Temporary facility for constructing box structure

The temporary construction equipment system addresses inefficiencies in underpass construction by enabling flexible coverage of unit boxes, improving work efficiency and material handling through movable roof structures.

JP2024143682APending Publication Date: 2024-10-11OKUMURA CORP +1

Patent Information

Application Number
JP2023056470
Authority / Receiving Office
JP · JP
Patent Type
Applications
Current Assignee / Owner
Filing Date
2023-03-30
Publication Date
2024-10-11

AI Technical Summary

Technical Problem

Existing underpass construction methods face inefficiencies due to weather dependence and interference from overhead roofs during concrete work, particularly when constructing multiple unit boxes for underground spaces, which affect work efficiency and material handling.

Method used

A temporary construction equipment system that allows individual opening or covering of the upper part of each unit box, using a roof structure with movable roof pieces supported by rail members, enabling efficient construction regardless of weather conditions.

Benefits of technology

Improves work efficiency by allowing flexible coverage of the construction area, enhancing material handling and reducing weather-related delays during the construction of multiple unit boxes for underground spaces.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure 2024143682000001_ABST
    Figure 2024143682000001_ABST
Patent Text Reader

Abstract

To provide a temporary facility for construction that improves work efficiency when constructing a plurality of unit boxes of a box structure that forms an underground space by pouring concrete in an underpass construction method.SOLUTION: Rail members 15 for moving a roof 12 are installed on both sides of a construction work area 11. The roof 12 is made up of a number of roof pieces 13, each of roof piece 13 includes a roof main body piece 13a, an erection base 13b and a supporting structure 13c. Each roof piece 13 can be moved to a predetermined position on the rail members 15 to switch between a state in which the entire upper part of a unit construction area 11a is covered by a number of roof main body pieces 13a arranged in succession, and a state in which the roof pieces 13 are retreated to the area 11b which becomes a gap portion 20b between adjacent unit box bodies 21, leaving the entire upper part of the unit construction area 11a open.SELECTED DRAWING: Figure 1
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to temporary equipment for the construction of box structures, which is installed when constructing multiple unit box structures that make up the box structure by pouring concrete and connecting them together at a launch base adjacent to the planned installation area where the box structure will be installed in the underpass construction method. [Background technology]

[0002] The underpass method is a method for forming an underground space that crosses the ground below existing structures such as railroad tracks and roads without interfering with the operation of railroads and vehicles, and examples of such methods include the SFT method (registered trademark) and the R&C method (registered trademark), which replace a box-shaped roof with a box-shaped structure having a rectangular cross section, and the Frontejacking method (registered trademark). The SFT method and the R&C method form a box-shaped roof, preferably made of hollow pipe members having a rectangular cross section, including a pipe roof (a row of pipes on the top surface) of the upper floor that supports existing structures such as railroad tracks and roads from below, on the ground in the planned installation area of ​​the box structure, which is the planned location for forming an underground space, and replace the box structure with the box-shaped roof including the pipe roof of the upper floor by propelling or towing a box structure having a rectangular cross section made of concrete into the ground in the planned installation area, thereby forming an underground space by the replaced box structure (see, for example, Patent Document 1 and Patent Document 2).

[0003] In addition, the Frontejacking method involves leaving a row of pipes, including a pipe roof on the upper floor formed on the ground in the planned installation area of ​​the box structure, in the ground, and towing the box structure at the departure base toward the arrival base while aligning the top surface of the left behind pipe row, particularly the pipe roof on the upper floor, to form an underground space made of the box structure inside the left behind pipe row (see, for example, Patent Documents 3 and 4).

[0004] Here, for example, when a box structure forming an underground space at a departure base or a destination base is constructed using cast-in-place concrete, generally, in the construction work area for the box structure at the departure base or destination base, formwork and reinforcing bars are assembled, concrete is poured, and then after a specified curing period has elapsed, the formwork is removed and the box structure is formed, which results in a long construction period. [Prior art documents] [Patent documents]

[0005] [Patent Document 1] JP 2007-177553 A [Patent Document 2] JP 2012-144942 A [Patent Document 3] Japanese Patent Application Publication No. 6-41996 [Patent Document 4] JP 2004-257025 A Summary of the Invention [Problem to be solved by the invention]

[0006] On the other hand, for example, when the ground below the existing structure is an embankment, and a large area of ​​land can be secured for the origination base and arrival base on at least one side of the existing structure, and the extension of the box structure that crosses the existing structure is long, it is preferable to construct the box structure by dividing it into a plurality of unit box bodies so that the weight can be moved by a propulsion jack, etc. In this case, these plurality of unit box bodies are preferably constructed in a state in which they are adjacently arranged at a predetermined interval in the moving direction so that a central push jack for moving can be attached between each pair of adjacent unit box bodies.

[0007] Furthermore, the efficiency of work when constructing each unit box using cast-in-place concrete is affected by weather conditions, etc. For example, in rainy weather, it is difficult to install formwork and reinforcing bars. Therefore, it is considered desirable to provide a roof that covers the entire work area so that these tasks can be carried out regardless of the weather.

[0008] However, when a plurality of unit boxes constituting a box structure are arranged in series at a predetermined interval in the moving direction and constructed by cast-in-place concrete, if a roof is provided to cover the entire working area of ​​the plurality of unit boxes, the roof covering the entire area may become an obstacle when hoisting and carrying in materials such as formwork and reinforcing bars to the working area of ​​each unit box, or when pouring concrete in the working area of ​​each unit box, and may actually reduce the efficiency of the work. In particular, since it is desirable to carry reinforcing bars as long as possible within the formwork to the working area of ​​each unit box, in order to facilitate the assembly work, it is desirable to carry reinforcing bars into the working area of ​​each unit box together, for example, when the reinforcing bars are carried in, it is desirable to make it possible to open the entire area above the working area of ​​each unit box as necessary, depending on the type of work.

[0009] For these reasons, it is desirable to develop equipment that will enable the upper part of the working area of ​​each unit box to be individually opened or covered as needed when constructing the multiple unit boxes that make up the box structure that forms the underground space in the underpass method by pouring concrete, thereby improving work efficiency when constructing these.

[0010] The present invention aims to provide a temporary facility for constructing box structures which enables the upper part of the working area of ​​each unit box to be individually opened or covered as needed when constructing multiple unit boxes that make up a box structure that forms an underground space in an underpass construction method by pouring concrete, thereby improving work efficiency when constructing these. [Means for solving the problem]

[0011] The present invention relates to an underpass construction method for forming an underground space directly below an existing structure by installing a box structure having a rectangular cross-sectional shape across the ground below the existing structure, and the method relates to a temporary construction facility for the box structure that is installed at a starting base on one side of a planned installation area where the box structure will be installed, when a plurality of unit boxes constituting the box structure are constructed by pouring concrete and connecting them in a transverse direction, the unit boxes are constructed by connecting them in a transverse direction with a gap of a predetermined width between an adjacent pair of the unit boxes, and on both sides of the construction work area when the unit boxes are connected and constructed, a pair of rail members for moving a roof are installed in a state of extending along the transverse direction and supported from the ground surface via a temporary side framework, the roof is composed of a plurality of roof pieces connected in a transverse direction, and each roof piece has a gap of a predetermined width between an adjacent pair of the unit boxes. The above-mentioned objective has been achieved by providing a temporary facility for constructing a box structure, which is composed of a roof main body piece having a roof width corresponding to the width of the box, an installation base with running members attached to both ends that is installed across a pair of rail members, and a support structure that is assembled on top of the installation base and supports the roof main body piece from below, and the multiple roof pieces are formed so that the roof main body of the roof roof has a length in the transverse direction that is capable of covering the entirety of at least one of the unit boxes to be constructed when the roof main body pieces are arranged in succession without any gaps, and by appropriately moving each of the roof pieces to a predetermined position on the rail member, it is possible to switch between a state in which the entire upper part of the area in which at least one of the unit boxes is constructed is covered with the multiple roof main body pieces arranged in succession, and a state in which the roof pieces are retreated to the gap portion, leaving the entire upper part of the area in which at least one of the unit boxes is constructed open.

[0012] Furthermore, it is preferable that the temporary equipment for constructing the box structure of the present invention is arranged so that the bottom steel plate on which the unit box to be constructed is slidably placed covers the ground surface of the construction work area.

[0013] In addition, it is preferable that the temporary equipment for constructing a box structure of the present invention is such that the roof main body piece of each of the roof pieces is a single-slope inclined piece that slopes to one side intersecting the transverse direction.

[0014] Furthermore, in the temporary facility for constructing a box structure of the present invention, the box structure is composed of five unit box bodies constructed in a connected manner, and it is preferable that the roof has a length sufficient to cover the entire upper part of the two unit box bodies constructed by the roof main body pieces of the multiple roof pieces arranged in succession.

[0015] Furthermore, in the temporary facility for constructing a box structure according to the present invention, it is preferable that the ground below the existing structure is a banked ground. Effect of the Invention

[0016] According to the temporary equipment for constructing box structures of the present invention, when multiple unit boxes that make up the box structure that forms an underground space in the underpass construction method are constructed by pouring concrete, it is possible to open or cover the entire area above each unit box individually as necessary, thereby improving work efficiency when constructing them. [Brief description of the drawings]

[0017] [Figure 1] FIG. 1 is a simplified perspective view illustrating a temporary facility for constructing a box structure according to a preferred embodiment of the present invention. [Diagram 2] FIG. 2 is a schematic front view of FIG. 1 as seen from the front side, illustrating a temporary facility for constructing a box structure according to a preferred embodiment of the present invention. [Diagram 3]FIG. 1 illustrates a temporary facility for constructing a box structure according to a preferred embodiment of the present invention, where (a) is a simplified top view in which the entire upper part of the work areas of two unit boxes is covered and the entire upper part of the other work areas is open, and (b) is a simplified top view in which only the entire upper part of the work area of ​​one unit box is covered and the entire upper part of each of the other work areas is open. [Figure 4] 13(a) to 13(c) are schematic vertical cross-sectional views illustrating a towing-type underpass construction method for forming an underground space by towing a box structure made of unit boxes constructed using temporary construction equipment. [Diagram 5] 13(a) to 13(d) are schematic vertical cross-sectional views illustrating a towing-type underpass construction method, in which a box structure made of unit boxes constructed using temporary construction equipment is towed to form an underground space. [Figure 6] 13(a) to 13(c) are schematic vertical cross-sectional views illustrating a towing-type underpass construction method for forming an underground space by towing a box structure made of unit boxes constructed using temporary construction equipment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS

[0018] The temporary facility 10 for constructing a box structure according to a preferred embodiment of the present invention shown in Figs. 1 to 3 is installed as a temporary facility for constructing a box structure having a hollow rectangular cross section 20 by dividing it into a plurality of unit box bodies 21 and pouring concrete into each of them, in order to form an underground space in which another road is to be installed by crossing the ground under a multi-lane expressway as an existing structure 50 in a towing-type underpass construction method shown in Figs. 4 and 5. In this embodiment, the towing-type underpass construction method is preferably a well-known towing-type R&C construction method (registered trademark), and the box structure 20 is towed and installed on the ground under the expressway 50 so as to replace the box roof 22 made of a plurality of hollow pipe members 23, preferably having a rectangular cross section, including a top pipe row 22a, which was previously formed on the ground directly under the expressway 50, to form an underground space.

[0019] In this embodiment, the ground below the expressway 50, which is an existing structure, to which the box structure 20 is towed is preferably a banked ground, and a large starting base 51 can be secured on one side of the site on both sides of the expressway 50. For this reason, in this embodiment, the concrete box structure 20 is preferably constructed as a structure having a sufficient length to cross the ground below the expressway 50 at one time, by constructing the divided multiple unit box bodies 21 in series in the towing direction X, which is the moving direction, preferably at the starting base 51. In this embodiment, since the starting base 51 is a site with a large area, the process of constructing the multiple unit box bodies 21 constituting the box structure 20 can be preferably performed in parallel with the process of pushing the multiple hollow pipe members 23 into the ground directly below the expressway 50 to form the box roof 22.

[0020] The temporary facility 10 for constructing a box structure in this embodiment is preferably provided at the starting base 51 when carrying out the process of constructing each of the multiple unit box bodies 21 that make up the box structure 20, and is provided as a facility for efficiently constructing each of the multiple unit box bodies 21 by connecting them together at a predetermined interval in the towing direction X, which is the direction of movement.

[0021] The temporary facility 10 for constructing a box structure in this embodiment is a temporary facility for box construction that is installed at a starting base 51 on one side of the planned installation area 24 where the box structure 20 will be installed in an underpass construction method (see Figures 4 and 5) in which a box structure 20 having a rectangular cross-sectional shape is installed across the ground below an existing structure, an expressway 50, to form an underground space directly below the expressway 50, when multiple unit box bodies 21 that make up the box structure 20 are constructed by pouring concrete and connecting them together in the transverse direction X, which is the towing direction, with a predetermined width gap maintained between each adjacent pair of unit box bodies 21. As shown in Figures 1 to 3(a) and (b), on both sides of the construction work area 11 when the unit box bodies 21 are connected together to construct the structure, a pair of rail members 15 for moving the roof 12 are installed extending along the transverse direction (towing direction) X and supported from the ground surface via a side temporary structure 16. The roof 12 is composed of a plurality of roof pieces 13 arranged in the transverse direction X, and each roof piece 13 includes a roof main body piece 13a having a roof width corresponding to the width of the gap portion 20b (see Figures 4(b) and (c)) maintained between a pair of adjacent unit box bodies 21, an installation base 13b having running members 13d (Figure 2) attached to both ends and installed so as to straddle a pair of rail members 15, and a support structure 13c assembled on the installation base 13b and supporting the roof main body piece 13a from below.The multiple roof pieces 13 are formed so that the roof main body 12a of the roof 12 has a length in the transverse direction X that is capable of covering the entirety of at least one (two in this embodiment) unit box body 21 to be constructed when the roof main body pieces 13a are arranged in succession without any gaps (see Figure 3(a)).By appropriately moving each roof piece 13 to a predetermined position on the rail member 15, it is possible to switch between a state in which the entire upper part of area 11a in which at least one unit box 21 (in this embodiment, the second unit box from the front) is constructed is covered with a plurality of roof main body pieces 13a arranged in succession (see Figure 3(a)), and a state in which the roof pieces 13 are retreated to area 11b which is the gap 20b between adjacent unit boxes 21, leaving the entire upper part of area 11a in which at least one unit box 21 (in this embodiment, the second and subsequent four unit boxes) is constructed open (see Figure 3(b)).

[0022] In this embodiment, a bottom iron plate 14 on which the unit box 21 to be constructed is placed so as to be slidable is laid, preferably so as to cover the ground surface of the construction work area 11 (see FIG. 1).

[0023] Furthermore, in this embodiment, the roof main body piece 13a of each roof piece 13 is preferably a one-way slope piece that slopes to one side intersecting with the transverse direction X (see Figs. 1 and 2).

[0024] In this embodiment, in order to carry out the towing-type underpass construction method, for example, removal and restoration of obstacles at the construction site, and chemical injection work 56a prior to excavation of the guide pit 56 are carried out as preparatory work, and then, as shown in FIG. 4(a), steel sheet piles for retaining soil are driven into both sides of the embankment ground below the expressway 50 to form mirror wall surfaces 53a, 53b on both sides of the expressway 50, and a temporary support wall 55 is erected as a roof propulsion reaction body at a predetermined interval between the mirror wall surface 53b and the starting base 51. Since the temporary support wall 55 is erected at the starting base 51 and formed, the starting base 51 is divided in the towing direction X into a propulsion work section 51A on the expressway 50 side across the temporary support wall 55, and a box construction work section 51B on the opposite side. Since the temporary support wall 55 needs to be removed after the box-shaped roof 22 is formed and before the box structure 20 is advanced, it is preferably formed by filling the interior of a rectangular area surrounded by, for example, steel sheet piles as an earth retaining member 55a with soil.

[0025] In addition, the towing support wall 41 is erected at the arrival base 52 with a predetermined interval between it and the mirror wall surface portion 53a. The towing support wall 41 is preferably formed by pouring concrete inside a rectangular area surrounded by, for example, steel sheet piles as the retaining members 41c so that it can bear at least a part of the reaction force when the box structure 20 is towed. A through hole for inserting the towing steel wire 42 is formed at a predetermined position in the support wall 41, penetrating between the opposing surface portion 41b and the back surface portion 41a in the towing direction X by the retaining members 41c. In addition, a guide pit 56 for inserting the towing steel wire 42 is formed in the area where the chemical injection work 56a is performed in the bottom corner portion of the planned installation area 24 of the box structure 20.

[0026] Furthermore, in this embodiment, a tie beam 43 for making the wall surface portion 53a on the arrival base 52 side of the embankment ground bear the support reaction force when towing the box structure 20 can be erected and attached between the opposing surface portion 41b in the towing direction X of the towing support wall body 41 and the mirror wall surface portion 53a on the arrival base 52 side below the expressway 50. The tie beam 43 is made of a retaining beam member made of, for example, H-shaped steel, and can be attached in an erected state between them by joining both ends to a wale member made of, for example, H-shaped steel installed on the opposing surface portion 41b and the mirror wall surface portion 53a. In this embodiment, the tie beam 43 is appropriately selected in a position so as not to interfere with the frame steel constituting the temporary hollow pipe removal facility 27 (see FIG. 4(b)) installed within the range surrounded by the box-shaped roof 22 at the arrival base 52, and is attached, for example, in two stages, one above the other.

[0027] In this embodiment, a process of forming the box-shaped roof 22 of the towed underpass construction method is carried out in the propulsion work area 51A of the starting base 51. That is, in the process of forming the box-shaped roof 22, as shown in Fig. 4(b), a propulsion facility 54 similar to that of the conventional R&C construction method is provided between the formed temporary support wall 55 and the mirror wall surface portion 53b on the starting base 51 side in the propulsion work area 51A of the starting base 51, and a plurality of hollow pipe members 23, preferably a plurality of unit pipe members 23a, are sequentially added from the starting base 51 to the arrival base 52, and the hollow pipe members 23 are each pushed into the ground immediately below the expressway 50, so that they are arranged in a line in the circumferential direction of the planned installation area 24. This makes it possible to form a box-shaped roof 22 having a U-shaped cross-sectional shape, preferably consisting of at least a top surface pipe row 22a and a pair of side surface pipe rows 22b on both sides, spanning the mirror wall portion 53a on the departure base 51 side and the mirror wall portion 53b on the arrival base 52 side.

[0028] In this embodiment, in parallel with the process of forming the box-shaped roof 22, a process of constructing each of the multiple unit box bodies 21 constituting the box structure 20 is carried out in a box body construction work area 51B located behind the temporary support wall body 55 in the starting base 51 in the towing direction X. In the process of constructing each of the multiple unit box bodies 21, a temporary construction facility 10 for the box structure of this embodiment shown in Figs. 1 to 3 is provided in the box body construction work area 51B, and in this temporary construction facility 10, formwork for each unit box body 21 and reinforcing bars are assembled, and then concrete is poured and hardened / cured. This allows the multiple unit box bodies 21 to be efficiently constructed in a state in which they are consecutively arranged at a predetermined interval in the towing direction X. As described above, the temporary facility 10 for constructing a box structure in this embodiment is composed of a pair of rail members 15 extending along the transverse direction (towing direction) X on both sides of the construction work area 11, and a roof 12 consisting of a plurality of roof pieces 13 arranged in series in the transverse direction X.

[0029] In this embodiment, the temporary facility 10 for constructing the box structure has a construction work area 11 large enough to construct five unit box bodies 21, each having a length in the towing direction X of about 15 m and a width of about 15 m. On both sides of the construction work area 11, a pair of rail members 15 made of, for example, H-shaped steel are arranged parallel to each other and are provided extending over the entire length of the construction work area 11 in the towing direction X while maintaining a wider interval than the width of the unit box body 21 in the direction perpendicular to the towing direction X. These rail members 15 are preferably erected from side sole plates 14a laid on the ground surface on both sides of the construction work area 11, and are supported from the ground surface via side temporary frameworks 16 assembled using known framework scaffolding materials, single pipes, etc., so that they are installed in a stable state. In addition, adjacent to the outside of each of the pair of rail members 15, work scaffolding 17, which serves as a foothold for workers when moving each of the roof pieces 13 that make up the roof 12 along the rail members 15, is installed and supported by the side temporary structure 16 using various known scaffolding materials.

[0030] In this embodiment, the roof 12 is formed so that the roof body 12a has a length in the towing direction X of about 32 m and a width in the direction perpendicular to the towing direction X of about 18 m, preferably large enough to cover the entire upper part of the two unit boxes 21 to be constructed (see FIG. 3(a)). The roof pieces 13 constituting the roof 12 are preferably provided in a number of 16, and each roof piece 13 has a roof width in the towing direction X of about 2 m, for example, corresponding to the width of the interval portion 20b, for example, about 1.5 m, held between a pair of adjacent unit boxes 21, and a roof body piece 13a having a length in the direction perpendicular to the towing direction X of about 18 m. Each roof piece 13 is also configured to include an erection base 13b erected so as to straddle a pair of rail members 15, and a support structure 13c assembled on the erection base 13b.

[0031] The roof body piece 13a can be easily formed to have the above-mentioned predetermined size, shape, etc., using various known roof materials such as roof slates and waterproof sheets. In this embodiment, the roof body piece 13a is a one-way slope piece that is inclined to one side intersecting with the transverse direction X, which is the towing direction, as described above. This makes it possible to simplify the structure of the support structure 13c and to avoid a structure that has a joint in the center, such as a triangular roof.

[0032] In this embodiment, the erection base 13b can be formed by connecting a pair of H-shaped steels arranged in parallel with an interval of, for example, about 1.2 m in the towing direction X. The erection base 13b is extended in a direction perpendicular to the towing direction X and erected so as to straddle a pair of rail members 15, and a known running member 13d such as a chill tank is attached to the underside of both end portions placed on the pair of rail members 15 (see FIG. 2). This makes it possible to easily move each roof piece 13 to a desired position in the towing direction X by the work of an operator while being guided by the pair of rail members 15 as necessary.

[0033] In this embodiment, the support structure 13c can be easily installed by assembling it onto the installation base 13b using temporary structure members such as known single-tube pipes, clamp members, joint members, etc., so as to straddle a pair of H-shaped steel beams that constitute the installation base 13b. The roof body piece 13a is attached in a single-slope inclined state to the upper end of the assembled support structure 13c, and is installed while being stably supported from below by the support structure 13c interposed between the installation base 13b.

[0034] To construct the multiple unit boxes 21 that make up the box structure 20 by pouring concrete using the temporary facility 10 for constructing a box structure of this embodiment having the above-mentioned configuration, preferably, as described above, a multiple number of bottom steel plates 14 on which the unit boxes 21 to be constructed are placed so as to be slidable are laid so as to cover the ground surface of the construction work area 11, and the upper surfaces of these bottom steel plates 14 are partitioned into work areas (unit work areas) 11a for each unit box, and in each unit work area 11a, formwork and reinforcing bars are assembled, concrete is poured, and the formwork is removed after a predetermined curing period has elapsed. This makes it possible to construct five unit boxes 21 individually. Furthermore, in this embodiment, by using the temporary facility 10 for constructing the box structure, in particular, when constructing these unit boxes 21 that make up the box structure 20 by pouring concrete, it is possible to improve the work efficiency when constructing them by individually opening or covering the entire unit work area 11a of each unit box 21 individually as necessary.

[0035] That is, in this embodiment, by appropriately moving each roof piece 13 to a predetermined position on the rail member 15, it is possible to switch between a state in which the entire upper part of the area 11a in which at least one unit box 21 (in this embodiment, the second unit box from the front) is constructed is covered with a plurality of roof main body pieces 13a arranged in succession (see Figure 3(a)), and a state in which the roof pieces 13 are retreated to the area 11b which corresponds to the spacing portion 20b between adjacent unit boxes 21, leaving the entire upper part of the unit work area 11a in which at least one unit box 21 (the second to fifth unit boxes) are constructed open (see Figure 3(b)). As a result, when work is being done in each unit work area 11a, for example, assembling formwork or reinforcing bars, the entire area can be covered from above, making it possible to carry out the work more efficiently regardless of the weather, and when work is being done in the unit work area 11a, for example, when hoisting and transporting materials such as formwork or reinforcing bars or when pouring concrete, the entire area can be opened from above, making it possible to carry out the work more efficiently.

[0036] In this embodiment, after the process of forming the box-shaped roof 22 and the process of constructing each of the multiple unit boxes 21 constituting the box structure 20 using the temporary construction facility 10, the propulsion facility 54 and the temporary support wall 55 of the propulsion work section 51A are dismantled and removed at the starting base 51 as shown in Fig. 4(c). In addition, the towing steel wire 42 is arranged and attached from the back part 41a in the towing direction X of the towing support wall 41 erected at the arrival base 52 to the rear end of the unit box 21 at the rear end of the box structure 20 constructed at the starting base 51, thereby making the box structure 20 towable.

[0037] That is, in the starting base 51, preferably in the portion from which the roof propulsion reaction body 55 and the propulsion base 54 have been removed, a steel sheet, for example, is laid so that the box structure 20 consisting of the five unit box bodies 21 can be smoothly slid in the towing direction X. Also, a known traction steel wire 42 made of, for example, a steel strand is inserted into a through hole formed in the towing support wall 41, and is inserted into a guide pit 56 formed in a bottom corner of the planned installation area 24 so as to cross the planned installation area 24 of the box structure 20, and further into an insertion hole provided in a bottom corner of the unit box body 21, and is arranged in a state of extending from a back part 41a of the support wall 41 in the towing direction X to a rear end part of the box structure 20 in the towing direction X. In this state, one end of the arranged traction steel wire 42 is fixed to and connected to the back part 41a in the towing direction X of the support wall 41 via a known fastener 28a, and the other end of the arranged traction steel wire 42 is fixed to and connected to the rear end part in the towing direction X of the box structure 20 made up of the multiple unit box bodies 21 connected together via a known front jack as the expansion jack 28b, for example, for support. As a result, in the box towing process described later, the box structure 20 can be towed toward the arrival base 52 while obtaining a support reaction force from the towing support wall 41 while extending and retracting the expansion jack 28b.

[0038] In this embodiment, the telescopic jack 28b is extended and retracted from the state in which both ends of the towing steel wire 42 shown in FIG. 4(c) are connected to the back part 41a of the supporting wall 41 and the rear end part of the box structure 20, and the box structure 20 made up of the five unit box bodies 21 can be towed as a whole in the towing direction X while obtaining a support reaction force from the supporting wall 41 during towing, and pulled toward the arrival base 52. When the box structure 20 is pulled toward the arrival base 52 and the front end of the box structure 20 made up of the unit box bodies 21 at the front end abuts against the rear end of the box roof 22 previously installed on the ground of the planned installation area 24, the box structure 20 is further pulled toward the arrival base 52 while excavating the ground inside the box roof 22. This makes it possible to push the box structure 20 as a whole into the ground of the planned installation area 24 directly below the expressway 50 while replacing it with the box roof 22, as shown in FIG. 5(a). Furthermore, each hollow pipe member 23 constituting the box-shaped roof 22 which has been pushed out to the arrival base 52 will be removed at the arrival base 52, one unit pipe member 23a at its tip, using temporary hollow pipe removal equipment 27.

[0039] In this embodiment, the support reaction force when towing the box structure 20 is borne not only by the supporting wall 41 but also by the mirror wall surface portion 53 of the banking ground, and the box structure 20 is pushed into the ground of the planned installation area 24 directly below the expressway 50 while replacing the box roof 22. When the box structure 20 reaches a predetermined position, as shown in Fig. 5(b), one end of the towing steel wire 42 fixed to the back surface portion 41a of the supporting wall 41 in the towing direction X is transferred to the tip of the box structure 20 by the unit box 21 at the tip and fixed by the fixing device 28a. Also, by attaching the ESA steel wire 29c to the upper portion of the box structure 20 via the fixing device 29a and the ESA jack 29b, the box structure 20 is changed over to a state in which it can be advanced by a known ESA construction method.

[0040] 5(c), the box structure 20 is further pushed into the ground of the planned installation area 24 directly below the expressway 50 by the ESA method, in which, for example, one of the five unit boxes 21 is used as a driving box and the remaining unit boxes 21 are used as reaction boxes, and the frictional resistance of the reaction boxes that are not being driven is used as a reaction force, without relying on external reaction resistance, by replacing the driving boxes and pushing in one direction. Also, each hollow pipe member 23 constituting the box roof 22 pushed out to the arrival base 52 by the pushing of the box structure 20 is removed at the arrival base 52 by the temporary hollow pipe removal equipment 27 for each unit pipe member 23a at the tip, as described above.

[0041] When the tip of the box structure 20 made of the unit pipe members 23a at the tip reaches the arrival base 52 by the ESA method, the tie beams 43 and the temporary hollow pipe removal equipment 27 installed between the support wall 41 and the mirror wall portion 53a of the embankment land below the expressway 50 are removed as shown in Fig. 5(d). Also, as shown in Fig. 6(a), by drawing the unit box 21 at the rear end toward the arrival base 52 by the ESA method, the box structure 20 having a rectangular cross section formed integrally by the five unit boxes 21 is installed across the ground directly below the expressway 50 (see Fig. 6(b)).

[0042] Furthermore, once the box structure 20 has been installed across the ground directly below the expressway 50, as shown in Figures 6(b) and (c), the towing steel wires 42 and ESA steel wires 29c, etc. will be removed, the cutting edge member 26 will be removed from the tip of the box structure 20, and the supporting wall 41 installed at the arrival base 52 will be removed. After that, the necessary waterproofing work, backing grout injection work, road ancillary work, etc. will be carried out, and an underground space in which other roads will be laid will be formed by the box structure 20, with a multi-level intersection in the ground directly below the expressway 50.

[0043] The present invention is not limited to the above embodiment and can be modified in various ways. For example, the temporary construction facility of the present invention does not necessarily have to be used in the R&C method (registered trademark) in which the box structure is towed while replacing it with a box roof while performing excavation work at the face of the front part of the box structure, but can also be used in the SFT method (registered trademark) in which excavation work is performed at a reach base, or the Frontejacking method (registered trademark) in which the box structure is towed while leaving the box roof in the ground while performing excavation work at the face of the front part in the towing direction of the box structure and aligning the top surface part with the underside of the top surface pipe row of the box roof. The roof body piece of the roof piece does not necessarily have to be a one-way slope piece. [Explanation of symbols]

[0044] 10 Temporary facilities for construction of box structures 11 Construction work area 11a Unit work area (area where each unit box is constructed) 11b Area that is the gap between adjacent unit boxes 12 Roof 12a Roof body 13 Roof Piece 13a Roof body piece 13b Erection base 13c Support frame 13d Running parts (chill tank) 14 Bottom steel plate 14a Side iron plate 15 Rail parts 16 Temporary side structure 17 Work scaffolding 20 Box structure 20a Top section 20b Spacing part 21 Unit Box 22 Box roof 22a Top pipe row 22b Side pipe row 23 Hollow pipe components 23a Unit pipe member 24 Planned installation area 25 Center Jack 26 Blade mouth parts 27 Hollow pipe removal equipment 28a Fixture 28b Telescopic jack (fronte jack) 29a Fixtures 29b ESA jack 29c ESA steel wire 41 Support wall for towing 41a Rear part in towing direction 41b Facing surface in the towing direction 42 Towing wire 43 Tie beam 50 Expressway (Existing Structures) 51 Launch Base 51A Propulsion Work Section 51B Box construction work area 52 Base reached 53a,53b Mirror wall section 54 Propulsion mount 55 Temporary support wall (roof support reaction body) 56 Guide Tunnel 56a Chemical grouting work X transverse direction (towing direction, direction of movement)

Claims

1. In an underpass construction method in which a box structure having a rectangular cross-sectional shape is installed across the ground below an existing structure to form an underground space directly below the existing structure, a temporary facility for constructing the box structure is provided at a starting base on one side of a planned installation area where the box structure will be installed, when constructing a plurality of unit boxes that make up the box structure by pouring concrete and connecting them in a transverse direction, comprising: The unit boxes are constructed by being connected in a transverse direction with a space of a predetermined width between adjacent pairs of the unit boxes, A pair of rail members for moving the roof are installed on both sides of the construction work area when the unit boxes are connected together and constructed, the rail members extending along the transverse direction and supported from the ground surface via a side temporary frame, The roof is composed of a plurality of roof pieces arranged in the transverse direction, each roof piece including a roof body piece having a roof width corresponding to the width of the gap between an adjacent pair of the unit boxes, an installation base having running members attached to both ends and installed so as to straddle the pair of rail members, and a support structure assembled on the installation base and supporting the roof body piece from below, and the plurality of roof pieces are formed so that the roof body of the roof roof has a length in the transverse direction that can cover the entirety of at least one of the unit boxes to be constructed when the roof body pieces are arranged continuously without any gaps, This temporary facility for constructing a box structure can be switched between a state in which the entire upper part of the area in which at least one unit box is to be constructed is covered with a plurality of roof main body pieces arranged in succession, and a state in which the roof pieces are retracted to the gap portion, leaving the entire upper part of the area in which at least one unit box is to be constructed open, by appropriately moving each roof piece to a predetermined position on the rail member.

2. 2. A temporary facility for constructing a box structure as described in claim 1, wherein a bottom steel plate on which the unit box to be constructed is slidably placed is laid so as to cover the ground surface of the construction work area.

3. 3. A temporary facility for constructing a box structure according to claim 1 or 2, wherein the roof body piece of each of the roof pieces is a one-way slope piece that slopes to one side intersecting the transverse direction.

4. The box structure is composed of three or more unit boxes constructed in a connected manner, and the roof is long enough to cover the entire upper part of the two unit boxes constructed by the roof main body pieces of the multiple roof pieces arranged in succession, as described in claim 1 or 2.

5. 3. A temporary facility for constructing a box structure according to claim 1 or 2, wherein the ground below the existing structure is a fill ground.

Citation Information

Patent Citations

  • Underground structure and its constructing method

    JP1981108493A

  • Temporary roof

    JP1995317326A

  • Building under construction with protective roof

    JP1996028058A

  • Thrusting method of underground casing