Tunnel finished shape management method and device
A self-propelled mobile body with a 3D laser scanner along a tunnel rope efficiently measures and manages tunnel shapes, addressing space limitations and improving efficiency and accuracy in tunnel construction.
Patent Information
- Application Number
- JP2023061695
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-04-05
- Publication Date
- 2024-10-18
AI Technical Summary
The inefficiency of measuring the 3D shape of tunnels due to the limited space on the tunnel floor, where heavy machinery and equipment are present, leading to labor-intensive and time-consuming work for manually moving and arranging 3D laser scanners.
A self-propelled mobile body equipped with a 3D laser scanner moves along a main rope stretched along the tunnel's peripheral wall, allowing for efficient measurement of the tunnel's 3D shape, with management information generated by comparing cross-sectional views and converting data to a local coordinate system.
This method improves measurement efficiency by securing a large, obstruction-free space for the scanner, simplifies pre-measurement work, and enables accurate quality control of tunnel construction without interfering with ongoing construction activities.
Smart Images

Figure 2024148509000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a method and device for managing the as-built state of a tunnel in a mountainous area or the like.
[0002] Tunnel construction has traditionally been carried out by excavating rock in mountainous areas to create space for vehicles and trains to pass through. In this case, it is disclosed that a 3D laser scanner is used to measure the 3D shape of the tunnel after excavation or after the first lining is laid, the cross-sectional shape of the tunnel is calculated from the measurement results, the measured cross-sectional shape is compared with the designed cross-sectional shape to evaluate the finished shape of the tunnel, and the excavation work is modified based on the evaluation results, thereby managing the construction of the tunnel (see Patent Document 1). In addition, an arch-shaped concrete layer (secondary lining) is constructed in the space excavated after the primary lining, and the three-dimensional shape of the tunnel is measured using a 3D laser scanner. The finished shape of the tunnel is evaluated based on the measurement results. [Prior art documents] [Patent documents]
[0003] [Patent Document 1] Patent No. 5631512 Summary of the Invention [Problem to be solved by the invention]
[0004] Incidentally, when measuring the three-dimensional shape of such a tunnel, workers must manually carry a 3D laser scanner along with a stand and place it on the tunnel floor, or a worker must manually operate a vehicle (automobile) equipped with a 3D laser scanner to move it across the floor and place it in place. On the other hand, the space on the floor of a tunnel under construction is limited because heavy machinery for excavation, conveyors for transporting the debris discharged during excavation, and transport vehicles for transporting the debris run on it. As a result, the time-consuming task of moving and positioning the 3D laser scanner in a limited space reduces work efficiency, and there is room for improvement in terms of improving the efficiency of measuring the 3D shape of tunnels. The present invention has been devised in consideration of the above-mentioned circumstances, and an object of the present invention is to provide a method and device for managing a tunnel's as-built shape that is advantageous in improving the work efficiency of measuring the three-dimensional shape of a tunnel and efficiently managing the tunnel's as-built shape. [Means for solving the problem]
[0005] In order to achieve the above-mentioned object, one embodiment of the present invention includes stretching main ropes along the longitudinal direction of the tunnel on the peripheral wall surface near the top end of the tunnel, providing a self-propelled mobile body that moves along the main ropes, attaching a 3D laser scanner to the self-propelled mobile body that measures the three-dimensional shape of the tunnel and generates 3D shape data, moving the self-propelled mobile body along the main ropes, measuring the three-dimensional shape using the 3D laser scanner, and generating management information for managing the completed shape of the tunnel based on the 3D shape data measured by the 3D laser scanner and design data for the tunnel. In addition, one embodiment of the present invention is characterized in that the management information includes image information comparing a cross-sectional view of the tunnel based on the three-dimensional shape data with a cross-sectional view of the tunnel based on the design data. Moreover, one embodiment of the present invention is characterized in that a reference target is placed at a predetermined location of the tunnel, and the 3D laser scanner obtains a reference point of the tunnel by measuring the reference target, and prior to generating the management information, a conversion process is performed in which the 3D shape data of the tunnel is converted from a machine coordinate system whose origin is the mechanical center of the 3D laser scanner to a local coordinate system of the tunnel whose origin is the reference point. Moreover, one embodiment of the present invention is characterized in that it comprises a self-propelled mobile body that moves along a main rope stretched along the longitudinal direction of the tunnel on the peripheral wall surface near the top end of the excavated tunnel, a 3D laser scanner attached to the self-propelled mobile body that measures the three-dimensional shape of the tunnel and generates 3D shape data, and an information processing device that generates management information for managing the completed shape of the tunnel based on the 3D shape data and design data for the tunnel. In addition, one embodiment of the present invention is characterized in that the self-propelled mobile body comprises a drive unit that moves the self-propelled mobile body along the main rope, a communication unit configured to communicate with a remote control device via a wireless line, and a control unit that controls the drive unit based on a control command given to the communication unit from the remote control device via the wireless line. Moreover, one embodiment of the present invention is characterized in that the main rope is stretched between a pair of brackets attached to the peripheral wall surface spaced apart in the longitudinal direction of the tunnel, and a reel section is provided around one of the pair of brackets around which the main rope is wound and which can be unwound and wound around the other bracket of the pair of brackets. Effect of the Invention
[0006] According to one embodiment of the present invention, main ropes are stretched along the longitudinal direction of the tunnel on the peripheral wall surface near the top end of the tunnel, and a self-propelled mobile body is provided that moves along the main ropes. A 3D laser scanner that measures the three-dimensional shape of the tunnel and generates three-dimensional shape data is attached to the self-propelled mobile body, the self-propelled mobile body is moved along the main ropes, the three-dimensional shape is measured using the 3D laser scanner, and management information for managing the completed shape of the tunnel is generated based on the three-dimensional shape data measured by the 3D laser scanner and the tunnel design data. Therefore, since a wide, clear space with no heavy machinery or equipment is available near the top end, the three-dimensional shape of the tunnel can be efficiently measured using a 3D laser scanner mounted on a self-propelled vehicle that moves along the main rope stretched near the top end, which is advantageous for improving the efficiency of measurement work and efficiently managing the completed shape of the tunnel. Furthermore, when measuring the three-dimensional shape of a tunnel, it is sufficient to lay a single main rope on a self-propelled mobile body in advance, which is advantageous in simplifying the work carried out prior to the measurement work. In addition, because the main rope only occupies a small space near the top of the tunnel, it does not interfere with heavy machinery and equipment inside the tunnel, which is advantageous for measuring the tunnel's three-dimensional shape without affecting construction work. Furthermore, according to one embodiment of the present invention, the management information includes image information comparing a cross-sectional view of the tunnel based on three-dimensional shape data with a cross-sectional view of the tunnel based on design data, which is advantageous in accurately controlling the quality of tunnel construction by comparing these two cross-sectional views. Furthermore, according to one embodiment of the present invention, prior to generating management information, the three-dimensional shape data of the tunnel is subjected to a conversion process in which the three-dimensional shape data is converted from a machine coordinate system having its origin at the mechanical center of the three-dimensional laser scanner to a local coordinate system of the tunnel having its origin at a reference point obtained based on a reference target. This is advantageous in accurately obtaining three-dimensional shape data of the tunnel with a simple task of simply placing the reference target. Furthermore, according to one embodiment of the present invention, workers can easily control the movement of the self-propelled mobile body by operating a remote control device from a location away from the self-propelled mobile body, which is advantageous in improving the efficiency of measurement work for three-dimensional shape data of a tunnel. Furthermore, according to one embodiment of the present invention, the length of the main rope stretched between a pair of brackets can be changed as desired, so that the measurement range measured by the 3D laser scanner can be flexibly changed along the longitudinal direction of the tunnel in response to the construction status of the tunnel, which is advantageous in improving the efficiency of the measurement work of the tunnel's 3D shape data. [Brief description of the drawings]
[0007] [Figure 1] FIG. 1 is a side cross-sectional view of a tunnel to which a tunnel performance management method according to an embodiment of the present invention is applied, showing a tunnel performance management device according to the embodiment of the present invention installed within the tunnel. [Diagram 2] 2 is a cross-sectional view taken along line AA in FIG. 1. [Diagram 3] FIG. 11 is a side view showing a modified example of the bracket supporting the main rope. [Figure 4] 1 is a block diagram showing the configuration of a tunnel completion management device according to an embodiment of the present invention; [Diagram 5] 1 is an explanatory diagram showing an example of management information in which a reference cross-sectional view and an actual cross-sectional view of a tunnel are displayed superimposed on each other. FIG. [Figure 6] 1 is a flowchart of a tunnel completion management method according to an embodiment. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0008] Hereinafter, a tunnel construction work management method will be described together with a tunnel construction work management device according to an embodiment of the present invention.
[0009] First, a general tunnel construction in mountainous areas will be described. In mountainous areas, tunnels are excavated by various conventionally known construction methods such as blasting and mechanical construction. For example, in the case of blasting construction, after the blasting work is completed, on-site workers carry out excavation work using backhoes and rock drills, and the excavation waste generated by the blasting and excavation work is transported outside the tunnel using heavy machinery such as wheel loaders and dump trucks. After the excavated waste is removed, steel supports are erected, and then concrete is sprayed onto the tunnel walls near the face and onto the tunnel floor using a concrete sprayer, forming the primary concrete lining. Next, rock bolt insertion holes are drilled into the peripheral wall surface, and rock bolts are then driven into the rock bolt insertion holes to stabilize the ground. In addition, each time the tunnel is excavated to a predetermined length, rails are laid on the floor of the tunnel and a movable formwork, the slide center, is moved on the rails and positioned opposite the surrounding wall surface. Concrete is then poured between the surrounding wall surface and the slide center to create a secondary concrete lining. A tunnel is constructed by repeating this process of tunnel excavation and lining. In the following, a case where a tunnel is excavated using a blasting method will be described, however, the present invention is of course also applicable to cases where a tunnel is excavated using a method other than the blasting method, such as a mechanical method.
[0010] Tunnel as-built management is carried out by measuring the three-dimensional shape of the tunnel after excavation work, the primary lining, and the secondary lining, and then evaluating the tunnel as-built based on the measured three-dimensional shape of the tunnel. In this embodiment, the present invention is applied to the management of tunnel as-builts at each stage after excavation work, after primary lining, and after secondary lining, and a case is described in which the three-dimensional shape of a tunnel is measured using a three-dimensional laser scanner attached to a self-propelled mobile body that moves along the main rope stretched within the tunnel.
[0011] Next, the completed form management device 10 according to the present embodiment will be described with reference to the drawings. As shown in Figures 1 and 2, the finished product management device 10 is composed of a self-propelled mobile body 12, a 3D laser scanner 14 attached to the self-propelled mobile body 12, and an information processing device (computer) 16 (see Figure 4). The tunnel 2 shown in Figures 1 and 2 is in a state immediately after excavation and before the first lining is installed. In the figures, the reference numeral 1 denotes the natural ground. The self-propelled mobile body 12 moves along a main rope 18 that is stretched along the longitudinal direction of the excavated tunnel 2 on a peripheral wall surface 2B near the top end of the tunnel 2. The main rope 18 is made of a rope (wire rope) twisted with wires made of, for example, hard steel wire or piano wire. The main ropes 18 are stretched between a pair of brackets 20 installed at a distance in the longitudinal direction near the top end of the tunnel 2. The pair of brackets 20 are attached to the peripheral wall surface 2B. Alternatively, one end of the main rope 18 may be fixed to one of the pair of brackets 20, and the other bracket 20 may be provided with a reel section 22 that allows the other end of the main rope to be reeled in and reeled out, as shown in Fig. 3. The reel section 22 is provided with a stopper (not shown) that prohibits the main rope 18 from being reeled out from the reel section 22. In this way, the length of the main rope 18 stretched between the pair of brackets 20 can be changed as desired.
[0012] As shown in FIGS. 1, 2, and 4, the self-propelled mobile body 12 includes a mobile body main body 24, a pair of drive pulleys 26, a drive unit 28, a communication unit 30, and a control unit 32. The moving body 24 has a rectangular cross section. The autonomous vehicle 12 is movable along the main rope 18 . The pair of drive pulleys 26 are supported by a support plate 2410 extending upward from the upper portion of the movable body main body 24. The support plate 2410 has a long length along the main ropes 18, and the pair of drive pulleys 26 are rotatably provided on the support plate 2410 near both ends in the long length direction. The drive unit 28 is housed in the moving body 24 and drives the pair of drive pulleys 26 to rotate in forward and reverse directions, moving the moving body 24 along the main ropes 18. The drive unit 28 is configured to include a drive source (not shown) made up of, for example, an engine that runs on fossil fuel or a motor that runs on electricity, and a power transmission mechanism (not shown) that transmits the rotational drive force of the engine or motor to the pair of drive pulleys 26. The communication unit 30 is configured to be able to communicate with a remote control device (remote controller) 34 via a wireless line, and upon receiving a control command transmitted from the remote control device 34 via a wireless line, supplies the control command to the control unit 32. The control unit 32 controls the drive unit 28 based on the control command, thereby controlling the movement of the self-propelled mobile body 12 along the main rope 18. Specifically, it controls the movement direction, movement speed, movement amount, etc. of the self-propelled mobile body 12. The self-propelled mobile body 12 may have any configuration as long as it is capable of moving along the main rope 18 with the 3D laser scanner 14 attached. For example, a commercially available self-propelled conveyor that moves along a main rope installed in mountainous areas to transport felled timber can be used as the self-propelled mobile body 12.
[0013] As shown in FIGS. 2 and 3, the three-dimensional laser scanner 14 is attached to the mobile body 24 of the self-propelled mobile body 12 so as to be able to measure the three-dimensional shape of the tunnel 2. 1, for example, the 3D laser scanner 14 is detachably attached to one end face 2402 of the mobile body 24 that faces the face 2A via a bracket 25. The 3D laser scanner 14 may also be detachably attached to the other end face 2404 of the mobile body 24 located opposite the end face 2402 via a bracket 25. In short, as long as it is possible to measure the three-dimensional shape of the tunnel 2, the attachment location of the 3D laser scanner 14 to the mobile body 24 is arbitrary.
[0014] The three-dimensional laser scanner 14 scans a laser beam in horizontal and vertical directions and receives reflected light from the laser irradiation point where the laser beam is irradiated, thereby obtaining data consisting of the horizontal and vertical angles of the laser beam and the distance from the center point of the three-dimensional laser scanner 14 to the laser irradiation point, and from this data generates three-dimensional shape data (also called point cloud data) of the tunnel 2 in a Cartesian coordinate system expressed by coordinate values (x, y, z). In this embodiment, the 3D laser scanner 14 measures the 3D shape data of the peripheral wall surface 2B and floor surface 2C of the tunnel 2. In the following, the peripheral wall surface 2B and floor surface 2C, which are the targets for measuring the 3D shape data, will be simply referred to as the peripheral wall surface 2B. It should be noted that the three-dimensional laser scanner 14 is only required to be able to measure three-dimensional shape data over the entire circumference of the peripheral wall surface 2B of the tunnel 2, and the number of three-dimensional laser scanners 14 may be two or more. However, if the measurement range of the three-dimensional laser scanner 14 is limited, attaching multiple three-dimensional laser scanners 14 to the mobile body 24 and using each of the multiple three-dimensional laser scanners 14 to measure the peripheral wall surface 2B of the tunnel 2 in a divided portion along its circumferential direction will be advantageous in terms of measuring three-dimensional shape data in a detailed and accurate manner around the entire circumference of the peripheral wall surface 2B of the tunnel 2. The 3D laser scanner 14 has its own center position as the origin of the machine coordinates, and the 3D shape data measured by the 3D laser scanner 14 is converted by an information processing device 16 (described later) into 3D shape data with a preset reference point of the tunnel 2 as the origin of the local coordinates.
[0015] In this embodiment, before the three-dimensional shape of tunnel 2 is measured by three-dimensional laser scanner 14, a reference target 36 is placed at a predetermined location of tunnel 2, for example, on peripheral wall surface 2B of tunnel 2. Then, the 3D laser scanner 14 obtains the reference point of the tunnel 2, in other words, the origin of the local coordinates of the tunnel 2, by measuring the reference target 36. The reference target 36 is configured to reflect the laser beam emitted from the 3D laser scanner 14 towards the 3D laser scanner 14 . It is preferable to install the reference target 36 at a location whose position does not change due to the excavation, primary lining, and secondary lining operations. However, if it is difficult to install such a reference target 36, it is also possible to place a reference target 36 at each stage after excavation, after primary lining, and after secondary lining, as in this embodiment.
[0016] The information processing device 16 shown in FIG. 4 is installed at a predetermined location within the tunnel 2, and is configured to include an input device 38, an output device 40, and an external storage device 42, in addition to a CPU, ROM, RAM, hard disk drive, and input / output interface, all of which are not shown. The ROM stores predetermined control programs and the like, while the RAM provides a working area. The hard disk device constitutes a storage unit 44A, which will be described later, and also stores control programs for implementing a coordinate conversion unit 44B, a cross-sectional view generation unit 44C, and a management information generation unit 44D. The input / output interface provides an interface with the 3D laser scanner 14, the input device 38, and the output device 40. The input device 38 receives operational inputs from a worker (operator) who operates the information processing device 16, and includes a keyboard and a mouse. The output device 40 outputs information and includes a display and a printer. The external storage device 42 stores information, and includes an external hard disk device, an external SSD (solid state drive device), a semiconductor recording medium such as a memory card or a USB memory, or an optical disk recording medium such as a DVD. The information processing device 16 is placed, for example, at an appropriate location within the tunnel 2, and the information processing device 16 and the 3D laser scanner 14 are connected to each other so that information can be communicated via a wireless line such as a wireless LAN, but the information processing device 16 and the 3D laser scanner 14 may also be connected by a wired cable instead of a wireless line.
[0017] The storage unit 44A stores design data for the tunnel 2 to be constructed. The design data includes various design data that define the shape of tunnel 2, such as a reference cross-sectional view of tunnel 2 (hereinafter referred to as the design cross-sectional view) showing the cross-sectional shape of tunnel 2 after excavation work (before the primary lining), the thickness of the concrete of the primary lining, and the thickness of the concrete of the secondary lining.
[0018] The CPU executes a control program for the hard disk device to realize a coordinate conversion section 44B, a cross-sectional view generation section 44C, and a management information generation section 44D. The coordinate conversion unit 44B converts the three-dimensional shape data in mechanical coordinates supplied from the 3D laser scanner 14, with the mechanical center of the 3D laser scanner 14 as the origin, into three-dimensional shape data with the reference point of the tunnel 2 as the origin of the local coordinates.
[0019] The cross-sectional view generating unit 44C generates a measured cross-sectional view of the tunnel 2, which shows the cross-sectional shape of the tunnel 2, based on the three-dimensional shape data of the tunnel 2 expressed in the local coordinates supplied from the coordinate conversion unit 44B. The measured cross-sectional view of the tunnel 2 is generated, for example, corresponding to a position in the longitudinal direction of the tunnel 2 inputted from the input device 38.
[0020] The management information generating section 44D generates management information based on the measured cross-sectional view generated by the cross-sectional view generating section 44C and the design data. The design data includes a design cross-sectional drawing showing the design cross-section of the tunnel 2 after excavation, the concrete thickness of the primary lining, the concrete thickness of the secondary lining, etc. The management information generating unit 44D can generate a first reference cross-sectional view that indicates the cross-sectional shape of the tunnel 2 after the primary lining is performed, by taking into account the thickness of the concrete of the primary lining for the design cross-sectional view. In addition, the management information generation unit 44D can generate a second reference cross-sectional view showing the cross-sectional shape of the tunnel 2 after the secondary lining by taking into account the concrete thickness of the primary lining and the concrete thickness of the secondary lining to the design cross-sectional view. That is, the design cross-sectional view, the first reference cross-sectional view, and the second reference cross-sectional view are cross-sectional views of the tunnel 2 generated based on the design data.
[0021] For example, as shown in FIG. 5, management information MI is generated as image information comparing a design cross-sectional view 46 shown by a solid line (hereinafter, the first reference cross-sectional view and the second reference cross-sectional view will also be described as symbol 46) with a measured cross-sectional view 48 shown by a dotted line. The management information MI is displayed as an image on a display, which is an output device 40, or is printed out by a printer. By visually checking the management information MI displayed as an image or printed out, it is possible to check any differences or deviations between the actually measured cross-sectional shape (contour) of the tunnel 2 and the designed cross-sectional shape (contour) of the tunnel 2 at each stage, after excavation, after primary lining, and after secondary lining. In addition to the above-mentioned image information, the management information generation unit 44D is capable of calculating various evaluation data as management information MI, which evaluates by comparing the cross-sectional shape of tunnel 2 shown in the design cross-sectional view 46 (first reference cross-sectional view 46, second reference cross-sectional view 46) with the cross-sectional shape of tunnel 2 shown in the measured cross-sectional view 48. In this embodiment, the management information MI only needs to be usable to manage the completed shape of the tunnel 2 after excavation work, after the primary lining, and after the secondary lining, and is not limited to the image information shown in this embodiment, and various conventionally known configurations and display forms of the management information MI can be adopted.
[0022] In addition, in this embodiment, at each stage, namely, when excavation work is completed, when primary lining is completed, and when secondary lining is completed, main ropes 18 are stretched on the peripheral wall near the top end of the tunnel 2, a self-propelled mobile body 12 is installed on the main ropes 18, the cross-sectional shape of the tunnel 2 is measured using a 3D laser scanner 14 attached (mounted) to the self-propelled mobile body 12, and the measurement results are input into an information processing device 16, thereby managing the finished shape of the tunnel 2 after excavation work, when primary lining is completed, and when secondary lining is completed.
[0023] (After excavation work) After the excavation work, the amount of deviation between the central axis of the cross-sectional shape of tunnel 2 shown in the design cross-sectional view 46 and the central axis of the cross-sectional shape of tunnel 2 shown in the measured cross-sectional view 48 is calculated as evaluation data (management information MI), and the excavation work can be corrected based on the amount of deviation. In addition, after the excavation work, the deviation between the cross-sectional shape of tunnel 2 shown in the design cross-sectional view 46 and the cross-sectional shape of tunnel 2 shown in the measured cross-sectional view 48 is calculated along the circumferential direction of tunnel 2 as evaluation data (management information MI), thereby identifying areas where excavation of tunnel 2 is insufficient or excessive, and making corrections to the excavation work. In addition, after the excavation work, the deviation between the cross-sectional area of tunnel 2 shown in the design cross-sectional view 46 and the cross-sectional area of tunnel 2 shown in the measured cross-sectional view 48 is calculated as evaluation data (management information MI), thereby determining whether tunnel 2 has been excavated excessively or insufficiently, and the excavation work can be corrected based on the result of this determination. Specifically, modifications to excavation work include additional excavation work using heavy machinery, modifications to the drilling pattern for the next blasting process, adding or removing charge holes, or increasing or decreasing the amount of explosives loaded into the charge holes.
[0024] (After primary lining) In addition, even after the first lining, the finished shape of the tunnel 2 can be managed using the same procedures as after the excavation work, and the excavation work can be corrected. In other words, after the primary lining, the amount of deviation between the central axis of the cross-sectional shape of the tunnel 2 shown in the first reference cross-sectional view 46 and the central axis of the cross-sectional shape of the tunnel 2 shown in the measured cross-sectional view 48 is calculated as evaluation data (management information MI), and the excavation work can be corrected based on the amount of deviation. In addition, after the primary lining, the deviation between the cross-sectional shape of tunnel 2 shown in the first reference cross-sectional view 46 and the cross-sectional shape of tunnel 2 shown in the measured cross-sectional view 48 is calculated along the circumferential direction of tunnel 2 as evaluation data (management information MI), thereby identifying areas where excavation of tunnel 2 is insufficient or excessive, and making corrections to the excavation work. In addition, after the primary lining, the deviation between the cross-sectional area of tunnel 2 shown in the first reference cross-sectional view 46 and the cross-sectional area of tunnel 2 shown in the measured cross-sectional view 48 is calculated as evaluation data (management information MI), thereby determining whether tunnel 2 has been excavated excessively or insufficiently, and corrections to the excavation work can be made in the same manner as described above based on the determination result. It should be noted that if, after the primary lining, the ground 1 is partially excavated together with the primary lining concrete in order to correct the above excavation work, the primary lining will have to be redone in that portion.
[0025] (After secondary lining) After the secondary lining, the cross-sectional shape of tunnel 2 can be measured according to the procedure described below, and the completed shape of tunnel 2 can be evaluated and confirmed based on the following evaluation data (management information MI). In other words, after the secondary lining, the deviation between the central axis of the cross-sectional shape of tunnel 2 shown in the second reference cross-sectional view 46 and the central axis of the cross-sectional shape of tunnel 2 shown in the measured cross-sectional view after the secondary lining is calculated and evaluated as evaluation data (management information MI), thereby making it possible to evaluate whether the excavation of tunnel 2 is being carried out in accordance with the design data. In addition, after the secondary lining, the deviation amount between the cross-sectional shape of tunnel 2 shown in the second reference cross-sectional view 46 and the cross-sectional shape of tunnel 2 after the secondary lining shown in the measured cross-sectional view 48 is calculated and evaluated as evaluation data (management information MI) along the circumferential direction of tunnel 2, thereby making it possible to evaluate whether the excavation of tunnel 2 is being carried out in accordance with the design data. In addition, by calculating the deviation between the cross-sectional area of tunnel 2 after the secondary lining shown in the second reference cross-sectional view 46 and the cross-sectional area of tunnel 2 after the secondary lining shown in the measured cross-sectional view 48 as evaluation data (management information MI), it is possible to evaluate whether the excavation of tunnel 2 is being carried out in accordance with the design data.
[0026] Next, an example of the completed form management method according to this embodiment will be described with reference to the flowchart of FIG. First, excavation is performed on the face 2A by blasting or heavy machinery, and the excavated waste is removed (step S10). Next, a pair of brackets 20 are installed at intervals in the longitudinal direction of the tunnel 2 on the peripheral wall surface 2B near the top end of the excavated tunnel 2, and the main ropes 18 are attached, and then the self-propelled mobile body 12 is installed on the main ropes 18 (step S12). A 3D laser scanner 14 is attached to the self-propelled mobile body 12. Then, while moving the self-propelled mobile body 12 along the main ropes 18, the three-dimensional shape of the tunnel 2 after excavation is measured (step S14). After the tunnel 2 is excavated, a reference target 36 is placed in the tunnel 2 prior to measuring the three-dimensional shape, and the position of the reference target 36 is included in the measured three-dimensional shape data as the origin of the local coordinate system. The three-dimensional shape of the tunnel 2 measured by the 3D laser scanner 14 is converted by the coordinate conversion unit 44B, and the cross-sectional view generation unit 44C generates a measured cross-sectional view 48 based on the measured three-dimensional shape of the tunnel 2 and a designed cross-sectional view 46 based on the design data read out from the memory unit 44A as management information MI (step S16). Based on the management information MI, the shape of the tunnel 2 after the excavation work is evaluated, and it is determined whether or not the excavation work needs to be corrected (step S18). After measuring the three-dimensional shape of the tunnel 2, the self-propelled mobile body 12 is removed, and the main ropes 18 and brackets 20 are detached (step S20). Then, if it becomes necessary to modify the excavation work in step S18, the excavation work is modified (step S22). If it is determined in step S18 that the excavation work does not need to be corrected, step S22 is skipped and the process proceeds to step S24.
[0027] Next, concrete is sprayed onto the excavated face 2A and the peripheral wall surface 2B by a concrete sprayer to perform primary lining (step S24). In addition, steel supports are erected and rock bolts are installed. Next, similarly to step S12, a pair of brackets 20 are installed at intervals in the longitudinal direction of the tunnel 2 on the peripheral wall surface 2B near the top end of the tunnel 2 after the primary lining, and the main ropes 18 are attached, and then the self-propelled mobile body 12 is installed on the main ropes 18 (step S26). A 3D laser scanner 14 is attached to the self-propelled mobile body 12. Then, while moving the self-propelled mobile body 12 along the main ropes 18, the three-dimensional shape of the tunnel 2 after the primary lining is measured (step S28). Note that after the primary lining, a reference target 36 is placed in the tunnel 2 prior to measuring the three-dimensional shape, and the position of the reference target 36 is included in the measured three-dimensional shape data as the origin of the on-site coordinates. The three-dimensional shape of the tunnel 2 measured by the 3D laser scanner 14 is converted by the coordinate conversion unit 44B, and the cross-sectional view generation unit 44C generates a measured cross-sectional view 48 based on the measured three-dimensional shape of the tunnel 2 and a first reference surface view 34 based on the design data read out from the memory unit 44A as management information MI (step S30). Based on the management information MI, the completed shape of the tunnel 2 after the primary lining is evaluated, and it is determined whether or not the excavation work needs to be corrected (step S32). After measuring the three-dimensional shape of the tunnel 2, the self-propelled mobile body 12 is removed, and the main ropes 18 and brackets 20 are detached (step S34). If it is determined in step S32 that the excavation work needs to be modified, the excavation work and the primary lining are modified (step S36). Therefore, this modification work includes partial redoing of the primary lining, etc. If it is determined in step S32 that no correction to the excavation work is required, step S36 is skipped and the process proceeds to step S38. In addition, if it is determined in step S32 that no correction to the excavation work is necessary, the thickness of the secondary lining concrete can be determined before the secondary lining work is performed in the following step S40 by comparing (calculating) the actual measured cross-sectional view after the primary lining obtained in step S28 with the second reference cross-sectional view 46 based on the design data (i.e., the cross-sectional shape of the tunnel 2 after the secondary lining).
[0028] Next, rails (not shown) are laid on the floor surface 2C so that a slide center (not shown) can be moved to the vicinity of the area that has been primarily lined, and the slide center is moved and positioned so that secondary lining can be performed using this slide center (step S38). Next, concrete is poured into the pouring space formed between the formwork member of the slide center and the peripheral wall surface 2B of the tunnel 2 to perform a secondary lining (step S40). After the poured concrete has hardened, the slide center is removed from the form, and similarly to steps S12 and S26, a pair of brackets 20 are installed at intervals in the longitudinal direction of the tunnel 2 on the peripheral wall surface 2B near the top end of the tunnel 2 after the secondary lining, and the main ropes 18 are attached. After that, the self-propelled mobile body 12 is installed on the main ropes 18 (step S42). Then, while moving the self-propelled mobile body 12 along the main ropes 18, the 3D shape of the tunnel 2 after the secondary lining is measured using the 3D laser scanner 14 (step S44). Note that after the secondary lining, a reference target 36 is placed in the tunnel 2 prior to measuring the 3D shape, and the position of the reference target 36 is included in the measured 3D shape data as the origin of the on-site coordinates. The three-dimensional shape of the tunnel 2 measured by the 3D laser scanner 14 is converted by the coordinate conversion unit 44B, and the cross-sectional view generation unit 44C generates, as management information MI, a measured cross-sectional view 48 based on the measured three-dimensional shape of the tunnel 2 and a second reference cross-sectional view 46 based on the design data read out from the memory unit 44A (step S46). The worker evaluates the completed shape of the tunnel 2 after the secondary lining based on the management information MI output from the information processing device 16 (step S48). After measuring the three-dimensional shape of the tunnel 2, the worker removes the self-propelled mobile body 12 and detaches the main ropes 18 and brackets 20 (step S50). From then on, the process returns to step S10 and the tunnel 2 is constructed sequentially by repeating the steps of excavation work for the next span, evaluation of the as-built shape of the excavation work, correction work based on the evaluation, primary lining, evaluation of the as-built shape of the primary lining, correction work based on the evaluation, secondary lining, and evaluation of the as-built shape of the secondary lining in the same manner as described above.
[0029] As described above, according to this embodiment, main ropes 18 are stretched along the longitudinal direction of tunnel 2 on the peripheral wall surface 2B near the top end of tunnel 2, and a self-propelled mobile body 12 is provided that moves along the main ropes 18. A 3D laser scanner 14 that measures the three-dimensional shape of tunnel 2 and generates three-dimensional shape data is attached to the self-propelled mobile body 12, the self-propelled mobile body 12 is moved along the main ropes 18, the three-dimensional shape is measured by the 3D laser scanner 14, and management information for managing the completed shape of tunnel 2 is generated based on the three-dimensional shape data measured by the 3D laser scanner 14 and the design data for tunnel 2. Therefore, since a wide, clear space with no heavy machinery or equipment is available near the top end, the three-dimensional shape of the tunnel 2 can be efficiently measured using a 3D laser scanner 14 mounted on a self-propelled vehicle 12 that moves along the main rope 18 stretched near the top end, which is advantageous for improving the efficiency of measurement work and efficiently managing the completed shape of the tunnel 2. In other words, conventionally, the three-dimensional shape of tunnel 2 was measured by installing a three-dimensional laser scanner 14 on floor surface 2C where heavy machinery, transport vehicles, equipment, etc. are present, which required time-consuming work to be performed in the limited available space involved in moving and positioning 3D laser scanner 14, reducing work efficiency. In contrast, in this embodiment, such time-consuming work can be omitted, so that the three-dimensional shape of tunnel 2 can be measured efficiently, which is advantageous for improving the work efficiency of measurement work and efficiently managing the completed shape of tunnel 2. Furthermore, when measuring the three-dimensional shape of the tunnel 2, it is sufficient to lay out in advance a single main rope 18 along which the self-propelled mobile body 12 runs, which is advantageous in simplifying the work carried out prior to the measurement work. In addition, since the main rope 18 only occupies a small space near the top end of the tunnel 2, it does not interfere with the heavy machinery and equipment inside the tunnel 2, which is advantageous for performing measurement work of the three-dimensional shape of the tunnel 2 without affecting the construction work of the tunnel 2.
[0030] Furthermore, in this embodiment, the management information MI includes image information comparing the measured cross-sectional view 48 of the tunnel 2 based on the three-dimensional shape data with the cross-sectional views of the tunnel 2 based on the design data (design cross-sectional view 46, first reference cross-sectional view 46, second reference cross-sectional view 46), which is advantageous in accurately controlling the quality of the construction of the tunnel 2 by comparing these two cross-sectional views.
[0031] Furthermore, in this embodiment, a reference target 36 is placed at a predetermined location in tunnel 2, and the 3D laser scanner 14 obtains the reference point of tunnel 2 by measuring the reference target 36. Prior to generating management information MI, a conversion process is performed in which the 3D shape data of tunnel 2 is converted from the machine coordinate system whose origin is the mechanical center of the 3D laser scanner 14 to the local coordinate system of tunnel 2 whose origin is the reference point. This is therefore advantageous in that the three-dimensional shape data of the tunnel 2 can be accurately acquired by a simple task of positioning the reference target 36.
[0032] In addition, in this embodiment, the self-propelled mobile body 12 is equipped with a drive unit 28 that moves the self-propelled mobile body 12 along the main rope 18, a communication unit 30 that is configured to be able to communicate with a remote control device 34 via a wireless line, and a control unit 32 that controls the drive unit 28 based on control commands given from the remote control device 34 to the communication unit 30 via the wireless line. Therefore, workers can easily control the movement of the self-propelled mobile body 12 by operating the remote control device 34 from a location away from the self-propelled mobile body 12, which is advantageous in improving the efficiency of measurement work for the three-dimensional shape data of the tunnel 2.
[0033] In addition, the main rope 18 may be stretched between a pair of brackets 20 attached to the peripheral wall surface 2B spaced apart in the longitudinal direction of the tunnel 2, and one of the pair of brackets 20 may be provided with a reel section 22 around which the main rope 18 is wound and which can be reeled out and reeled in to the other bracket 20 of the pair of brackets 20 of the main rope 18. In this way, the length of the main rope 18 stretched between a pair of brackets 20 can be changed as desired, so that the movement range of the self-propelled mobile body 12, in other words, the measurement range measured by the 3D laser scanner 14, can be flexibly changed along the longitudinal direction of the tunnel 2 in response to the construction status of the tunnel 2, which is advantageous in improving the efficiency of the measurement work of the 3D shape data of the tunnel 2.
[0034] In this embodiment, the case has been described where the cross-sectional shape of the tunnel 2 is measured using a 3D laser scanner 14 mounted on a self-propelled mobile body 12 at all stages after excavation work, primary lining, and secondary lining. However, it is optional to apply the present invention at one or two of the above three stages, and measure the cross-sectional shape of the tunnel 2 using a 3D laser scanner 14 installed on the floor surface 2C in the remaining stages as in the conventional manner. [Explanation of symbols]
[0035] 1. Ground 2. Tunnel 2A Face 2B Surrounding wall surface 2C Floor 10 Performance management device 12 Self-propelled vehicles 14 3D Laser Scanner 16 Information processing equipment 18 Main rope 20 Bracket 22 Reel section 24 Mobile body 2402 End face 2404 End face 2410 Support plate 25 Bracket 26 Drive pulley 28 Drive unit 30 Communications Department 32 Control section 34 Remote control device 36 Reference Targets 38 Input Devices 40 Output Device 42 External storage device 44A Storage section 44B Coordinate conversion section 44C Sectional view generation section 44D Management information generation section 46 Design Sectional Drawings (First Reference Sectional Drawing, Second Reference Sectional Drawing) 48 Measured cross section MI management information
Claims
1. A main rope is stretched along the longitudinal direction of the tunnel on a peripheral wall surface near the top end of the tunnel, and a self-propelled mobile body is provided that moves along the main rope; The self-propelled mobile body is moved along the main rope, and three-dimensional shape data of the tunnel is generated by a three-dimensional laser scanner equipped on the autonomous mobile body. generating management information for managing the completed shape of the tunnel based on the three-dimensional shape data and the design data of the tunnel; A tunnel construction management method characterized by the above.
2. The management information includes image information obtained by comparing a cross-sectional view of the tunnel based on the three-dimensional shape data with a cross-sectional view of the tunnel based on the design data.
2. A tunnel completion management method according to claim 1.
3. placing a reference target at a predetermined location of said tunnel; the 3D laser scanner obtains a reference point for the tunnel by measuring the reference target; Prior to the generation of the management information, the three-dimensional shape data is subjected to a conversion process in which the data is converted from a machine coordinate system having the mechanical center of the three-dimensional laser scanner as its origin to a local coordinate system of the tunnel having the reference point as its origin.
3. A tunnel completion management method according to claim 1 or 2.
4. a self-propelled mobile body that moves along a main rope that is stretched along the longitudinal direction of the excavated tunnel on a peripheral wall surface near the top end of the tunnel; a three-dimensional laser scanner attached to the self-propelled mobile body, which measures a three-dimensional shape of the tunnel and generates three-dimensional shape data; an information processing device that generates management information for managing the completed shape of the tunnel based on the three-dimensional shape data and design data of the tunnel; A tunnel construction management device comprising:
5. The self-propelled mobile body is A drive unit that moves the self-propelled movable body along the main rope; A communication unit configured to be able to communicate with the remote control device via a wireless line; a control unit that controls the drive unit based on a control command given to the communication unit from the remote control device via the wireless line, 5. A tunnel construction management device according to claim 4.
6. The main rope is stretched between a pair of brackets attached to the peripheral wall surface spaced apart in the longitudinal direction of the tunnel, One end of the main rope is fixed to one of the pair of brackets, and a reel unit that enables the other end of the main rope to be unwound and wound is provided to the other bracket of the pair of brackets.
6. A tunnel construction management device according to claim 4 or 5.