embedded at the connection position between the basement external wall and the basement roof beam, and a first tie rod connected between the first anchor and the second anchor.
[0012] The base plate tie rod assembly includes a first anchor, a pull-out anchor rod disposed on the basement base plate, a third anchor rod sleeved on the top of the pull-out anchor rod, and a second tie rod connected between the first anchor and the third anchor.
[0013] The retaining wall tie rod assembly includes a fourth anchor embedded in the cantilever retaining wall, an anchor plate fixed in the layered compacted backfill soil, and an anchor rod connected between the fourth anchor and the anchor plate.
[0014] Preferably, the first anchor, the second anchor, the third anchor, and the fourth anchor each include a pre-embedded connecting sleeve, and the end of the connecting sleeve is provided with a pull ring; wherein, the first anchor, the second anchor, and the fourth anchor also include a pre-embedded load-bearing steel plate fixedly connected to the corresponding connecting sleeve.
[0015] Preferably, a water-stop ring is also provided around the outer side of the connecting sleeve of the second and third anchors, and the water-stop ring is fully welded to the connecting sleeve.
[0016] Preferably, the water-stop ring has a thickness of 3mm and its outer diameter is 50mm larger than the diameter of the connecting sleeve.
[0017] Preferably, both the first and second pull rods are galvanized steel bars with the same structure, and both ends are provided with hooks for hooking the pull rings of the corresponding anchors; a turnbuckle is connected in series in the middle, and the tension of the pull rod is adjusted by turning the turnbuckle.
[0018] Preferably, the tie structure includes a replacement beam connecting the support pile and the basement exterior wall, one end of which is connected to the support pile by rebar installation, and the other end is anchored to the basement exterior wall by pre-embedded steel bars and cast-in-place.
[0019] Preferably, the system also includes a replacement support plate, which is a plain concrete structure that fills the space between the basement floor slab and the support piles, and has the same thickness as the basement floor slab.
[0020] Compared with the prior art, the beneficial effects of this utility model are as follows:
[0021] (1) Functional Integration for Permanent-Temporary Unity: By integrating the functions of the temporary support structure and the permanent wall foundation, and adopting an integrated design for the temporary support structure and the permanent wall foundation, the support system is directly transformed into a permanent structure. This structure serves as a retaining component during the foundation pit support stage and directly as the load-bearing foundation of the permanent wall in the later stages of the project. This completely eliminates the obstacle caused by the asynchronous construction progress of adjacent plots, which prevents the wall from being constructed synchronously with the main structure. It avoids secondary excavation and repeated construction, significantly saving time and costs.
[0022] (2) Reasonable stress distribution, solving the eccentricity problem: The cantilever retaining wall is arranged directly below the permanent retaining wall, which solves the fundamental contradiction that the support piles were set back from the boundary line due to construction technology limitations and that their positions did not coincide with the foundation of the retaining wall. In other words, the cantilever retaining wall solves the problem that the support structure and the permanent retaining wall are not in the same position. At the same time, by setting up a flexibly configurable tie structure, the overturning moment formed by the unilateral earth pressure borne by the cantilever retaining wall is effectively transferred to the stable basement main structure (bottom slab, outer wall) or soil inside the foundation pit for balance, forming a clear and reliable multi-path balance stress system, solving the eccentricity problem of the cantilever retaining wall, and ensuring the safety and stability of the structure throughout the entire life cycle from construction to use.
[0023] (3) Optimized timing, overcoming construction limitations: The permanent and temporary combined support pile retaining wall structure provided by this utility model allows for the simultaneous construction of the permanent retaining wall (i.e., the wall foundation) during the support stage before foundation pit excavation. This enables the retaining wall to perform its retaining function early and utilizes the existing foundation pit support system as its temporary support, thus cleverly circumventing the restriction in the regulations that "loads are prohibited on the top of the pit before backfilling." This allows for backfilling of the earthwork and site preparation outside the retaining wall before the foundation pit is backfilled, significantly advancing the time for subsequent procedures and providing a crucial guarantee for the overall project delivery. Attached Figure Description
[0024] Figure 1 This is a schematic diagram of the structure of a permanent and temporary combined support pile retaining wall structure according to the present invention.
[0025] Figure 2 yes Figure 1 Enlarged schematic diagram of the first anchor connection at point A in the middle;
[0026] Figure 3 yes Figure 1 Enlarged schematic diagram of the second anchor connection at point B;
[0027] Figure 4 yes Figure 1 Enlarged schematic diagram of the third anchor connection at point C;
[0028] Figure 5 yes Figure 1Enlarged schematic diagram of the fourth anchor connection at point D;
[0029] Figure 6 yes Figure 1 A schematic diagram of the structure of the first tie rod;
[0030] Figure 7 This is a schematic diagram of the structure of a permanent and temporary combined support pile retaining wall structure according to Embodiment 2 of this utility model;
[0031] Figure 8 yes Figure 7 Enlarged schematic diagram of the replacement beam connection at point E.
[0032] Explanation of key component symbols:
[0033] 1. Support pile; 2. Crown beam; 3. Cantilever retaining wall; 31. Drainage hole; 4. Tie structure; 41. First anchor; 411. First connecting sleeve; 412. First load-bearing steel plate; 413. First pull ring; 42. Second anchor; 421. Second connecting sleeve; 422. Second load-bearing steel plate; 423. Second pull ring; 424. First water-stop ring; 43. First tie rod; 431. Upper tie rod; 432. Lower tie rod; 433. Turnbuckle; 434. Upper hook; 435. Lower hook; 44. Pull-out anchor; 45. Third anchor; 451. Third pull ring; 452. Second water-stop ring 453; Second tie rod 46; Fourth anchor 47; Fourth connecting sleeve 471; Fourth load-bearing steel plate 472; Fourth tie ring 473; Anchor plate 48; Anchor rod 49; Foundation bearing layer 5; Permanent wall 6; Cantilever structure 7; Cantilever slab 71; Upper stiffening plate 72; Lower stiffening plate 73; Basement main structure 8; Basement exterior wall 81; Basement top beam slab 82; Basement floor slab 83; Replacement support plate 84; Internal support beam 85; Replacement support beam 86; Anchoring steel bar 861; Basement beam slab 87; Underground pipelines 9; Underground structures 10. Detailed Implementation
[0034] This utility model will be further described in detail below with reference to the accompanying drawings:
[0035] Example 1
[0036] This embodiment provides a permanent and temporary combined retaining wall structure with pile supports, suitable for single-story basement foundation pits. For example... Figure 1As shown, the permanent and temporary combined retaining wall structure includes: retaining piles 1, capping beam 2, cantilever retaining wall 3, and tie structure 4. The retaining piles 1 are vertically installed at the edge of the foundation pit, with their bottoms embedded in the bearing layer 5 of the foundation to ensure vertical load-bearing capacity. The capping beam 2 is cast and connected to the top of the retaining piles 1. The cantilever retaining wall 3 is located directly below the permanent retaining wall 6, serving as the foundation of the permanent retaining wall 6. Its bottom is fixed to the capping beam 2 via a cantilever structure 7 and cantilevered outwards from the foundation pit. The wall body is equipped with drainage holes 31 to drain accumulated water from the backfill behind the wall, eliminating the additional hydrostatic pressure generated by the accumulated water and ensuring the structural safety of the retaining wall. The tie structure connects the retaining piles 1, capping beam 2, and cantilever retaining wall 3 to the main basement structure 8 within the foundation pit, balancing the lateral pressure and overturning moment generated by the backfill soil on the cantilever retaining wall 3.
[0037] It is worth noting that due to the construction characteristics of the support structure, there is a certain distance between the support structure and the red line, and the foundation of the wall cannot be placed on the support piles; furthermore, if Figure 1 As shown, there are underground pipelines 9 and adjacent underground structures 10 outside the foundation pit that cannot be demolished or altered, which places high demands on the support deformation during the foundation pit construction. Therefore, the permanent and temporary combined support pile retaining wall structure provided in this embodiment sets up a cantilever retaining wall 3 on the support pile cap beam structure of the foundation pit support to solve the problems of retaining wall foundation and pit edge surcharge. By setting a tie structure 4 between the cantilever load-bearing part composed of support piles 1, cap beam 2 and cantilever retaining wall 3 and the basement main structure 8 in the foundation pit, the eccentricity problem of the cantilever retaining wall is balanced, and the lateral pressure of the backfill soil is avoided from affecting the support structure of the adjacent plot.
[0038] Please see Figure 1 As shown, the cantilever structure 7 includes a cantilever plate 71 connecting the cap beam 2 and the cantilever retaining wall 3, and an upper stiffening plate 72 and a lower stiffening plate 73 set at the connection between the cantilever plate 71 and the cantilever retaining wall 3. By setting the reinforced concrete upper stiffening plate 72 and lower stiffening plate 73, the stress of the cantilever retaining wall 3 during the backfilling process is guaranteed.
[0039] Please see Figure 1 As shown, in the structure of a single-story basement, the tie structure 4 includes at least one of the following: external wall tie assembly, base plate tie assembly, and retaining wall tie assembly.
[0040] The external wall tie assembly includes a first anchor 41 embedded in the cap beam 2, a second anchor 42 embedded at the connection position between the basement external wall 81 and the basement top beam 82, and a first tie rod 43 connected between the first anchor 41 and the second anchor 42.
[0041] The base plate tie rod assembly includes a first anchor 41, an anti-pull-out anchor 44 disposed on the basement base plate, a third anchor 45 sleeved on the top of the anti-pull-out anchor 44, and a second tie rod 46 connecting the first anchor 41 and the third anchor 45.
[0042] The retaining wall tie assembly includes a fourth anchor 47 pre-embedded in the cantilever retaining wall 3, an anchor plate 48 fixed in the layered compacted backfill soil, and an anchor rod 49 connecting the fourth anchor 47 and the anchor plate 48.
[0043] It is worth noting that, in actual construction, the tie structure 4 is installed after the main basement structure 8 is ready to bear loads. If external wall tie is used, the first tie rod 43 is installed between the first anchor 41 and the second anchor 42. If base plate tie is used, the second tie rod 46 is installed between the first anchor 41 and the third anchor 45. If retaining wall tie is used, during layered backfilling, the soil is compacted as it is filled, and one end of the anchor rod 49 is connected to the fourth anchor 47, while the other end is anchored in the compacted soil layer with the anchor plate 48. Any one, two, or all of these three methods can be used in combination to meet design and construction requirements.
[0044] Furthermore, the first anchor 41, the second anchor 42, the third anchor 45, and the fourth anchor 47 each include a pre-embedded connecting sleeve, with a pull ring at the end of the connecting sleeve for easy connection of the pull rod; wherein, the first anchor, the second anchor, and the fourth anchor also include a pre-embedded load-bearing steel plate fixedly connected to the corresponding connecting sleeve to increase the load-bearing area and increase the pull-out resistance; the connecting sleeves of the second anchor and the third anchor are also provided with a water-stop ring on the outside, the water-stop ring is 3mm thick, and its outer diameter is 50mm larger than the diameter of the connecting sleeve, and the water-stop ring is fully welded to the connecting sleeve to prevent water leakage.
[0045] For details, please refer to Figure 2 As shown, the first anchor 41 includes a first connecting sleeve 411 and a first load-bearing steel plate 412 pre-embedded in the cap beam 2. The end of the first connecting sleeve 411 is provided with a first pull ring 413 to form a first anchor end, which serves as the point of force for the first tie rod and / or the second tie rod to pull against each other during the earthwork backfilling process.
[0046] Please see Figure 3 As shown, the second anchor 42 includes a second connecting sleeve 421 and a second load-bearing steel plate 422 pre-embedded in the basement exterior wall 81. The end of the second connecting sleeve 421 is provided with a second pull ring 423, forming a second anchoring end, which serves as the force point for the first tie rod during the backfilling process. Since the basement exterior wall 81 has waterproofing requirements, a first water-stop ring 424 is welded around the middle of the second connecting sleeve 421.
[0047] Please see Figure 4As shown, the third anchor 45 includes a third connecting sleeve 451 pre-embedded in the basement floor slab 83. The third connecting sleeve 451 is sleeved on the top of the pull-out anchor rod 44. The end of the third connecting sleeve 451 is provided with a third pull ring 452, forming a third anchoring end, which serves as the force point for the second tie rod during the backfilling process. Since the basement floor slab 83 has waterproofing requirements, a second water-stop ring 453 is welded around the middle of the third connecting sleeve 451.
[0048] Please see Figure 5 As shown, the fourth anchor 47 includes a fourth connecting sleeve 471 and a fourth load-bearing steel plate 472 pre-embedded in the cantilever retaining wall 3. The end of the fourth connecting sleeve 471 is provided with a fourth pull ring 473, forming a fourth anchoring end, which serves as the point of force for the anchor rod to pull during the backfilling process.
[0049] In this embodiment, the first pull rod 43 and the second pull rod 46 are both galvanized steel bars with the same structure. The two ends of the pull rod are provided with hooks for hooking the pull rings of the corresponding anchors. A turnbuckle is connected in series in the middle of the pull rod, and the tension of the pull rod can be adjusted by turning the turnbuckle.
[0050] Specifically, such as Figure 6 As shown, the first pull rod 43 includes an upper pull rod 431, a lower pull rod 432, and a turnbuckle 433. One end of the upper pull rod 431 is provided with an upper hook 434 for hooking the second pull ring 423, and the other end is provided with an external thread. One end of the lower pull rod 432 is provided with a lower hook 435 for hooking the first pull ring 413, and the other end is provided with an external thread. The external threads of the upper pull rod 431 and the lower pull rod 432 are fastened to the internal threads of the turnbuckle 433 to adjust the tension of the first pull rod 43.
[0051] Please see Figure 1 As shown, the permanent and temporary combined retaining pile retaining wall structure also includes a replacement support plate 84, which is a plain concrete structure that fills the space between the basement floor slab 83 and the retaining pile 1, and its thickness is the same as that of the basement floor slab 83.
[0052] The construction process of the permanent and temporary combined support pile retaining wall structure provided in this embodiment is as follows:
[0053] 1. Install support piles: Construct a row of support piles at the edge of the foundation pit. In addition to meeting the horizontal force requirements of the foundation pit support, the support piles also need to consider the load of the retaining wall and the backfill soil above the retaining wall. The support piles need to enter the corresponding bearing layer to ensure vertical force.
[0054] 2. Casting of the capping beam and installation of the first anchor: Cast a reinforced concrete capping beam on top of the support piles to connect them into a whole; during the construction of the capping beam structure, pre-embed the first anchor as the point of force for the first tie rod and / or the second tie rod during the earthwork backfilling process.
[0055] 3. Cantilever Retaining Wall Construction and Fourth Anchor Installation: The cantilever retaining wall is constructed on the capping beam. The distance between the retaining wall and the support piles is relatively large. The retaining wall is fixed by a reinforced concrete cantilever slab extending from the capping beam, and upper and lower stiffening plates are installed at the connection to enhance bending resistance and ensure the stress distribution during backfilling. Drainage holes are pre-reserved in the retaining wall body, and the fourth anchor is pre-embedded on the side adjacent to the foundation pit. Since the cantilever retaining wall is located directly below the permanent retaining wall, this retaining wall serves as the direct foundation for the later permanent retaining wall.
[0056] 4. Excavation of the foundation pit.
[0057] 5. Construction of pull-out anchor bolts: When the earthwork is excavated to the bottom of the foundation pit, an anchor bolt machine is used to drill a hole with a diameter of about 300mm at the bottom of the foundation pit, and steel bars are placed in the hole. Cement grout is then poured in. After the cement grout has solidified, the installation of pull-out anchor bolts is completed.
[0058] 6. Construction of basement floor slab and replacement support plate and installation of third anchor: During the construction of basement floor slab, a third anchor is installed at the top of the pull-out anchor for connection of the second tie rod.
[0059] 7. Construction of basement walls, columns, beams, slabs, and roof slab, and installation of the second anchor: During the construction of the basement, a second anchor is pre-embedded at the connection position between the basement exterior wall and the roof beam slab for the connection of the first tie rod.
[0060] 8. Tie Rod Installation: After the basement main structure is ready to bear loads, install the tie rod structure according to design requirements. If external wall tie rods are used, install the first tie rod between the first and second anchors. If base slab tie rods are used, install the second tie rod between the first and third anchors. If retaining wall tie rods are used, compact the soil as you backfill, connecting one end of the anchor rod to the fourth anchor and anchoring the other end to the compacted soil layer with an anchor plate. Any one, two, or a combination of these three methods can be used.
[0061] 9. Backfill below the basement roof slab.
[0062] 10. When using retaining walls with tie rods, install anchor rods: one end of the anchor rod holds the anchoring end of the cantilever retaining wall, and the other end is the anchoring end. During the backfilling of the upper layer of soil, after the lower layer of soil is compacted, install the anchor plate and anchor rod, and then carry out the backfilling of the upper layer of soil, so that the anchor rod is anchored in the backfill soil and holds the cantilever retaining wall.
[0063] 11. Earthwork backfilling.
[0064] 12. Permanent wall installation: After the earthwork is backfilled to the design elevation, the permanent wall will be installed.
[0065] 13. Backfilling outside the retaining wall: After the foundation pit of the adjacent plot is backfilled to the design elevation, the retaining wall is buried in the soil. At this point, the earthwork lateral pressure on both sides of the retaining wall is basically balanced. After this, the tie structure will no longer be used as the main load-bearing component and will be converted into a safety reserve.
[0066] Example 2
[0067] Example 2 provides a permanent and temporary combined retaining wall structure, suitable for deep foundation pits containing multi-story basements and internal supports. The difference from Example 1 lies in the different tie structure. In the multi-story basement, due to the presence of internal support beams 85 and replacement beams 86, the replacement beam structure is anchored to the retaining piles 1 and the basement exterior wall 81. The replacement beam 86 replaces the tie structure 4 in Example 1 for balancing the cantilever retaining wall 3.
[0068] Please see Figure 7 , Figure 8 As shown, in this embodiment, the tie structure includes a replacement beam 86 connecting the support pile 1 and the basement exterior wall 81. The replacement beam 86 has a cross-section of 500*500mm and is a reinforced concrete structure. It is anchored to the basement exterior wall 81 and the basement beam 87 at one end by anchoring the anchoring steel bar 861, and the other end is anchored to the support pile 1. The anchoring steel bar 861 is connected to the support pile 1 by rebar installation, and the anchoring steel bar 861 is connected to the basement exterior wall 81 by cast-in-place anchoring.
[0069] The construction process of the permanent and temporary combined support pile retaining wall structure provided in this embodiment is as follows:
[0070] 1. Drive support piles;
[0071] 2. Casting the cap beam and internal support beam: When casting the cap beam, the reinforced concrete internal support beam connected to the cap beam is constructed simultaneously to form the initial form of the tie structure.
[0072] 3. Construction of cantilever retaining wall.
[0073] 4. Excavation of the foundation pit: Excavation is carried out in layers. After excavation to the bottom slab elevation of each layer, the basement structure of each layer is constructed in sequence.
[0074] 5. Construction of basement floor slab and replacement support slab: When construction reaches the lowest floor slab, pour the replacement support slab.
[0075] 6. Construction of basement walls, columns, beams, slabs and replacement beams: After the basement exterior walls have reached a certain strength, replacement beams will be constructed at the preset elevation. The replacement beams are 500*500mm reinforced concrete beams. One end of the beam is anchored to the basement exterior wall by pre-embedded steel bars, and the other end is reliably connected to the support piles by rebar installation.
[0076] 7. Removal of internal support beam: After the concrete of the replacement support beam reaches the design strength and can effectively transmit horizontal forces, the original internal support beam can be removed according to the conventional construction process; at this point, the responsibility of balancing the overturning moment of the cantilever retaining wall is smoothly transferred from the internal support beam to the replacement support beam.
[0077] 8. Construction of basement walls, columns, beams, slabs, and roof slabs.
[0078] 9. Basement backfilling.
[0079] The subsequent construction of basement walls, columns, beams, slabs, and roof slabs, basement backfilling, and permanent wall installation are similar to those in Example 1. Once the foundation pit of the adjacent plot is backfilled to the design elevation, the retaining wall is buried in the soil, at which point the earthwork lateral pressure on both sides of the retaining wall is basically balanced.
[0080] The above description is only a preferred embodiment of the present utility model. All equivalent changes and modifications made within the scope of the claims of the present utility model should be covered by the claims of the present utility model.
Claims
1. A permanent-temporary combined support pile retaining wall structure, characterized by, include: Support piles are vertically installed at the edge of the foundation pit, with the bottom of the piles embedded in the bearing layer of the foundation. The cap beam is cast and connected to the top of the support piles; The cantilever retaining wall, as the foundation of the permanent enclosure wall, is fixed at its bottom to the capping beam through a cantilever structure and cantilevered outward from the foundation pit, and its wall body is provided with drainage holes; A tie structure is connected between the support piles, capping beam, and cantilever retaining wall and the main structure of the basement in the foundation pit, and is used to balance the lateral pressure and overturning moment generated by the backfill soil on the cantilever retaining wall.
2. The permanent-temporary combined support pile retaining wall structure according to claim 1, characterized by, The cantilever structure includes a cantilever plate connecting the cap beam and the cantilever retaining wall, and an upper stiffening plate and a lower stiffening plate disposed at the connection between the cantilever plate and the cantilever retaining wall.
3. The permanent and temporary combined support pile retaining wall structure according to claim 1, characterized in that, The pull structure includes at least one of the following: The external wall tie assembly includes a first anchor embedded in the cap beam, a second anchor embedded at the connection position between the basement external wall and the basement roof beam, and a first tie rod connected between the first anchor and the second anchor. The base plate tie rod assembly includes a first anchor, a pull-out anchor rod disposed on the basement base plate, a third anchor rod sleeved on the top of the pull-out anchor rod, and a second tie rod connected between the first anchor and the third anchor. The retaining wall tie rod assembly includes a fourth anchor embedded in the cantilever retaining wall, an anchor plate fixed in the layered compacted backfill soil, and an anchor rod connected between the fourth anchor and the anchor plate.
4. The permanent and temporary combined support pile retaining wall structure according to claim 3, characterized in that, The first anchor, the second anchor, the third anchor, and the fourth anchor each include a pre-embedded connecting sleeve, and the end of the connecting sleeve is provided with a pull ring; wherein, the first anchor, the second anchor, and the fourth anchor also include a pre-embedded load-bearing steel plate fixedly connected to the corresponding connecting sleeve.
5. The permanent and temporary combined support pile retaining wall structure according to claim 4, characterized in that, The second and third anchors are also provided with a water-stop ring on the outer side of the connecting sleeve, and the water-stop ring is fully welded to the connecting sleeve.
6. The permanent and temporary combined support pile retaining wall structure according to claim 5, characterized in that, The water-stop ring is 3mm thick, and its outer diameter is 50mm larger than that of the connecting sleeve.
7. The permanent and temporary combined support pile retaining wall structure according to claim 4, characterized in that, The first and second pull rods are both galvanized steel bars with the same structure. They are equipped with hooks at both ends for hooking the pull rings of the corresponding anchors. Turnbuckles are connected in series in the middle, and the tension of the pull rods can be adjusted by turning the turnbuckles.
8. The permanent and temporary combined support pile retaining wall structure according to claim 1, characterized in that, The tie structure includes a replacement beam connecting the support pile and the basement exterior wall. One end of the beam is connected to the support pile by rebar installation, and the other end is anchored to the basement exterior wall by pre-embedded steel bars and cast-in-place.
9. The permanent and temporary combined support pile retaining wall structure according to claim 1, characterized in that, It also includes a replacement support plate, which is a plain concrete structure that fills the space between the basement floor slab and the support piles, and has the same thickness as the basement floor slab.