Semiconductor manufacturing apparatus, and semiconductor manufacturing method
Patent Information
- Application Number
- JP2021192442
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2021-11-26
- Publication Date
- 2024-11-06
- Estimated Expiration
- 2041-11-26
AI Technical Summary
Existing semiconductor manufacturing apparatuses face challenges in efficiently controlling gas concentration and cleaning processes in both ALD and CVD methods, leading to wasteful gas consumption and process delays, especially when using liquid or solid materials as gas sources.
A semiconductor manufacturing apparatus and method that includes a canister, fill tank, process chamber, and densitometers to control gas supply and concentration, utilizing valves and densitometers to optimize gas flow and cleaning processes, ensuring precise control and efficient use of gases.
The solution minimizes unnecessary gas consumption and shortens process time by accurately measuring and controlling gas concentrations and cleaning processes, thereby improving efficiency and quality in semiconductor manufacturing.
Smart Images

Figure 00000000_0000_ABST
Abstract
Description
[Technical Field]
[0001] The present invention relates to a semiconductor manufacturing apparatus and a semiconductor manufacturing method, and more particularly to a semiconductor manufacturing apparatus equipped with a densitometer and a semiconductor manufacturing method using the same.
[0002] Semiconductor manufacturing equipment is configured to supply material gases to a process chamber and form films on wafers or substrates using methods such as CVD (Chemical Vapor Deposition) and ALD (Atomic Layer Deposition).Mass flow controllers (thermal mass flow controllers) and pressure-type flow control devices are widely used to control the flow rate of gases supplied to the process chamber.
[0003] Recently, semiconductor manufacturing equipment has been developed that vaporizes or sublimates liquid or solid materials using a heater to generate the desired gas within a canister, which is then supplied to the process chamber. Examples of liquid or solid materials include hafnium chloride (solid at room temperature), organolanthanum compounds (solid at room temperature), and organoruthenium compounds (liquid at room temperature). These materials are used as precursors for producing high-k dielectric films (e.g., hafnium oxide films, lanthanum oxide films), and ruthenium-containing electrode films.
[0004] By using these high-k films instead of conventional silicon oxide films to form transistor gate insulating films and capacitor dielectric films, it is possible to achieve higher density and finer integrated circuits. Hafnium dioxide-based compounds are also attracting attention as materials for fabricating high-performance ferroelectric memories. Ruthenium-containing materials are expected to be next-generation fine wiring materials or barrier metal layer materials to replace copper wiring. [Prior art documents] [Patent documents]
[0005] [Patent Document 1] International Publication No. 2020 / 158506 [Patent Document 2] Japanese Patent Application Publication No. 9-203707 Summary of the Invention [Problem to be solved by the invention]
[0006] In the ALD method, a pulsed batch supply of gas is repeatedly supplied to the process chamber. Before film formation, the process chamber must be cleaned to remove any remaining unwanted chemicals. Conventionally, cleaning has been achieved by stopping the supply of source gases and then continuously flowing an inert gas or other gas into the process chamber for a certain period of time while evacuating the chamber. However, this method makes it difficult to determine whether cleaning has been achieved reliably. Therefore, a practical solution is to continue flowing the cleaning gas for a longer period than necessary.
[0007] Furthermore, when continuously supplying gas in a CVD process, the concentration of the process gas may be adjusted by adjusting the mixture ratio of the source gas and the dilution gas before being supplied to the chamber. In this case, to determine whether the gas filled in the process chamber has the desired concentration, it is preferable to directly measure the gas concentration in the process chamber using a concentration meter. However, it is not easy to install a concentration meter in the process chamber, and simply installing a concentration meter in one location can sometimes make it difficult to determine whether the gas concentration in the chamber is uniform. For this reason, a practical solution has been to continue flowing a mixed gas whose concentration has been confirmed for a relatively long time until the gas concentration in the process chamber becomes uniform and the desired concentration, and then close the exhaust system and start the film formation process.
[0008] In semiconductor manufacturing equipment compatible with ALD and CVD processes, excessive flow of cleaning gas or concentration-adjusted process gas into the chamber results in unnecessary gas consumption and process delays. Therefore, there is a need for a semiconductor manufacturing equipment and method that can be used with both ALD and CVD processes and that can reduce the period of unnecessary gas outflow and shorten the process time. Furthermore, there is a need for such a semiconductor manufacturing equipment and method that is effective even in systems that use liquid or solid materials as gas supply sources and have a dilution gas line connected to the process gas supply line.
[0009] The present invention has been made in consideration of the above-mentioned problems, and its main object is to provide a semiconductor manufacturing apparatus and a semiconductor manufacturing method that can accommodate both batch and continuous gas supply and can shorten the period of unnecessary gas outflow to reduce the process time. [Means for solving the problem]
[0010] A semiconductor manufacturing apparatus according to an embodiment of the present invention comprises a canister capable of storing a material gas, a fill tank provided downstream of the canister, a process chamber provided downstream of the fill tank, a tank downstream valve provided in a flow path between the fill tank and the process chamber, an exhaust line connected to the process chamber, an exhaust valve provided in the exhaust line, a first concentration meter provided in a flow path between the fill tank and the process chamber, and a second concentration meter provided in the exhaust line.
[0011] In one embodiment, a dilution gas supply line is connected to a flow path between the fill tank and the first concentration meter, and the dilution gas supply line is provided with a dilution gas supply valve.
[0012] In one embodiment, the semiconductor manufacturing apparatus further includes a control device that controls the gas supply to the process chamber based on the measurement values of the first concentration meter and the second concentration meter, and the control device is configured to determine that the gas concentration in the process chamber is the specified concentration when the concentrations output by the first concentration meter and the second concentration meter become approximately the same.
[0013] In one embodiment, the semiconductor manufacturing apparatus further includes a third concentration meter that measures the concentration of the material gas stored in the canister.
[0014] In one embodiment, the canister is configured to vaporize or sublimate a liquid or solid material to generate a material gas.
[0015] A semiconductor manufacturing method according to an embodiment of the present invention is carried out using a semiconductor manufacturing apparatus including: a canister capable of storing a source gas; a fill tank provided downstream of the canister; a process chamber provided downstream of the fill tank; a tank downstream valve provided in a flow path between the fill tank and the process chamber; an exhaust line connected to the process chamber; an exhaust valve provided in the exhaust line; a first concentration meter provided in a flow path between the fill tank and the process chamber; and a second concentration meter provided in the exhaust line. The method includes the steps of: supplying the source gas in the canister to the fill tank while closing the tank downstream valve; opening the tank downstream valve to supply the source gas supplied to the fill tank to the process chamber; opening the dilution gas supply valve and the exhaust valve to supply and exhaust dilution gas to the process chamber after a chemical reaction of the source gas supplied to the process chamber occurs; stopping the supply and exhaust of the dilution gas based on an output of the second concentration meter; and performing a process in the process chamber after stopping the supply and exhaust of the dilution gas.
[0016] A semiconductor manufacturing method according to an embodiment of the present invention is carried out using a semiconductor manufacturing apparatus including: a canister capable of storing a material gas; a fill tank provided downstream of the canister; a process chamber provided downstream of the fill tank; a tank downstream valve provided in a flow path between the fill tank and the process chamber; a dilution gas supply line connected to a flow path between the fill tank and the process chamber; a dilution gas supply valve provided in the dilution gas supply line; an exhaust line connected to the process chamber; an exhaust valve provided in the exhaust line; a first concentration meter provided in a flow path between a connection portion of the dilution gas supply line and the process chamber; and a second concentration meter provided in the exhaust line, The method includes the steps of: supplying the material gas in the canister to the fill tank while the tank downstream valve is closed; opening the tank downstream valve to supply the material gas supplied to the fill tank to the process chamber; opening the dilution gas supply valve and the exhaust valve to supply a mixed gas of the material gas and dilution gas to the process chamber and exhausting it; adjusting the concentration of the mixed gas by controlling the flow rate of the dilution gas based on the output of the first concentration meter; determining the concentration of the mixed gas in the process chamber by referring to both the output of the first concentration meter and the output of the second concentration meter; and performing a process in the process chamber using the mixed gas determined to be at a predetermined concentration.
[0017] In one embodiment, the semiconductor manufacturing apparatus further includes a purge gas supply line provided downstream of the fill tank, and the semiconductor manufacturing method further includes the steps of: after performing a process in a process chamber using the mixed gas, supplying purge gas from the purge gas supply line to the process chamber via the fill tank; and, referring to the outputs of the first concentration meter and the second concentration meter, stopping the supply of purge gas when the concentration of the material gas becomes equal to or lower than a predetermined concentration. [Effects of the Invention]
[0018] According to the semiconductor manufacturing method and semiconductor manufacturing method of the embodiments of the present invention, it is possible to reduce the process time by suppressing the outflow of unnecessary gas. [Brief explanation of the drawings]
[0019] [Figure 1] 1 is a schematic diagram showing a semiconductor manufacturing apparatus according to a first embodiment of the present invention. [Figure 2] 1 is a flowchart illustrating a semiconductor manufacturing method according to an embodiment of the present invention. [Figure 3] 4 is a flowchart illustrating a semiconductor manufacturing method according to another embodiment of the present invention. [Figure 4] FIG. 10 is a schematic diagram showing a semiconductor manufacturing apparatus according to a second embodiment of the present invention. [Figure 5] FIG. 10 is a schematic diagram showing a semiconductor manufacturing apparatus according to a third embodiment of the present invention. DETAILED DESCRIPTION OF THE INVENTION
[0020] Hereinafter, embodiments of the present invention will be described with reference to the drawings, but the present invention is not limited to the following embodiments.
[0021] (Embodiment 1) 1 shows the configuration of a semiconductor manufacturing apparatus 100 according to a first embodiment of the present invention. The semiconductor manufacturing apparatus 100 includes a canister 10 containing a source gas supply source, a third valve (canister valve) V3 provided on the outlet side of the canister, a fill tank 20 provided in a flow path downstream of the canister 10, a process chamber 30 provided downstream of the fill tank 20, and an exhaust line 40 for exhausting gas from the process chamber 30. The semiconductor manufacturing apparatus 100 is configured so that the source gas Gm in the canister 10 can be temporarily stored in the fill tank 20 and then supplied to the process chamber 30.
[0022] In this embodiment, the canister 10 is equipped with a heater (not shown) and is configured to heat and gasify a material gas source that is liquid or solid at room temperature, such as hafnium chloride, an organolanthanum compound, or an organoruthenium compound. As long as there is a sufficient amount of material gas source, gasification continues inside the canister 10 until a vapor pressure determined by the gas temperature and the material is reached. However, the canister 10 is not limited to this and may be a pressure vessel that stores a material that is originally in a gaseous state.
[0023] A fourth valve (tank upstream valve) V4 is provided upstream of the fill tank 20, and a fifth valve (tank downstream valve) V5 is provided downstream of the fill tank 20. Furthermore, a sixth valve (chamber upstream valve) V6 is provided upstream of the process chamber 30, and a seventh valve (exhaust valve) V7 is provided in the exhaust line 40 on the downstream side.
[0024] A purge gas supply line 50 having a second valve (purge gas supply valve) V2 is connected to the flow path between the canister valve V3 and the tank upstream valve V4. The semiconductor manufacturing apparatus 100 can supply either or both of the purge gas Gp and the material gas Gm to the process chamber 20 by controlling the opening and closing of the purge gas supply valve V2 and the canister valve V3.
[0025] A dilution gas supply line 60 having a first valve (dilution gas supply valve) V1 is connected to the flow path between the tank downstream valve V5 and the chamber upstream valve V6. A flow rate controller 62 is provided on the dilution gas supply line 60. The flow rate controller 62 may be, for example, a thermal mass flow controller or a pressure flow rate controller. By adjusting the aperture of a control valve (for example, a proportional valve such as a piezoelectric element-driven valve) of the flow rate controller 62, the dilution gas Gd can be supplied to the process chamber 20 at a desired flow rate.
[0026] The first to seventh valves V1 to V7 provided in each flow path are preferably on-off valves with excellent shutoff and responsiveness, such as AOVs (air-operated valves), solenoid valves, or motor-operated valves, but are not limited thereto, and control valves with adjustable openings can also be used as the first to seventh valves V1 to V7.
[0027] Furthermore, in the semiconductor manufacturing apparatus 100 of this embodiment, a first concentration meter (chamber upstream concentration meter) UV1 is provided upstream of the process chamber 30, more specifically, in the flow path between the connection point J of the dilution gas supply line 60 to the process gas supply line and the chamber upstream valve V6. Furthermore, a second concentration meter (exhaust line concentration meter) UV2 is provided in the exhaust flow path 40 downstream of the process chamber 30, more specifically, in the flow path between the exhaust valve V7 and an exhaust device such as a vacuum pump (not shown).
[0028] The first densitometer UV1 and the second densitometer UV2 may be, for example, the optical densitometer disclosed in Patent Document 1 (WO 2020 / 158506) by the present applicant. This optical densitometer is incorporated inline into the fluid system and is configured to measure the absorbance of the gas in the cell by measuring the transmitted light intensity of light from a light source that passes through a measurement cell into which the gas is introduced. The gas concentration can be calculated from the measured absorbance based on the Beer-Lambert law.
[0029] The wavelength of the light source light is appropriately selected according to the absorption characteristics of the gas to be measured. For example, when forming a film using hafnium chloride (HfCl4) as a raw material, chlorine gas (Cl2) may be generated as an unnecessary gas inside the process chamber 20 after the reaction. In this case, the concentration of the remaining chlorine gas can be appropriately measured by using the second concentration meter UV2 equipped with a light source that emits ultraviolet light of about 280 nm to about 380 nm (e.g., ultraviolet light with a wavelength of 300 nm), which is well absorbed by chlorine gas.
[0030] Furthermore, the inventors have confirmed that many organometallic gases absorb ultraviolet light of approximately 300 nm well, while common diluent gases (such as N2, Ar, He, and H2) hardly absorb ultraviolet light of approximately 300 nm. Therefore, by using a first concentration meter UV1 equipped with an ultraviolet light source of an appropriate wavelength, it is possible to measure the concentration of organometallic gas components in a mixed gas of an organometallic gas and a diluent gas. The ultraviolet light source can be, for example, an LED or a laser diode, and the light-receiving element for measuring the transmitted light intensity can be, for example, a Si photodiode. In this specification, ultraviolet light means light with a wavelength of 10 nm to 400 nm.
[0031] (batch supply) The following describes a gas batch supply method using semiconductor manufacturing equipment 100. It is assumed here that a sufficient amount of material gas Gm has been generated or stored in canister 10. It is also assumed that the interior of process chamber 30 has been evacuated to a vacuum using exhaust line 40, and that the interior is in a reduced pressure state with exhaust valve V7 closed.
[0032] In batch supply, as shown in step S1 of Fig. 2, first, with the second valve V2 and the fifth valve V5 closed, the third valve V3 and the fourth valve V4 are opened, and the material gas inside the canister 10 is stored in the fill tank 20. The fill tank 20 is usually formed to have a smaller capacity than the process chamber 30, but is configured to be able to store high-pressure gas inside. Note that the fill tank 20 is not limited to being a separate tank attached to the flow path, but may be a container-like space portion formed in a metal block and expanded beyond the front and rear flow paths.
[0033] Semiconductor manufacturing equipment 100 may be equipped with a pressure sensor (not shown) that can measure the pressure inside fill tank 20. This makes it possible to determine whether a desired amount of gas has been stored in fill tank 20. Fill tank 20 may also be equipped with a heater to keep the gas warm.
[0034] After the material gas is stored in the fill tank 20, the third valve V3 and the fourth valve V4 are usually closed. When the material gas is subsequently supplied in batches from the fill tank 20, the first valve V1 on the dilution gas line 60 is closed.
[0035] Next, as shown in step S2, with the fourth valve V4 closed, the fifth valve V5 and the sixth valve V6 are opened to supply the material gas in the fill tank 20 to the process chamber 30 all at once. This causes a chemical reaction of the material gas on the wafer in the process chamber 30.
[0036] After the material gas is batch-supplied to the process chamber 30 in this manner, the fifth valve V5 and the sixth valve V6 are typically closed, and then the third valve V3 and the fourth valve V4 are opened to supply the material gas Gm for the next batch supply from the canister 10 to the fill tank 20.
[0037] On the other hand, unwanted gases (e.g., chlorine gas) may be generated as the chemical reaction progresses inside the process chamber 30. In this case, it is necessary to remove the unwanted gases generated by the chemical reaction from inside the chamber before performing the next process, such as electrolytic processing of the material gas adsorbed on the wafer.
[0038] Therefore, in this embodiment, after the chemical reaction has progressed, as shown in step S3, the first valve V1, the sixth valve V6, and the seventh valve V7 are opened to supply the dilution gas Gd from the dilution gas line 60 to the process chamber 30 and then exhaust it.
[0039] At this time, the second concentration meter UV2 can be used to measure the concentration of unwanted gases contained in the gas flowing through the exhaust line 40. Therefore, the state of cleaning of the process chamber 30 can be monitored, and as shown in step S4, by determining whether the concentration of unwanted gases has decreased to approximately 0, it can be known whether cleaning of the chamber has been completed.
[0040] In step S4, if it is determined based on the output of the second concentration meter UV2 that the concentration of the unwanted gas has not decreased to approximately zero, the process returns to step S3, and the supply and exhaust of the dilution gas continue. The exhaust of the unwanted gas progresses over time, and the concentration of the unwanted gas in the exhaust gas also decreases over time. On the other hand, if it is determined in step S4 that the concentration of the unwanted gas has decreased to approximately zero (the UV2 output is below a predetermined threshold), it is determined that sufficient cleaning of the process chamber 30 has been achieved, and as shown in step S5, the first valve V1 and the sixth valve V6 are closed to stop the supply of the dilution gas, thereby completing the cleaning of the chamber.
[0041] Thereafter, the chamber is evacuated as necessary, and after closing the exhaust valve V7, the next process in the chamber (e.g., electrolysis of the adsorption gas) is performed as shown in step S6. In this manner, in this embodiment, the next process can be performed once sufficient exhaust of unnecessary gases has been confirmed using the second concentration meter UV2, thereby minimizing the time required for cleaning, preventing unnecessary consumption of dilution gas, and shortening the overall process time. Furthermore, since the next process is performed only after sufficient exhaust of unnecessary gases has been confirmed, deterioration in the quality of the semiconductor device to be formed can be prevented.
[0042] Thereafter, by repeating the same process of batch supply of material gas from the fill tank 20, cleaning the chamber, electrolytic treatment, evacuation, etc., in order, a desired high-quality film can be formed on the wafer. According to the above method, cleaning is performed reliably and in the shortest time possible each time, so a good film formation process can be carried out.
[0043] Patent Document 2 describes an apparatus that detects impurities (such as water vapor) using an adsorption spectroscopy measurement system installed in the exhaust line of a process chamber. However, the apparatus in Patent Document 2 is merely installed to enable the detection of trace amounts of water vapor as an impurity in a chamber in a typical semiconductor manufacturing process, and is not intended to reduce the process time when supplying gas in batches.
[0044] (continuous supply) A method for continuously supplying gas using semiconductor manufacturing equipment 100 will now be described. As in the case of batch supply, it is assumed that a sufficient amount of material gas Gm has been generated or stored in canister 10. It is also assumed that the interior of process chamber 30 has been evacuated in advance using exhaust line 40, and that the pressure is reduced and exhaust valve V7 is closed.
[0045] In continuous supply, as in batch supply, first, as shown in step S11 of Figure 3, with the second valve V2 and the fifth valve V5 closed, the third valve V3 and the fourth valve V4 are opened, and the material gas in the canister 10 is stored in the fill tank 20.
[0046] The third valve V3 and the fourth valve V4 are closed after the material gas is stored in the fill tank 20. Next, as shown in step S12, with the third valve V3 and the fourth valve V4 closed, the fifth valve V5 and the sixth valve V6 are opened to supply the material gas in the fill tank 20 to the process chamber 30.
[0047] At this time, as shown in step S13, the concentration of the material gas is confirmed using the first concentration meter UV1, and the flow rate of the dilution gas Gd is adjusted by controlling the opening and closing of the first valve V1 in the dilution gas supply line 60 and adjusting the opening of the control valve of the flow control device 62, thereby adjusting the concentration of the mixed gas to be flowed into the process chamber 30. During the concentration adjustment, the exhaust valve V7 is open, and the mixed gas continues to flow out.
[0048] However, immediately after the output of the first concentration meter UV1 reaches the desired concentration, the gas concentration in the process chamber 30, including the gas before the concentration adjustment is completed, may not have reached the desired concentration. Therefore, even after the flow rate control of the dilution gas based on the first concentration meter UV1 is completed, it is necessary to continue flowing the mixed gas into the process chamber 30 in this state for a relatively long time to adjust the gas concentration in the process chamber 30 to the desired concentration. Furthermore, if only the output of the first concentration meter UV1 is referenced, information on the gas concentration in the process chamber 30 cannot be obtained, so it is necessary to continue flowing the mixed gas for a relatively long time.
[0049] Therefore, in this embodiment, whether or not the gas concentration in the process chamber has settled within the desired concentration range is determined by referring to not only the output of the first concentration meter UV1 but also the output of the second concentration meter UV2 provided in the exhaust line 40. Specifically, as shown in step S14, the outputs of both the first concentration meter UV1 and the second concentration meter UV2 are monitored, and when both of these outputs are within the desired concentration range, it is determined that adjustment of the gas concentration in the process chamber has been completed, and the exhaust valve V7 is closed in step S15.
[0050] To perform the above steps, the semiconductor manufacturing apparatus 100 is equipped with a control device (not shown) that can control the gas supply to the process chamber 30 based on the outputs of the first concentration meter UV1 and the second concentration meter UV2. This control device is configured to monitor the outputs of the first concentration meter UV1 and the second concentration meter UV2, and determine that the gas concentration inside the process chamber 30 has reached that concentration when these outputs become approximately the same. Here, "approximately the same concentration" or "the same concentration" means that the difference between the concentration output by the first concentration meter UV1 and the concentration output by the second concentration meter UV2 is equal to or less than a predetermined threshold value set as an allowable error range (for example, a value set to 0 to 10% of the concentration output by the first concentration meter UV1).
[0051] Thereafter, as shown in step S16, when it is confirmed using a pressure sensor (not shown) that the process chamber 30 has been filled with the desired amount (predetermined pressure) of material gas at the desired concentration, the first valve V1, fifth valve V5, and sixth valve V6 on the gas supply side are closed to stop the gas supply, as shown in step S17, and then processing in the chamber, such as ionization processing, is performed. This allows the concentration adjustment of the material gas to be completed reliably and in a short period of time, and the desired film formation process can be performed.
[0052] After the film formation process is completed, as shown in step S18, the first valve V1 and the third valve V3 are closed, and the second valve V2, the fourth valve V4, the fifth valve V5, the sixth valve V6, and the seventh valve V7 are opened. Then, a process is performed in which a purge gas (e.g., an inert gas such as N2, Ar, or He) Gp is flowed into the process chamber 30 using the purge gas supply line 50, and the remaining material gas is exhausted (step S18).
[0053] Even in this case, the first concentration meter UV1 and the second concentration meter UV2 can be used to measure the material gas concentration both upstream and downstream of the process chamber 30 (step S19), so the material gas concentration in the process chamber can be reliably reduced to a predetermined concentration or less, and the purge step does not need to be performed for longer than necessary. As a result, the purge step can be completed in a relatively short time (step S20), allowing for quick transition to the next step.
[0054] (Embodiment 2) 4 shows the configuration of a semiconductor manufacturing apparatus 200 according to a second embodiment of the present invention. Similar to the semiconductor manufacturing apparatus 100 according to the first embodiment, the semiconductor manufacturing apparatus 200 according to this embodiment is configured so that the source gas Gm1 in the canister 10 can be supplied to the process chamber 30 via the fill tank 20. In the semiconductor manufacturing apparatus 200, components similar to those in the semiconductor manufacturing apparatus 100 are designated by the same reference numerals, and detailed description thereof may be omitted below.
[0055] The semiconductor manufacturing apparatus 200 differs from the semiconductor manufacturing apparatus 100 of the first embodiment in that it also has a second canister 18 and a third canister 19, which are separate material supply sources, in addition to the first canister 10. An eighth valve (second canister valve) is provided in the outlet-side flow path of the second canister 18, and a ninth valve (third canister valve) is provided in the outlet-side flow path of the third canister 19.
[0056] The second canister 18 and the third canister 19 are connected to a flow path between the canister valve V3 of the first canister 10 and the tank upstream valve V4. In this configuration, by controlling the opening and closing of the canister valves V3, V8, and V9, it is possible to selectively supply any of the material gases Gm1, Gm2, and Gm3 to the fill tank 20 and the process chamber 30.
[0057] In the ALD method, a precursor material gas is supplied, then exhausted, and then a different material gas is supplied to cause a reaction and form a film. The semiconductor manufacturing apparatus 200 is suitable for batch supply of different gases in this manner because it can easily switch between gas types. However, the materials contained in the canisters are not limited to different materials and may be the same material.
[0058] It goes without saying that the canisters 10, 18, and 19 may be connected in any manner, not limited to the manner shown in the figure, as long as they are able to supply material gas to the fill tank 20. Furthermore, as shown in the figure, four or more canisters may be connected downstream of the fill tank 20.
[0059] In the semiconductor manufacturing apparatus 200, similarly to the semiconductor manufacturing apparatus 100 of the first embodiment, a first concentration meter UV1 is provided upstream of the process chamber 30, and a second concentration meter UV2 is provided in the exhaust line 40. Therefore, in the batch supply of gas, a cleaning step of removing unnecessary gas from the process chamber 30 can be efficiently performed. Furthermore, in the continuous supply of gas, the concentration of the mixed gas in the chamber can be efficiently controlled.
[0060] Furthermore, when using various material gases as described above, the types of gases produced by the chemical reaction may also vary. Therefore, it may be advantageous for the first concentration meter UV1 and the second concentration meter UV2 to be configured to be able to measure the concentrations of various gases. Therefore, the first concentration meter UV1 and the second concentration meter UV2 may be configured to switch between outputting light of multiple wavelengths to accommodate the absorption characteristics of each gas type. For example, by using a light source that can output near-infrared light in addition to ultraviolet light, it is possible to detect the concentration of not only chlorine gas and organometallic gases, but also moisture.
[0061] (Embodiment 3) 5 shows the configuration of a semiconductor manufacturing apparatus 300 according to a third embodiment of the present invention. Similar to the semiconductor manufacturing apparatus 100 according to the first embodiment, the semiconductor manufacturing apparatus 300 according to this embodiment is configured so that the material gas Gm in the canister 10 can be supplied to the process chamber 30 via the fill tank 20. In the semiconductor manufacturing apparatus 300, components similar to those in the semiconductor manufacturing apparatus 100 are designated by the same reference numerals, and detailed description thereof may be omitted below.
[0062] The semiconductor manufacturing apparatus 300 differs from the semiconductor manufacturing apparatus 100 of the first embodiment in that a third concentration meter UV3 capable of measuring the concentration of the material gas in the canister 10 is additionally provided. The other configurations are the same as those of the semiconductor manufacturing apparatus 100 of the first embodiment, with a first concentration meter UV1 provided upstream of the process chamber 30 and a second concentration meter UV2 provided in the exhaust line 40. Therefore, in the batch supply of gas, a cleaning process for removing unnecessary gas from the process chamber 30 can be efficiently performed. Furthermore, in the continuous supply of gas, the concentration of the mixed gas in the chamber can be efficiently controlled.
[0063] In the semiconductor manufacturing equipment 300, the state of the material gas inside the canister 10 can be determined based on the output of the third concentration meter UV3. For example, when the canister 10 is generating material gas by gasifying a liquid or solid material, if the output of the third concentration meter UV3 drops significantly below normal, it can be determined that the liquid or solid material has run out and gas generation is not progressing. The semiconductor manufacturing equipment 300 may be configured to issue a warning to the user when the output of the third concentration meter UV3 falls below a threshold during operation.
[0064] Although the above describes an aspect in which the third concentration meter UV3 is provided in the canister 10 of the semiconductor manufacturing apparatus 100 of the first embodiment, the present invention is not limited to this, and a concentration meter corresponding to each gas type may be provided in each of the multiple canisters 10, 18, and 19 included in the semiconductor manufacturing apparatus 200 of the second embodiment. Furthermore, the third concentration meter UV3 may be disposed inside the canister 10, or may be disposed in the flow path between the outlet of the canister 10 and the canister valve V3.
[0065] Although the embodiment of the present invention has been described above, various modifications are possible. For example, a fourth concentration meter may be additionally provided in the fill tank 20 so that the concentration of gas inside the tank can be measured. [Industrial Applicability]
[0066] A semiconductor manufacturing apparatus and a semiconductor manufacturing method according to an embodiment of the present invention are suitably used for performing a film formation process in semiconductor manufacturing by a CVD method or an ALD method. [Explanation of symbols]
[0067] 10 canisters 18 Second Canister 19 Third Canister 20 Fill Tank 30 Process Chamber 40 Exhaust line 50 Purge gas supply line 60 Dilution gas supply line 62 Flow control device 100, 200, 300 Semiconductor manufacturing equipment UV1 First concentration meter (upstream of chamber) UV2 Secondary Concentration Meter (Exhaust Line Concentration Meter) UV3 3rd densitometer (canister densitometer) V1 First valve (dilution gas supply valve) V2 Second valve (purge gas supply valve) V3 3rd valve (canister valve) V4 4th valve (tank upstream valve) V5 5th valve (tank downstream valve) V6 6th valve (upstream valve of the chamber) V7 7th valve (exhaust valve) V8 8th valve (2nd canister valve) V9 9th valve (3rd canister valve)
Claims
1. a canister capable of storing the material gas; a fill tank provided downstream of the canister; a process chamber disposed downstream of the fill tank; a tank downstream valve disposed in a flow path between the fill tank and the process chamber; an exhaust line connected to the process chamber; an exhaust valve provided in the exhaust line; a first concentration meter provided in a flow path between the fill tank and the process chamber; a second concentration meter provided in the exhaust line; A semiconductor manufacturing apparatus comprising:
2. 2. The semiconductor manufacturing apparatus according to claim 1, wherein a dilution gas supply line is connected to a flow path between said fill tank and said first concentration meter, and said dilution gas supply line is provided with a dilution gas supply valve.
3. a control device that controls gas supply to the process chamber based on the measurement values of the first concentration meter and the second concentration meter; 3. The semiconductor manufacturing apparatus according to claim 1, wherein the control device is configured to determine that the gas concentration in the process chamber is the specified concentration when the concentrations output by the first concentration meter and the second concentration meter become approximately the same.
4. 4. The semiconductor manufacturing apparatus according to claim 1, further comprising a third concentration meter for measuring the concentration of the material gas stored in the canister.
5. 5. The semiconductor manufacturing apparatus according to claim 1, wherein the canister is configured to vaporize or sublimate a liquid or solid material to generate a material gas.
6. A semiconductor manufacturing method using a semiconductor manufacturing apparatus including: a canister capable of storing a material gas; a fill tank provided downstream of the canister; a process chamber provided downstream of the fill tank; a tank downstream valve provided in a flow path between the fill tank and the process chamber; an exhaust line connected to the process chamber; an exhaust valve provided in the exhaust line; a first concentration meter provided in the flow path between the fill tank and the process chamber; and a second concentration meter provided in the exhaust line, supplying the material gas in the canister to the fill tank while the tank downstream valve is closed; Opening the tank downstream valve to supply the material gas supplied to the fill tank to the process chamber; After a chemical reaction of the material gas supplied to the process chamber occurs, the dilution gas supply valve and the exhaust valve are opened to supply a dilution gas to the process chamber and exhaust the dilution gas; stopping the supply and exhaust of the dilution gas based on the output of the second concentration meter; After the step of stopping the supply and exhaust of the dilution gas, performing a process in the process chamber; A semiconductor manufacturing method comprising:
7. a first concentration meter provided in a flow path between a connection portion of the dilution gas supply line and the process chamber; and a second concentration meter provided in the exhaust line. supplying the material gas in the canister to the fill tank while the tank downstream valve is closed; Opening the tank downstream valve to supply the material gas supplied to the fill tank to the process chamber; opening the dilution gas supply valve and the exhaust valve to supply a mixture of the material gas and the dilution gas into the process chamber and exhaust the mixture; adjusting the concentration of the mixed gas by controlling the flow rate of the dilution gas based on the output of the first concentration meter; determining the concentration of the mixed gas in the process chamber by referring to both the output of the first concentration meter and the output of the second concentration meter; performing a process in the process chamber using the determined gas mixture at a predetermined concentration; A semiconductor manufacturing method comprising:
8. The semiconductor manufacturing equipment further includes a purge gas supply line provided downstream of the fill tank, After performing a process in the process chamber using the mixed gas, supplying a purge gas from the purge gas supply line to the process chamber via the fill tank; a step of stopping the supply of purge gas when the concentration of the material gas becomes equal to or lower than a predetermined concentration by referring to the outputs of the first concentration meter and the second concentration meter; The semiconductor manufacturing method of claim 7 further comprising: