Cultivated crop harvesting method and harvesting device
The conveyor system on trellises addresses the inefficiencies of manual basket carrying by transporting harvest baskets directly to a collection point, reducing worker burden and preventing contamination, thereby enhancing harvesting efficiency.
Patent Information
- Application Number
- JP2023065599
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-04-13
- Publication Date
- 2024-10-25
AI Technical Summary
Harvesting cultivated crops from trellised trees is labor-intensive due to the need for workers to carry full harvest baskets to a central collection point, reducing efficiency and increasing the risk of contamination.
A method and device that uses a conveyor system with a support wire and transport wire to move harvest baskets along a trellis, allowing fruits to be collected and transported directly to a collection point without manual carrying, using a movable pulley and elastic guide member to facilitate movement.
Reduces worker burden by eliminating the need for manual transport, prevents contamination, and enhances harvesting efficiency by minimizing direct contact with the ground, thus improving overall productivity.
Smart Images

Figure 2024151853000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a method and an apparatus for harvesting cultivated crops. [Background technology]
[0002] A typical harvesting operation in trellis cultivation is carried out, for example, as follows. First, a worker picks fruit from the trees and places the picked fruit in a harvesting basket. When the harvesting basket is full of fruit, the worker carries it to a location where a special container is placed, where the fruit is sorted and transferred into the container. Next, the worker loads the container with the fruit transferred into it onto a truck and drives it to a sorting facility. Another conventional method for harvesting fruit from trees is a fruit cultivation support device that uses a transport machine moving mechanism (see, for example, Patent Document 1). [Prior art documents] [Patent documents]
[0003] [Patent Document 1] Japanese Utility Model Application Publication No. 52-25944 Summary of the Invention [Problem to be solved by the invention]
[0004] In recent years, when cultivating crops such as apples, it has become common to plant apple trees in rows, with the trunks of the trees secured to a trellis to prevent them from falling over. The above harvesting procedures are also performed when harvesting apples planted in rows, but the containers into which the fruit are transferred are generally placed together in a large space at the end of the tree row so that they can be easily carried out of the orchard. It takes a lot of time and effort for workers to carry the harvesting baskets full of fruit to the end of the tree row, and the work efficiency is not necessarily high.
[0005] Therefore, the problem that the present invention aims to solve is to provide a method and an apparatus for harvesting cultivated crops that can reduce the burden on workers involved in harvesting. [Means for solving the problem]
[0006] A method of harvesting cultivated crops that solves the above-mentioned problems is a method of harvesting cultivated crops that are attached in rows above ground level to trees supported by a support, in which a collection unit for collecting the cultivated crops is disposed between one end side and the other end side of a guide member supported by the support at one end side and the other end side of the row, the cultivated crops picked from the trees are placed in a carrier that transports the cultivated crops, and the carrier is moved in a direction along the row while dropping along the guide member, thereby transporting the cultivated crops to the collection unit.
[0007] The transport body may also include a movable pulley that moves along the guide member, and the movable pulley may rotate and run on the guide member to move the transport body.
[0008] In addition, the transport body may be equipped with a harvest basket that contains the cultivated crop and has an openable bottom, and the cultivated crop may be placed in the harvest basket with the bottom of the harvest basket closed, the transport body may be transported to the collection section, the bottom of the harvest basket may be opened, and the cultivated crop may be discharged from the harvest basket and collected at the collection section.
[0009] The guide member may be elastic so as to slacken when the conveyor is hung thereon.
[0010] Also, the cultivated crop may be harvested after adjusting the slack of the guide member in accordance with the height position of the harvesting section.
[0011] In addition, a cultivated crop harvesting device that solves the above-mentioned problems is a cultivated crop harvesting device that harvests cultivated crops that are attached to trees supported by a support above ground surface and arranged in a row, and is equipped with a guide member supported by the support at one end and the other end of the row, and a transport body that stores the cultivated crops picked from the trees and moves along the guide member to transport them to a collection section that collects the cultivated crops and is arranged between the one end and the other end of the guide member. Effect of the Invention
[0012] According to the cultivated crop harvesting method and harvesting apparatus of the present invention, the burden on workers involved in harvesting can be reduced. [Brief description of the drawings]
[0013] [Figure 1] 1 is a perspective view of a crop cultivation field H in which a harvesting device 20 is installed, viewed obliquely from above. [Diagram 2] FIG. 2 is a plan view of crop cultivation field H seen from above. [Diagram 3] FIG. [Figure 4] 2 is an enlarged front view of a portion of the conveying body 23. FIG. [Diagram 5] 4 is a flowchart showing an example of a procedure for installing the harvesting device 20. [Figure 6] 10 is a flowchart showing an example of a procedure for harvesting fruit W. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0014] Hereinafter, the cultivated crop harvesting method and harvesting device according to the present invention will be described with reference to the drawings. Fig. 1 is a perspective view of a crop cultivation field H on which a harvesting device 20 is installed, viewed from diagonally above. Fig. 2 is a plan view of the crop cultivation field H, viewed from above. In the following description, when there is no need to distinguish between components with branch numbers, the branch numbers will be omitted.
[0015] As shown in Figures 1 and 2, in a crop cultivation field H of the embodiment, for example, a plurality of trellises 10 (10-1, 10-2, ...) are erected so as to be approximately parallel to each other in a plan view. As shown in Figure 2, a plurality of fruit trees T are planted in the crop cultivation field H. The fruit trees T are, for example, columnar type trees. The fruit trees T may be trees other than columnar type trees. Note that the fruit trees are not shown in Figure 1.
[0016] A number of fruit trees T are arranged side by side along a trellis 10, and each fruit tree T is supported by the trellis 10. A cultivated crop, for example, apple fruits W, are attached to the fruit trees T. The fruits W are attached to the fruit trees T in a row along the trellis 10 above ground level. The trellis 10 is an example of a support body.
[0017] In the crop cultivation field H, a harvesting device 20 is attached to the trellis 10. The harvesting device 20 includes, for example, a support wire 21, a conveying wire 22, and a conveying body 23. The conveying body 23 is capable of storing fruits W picked from fruit trees T. The conveying body 23 storing the fruits W transports the fruits W while moving along the conveying wire 22 in a direction following the rows of fruits W on the fruit trees T. In the crop cultivation field H, a picker F1 picks fruits W from the fruit trees T supported by the trellis 10 and stores them in the conveying body 23.
[0018] The support wires 21 are, for example, stretched between the first trellis 10-1 and the second trellis 10-2. For example, the first support wire 21-1 is stretched between one ends of the first trellis 10-1 and the second trellis 10-2, and the second support wire 21-2 is stretched between the other ends of the first trellis 10-1 and the second trellis 10-2. The first support wire 21-1 and the second support wire 21-2 are stretched, for example, at a position 2 m above the ground.
[0019] The supporting wire 21 is, for example, a steel wire. The supporting wire 21 may be another supporting member that is hung between the trellises 10. As a supporting member, for example, instead of the supporting wire 21, a metallic or non-metallic string-like member other than a wire may be hung, or a supporting member having a shape other than a string, for example, a rod-like or plate-like member may be hung.
[0020] The conveying wire 22 is installed by connecting a first joint P1 at the longitudinal center of the first support wire 21-1 and a second joint P2 at the longitudinal center of the second support wire 21-2. The conveying wire 22 is, for example, a steel wire. The conveying wire 22 is supported by the trellis 10 via the support wires 21 at one end and the other end of the row. The conveying wire 22 is installed with tension applied between the first support wire 21-1 and the second support wire 21-2. The conveying wire 22 has a degree of elasticity that allows it to slacken when the conveying body 23 is hung thereon.
[0021] Since the conveying wire 22 slackens when the conveying body 23 is hung, when the trellis 10 is installed on land with no slope, the conveying body 23 can move toward the intermediate position between the first joint part P1 and the second joint part P2 due to the slackness of the conveying wire 22 when the conveying body 23 is hung from the conveying wire 22. At a position between the first joint part P1 and the second joint part P2, for example at the intermediate position, a collecting part P3 that collects the fruit W is disposed.
[0022] The collecting part P3 is formed, for example, in an aisle formed in the middle of the tree row and crossing the tree row. The aisle is, for example, a road along which a transport vehicle M, such as a light truck for transporting harvested fruit trees, passes, and the transport vehicle M stops at the collecting part P3. A container into which the fruit W is transferred is loaded on the loading platform of the transport vehicle M. The conveying wire 22 guides the conveyor 23 from between the first connecting position and the collecting part P3 and between the second connecting position P2 and the collecting part P3 to the collecting part P3. The conveying wire 22 is an example of a guide member.
[0023] The conveyance body 23 is a member that stores fruits W picked from fruit trees T and conveys them to the transport vehicle M parked at the collection section P3. Fig. 3 is a side view of the conveyance body 23. Fig. 4 is an enlarged front view of a portion of the conveyance body 23. The conveyance body 23 includes, for example, a harvesting basket 31, a suspending member 32, and a pulley member 33.
[0024] Harvesting basket 31 is configured to include, for example, storage section 31A, bottom plate 31B, and hanging section 31C. Hanging member 32 is configured to include, for example, rod-shaped member 32A and hook section 32B. It is configured to include a pair of hook members. Pulley member 33 is configured to include, for example, movable pulley 33A and rotating shaft 33B. Harvesting basket 31 is basket-shaped. Harvesting basket 31 may be a bag-shaped harvesting bag.
[0025] The storage section 31A in the harvesting basket 31 is a basket of a size capable of storing, for example, about several tens of fruits W. For example, the harvesting basket 31 can store about 30 to 40 small fruits W and about 20 to 25 large fruits. The size of the harvesting basket 31 may be larger or smaller than this. The bottom of the harvesting basket 31 is open, but is normally closed by a bottom plate 31B. By closing the bottom of the harvesting basket 31, the fruits W stored in the storage section 31A are prevented from falling. The storage section 31A may be closed without being open. The storage section 31A may be provided with, for example, a tipping structure that allows it to be easily tipped over. The harvesting basket 31 may be provided with a basket for storing the fruits W instead of the storage section 31A.
[0026] Bottom plate 31B has a hinge structure that rotates around one end edge as shown by the imaginary line in Fig. 3. Bottom plate 31B has a hinge structure that allows the bottom of storage section 31A to be opened and closed. When the bottom of storage section 31A is closed by bottom plate 31B, fruit W can be stored in storage section 31A. The bottom of harvesting basket 31 is openable. When bottom plate 31B rotates from a state in which the bottom is closed by bottom plate 31B, and the bottom of harvesting basket 31 is opened, fruit W stored in storage section 31A can fall from the bottom of harvesting basket 31.
[0027] Suspension part 31C is attached to the upper end of storage part 31A. Suspension part 31C is U-shaped with an open bottom when viewed from the front as shown in Fig. 4. The lower end of suspension part 31C is fixed to the upper end edge of storage part 31A. Suspension part 31C is a molded product having a U-shape, but suspension part 31C may be, for example, a string-like member.
[0028] The suspending members 32 are arranged in pair, sandwiching the movable pulley 33A of the pulley member 33. The rod-shaped member 32A of the suspending member 32 extends vertically with the conveyor 23 suspended from the conveyor wire 22. The hook portion 32B extends from the lower end of the rod-shaped member 32A and curves gradually upward. A suspension portion 31C of the harvest basket 31 is suspended from the hook portion 32B.
[0029] The movable pulley 33A of the pulley member 33 has a groove with a width substantially equal to the diameter of the conveying wire 22. The pulley member 33 runs while rotating on the conveying wire 22 with the conveying wire 22 fitted in the groove formed in the movable pulley 33A, and moves along the conveying wire 22 using the conveying wire 22 as a track. The depth of the groove formed in the movable pulley 33A is longer (deeper) than the diameter of the conveying wire 22. For this reason, the movable pulley 33A is less likely to come off the conveying wire 22 as it moves along the conveying wire 22.
[0030] A rotating shaft 33B passes through the center of rotation of the movable pulley 33A. Both ends of the rotating shaft 33B are attached to the hanging member 32 of the hanging member 32 so as to be rotatable. When the movable pulley 33A rotates, the hanging member 32 moves via the rotating shaft 33B, and further, the harvesting basket 31 suspended from the hanging member 32 moves. In this way, the harvesting basket 31 moves along the conveying wire 22 together with the hanging member 32 and the pulley member 33.
[0031] Since the conveying wire 22 is installed in a slack state, the conveying body 23 moves along the conveying wire 22 while receiving a force in a direction to fall due to its own weight. Therefore, after the conveying body 23 is suspended from the conveying wire 22, it moves toward the lowest end position of the slack in the conveying wire 22, for example, toward the collecting section P3 where the conveying vehicle M is parked. The slack of the conveying wire 22 is adjusted by the joining positions of the conveying wire 22 at the first joining part P1 and the second joining part P2 according to, for example, the height of the platform of the conveying vehicle M.
[0032] Fruits W from fruit trees T are picked by multiple pickers F1 at picking positions near the fruit trees T, as shown in FIG. 2, for example. The pickers F1 place the picked fruits W in a carrier 23. The pickers F1 place the fruits W in the carrier 23 until the carrier 23 is to some extent full. The pickers F1 hang the carrier 23, now filled with fruits W, on the carrier wire 22. The pickers F1 sequentially perform the tasks from picking the fruits W to hanging the carrier 23.
[0033] The suspended conveyance body 23 is transported to the collection section P3. At the collection section P3, a collection worker F2 works or waits on the loading platform of the transport vehicle M. The collection worker F2 discharges the fruit W from the conveyance body 23 transported to the collection section P3 and transfers it to a container or the like loaded on the loading platform of the transport vehicle M. The conveyance body 23 from which the fruit W has been discharged is collected and stored on or near the loading platform of the transport vehicle M. Thereafter, the transport vehicle M loaded with the harvested fruit W transports the fruit W to a sorting site or the like.
[0034] Next, a specific procedure for harvesting the fruits W using the harvesting device 20 will be described. The harvesting device 20 remains attached to the trellis 10 even during the growth of the fruits W before they are harvested. Thereafter, when it is time to harvest the fruits W, the worker then uses the harvesting device 20 to harvest the fruits W. Here, a procedure for installing the harvesting device 20 on the trellis 10 will be described, and then a procedure for harvesting the fruits W using the installed harvesting device 20 will be described.
[0035] 5 is a flow chart showing an example of a procedure for installing the harvesting device 20. To install the harvesting device 20, first, a first support wire 21-1 is hung between one ends of the adjacent first trellis 10-1 and second trellis 10-2, and a second support wire 21-2 is hung between the other ends (step S11). The trellis 10 has a sufficient strength to support a plurality of fruit trees T, but when the support wire 21 is hung between the trellises 10, if the strength to maintain the trellis 10 standing is insufficient or likely to be insufficient, a support pole for reinforcing the trellis 10 may be erected separately.
[0036] After the first support wire 21-1 and the second support wire 21-2 are hung between the trellises 10, one end and the other end of the conveying wire 22 are joined to the middle positions of the first support wire 21-1 and the second support wire 21-2, respectively, to install the conveying wire 22 (step S13). The conveying wire 22 may be joined to the support wire 21 in any manner. For example, the end of the conveying wire 22 may be wound around the support wire 21, the end of the conveying wire 22 may be fastened to the support wire 21 using a wire or the like, or a joining tool for joining wires (wire rods) together may be used.
[0037] The conveying wire 22 connected to the supporting wire 21 is in a state of being somewhat slack. In the slack state, the conveying wire 22 has the first joint P1 and the second joint P2 at a high position, and gradually becomes lower until it reaches approximately the center position between the first joint P1 and the second joint P2. The collecting portion P3 is set at a position where the conveying wire 22 is at its lowest, for example, approximately the center position between the first joint P1 and the second joint P2.
[0038] When joining the conveying wire 22 to the supporting wire 21, the length of the conveying wire 22 between the first supporting wire 21-1 and the second supporting wire 21-2 is adjusted at the joining position of the conveying wire 22 to the supporting wire 21 in accordance with the height of the platform of the transport vehicle M to adjust the slack of the conveying wire 22. For example, when the platform of the transport vehicle M is high, the length of the conveying wire 22 between the first supporting wire 21-1 and the second supporting wire 21-2 is shortened to reduce the slack of the conveying wire 22. On the other hand, when the platform of the transport vehicle M is low, the length of the conveying wire 22 between the first supporting wire 21-1 and the second supporting wire 21-2 is lengthened to increase the slack of the conveying wire 22.
[0039] Next, a transport vehicle M (vehicle) for transporting the fruits W is placed at the collection section P3 (step S15). Next, a plurality of carriers 23 are brought into the vicinity of the trellis 10 (step S17). Furthermore, pickers F1 and collectors F2 are deployed at predetermined positions. The deployment of the pickers F1 and collectors F2 may be performed sequentially at different times. In this way, preparations are made to start harvesting the fruits W, the process shown in FIG. 5 is completed, and preparations for harvesting the fruits W are completed.
[0040] Next, a procedure for harvesting fruits W using the harvesting device 20 will be described. Fig. 6 is a flow chart showing an example of the procedure for harvesting fruits W. When harvesting fruits W, the picker F1 first moves to the vicinity of the fruit tree T with the carrier 23 that has been returned to the vicinity of the transport vehicle M or another return position, and picks fruits W from the tree T (step S21).
[0041] Next, the picker F1 places the picked fruits W in the harvest basket 31 (step S23). The picker F1 checks whether the harvest basket 31 is full of fruits W (step S25). If the harvest basket 31 is not full of fruits W, the picker F1 repeats the process of steps S23 and S25.
[0042] When the harvest basket 31 is full of fruits W, the picker F1 carries the carrier 23 with the harvest basket 31 full of fruits W to the vicinity of the conveying wire 22 and suspends the harvest basket 31 on the carrier 23 from the conveying wire 22 (step S27). When picking fruits W, the picker F1 may remove the harvest basket 31, the suspending member 32, and the pulley member 33 from the conveying wire 22, place the suspending member 32 and the pulley member 33 near the conveying wire 22, and then take the harvest basket 31 with him / her.
[0043] When suspending the conveyor 23 from the conveyor wire 22, the picker F1 first removes the harvesting basket 31 from the suspending member 32 and pulley member 33 of the conveyor 23, and hooks the movable pulley 33A of the pulley member 33 onto the conveyor wire 22. At this time, the conveyor wire 22 fits into the groove of the movable pulley 33A, a pair of suspending members 32 are disposed on each side of the conveyor wire 22, and the weights of the suspending members 32 and the pulley member 33 are applied to the conveyor wire 22 almost evenly, so that the movable pulley 33A is placed on the conveyor wire 22.
[0044] Once the movable pulley 33A is placed on the conveying wire 22, the hanging part 31C of the harvesting basket 31 is hooked onto the hook part 32B of the hanging member 32. The harvesting basket 31 is suspended from the conveying wire 22 by the hanging part 31C being hooked onto the hook part 32B. Once the harvesting basket 31 is suspended from the conveying wire 22, the picker F1 releases the conveying body 23 from his / her hands.
[0045] Since the conveying wire 22 is loose between the first joint P1 and the second joint P2, the conveying body 23 that has left the hands of the picker F1 moves by dropping by its own weight along the conveying wire 22 toward the collecting part P3 between the first joint P1 and the second joint P2. Therefore, the conveying body 23 moves to the collecting part P3 by itself without the help of the picker F1 (step S29).
[0046] The transport body 23 that has reached the collection section P3 is either retained at the collection section P3 or received by the collection worker F2. The collection worker F2 rotates the bottom plate 31B of the transport body 23 that has been retained or received by himself to open the bottom of the storage section 31A. With the bottom of the storage section 31A now open, the stored fruit W is discharged from the harvest basket 31. The collection worker F2 collects the discharged fruit W (step S31).
[0047] The collector F2 collects the discharged fruits W by transferring them to a container or the like loaded on the bed of the transport vehicle M. The fruits W discharged from the harvesting basket 31 may be dropped and transferred directly to the container or the like. In this case, the container or the like may be provided with a cushioning material to protect the falling fruits W from damage.
[0048] The carrier 23 with the fruits W collected from the harvest basket 31 is removed from the conveying wire 22 by the hands of the collector F2. When removing the carrier 23 from the conveying wire 22, the collector F2 first removes the harvest basket 31 from the suspending member 32. Next, the collector F2 moves the pulley member 33 and the suspending member 32 above the conveying wire 22 to remove them from the conveying wire 22. The harvest basket 31 and the suspending member 32 can be easily removed, and the pulley member 33 can also be easily removed since it is only hooked on the conveying wire 22. The collector F2 returns the removed carrier 23 to a return position near the transport vehicle M (step S33). The carrier 23 returned to the return position is then brought to the picker F1.
[0049] Thereafter, the picker F1 and the collector F2 repeat the same process, and when the amount of fruit W transferred to the transport vehicle M reaches a predetermined amount, the process shown in Fig. 6 ends. The fruit W loaded onto the transport vehicle M is then transported to a sorting facility by the transport vehicle M. At the sorting facility, the fruit W undergoes sorting, inspection, and other processes before being distributed to the market.
[0050] In the embodiment of the cultivated crop harvesting method, fruits W picked from fruit trees T are stored in a conveyor 23, and the conveyor 23 is moved in a direction along the row of fruits W on the fruit trees T while dropping along the conveyor wire 22, thereby conveying the fruits W to the collection section P3. This eliminates the need for the worker to carry the fruits from the picking position to the collection section. This reduces the burden on the worker involved in harvesting.
[0051] Conventionally, containers into which fruits are transferred are placed together in a large space at the end of the tree row, which is labor-intensive, time-consuming, and inefficient. Placing the harvest baskets on the ground can also cause problems such as dirt getting on the harvest baskets and fruits W. In addition, small transport vehicles that run between the trellises 10 have been developed to transport the fruits W picked by workers from the fruit trees T to the collection area, but these vehicles cannot carry a large amount of fruit at one time, so depending on the amount of harvested crops, the number of round trips increases, making it difficult to perform the work efficiently. Furthermore, there were also cases where the transport vehicles interfered with the workers.
[0052] In this regard, in the cultivated crop harvesting method of the embodiment, the fruit W is transported from the picked position to the collection section P3 by a transport body 23 running on the transport wire 22. Since the transport body 23 moves along the track of the transport wire 22, the picked fruit W can be efficiently transported to the collection section P3 even if the amount that can be transported at one time is not large. In addition, since the work of placing the harvesting basket on the ground can be avoided, it is possible to prevent mud from getting on the harvesting basket and the fruit W, which can cause spoilage during storage. Furthermore, the harvesting basket 31 moves in the air. Therefore, it is possible to prevent the fruit W from being contaminated by mud splashes while being transported using the harvesting basket 31.
[0053] Furthermore, the carrier 23 that has completed transportation is removed from the carrier wire 22 by the harvester F2 and returned to a return position near the transport vehicle M. The returned carrier 23 is collected, for example, by the picker F1 who picks the next fruit W or by a worker who hands the carrier 23 to the picker, and is used to transport the next fruit W. This makes it possible to prevent interference between the worker and the carrier 23 before the carrier 23 is returned to the picking position for the fruit W, further reducing the burden on the workers involved in harvesting.
[0054] In the above embodiment, the cultivated crop is an apple, but the cultivated crop may be other fruits, for example, other fruits such as pears, persimmons, cherries, etc., or non-fruit crops such as tomatoes, cucumbers, hops, corn, etc. Also, in the above embodiment, the support is a trellis 10, but the support may be something else, for example, a trellis such as a grape trellis. When the support is a grape trellis, the cultivated crop is grapes.
[0055] In the above embodiment, the collecting part P3 is located approximately in the center between the first connecting part P1 and the second connecting part P2, but the collecting part P3 may be located at another position between the first connecting part P1 and the second connecting part P2. In addition, when the support body is erected on a slope and the height position of the second connecting part P2 is lower than the first connecting part P1, for example, the second connecting part P2 may be the collecting part P3.
[0056] In the above embodiment, the conveyor 23 includes the movable pulley 33A, but the conveyor 23 does not have to include a member that functions as a pulley. The conveyor 23 may also include a suppression structure that suppresses the falling of the cultivated crop during transportation due to the harvest basket 31 tipping over, etc., while the cultivated crop is being transported. The suppression structure may, for example, be configured by stretching auxiliary wires parallel to the conveyor wire 22 on both sides of the conveyor wire 22, and providing auxiliary members that move on the auxiliary wires to protrude from the sides of the conveyor 23. The auxiliary members may include pulleys that run on the auxiliary wires.
[0057] Carrier 23 may be in a form other than that of traveling on conveyor wire 22. Carrier 23 may be suspended from conveyor wire 22, or may move while being sandwiched between two conveyor wires 22. In the above embodiment, carrier 23 has a structure in which suspending member 32 and pulley member 33 are integrated and harvesting basket 31 is suspended from suspending member 32, but harvesting basket 31, suspending member 32, and pulley member 33 may be integrated.
[0058] In the above embodiment, the suspension member 32 is attached to the pulley member 33, and the harvesting basket 31 is suspended from the suspension member 32. However, the pulley member 33 attached to the harvesting basket 31 may be set on the conveying wire 22. In this case, for example, a connecting member is interposed between the harvesting basket 31 and the pulley member 33, and the connecting member may be arranged on only one side of the conveying wire 22, or may be ring-shaped, with a part of the circumference being an openable / closable opening / closing portion, and may have a so-called carabiner-like opening / closing structure in which the opening / closing portion is biased in the closing direction. With such a structure, the harvesting basket 31 and the pulley member 33 can be integrated, and the harvesting basket 31 and the pulley member 33 are not separated at the collecting section P3, which makes it easy to store and transport the conveying body 23. [Explanation of symbols]
[0059] 10(10,1,10,2)…Trellis 20...Harvesting device 21 (21-1, 21-2)…Support wire 22...Transport wire 23...Transport body 31...Harvest Basket 31A…Housing section 31B…Bottom plate 31C…hanging part 32... Suspension member 32A... Rod-shaped member 32B…Hook section 33... Pulley member 33A…Moving pulley 33B…Rotary axis F1…Plucking worker F2: Collection workers H: Crop cultivation field M...Transport vehicle P1...first joint part P2…Second joint part P3…Collection section
Claims
1. 1. A method for harvesting cultivated crops, the method comprising harvesting cultivated crops in rows above ground level on a tree supported by a support, the method comprising: A collection unit for collecting the cultivated crop is disposed between the one end side and the other end side of a guide member supported by the support at one end side and the other end side of the row, The cultivated crops picked from the trees are accommodated in a carrier for transporting the cultivated crops; The conveyor is moved in a direction along the row while dropping along the guide member to convey the cultivated crop to the collection section. How to harvest cultivated crops.
2. The conveyor includes a movable pulley that moves along the guide member, The movable pulley rotates and travels on the guide member, and the conveyor moves. A method for harvesting cultivated crops according to claim 1.
3. The transport body includes a harvest basket that contains the cultivated crop and has an openable bottom, The cultivated crop is placed in the harvest basket with the bottom of the harvest basket closed; Transporting the carrier to the collecting section; The bottom of the harvest basket is opened, and the cultivated crop is discharged from the harvest basket and collected in the collection section. A method for harvesting a cultivated crop according to claim 1 or 2.
4. The guide member has elasticity that allows it to slacken by suspending the conveying body. A method for harvesting cultivated crops according to claim 1.
5. After adjusting the slack of the guide member according to the height position of the collection section, harvesting the cultivated crop; A method for harvesting cultivated crops according to claim 4.
6. A harvesting device for harvesting cultivated crops that are attached to a tree supported by a support above ground level and arranged in a row, comprising: A guide member supported by the support at one end side and the other end side of the row; a carrier that receives the cultivated crops picked from the trees, moves along the guide member, and carries the cultivated crops to a collection unit that is disposed between the one end side and the other end side of the guide member and collects the cultivated crops, Cultivated crop harvesting equipment.
Citation Information
Patent Citations
Loading device
JP1994007021A
Ropeway with gliding tool for automatic returning mechanism
JP2000262753A
Suspension pulley mechanism for carrying load and load carrying system using the suspension pulley mechanism
JP2014008937A
Simple transport cableway device and system
JP4450685B2
JP1977025944U