Wall construction method
By installing wall panels between columns before ceiling beams and using temporary braces, the method addresses installation challenges, ensuring safe and efficient construction with improved workability and material handling.
Patent Information
- Application Number
- JP2023083588
- Authority / Receiving Office
- JP · JP
- Patent Type
- Applications
- Current Assignee / Owner
- Filing Date
- 2023-05-22
- Publication Date
- 2024-12-04
- Estimated Expiration
- 2043-05-22
AI Technical Summary
The existing methods for attaching wall panels to building frames at construction sites face challenges such as difficulty in vertical alignment, interference from ceiling beams, and the need for adjusting hanging positions, leading to troublesome and dangerous installation processes, especially when exterior materials are pre-attached.
The method involves installing wall panels between columns before ceiling beams, using temporary braces for support, and attaching hanging tools to the upper end surfaces of the panels, allowing for vertical alignment and safe installation without interference, while also optimizing spacing and material dimensions for easier installation and coverage.
This approach enhances workability by ensuring safe, efficient, and trouble-free installation of wall panels, reduces the need for mid-process adjustments, and improves the installation of exterior and interior materials, contributing to improved construction efficiency and safety.
Smart Images

Figure 2024167490000001_ABST
Abstract
Description
[Technical field]
[0001] The present invention relates to a method for constructing a wall. [Background technology]
[0002] Patent Document 1 discloses a modular building constructed by arranging a plurality of building units each consisting of a column and a girder. In this modular building, a building exterior wall section is attached to the column, ceiling girder, and floor girder that are arranged on the outdoor side of the side of the building unit. The building exterior wall section has a column exterior wall unit attached to the column, a beam exterior wall unit attached to the ceiling girder or floor girder, and a main exterior wall unit arranged side by side with the column exterior wall unit between the upper and lower beam exterior wall units. The building unit of Patent Document 1 is manufactured at a unit manufacturing factory. Furthermore, at the unit manufacturing factory, the main insulation part of the main exterior wall unit and the pre-attached insulation part of the beam exterior wall unit are attached to the building unit. The main insulation part is a wall panel having vertical frame members extending in the up-down direction, a main interior wall surface member arranged on the indoor side of the vertical frame members, a wall base surface member arranged on the outdoor side of the vertical frame members, and a filling insulation material provided between the main interior wall surface member and the wall base surface member, and is disposed between two columns and between the ceiling beams and the floor beams. [Prior art documents] [Patent documents]
[0003] [Patent Document 1] JP 2012-154063 A Summary of the Invention [Problem to be solved by the invention]
[0004] In the case of Patent Document 1, there is no problem because the wall panel (the main insulating part of the main exterior wall unit) is attached to the building unit at the factory. However, for example, when attaching a wall panel to a building unit at a construction site, there are problems such as the difficulty of the installation work. Specifically, when attaching a wall panel to a building unit at a construction site, the wall panel is lifted by a crane and fitted between the pillars and beams of the building unit. If a lifting device is attached to the top end face of the wall panel, the ceiling beams get in the way when the wall panel is being fitted between the pillars and beams (when the wall panel is being installed), so the lifting device must be removed in the middle to change the hanging position, which is troublesome and dangerous.
[0005] On the other hand, if a hanger is attached to the surface of a wall panel (for example, the surface facing the outdoors), there is no need to change the hanging position midway. However, if a hanger is attached to the surface of a wall panel, it is difficult to hang the wall panel vertically, which creates problems such as making it difficult to fit the wall panel between beams (making it difficult to install the wall panel). Furthermore, there are cases where exterior materials such as external wall materials are attached to the wall panel in advance, and in such cases, if a hanger is attached to the surface of the wall panel, there is also the problem that the installation position of the hanger must be set in consideration of the exterior materials.
[0006] The present invention has been made in consideration of the above circumstances, and an object of the present invention is to provide a construction method for a wall comprising a frame consisting of pillars and beams and a wall panel attached to the frame, which improves construction ease. [Means for solving the problem]
[0007] The invention described in claim 1 is, for example, as shown in Figs. 1 to 16, a construction method for a wall 1 in a building, The wall 1 includes a frame 10 consisting of columns 11, 12 and beams 13, 14, and a wall panel 20 attached to the frame 10. After the pillar installation step of installing the plurality of pillars 11, 12, a wall panel installation step of lifting the wall panel 20 and installing it between the pillars is performed; The method is characterized in that after the wall panel installation step, a ceiling beam installation step is carried out in which a ceiling beam 13 among the beams is lifted and installed between the upper ends of the columns 11.
[0008] According to the invention described in claim 1, the wall panel installation step is performed before the ceiling beam installation step, so that even if a hanging device is attached to the upper end surface of the wall panel 20, the ceiling beam 13 does not get in the way during the installation of the wall panel 20. Therefore, there is no need to remove the balls to change the hanging position while installing the wall panel 20, which eliminates problems such as inconvenience and danger. Also, by attaching the hanging fixture to the upper end surface of the wall panel 20, it becomes easy to hang the wall panel 20 vertically, so there is no problem such as difficulty in installing the wall panel 20. Furthermore, by attaching the hanging fixture to the upper end surface of the wall panel 20, even if an exterior material (exterior wall material 31, etc.) is attached to the wall panel 20 in advance, there is no need to set the installation position of the hanging fixture in a position that takes into consideration the exterior material. Therefore, a construction method for a wall 1 comprising a frame 10 consisting of columns 11, 12 and beams 13, 14, and a wall panel 20 attached to the frame 10, with improved workability, can be provided.
[0009] The invention described in claim 2 is, for example, as shown in Figs. 4 to 16, in the construction method described in claim 1, A temporary fixing step of attaching a temporary brace 100 for supporting the wall panel 20 to the wall panel 20; and a final fixing step of fixing the wall panel 20 to the ceiling beam 13. The method is characterized in that the temporary brace 100 is removed after the main fixing step.
[0010] According to the invention described in claim 2, a temporary fixing step is performed in which temporary braces 100 are attached to the installed wall panel 20, so that the wall panel 20 can be supported by the temporary braces 100 from the time the wall panel 20 is installed until the time the wall panel 20 is fixed to the ceiling beam 13. Therefore, even if the ceiling beam installation step is performed after the wall panel installation step, the wall panel 20 will not collapse before the ceiling beam 13 is installed (specifically, before the main fixing step), so safety can be ensured. Furthermore, if there is a possibility that the wall panel 20 may collapse, it is necessary to work while taking care not to let the wall panel 20 collapse, which requires more work than performing the temporary fixing step (including removal of the temporary braces 100). In contrast, according to the invention described in claim 2, the temporary fixing step is performed to eliminate the possibility that the wall panel 20 may collapse, so that workability is improved even if the temporary fixing step (including removal of the temporary braces 100) is performed.
[0011] The invention described in claim 3 is, for example, as shown in Figs. 4 to 16, in the construction method described in claim 1, The spacing dimensions L11, L12, L31, and L32 between the pillars are set longer than the width dimensions L21, L22, L41, and L42 of the wall panels installed between the pillars.
[0012] According to the invention described in claim 3, the spacing dimensions L11, L12, L31, and L32 between the pillars are longer than the width dimensions L21, L22, L41, and L42 of the wall panels installed between the pillars, i.e., clearances are provided between the pillars, so that the wall panel installation step can be easily performed and workability is improved.
[0013] The invention described in claim 4 is, for example, as shown in Figs. 4 to 16, in the construction method described in claim 1, The method includes a step of installing a column exterior material 40 that covers the columns 11 and 12, The width dimension L52 of the indoor side portion of the column exterior material 40 is set shorter than the interval dimension L61 between the wall panels 20, The column exterior material 40 is characterized in that a width dimension L51 of the outdoor portion thereof is set longer than a distance L61 between the wall panels 20.
[0014] According to the invention described in claim 4, the width dimension L52 of the indoor side portion of the pillar exterior material 40 is shorter than the spacing dimension L61 between the wall panels 20, i.e., a clearance is provided between the wall panels 20, so that the exterior material installation step can be easily performed and workability is improved. On the other hand, since the width dimension L51 of the outdoor side portion of the pillar exterior material 40 is longer than the interval dimension L61 between the wall panels 20, the boundaries between the pillars 11, 12 and the wall panel 20 can be covered by both ends (folded portions) of the outdoor side portion of the pillar exterior material 40. Therefore, compared to the case where a separate member is provided to cover the boundaries between the pillars 11, 12 and the wall panel 20, workability is improved and the number of parts can be reduced.
[0015] The invention described in claim 5 is, for example, as shown in Figs. 4 to 16, in the construction method described in claim 4, The method is characterized by having a waterproofing means installation step of installing waterproofing means 70 between the column exterior material 40 and the wall panel 20.
[0016] According to the invention described in claim 5, a waterproofing means installation step is performed in which waterproofing means 70 is installed between the column exterior material 40 and the wall panel 20, thereby improving the watertightness and airtightness between the column exterior material 40 and the wall panel 20, and further between the columns 11, 12 and the wall panel 20. Effect of the Invention
[0017] According to the present invention, it is possible to provide a construction method with improved workability. [Brief description of the drawings]
[0018] [Figure 1] FIG. [Diagram 2] A diagram showing the joint structure between the first pillar and the ceiling beam. [Diagram 3] A diagram showing the joint structure between the second column and the ceiling beam. [Figure 4] FIG. 1 is a diagram illustrating a method for constructing a wall. [Diagram 5]FIG. 1 is a diagram illustrating a method for constructing a wall. [Figure 6] FIG. 1 is a diagram illustrating a method for constructing a wall. [Figure 7] FIG. 1 is a diagram illustrating a method for constructing a wall. [Figure 8] FIG. 1 is a diagram illustrating a method for constructing a wall. [Figure 9] FIG. 1 is a diagram illustrating a method for constructing a wall. [Figure 10] FIG. 1 is a diagram illustrating a method for constructing a wall. [Figure 11] FIG. 1 is a diagram illustrating a method for constructing a wall. [Figure 12] FIG. 1 is a diagram illustrating a method for constructing a wall. [Figure 13] FIG. 1 is a diagram illustrating a method for constructing a wall. [Figure 14] FIG. 1 is a diagram illustrating a method for constructing a wall. [Figure 15] FIG. 1 is a diagram illustrating a method for constructing a wall. [Figure 16] FIG. 1 is a diagram illustrating a method for constructing a wall. [Figure 17] FIG. 1 is a diagram for explaining problems with a method different from the construction method of the present invention. DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0019] Hereinafter, an embodiment of the present invention will be described with reference to the drawings. However, the embodiment described below is subject to various limitations that are technically preferable for implementing the present invention, but the technical scope of the present invention is not limited to the following embodiment and illustrated examples. Note that the directions (front-back, left-right, up-down) in the following embodiment and illustrated examples are set solely for the convenience of explanation.
[0020] "Wall Structure" FIG. 1 is a perspective view showing an example of a wall 1 in the present embodiment. The wall 1 is a wall (exterior wall, interior wall) in a building such as a house, and is configured with a wooden frame 10 consisting of pillars 11, 12 and beams 13, 14, and a wooden wall panel 20 attached to the frame 10.
[0021] Frame Fig. 2 shows an example of a joint structure between a first pillar 11 and a ceiling beam 13 in this embodiment, where (a) is an exploded perspective view and (b) is a perspective view. Fig. 3 shows an example of a joint structure between a second pillar 12 and a ceiling beam 13 in this embodiment, where (a) is an exploded perspective view and (b) is a perspective view. The frame 10 is a framework of a conventional framework. The frame 10 includes a first pillar 11 and a second pillar 12 that is shorter than the first pillar 11 as pillars (wooden pillars), and includes a ceiling beam 13 and a floor beam 14 as beams (wooden beams). Although the frame 10 in this embodiment is made of wood, the present invention is not limited to this and may be made of steel, for example.
[0022] As shown in FIG. 2, a beam support metal fitting 16 is attached to the upper end of the first pillar 11 (specifically, the portion located above the upper end surface of the second pillar 12). The beam support hardware 16 is a joint member having a U-shape in plan view. The bottom of the U-shape of the beam support hardware 16 is fixed to one of the four side surfaces (left side surface, right side surface, front side surface, and rear side surface) of the first column 11 that faces another first column 11 (an adjacent first column 11), and both ends of the U-shape face toward the other first column 11.
[0023] A pair of slits 13a into which both ends (both tips of the U-shape) of the beam support hardware 16 can be inserted are provided at the side ends (left end, right end) of the ceiling beam 13. The slits 13a are provided perpendicular to the side surfaces (left surface, right surface) of the ceiling beam 13. Furthermore, at the side ends (left end, right end) of the ceiling beam 13, there are provided through holes 13b into which a connector 51 (drift pin, etc.) can be inserted for connecting the beam support hardware 16 to the ceiling beam 13. Also, at both ends (both ends of the U-shape) of the beam support hardware 16, there are provided through holes into which the connectors 51 can be inserted.
[0024] With the ceiling beam 13 placed in the appropriate position, the connecting tool 51 is inserted into the through hole 13b of the ceiling beam 13, thereby fixing the ceiling beam 13 to the beam support hardware 16. This allows the ceiling beam 13 to be fixed to the first column 11 via the beam support hardware 16. Here, the state in which the ceiling beam 13 is positioned in the appropriate position means, for example, a state in which both ends of the beam support hardware 16 are inserted into a pair of slits 13a in the ceiling beam 13, so that the side end faces (left end face, right end face) of the ceiling beam 13 are in contact with the side faces of the first column 11, and also a state in which the upper end face of the ceiling beam 13 is flush with the upper end face of the first column 11.
[0025] Specifically, the side ends (left end, right end) of the ceiling beam 13 are provided with a pair of slits 13a into which both ends of the beam support hardware 16 can be inserted, and a number of through holes 13b perpendicular to the slits 13a. The through holes 13b are provided parallel to the side surfaces (left and right surfaces) of the ceiling beam 13. That is, the through holes 13b penetrate the ceiling beam 13 in the width direction (front-rear direction). Each through hole 13b of the ceiling beam 13 is provided at a position that communicates with one of the through holes provided at one end (one tip of the U-shape) of the beam support hardware 16 and one of the through holes provided at the other end (the other tip of the U-shape) of the beam support hardware 16 when the ceiling beam 13 is placed at an appropriate position. Therefore, when the ceiling beam 13 is placed at an appropriate position, the connector 51 is driven from one end side (rear end side) to the other end side (front end side) of the through hole 13b of the ceiling beam 13, so that the connector 51 penetrates the through hole provided at one end of the beam support hardware 16 and the through hole provided at the other end of the beam support hardware 16.
[0026] As shown in FIG. 3, a tenon fitting 17 is attached to the upper end of the second pillar 12. The tenon hardware 17 is a pipe-shaped (rod-shaped) joint member. The lower part of the tenon hardware 17 is fixed inside the second pillar 12, and the upper part protrudes upward from the upper end surface of the second pillar 12. The lower part of the tenon hardware 17 is provided with two through holes arranged perpendicular to each other as through holes into which a fastener (drift pin or the like) for joining the tenon hardware 17 and the second pillar 12 can be inserted. The upper end part of the second pillar 12 is also provided with a first through hole 12a and a second through hole 12b arranged perpendicular to each other as through holes into which a fastener for joining the tenon hardware 17 and the second pillar 12 can be inserted.
[0027] The first through hole 12a of the second pillar 12 is provided at a position communicating with one of the through holes provided in the lower part of the tenon hardware 17 when the lower part of the tenon hardware 17 is inserted into the second pillar 12. Therefore, when the lower part of the tenon hardware 17 is inserted into the second pillar 12, a connector for connecting the tenon hardware 17 and the second pillar 12 is driven from one end side to the other end side of the first through hole 12a of the second pillar 12, so that the connector penetrates one of the through holes provided in the lower part of the tenon hardware 17. Furthermore, the second through hole 12b of the second pillar 12 is provided at a position communicating with the other through hole provided in the lower part of the tenon hardware 17 when the lower part of the tenon hardware 17 is inserted into the second pillar 12. Therefore, when the lower part of the tenon hardware 17 is inserted into the second pillar 12, a connector for connecting the tenon hardware 17 and the second pillar 12 is driven from one end side to the other end side of the second through hole 12b of the second pillar 12, so that the connector penetrates the other through hole provided in the lower part of the tenon hardware 17.
[0028] In this way, with the lower part of the tenon hardware 17 inserted into the second pillar 12, the tenon hardware 17 is fixed to the second pillar 12 by inserting a connector into the through holes 12a, 12b of the second pillar 12. In other words, the tenon hardware 17 is fixed to the second pillar 12 by a fastener inserted from one of the four sides (left side, right side, front side, rear side) of the second pillar 12 and a fastener inserted from the other side perpendicular to the one side.
[0029] A mortise hole is provided on the lower end surface of the ceiling beam 13 into which the upper part of the mortise hardware 17 can be inserted. The mortise hardware 17 fixed to the second pillar 12 is inserted into the mortise hole of the ceiling beam 13 until the lower end surface of the ceiling beam 13 abuts against the upper end surface of the second pillar 12, whereby the ceiling beam 13 is positioned in the appropriate position. Furthermore, a through hole 13c is provided at the lower end of the ceiling beam 13, into which a connector 53 (drift pin or the like) for connecting the tenon hardware 17 to the ceiling beam 13 can be inserted. A through hole is also provided at the upper part of the tenon hardware 17, into which the connector 53 can be inserted.
[0030] With the ceiling beam 13 placed in the appropriate position, the connector 53 is inserted into the through hole 13c of the ceiling beam 13, thereby fixing the ceiling beam 13 to the tenon hardware 17. This allows the ceiling beam 13 to be fixed to the second column 12 via the tenon hardware 17. Specifically, the lower end of the ceiling beam 13 is provided with a mortise hole into which a mortise fitting 17 can be inserted, and a plurality of through holes 13c perpendicular to the mortise hole. The through holes 13c are provided parallel to the side surfaces (left and right surfaces) of the ceiling beam 13. That is, the through holes 13c penetrate the ceiling beam 13 in the width direction (front-rear direction). Each through hole 13c of the ceiling beam 13 is provided at a position that communicates with one of the through holes provided at the upper part of the tenon hardware 17 when the ceiling beam 13 is placed at an appropriate position. Therefore, when the ceiling beam 13 is placed at an appropriate position, the connector 53 is driven from one end side (front end side) to the other end side (rear end side) of the through hole 13c of the ceiling beam 13, so that the connector 53 penetrates the through hole provided at the upper part of the tenon hardware 17.
[0031] [Wall Panel] The wall panel 20 is a wood panel for a wall. A wooden panel is a construction panel that is made up of a rectangular frame made up of vertical and horizontal frame materials A assembled into a rectangular shape, a frame body made up of auxiliary beam materials assembled vertically and horizontally inside this rectangular frame, and a facing material C attached to one or both sides of this frame body, resulting in a hollow structure. The internal hollow portion (the back side of the facing material) is usually filled with a heat insulating material D such as glass wool or rock wool. Although the wall panel 20 of this embodiment includes a polystyrene foam heat-insulating board as the heat insulating material D, the heat insulating material D is not limited to this.
[0032] The wall panel 20 is arranged, for example, within a rectangular area defined by the columns 11, 12 and the beams 13, 14. Specifically, the wall panel 20 is arranged within a rectangular area formed by adjacent first and second columns 11, 12, a ceiling beam 13 connecting the upper ends of these columns 11, 12, and a floor beam 14 connecting the lower ends of these columns 11, 12. In addition, the wall panel 20 is arranged within a rectangular area formed by two adjacent second columns 12, a ceiling beam 13 connecting the upper ends of these second columns 12, and a floor beam 14 connecting the lower ends of these second columns 12.
[0033] That is, of the frame members A constituting the wall panel 20, the vertical frame members extending in the up-down direction have their outer surfaces (outer surfaces in the left-right direction) joined to the pillars 11, 12. Specifically, of the frame members A constituting the wall panel 20, the vertical frame member adjacent to the first pillar 11 has its outer surface (the surface facing the first pillar 11) joined to the first pillar 11. Also, of the frame members A constituting the wall panel 20, the vertical frame member adjacent to the second pillar 12 has its outer surface (the surface facing the second pillar 12) joined to the second pillar 12.
[0034] Further, of the frame members A constituting the wall panel 20, the horizontal frame members extending in the left-right direction have their outer surfaces (the outer surfaces in the up-down direction) joined to the beams 13, 14. Specifically, of the frame members A constituting the wall panel 20, the horizontal frame member adjacent to the ceiling beam 13 (the upper horizontal frame member) has its outer surface (the surface facing the ceiling beam 13) joined to the ceiling beam 13. Also, of the frame members A constituting the wall panel 20, the horizontal frame member adjacent to the floor beam 14 (the lower horizontal frame member) has its outer surface (the surface facing the floor beam 14) joined to the floor beam 14. The joining means for joining the wall panel 20 to the columns 11, 12 and the beams 13, 14 may be joints (such as screws), adhesive, or a combination of these.
[0035] When the wall panel 20 is an exterior wall panel, an exterior wall material 31 is provided on one surface (the surface facing the outdoors) of the wall panel 20, and an interior wall material 32 is provided on the other surface (the surface facing the indoors). Furthermore, when the wall panel 20 is a wall panel for an interior wall, an interior wall material 32 is provided on at least one of one surface and the other surface of the wall panel 20. In addition, the exterior wall material 31 in this embodiment is a galvalume steel sheet (registered trademark), but is not limited to this. Furthermore, the inner wall material 32 in this embodiment is a calcium silicate board, but is not limited to this.
[0036] 《Wall construction method》 Next, an example of a construction method for the wall 1 in this embodiment will be described with reference to FIGS. In the construction method of this embodiment, the floor beams 14, the columns 11 and 12, the wall panel 20, and the ceiling beams 13 are assembled in this order at the construction site. Specifically, first, the pillars 11, 12, the beams 13, 14, the wall panel 20, etc. are transported from a factory to the construction site.
[0037] [Floor beam installation steps] Next, as shown in FIG. 4, floor beams 14 are installed at the construction site.
[0038] [Floor panel installation steps] Next, a floor panel 30 (wooden floor panel) is installed within a rectangular area defined by floor beams 14 arranged along a first direction perpendicular to the height direction (up-down direction) of wall 1 and floor beams 14 arranged along a second direction perpendicular to both the height direction of wall 1 and the first direction. Note that in Figs. 4 to 13, the reference numeral "30" indicating the floor panel is omitted, and some of the reference numerals "14" indicating the floor beams are omitted to avoid complexity.
[0039] [Column installation steps] Next, as shown in FIG. 4, the pillars 11 and 12 are installed. In this embodiment, the first pillar 11 with the beam support hardware 16 attached is transported from a factory to the construction site. That is, in this embodiment, the beam support hardware 16 is attached to the first pillar 11 at the factory, but this is not limited to this, and the beam support hardware 16 may be attached to the first pillar 11 at the construction site. When attaching the beam support hardware 16 to the first pillar 11 at the construction site, the timing of attaching the beam support hardware 16 can be appropriately selected as long as it is before installing the ceiling beam 13 (the ceiling beam 13 that is supported by the beam support hardware 16).
[0040] In this embodiment, the second pillar 12 with the tenon hardware 17 attached is transported from a factory to the construction site. That is, in this embodiment, the tenon hardware 17 is attached to the second pillar 12 at the factory, but this is not limited to this, and the tenon hardware 17 may be attached to the second pillar 12 at the construction site. When attaching the tenon hardware 17 to the second pillar 12 at the construction site, the timing of attaching the tenon hardware 17 can be appropriately selected as long as it is before the wall panel 20 is installed.
[0041] As shown in Fig. 3, the second pillar 12 is provided with a first through hole 12a and a second through hole 12b that penetrate perpendicularly to each other. The tenon hardware 17 is fixed to the second pillar 12 by a fastener (a fastener for joining the tenon hardware 17 and the second pillar 12) that is driven from one end side to the other end side of these through holes 12a and 12b. Therefore, after the wall panel 20 is installed, one end or the other end of the through holes 12a and 12b may be hidden by the wall panel 20, making it impossible to drive in the fastener. Therefore, the tenon hardware 17 is attached to the second pillar 12 before the wall panel 20 is installed.
[0042] [Wall panel installation step A] Next, a hoist is attached to the upper end surface of the wall panel 20 (here, an exterior wall panel). Then, as shown in Fig. 5, the wall panel 20 is lifted by a crane and installed between adjacent columns 11, 12 (between the first column 11 and the second column 12, and between the second columns 12). After that, the hoist is removed from the wall panel 20. In this embodiment, as shown in Fig. 14(a), for example, a positioning material 61a is provided on the upper surface of the floor beam 14 adjacent to the wall panel 20. In addition, a positioning material 61b is provided on the lower surface of the lower horizontal frame member of the frame members A constituting the wall panel 20. When the wall panel 20 is lifted by a crane and lowered onto the floor beam 14, the wall panel 20 is lowered at a position where the positioning material 61a of the floor beam 14 and the positioning material 61b of the wall panel 20 are in contact with each other while being aligned in the thickness direction (front-rear direction) of the wall panel 20, as shown in Fig. 14(b), for example.
[0043] In this embodiment, as shown in Fig. 15, for example, a positioning material 63a is provided on the side of the columns 11 and 12 adjacent to the wall panel 20. Also, a positioning material 63b is provided on the side of the vertical frame material A constituting the wall panel 20. When the wall panel 20 is placed in an appropriate position on the floor beam 14 (a position where the positioning material 61a of the floor beam 14 and the positioning material 61b of the wall panel 20 are in contact with each other while being aligned in the thickness direction of the wall panel 20), the positioning material 63a of the columns 11 and 12 and the positioning material 63b of the wall panel 20 are in contact with each other while being aligned in the thickness direction (front-rear direction) of the wall panel 20.
[0044] In this embodiment, the beam support hardware 16 is attached to the first column 11 at the factory, so that the beam support hardware 16 is attached to the first column 11 at a stage before the wall panel 20 is installed. Therefore, the wall panel 20 to be installed between the first column 11 and the second column 12 cannot be lowered as shown in Fig. 14(a), that is, cannot be lowered from directly above the floor beam 14, because the beam support hardware 16 attached to the first column 11 gets in the way. Therefore, the wall panel 20 to be installed between the first column 11 and the second column 12 is lowered from a position that is not directly above the floor beam 14, as shown in Fig. 5, and then pulled to directly above the floor beam 14, so that it is positioned in an appropriate position on the floor beam 14.
[0045] 15, for example, the interval dimension L11 between the first pillar 11 and the second pillar 12 is set to be longer than the width dimension (width dimension including the positioning material 63b) L21 of the wall panel 20 to be installed between the first pillar 11 and the second pillar 12 (L11>L21). Specifically, in this embodiment, the difference between the interval dimension L11 and the width dimension L21 is set to be 5 mm. In addition, the spacing dimension L31 (spacing dimension including the positioning material 63a) between the first pillar 11 and the second pillar 12 is set to be longer than the width dimension L41 of the wall panel 20 installed between the first pillar 11 and the second pillar 12 (L31>L41). Specifically, in this embodiment, the difference between the spacing dimension L31 and the width dimension L41 is set to be 5 mm. In this manner, in this embodiment, a clearance is provided between the first column 11 and the second column 12, so that the work of placing the wall panel 20 between the first column 11 and the second column 12 is easy to work on. It should be noted that the difference between the space dimension L11 and the width dimension L21 and the difference between the space dimension L31 and the width dimension L41 do not have to be the same.
[0046] 15, for example, the interval L12 between the second columns 12 is set to be longer than the width L22 (width including the positioning material 63b) of the wall panel 20 to be installed between the second columns 12 (L12>L22). Specifically, in this embodiment, the difference between the interval L12 and the width L22 is set to be 5 mm. In addition, the spacing dimension L32 (spacing dimension including the positioning material 63a) between the second columns 12 is set to be longer than the width dimension L42 of the wall panel 20 installed between the second columns 12 (L32>L42). Specifically, in this embodiment, the difference between the spacing dimension L32 and the width dimension L42 is set to be 5 mm. In this manner, in the present embodiment, since a clearance is provided between the second columns 12, the work of placing the wall panels 20 between the second columns 12 is easy to carry out. It should be noted that the difference between the space dimension L12 and the width dimension L22 and the difference between the space dimension L32 and the width dimension L42 do not have to be the same.
[0047] Furthermore, the spacing dimension L11 between the first column 11 and the second column 12 and the spacing dimension L12 between the second columns 12 may or may not be the same. Furthermore, the spacing dimension L11 may or may not be uniform in one wall 1 or between multiple walls 1. Furthermore, the spacing dimension L12 may or may not be uniform in one wall 1 or between multiple walls 1.
[0048] Furthermore, the width dimension (width dimension including positioning material 63b) L21 of the wall panel 20 installed between the first pillar 11 and the second pillar 12 and the width dimension (width dimension including positioning material 63b) L22 of the wall panel 20 installed between the second pillars 12 may or may not be the same. Furthermore, the width dimension L21 may or may not be uniform in one wall 1 or between multiple walls 1. Furthermore, the width dimension L22 may or may not be uniform in one wall 1 or between multiple walls 1.
[0049] Furthermore, the spacing dimension L31 (spacing dimension including positioning member 63a) between the first column 11 and the second column 12 and the spacing dimension L32 (spacing dimension including positioning member 63a) between the second columns 12 may or may not be the same. Furthermore, the spacing dimension L31 may or may not be uniform in one wall 1 or between multiple walls 1. Furthermore, the spacing dimension L32 may or may not be uniform in one wall 1 or between multiple walls 1.
[0050] Furthermore, the width dimension L41 of the wall panel 20 installed between the first pillar 11 and the second pillar 12 and the width dimension L42 of the wall panel 20 installed between the second pillars 12 may or may not be the same. Furthermore, the width dimension L41 may or may not be uniform in one wall 1 or between multiple walls 1. Furthermore, the width dimension L42 may or may not be uniform in one wall 1 or between multiple walls 1.
[0051] 15, the wall panel 20 is fixed to the pillars 11, 12 by joining the positioning members 63b of the wall panel 20 to the positioning members 63a of the pillars 11, 12. In this embodiment, the joining means for joining the wall panel 20 to the pillars 11, 12 (joining means for joining the positioning members 63a of the pillars 11, 12 and the positioning members 63b of the wall panel 20) is a combination of a fastener such as a screw and an adhesive, but is not limited thereto and may be, for example, either one of them.
[0052] The wall panel 20 is fixed to the floor beam 14 by joining the positioning material 61b of the wall panel 20 to the positioning material 61a of the floor beam 14. In this embodiment, the joining means for joining the wall panel 20 to the floor beam 14 (joining the positioning material 61a of the floor beam 14 and the positioning material 61b of the wall panel 20) is a combination of a fastener such as a screw and an adhesive, but is not limited to this and may be, for example, either one of them.
[0053] [Temporary Fixation Step A] Next, as shown in FIG. 5, a temporary brace 100 for supporting the wall panel 20 is attached to the wall panel 20 installed in the above-mentioned "wall panel installation step A" to temporarily fix the wall panel 20. The temporary braces 100 attached to the wall panel 20 in this step are removed after the wall panel 20 is fixed to the ceiling beam 13 (after the "full fixing step A" described later).
[0054] In the example shown in Fig. 5, a temporary brace 100 is attached each time one of the multiple wall panels 20 to be installed in the "wall panel installation step A" is installed. That is, the temporary brace 100 is attached at an appropriate time during the "wall panel installation step A". Therefore, in this embodiment, since the "temporary fixing step A" is performed during the "wall panel installation step A", the "temporary fixing step A" in this embodiment can be said to be a step included in the "wall panel installation step A".
[0055] [Ceiling beam installation step A] Next, a hoist is attached to the upper end surface of the ceiling beam 13 (here, the main beam). Then, as shown in Fig. 6, the ceiling beam 13 is lifted by a crane and installed between the upper ends of the adjacent first columns 11. After that, the hoist is removed from the ceiling beam 13. Specifically, for example, as shown in Figure 2, a ceiling beam 13 is fixed to a first pillar 11 via a beam support hardware 16 attached to the first pillar 11, and, for example, as shown in Figure 3, a ceiling beam 13 is fixed to a second pillar 12 via a tenon hardware 17 attached to the second pillar 12.
[0056] [Main Fixation Step A] Next, the wall panel 20 installed in the above-mentioned "wall panel installation step A" is fixed to the ceiling beam 13 installed in the above-mentioned "ceiling beam installation step A". In this embodiment, as shown in FIG. 14(b), the positioning material 62a is provided on the lower surface of the ceiling beam 13 adjacent to the wall panel 20. In addition, the upper horizontal frame member of the frame members A constituting the wall panel 20 is also provided with the positioning material 62b on its upper surface. When the ceiling beam 13 is lifted by a crane and lowered onto the wall panel 20, the ceiling beam 13 is lowered to a position where the positioning material 62a of the ceiling beam 13 and the positioning material 62b of the wall panel 20 are in contact with each other while being aligned in the thickness direction (front-back direction) of the wall panel 20, as shown in FIG. 14(c), for example. That is, when the ceiling beam 13 is disposed in the appropriate position, the positioning material 62a of the ceiling beam 13 and the positioning material 62b of the wall panel 20 are in contact with each other while being aligned in the thickness direction (front-back direction) of the wall panel 20.
[0057] Here, the wall panel 20 is fixed to the ceiling beam 13 by joining the positioning member 62b of the wall panel 20 to the positioning member 62a of the ceiling beam 13. In this embodiment, the joining means for joining the wall panel 20 to the ceiling beam 13 (the joining means for joining the positioning member 62a of the ceiling beam 13 and the positioning member 62b of the wall panel 20) is a combination of a fastener such as a screw and an adhesive, but is not limited thereto and may be, for example, either one of them. In order to avoid complexity, in Figs. 4 to 13, the positioning members 61a, 61b, 62a, 62b, 63a, and 63b are not shown, or the reference numerals indicating the positioning members are not shown.
[0058] In this embodiment, the floor beam 14 with the positioning material 61a attached thereto is transported from the factory to the construction site. That is, in this embodiment, the positioning material 61a is attached to the floor beam 14 at the factory, but this is not limited thereto, and the positioning material 61a may be attached to the floor beam 14 at the construction site. In this embodiment, the ceiling beam 13 with the positioning material 62a attached thereto is transported from the factory to the construction site. That is, in this embodiment, the positioning material 62a is attached to the ceiling beam 13 at the factory, but this is not limited thereto, and the positioning material 62b may be attached to the ceiling beam 13 at the construction site.
[0059] In this embodiment, the pillars 11 and 12 with the positioning materials 63a attached thereto are transported from a factory to a construction site. That is, in this embodiment, the positioning materials 63a are attached to the pillars 11 and 12 at the factory, but this is not limited thereto, and the positioning materials 63a may be attached to the pillars 11 and 12 at the construction site. In this embodiment, the wall panel 20 with the positioning materials 61b, 62b, and 63b attached thereto is transported from a factory to a construction site. That is, in this embodiment, the positioning materials 61b, 62b, and 63b are attached to the wall panel 20 at the factory, but this is not limited thereto, and the positioning materials 61b, 62b, and 63b may be attached to the wall panel 20 at the construction site.
[0060] [Wall panel installation step B] Next, a hoist is attached to the upper end surface of the wall panel 20 (here, a wall panel for an interior wall (partition wall, etc.)). Then, the wall panel 20 is hoisted by a crane and installed between adjacent pillars 11, 12 (here, between the first pillar 11 and the second pillar 12) as shown in Fig. 7. After that, the hoist is removed from the wall panel 20. In this step, a wall panel 20 is installed that is arranged in a perpendicular direction to the wall panel 20 installed in the above-mentioned "wall panel installation step A" and that is adjacent to the same first pillar 11 as the wall panel 20 installed in "wall panel installation step A". This step is substantially the same as the above-mentioned "wall panel installation step A," so a detailed description thereof will be omitted.
[0061] [Temporary Fixation Step B] Next, the temporary braces 100 that support the wall panel 20 installed in the above-mentioned "wall panel installation step B" are attached to the wall panel 20, thereby temporarily fixing the wall panel 20. The temporary braces 100 attached to the wall panel 20 in this step are removed after the wall panel 20 is fixed to the ceiling beam 13 (after the "full fixing step B" described later). In the examples shown in Figures 4 to 13, this step is omitted. Specifically, the temporary braces 100 attached in the above-mentioned "temporary fixing step A" are not removed until the "permanent fixing step B" described later is completed, and the temporary braces 100 support the wall panel 20 installed in the "wall panel installation step B".
[0062] [Ceiling beam installation step B] Next, a hoist is attached to the upper end surface of the ceiling beam 13 (here, the main beam). Then, as shown in Fig. 7, the ceiling beam 13 is lifted by a crane and installed between the upper ends of the adjacent first columns 11. After that, the hoist is removed from the ceiling beam 13. In this step, a ceiling beam 13 is installed that is arranged perpendicular to the ceiling beam 13 installed in the above-mentioned "ceiling beam installation step A" and adjacent to the same first pillar 11 as the ceiling beam 13 installed in "ceiling beam installation step A". This step is substantially the same as the above-mentioned "Ceiling Beam Installation Step A," so a detailed explanation will be omitted.
[0063] [Main Fixation Step B] Next, the wall panel 20 installed in the above-mentioned "wall panel installation step B" is fixed to the ceiling beam 13 installed in the above-mentioned "ceiling beam installation step B". This step is substantially the same as the above-mentioned "main fixing step A," so a detailed description thereof will be omitted.
[0064] [Wall panel installation step C] Next, a hoist is attached to the upper end surface of the wall panel 20 (here, a wall panel for an interior wall (partition wall, etc.)). Then, the wall panel 20 is hoisted by a crane and installed between adjacent pillars 11, 12 (here, between the first pillar 11 and the second pillar 12) as shown in Fig. 8. After that, the hoist is removed from the wall panel 20. In this step, a wall panel 20 is installed that is arranged in a direction parallel to the wall panel 20 installed in the above-mentioned "wall panel installation step B" and that is adjacent to the same first pillar 11 as the wall panel 20 installed in "wall panel installation step A". This step is substantially the same as the above-mentioned "wall panel installation step A," so a detailed description thereof will be omitted.
[0065] [Temporary Fixation Step C] Next, the temporary braces 100 that support the wall panel 20 installed in the above-mentioned "wall panel installation step C" are attached to the wall panel 20, thereby temporarily fixing the wall panel 20. The temporary braces 100 attached to the wall panel 20 in this step are removed after the wall panel 20 is fixed to the ceiling beam 13 (after the "full fixing step C" described later). This step can be omitted, similar to the above-mentioned "temporary fixing step B." In the case of omitting this step, for example, it is preferable not to remove the temporary braces 100 installed in the above-mentioned "temporary fixing step A" until the completion of the later-described "permanent fixing step C," and to use the temporary braces 100 to support the wall panel 20 installed in the "wall panel installation step C."
[0066] [Ceiling beam installation step C] Next, a hoist is attached to the upper end surface of the ceiling beam 13 (here, the main beam). Then, as shown in Fig. 8, the ceiling beam 13 is lifted by a crane and installed between the upper ends of the adjacent first columns 11. After that, the hoist is removed from the ceiling beam 13. In this step, a ceiling beam 13 is installed that is arranged in a direction parallel to the ceiling beam 13 installed in the above-mentioned "ceiling beam installation step B" and adjacent to the same first pillar 11 as the ceiling beam 13 installed in "ceiling beam installation step A". This step is substantially the same as the above-mentioned "Ceiling Beam Installation Step A," so a detailed explanation will be omitted.
[0067] Here, as shown in FIG. 8, of the ceiling beams 13 installed in this step, a beam support hardware 16 is attached to the side facing the ceiling beams 13 installed in the above-mentioned "ceiling beam installation step B". Similarly, the ceiling beams 13 installed in "ceiling beam installation step B" also have beam support hardware 16 attached. That is, of the ceiling beams 13 installed in "ceiling beam installation step B", the beam support hardware 16 is attached to the side facing the ceiling beams 13 installed in this step (ceiling beam installation step C).
[0068] [Main Fixation Step C] Next, the wall panel 20 installed in the above-mentioned "wall panel installation step C" is fixed to the ceiling beam 13 installed in the above-mentioned "ceiling beam installation step C". This step is substantially the same as the above-mentioned "main fixing step A," so a detailed description thereof will be omitted.
[0069] [Ceiling beam installation step Z1] Next, a hoist is attached to the upper end surface of the ceiling beam 13 (here, a main beam). Then, as shown in Fig. 9, the ceiling beam 13 is lifted by a crane and installed between the upper ends of adjacent first columns 11. After that, the hoist is removed from the ceiling beam 13. In this step, a ceiling beam 13 is installed that is arranged in a direction parallel to the ceiling beam 13 installed in the above-mentioned "ceiling beam installation step A" and adjacent to the same first column 11 as the ceiling beam 13 installed in the above-mentioned "ceiling beam installation step B" and "ceiling beam installation step C". This step is substantially the same as the above-mentioned "Ceiling Beam Installation Step A," so a detailed explanation will be omitted.
[0070] Here, as shown in FIG. 9, of the ceiling beams 13 installed in this step, a beam support hardware 16 is attached to the side facing the ceiling beams 13 installed in the above-mentioned "ceiling beam installation step A". Similarly, the ceiling beams 13 installed in "ceiling beam installation step A" also have beam support hardware 16 attached. That is, of the ceiling beams 13 installed in "ceiling beam installation step A", the beam support hardware 16 is attached to the side facing the ceiling beams 13 installed in this step (ceiling beam installation step Z1).
[0071] [Ceiling beam installation step Z2] Next, a hoist is attached to the upper end surface of the ceiling beam 13 (here, a small beam). Then, as shown in Fig. 10, the ceiling beam 13 is lifted by a crane and installed between the parallel ceiling beams 13. After that, the hoist is removed from the ceiling beam 13. In this step, ceiling beams 13 (minor beams) are installed between the ceiling beams 13 (main beams) installed in the above-mentioned "ceiling beam installation step A" and the ceiling beams 13 (main beams) installed in the above-mentioned "ceiling beam installation step Z1", so that the ceiling beams 13 are arranged perpendicular to these ceiling beams 13.
[0072] Specifically, a ceiling beam 13 (minor beam) is fixed to an installed ceiling beam 13 (main beam) via a beam support hardware 16 attached to the ceiling beam 13, and the ceiling beam 13 (minor beam) is fixed to a second pillar 12 via a tenon hardware 17 attached to the second pillar 12, as shown in Figure 3, for example. As shown in FIG. 10, beam support hardware 16 is attached to the side of ceiling beam 13 installed in this step.
[0073] [Wall panel installation step D] Next, a hoist is attached to the upper end surface of the wall panel 20 (here, a wall panel for an interior wall (partition wall, etc.)). Then, as shown in Fig. 11, the wall panel 20 is lifted by a crane and installed between adjacent pillars 11, 12 (here, between the second pillars 12). After that, the hoist is removed from the wall panel 20. In this step, a wall panel 20 is installed that is arranged in a direction parallel to the wall panel 20 installed in the above-mentioned "wall panel installation step A", and that is arranged below the beam support hardware 16 attached to the ceiling beam 13 installed in the above-mentioned "ceiling beam installation step B", "ceiling beam installation step C", and "ceiling beam installation step Z2". This step is substantially the same as the above-mentioned "wall panel installation step A," so a detailed description thereof will be omitted.
[0074] The wall panel 20 installed in this step is the wall panel 20 that is placed below the beam support hardware 16 attached to the ceiling beams 13 installed in "ceiling beam installation step B", "ceiling beam installation step C", and "ceiling beam installation step Z2". Therefore, the wall panel 20 installed in this step cannot be lowered from directly above the floor beams 14 because these beam support hardware 16 get in the way. Therefore, the wall panel 20 installed in this step is lowered from a position that is not directly above the floor beams 14, as shown in Figure 11, and then pulled to directly above the floor beams 14, so that it is placed in the appropriate position on the floor beams 14.
[0075] [Temporary Fixation Step D] Next, the temporary braces 100 that support the wall panel 20 installed in the above-mentioned "wall panel installation step D" are attached to the wall panel 20, thereby temporarily fixing the wall panel 20. The temporary braces 100 attached to the wall panel 20 in this step are removed after the wall panel 20 is fixed to the ceiling beam 13 (after the "full fixing step D" described later). This step is substantially the same as the above-mentioned "temporary fixing step A," and therefore a detailed description thereof will be omitted.
[0076] [Ceiling beam installation step D] Next, a hoist is attached to the upper end surface of the ceiling beam 13 (here, a small beam). Then, as shown in Fig. 12, the ceiling beam 13 is lifted by a crane and installed between the parallel ceiling beams 13. After that, the hoist is removed from the ceiling beam 13. In this step, ceiling beams 13 (minor beams) are installed between the ceiling beams 13 (main beams, minor beams) installed in the above-mentioned "ceiling beam installation step B", "ceiling beam installation step C", and "ceiling beam installation step Z2", in a direction parallel to the ceiling beams 13 installed in the above-mentioned "ceiling beam installation step A". Specifically, the ceiling beams 13 (minor beams) are fixed to the ceiling beams 13 (main beams, minor beams) via beam support hardware 16 attached to the ceiling beams 13 (main beams, minor beams) that have already been installed.
[0077] In this embodiment, the ceiling beam 13 with the beam support hardware 16 attached is transported from a factory to a construction site. That is, in this embodiment, the beam support hardware 16 is attached to the ceiling beam 13 at the factory, but this is not limited to this, and the beam support hardware 16 may be attached to the ceiling beam 13 at the construction site. When attaching the beam support hardware 16 to the ceiling beam 13 at the construction site, the timing of attaching the beam support hardware 16 can be appropriately selected as long as it is before the ceiling beam 13 that the beam support hardware 16 will support is installed.
[0078] [Main Fixation Step D] Next, the wall panel 20 installed in the above-mentioned "wall panel installation step D" is fixed to the ceiling beam 13 installed in the above-mentioned "ceiling beam installation step D". This step is substantially the same as the above-mentioned "main fixing step A," so a detailed description thereof will be omitted. In this manner, as shown in FIG. 13, a wall 1 including a frame 10 consisting of columns 11, 12 and beams 13, 14, and a wall panel 20 attached to the frame 10 can be constructed.
[0079] Furthermore, the frame 10 constituting the wall 1 is not limited to a frame having a first pillar 11 and a second pillar 12 as pillars, but may be, for example, a frame having only the second pillar 12 as a pillar, or a frame having only the first pillar 11 as a pillar. In the examples shown in Figures 4 to 13, the frames having a first pillar 11 and a second pillar 12 as pillars are frame 10 formed by a "floor beam installation step", a "pillar installation step", and a "ceiling beam installation step A", frame 10 formed by a "floor beam installation step", a "pillar installation step", and a "ceiling beam installation step B", and frame 10 formed by a "floor beam installation step", a "pillar installation step", and a "ceiling beam installation step C". Moreover, the frame having only the second pillar 12 as a pillar is frame 10 formed by a "floor beam installation step", a "pillar installation step", and a "ceiling beam installation step D (and ceiling beam installation step Z2)".
[0080] That is, in the examples shown in Figures 4 to 13, wall 1 in this embodiment is a wall formed by a "floor beam installation step", a "pillar installation step", a "wall panel installation step A", and a "ceiling beam installation step A", a wall formed by a "floor beam installation step", a "pillar installation step", a "wall panel installation step B", and a "ceiling beam installation step B", a wall formed by a "floor beam installation step", a "pillar installation step", a "wall panel installation step C", and a "ceiling beam installation step C", a wall formed by a "floor beam installation step", a "pillar installation step", a "wall panel installation step D", and a "ceiling beam installation step D (and ceiling beam installation step Z2)".
[0081] [Exterior material installation steps] Next, as shown in FIG. 16, the column exterior material 40 for covering the columns 11 and 12 is installed. The exterior materials covering the wall 1 in this embodiment include at least an exterior wall material 31 covering the wall panel 20 and a pillar exterior material 40 covering the pillars 11, 12. In this embodiment, the wall panel 20 with the exterior wall material 31 attached is transported from the factory to the construction site. That is, in this embodiment, the exterior wall material 31 is attached to the wall panel 20 at the factory, but this is not limited to this, and the exterior wall material 31 may be attached to the wall panel 20 at the construction site. When attaching the exterior wall material 31 to the wall panel 20 at the construction site, the timing of attaching the exterior wall material 31 may be before or after the wall panel 20 is installed. Therefore, it is also possible to install the exterior wall material 31 that covers the wall panel 20 in this step.
[0082] In the wall 1 of this embodiment, as shown in Fig. 15, for example, the outdoor surfaces of the columns 11, 12 are located closer to the indoor side than the outdoor surface of the wall panel 20. That is, before the pillar exterior material 40 is installed, the wall 1 has, on the outdoor side, a plurality of grooves 1a extending in the height direction (up and down direction) of the wall 1. The pillar exterior material 40 has a shape that fits into the grooves 1a.
[0083] Specifically, as shown in FIG. 16(a), for example, the pillar exterior material 40 is composed of a base portion 41 arranged between adjacent wall panels 20, and a covering portion 42 that covers the base portion 41. The base portion 41 in this embodiment is made of LVL (Laminated Veneer Lumber) having a thickness of 50 mm, but is not limited to this. In addition, the covering portion 42 in this embodiment is made of a galvalume steel sheet (registered trademark), but is not limited to this. In addition, the covering portion 42 may be made of the same material as the exterior wall material 31, or may be made of a different material.
[0084] The pillar exterior material 40 is designed so that the width dimension L51 of the outdoor side portion is longer than the width dimension L52 of the indoor side portion (L51>L52). Specifically, the covering portion 42 has a first portion covering the surface of the base portion 41 facing the wall panel 20, a second portion covering the surface of the base portion 41 facing the outdoors, and a folding portion provided between the first and second portions and protruding toward the wall panel 20.
[0085] As described above, the spacing dimensions L11, L31 between the first column 11 and the second column 12 are longer than the width dimensions L21, L41 of the wall panel 20 installed between the first column 11 and the second column 12 (L11>L21, L31>L41). In addition, the spacing dimensions L12, L32 between the second columns 12 are longer than the width dimensions L22, L42 of the wall panel 20 installed between the second columns 12 (L12>L22, L32>L42). Therefore, the width dimension of the groove 1a, i.e., the spacing dimension L61 between the wall panels 20, is greater than or equal to the width dimension L62 (including the width dimension of the positioning material 63a) of the pillars 11, 12 installed between the wall panels 20 (L61≧L62).
[0086] In addition, since clearances (clearances for installing the wall panels 20) are provided between the first pillar 11 and the second pillar 12 and between the second pillars 12, the spacing dimension L61 is not uniform. Specifically, in this embodiment, the difference between the spacing dimension L11 and the width dimension L21 is set to 5 mm, the difference between the spacing dimension L31 and the width dimension L41 is set to 5 mm, the difference between the spacing dimension L12 and the width dimension L22 is set to 5 mm, and the difference between the spacing dimension L32 and the width dimension L42 is set to 5 mm. Therefore, in this embodiment, the minimum value of the spacing dimension L61 between the wall panels 20 is the same as the width dimension (width dimension including the positioning material 63a) L62 of the columns 11, 12 installed between the wall panels 20, and the maximum value is 10 mm longer than the width dimension (width dimension including the positioning material 63a) L62 of the columns 11, 12 installed between the wall panels 20 (L62≦L61≦L62+10 mm).
[0087] The width dimension L52 of the indoor side portion of the column exterior member 40 is set to be shorter than the minimum value of the interval dimension L61 between the wall panels 20 adjacent to the columns 11 and 12 covered by the column exterior member 40 (L52 < minimum value of L61). As a result, regardless of the length of the interval dimension L61 between the wall panels 20 (that is, whether the interval dimension L61 is the minimum value, the maximum value, or a value between the minimum value and the maximum value), the indoor side portion of the column exterior member 40 can be inserted into the groove portion 1a. That is, the width dimension L52 of the indoor side portion of the column exterior member 40 is set to a dimension that can be inserted into the groove portion 1a.
[0088] Also, the width dimension L51 of the outdoor side portion of the column exterior member 40 is set to be longer than the maximum value of the interval dimension L61 between the wall panels 20 adjacent to the columns 11 and 12 covered by the column exterior member 40 (L51 > maximum value of L61). As a result, regardless of the length of the interval dimension L61 between the wall panels 20 (that is, whether the interval dimension L61 is the minimum value, the maximum value, or a value between the minimum value and the maximum value), the end portions (the end portions on the column 11 and 12 sides) of these wall panels 20 can be covered by the folding portion in the covering portion 42 of the column exterior member 40. That is, the width dimension L51 of the outdoor side portion of the column exterior member 40 is set to a dimension that can cover the gap (in this embodiment, the dimension G of the gap is 0 mm ≦ G ≦ 5 mm) formed between the columns 11 and 12 covered by the column exterior member 40 and the wall panels 20 adjacent to the columns 11 and 12 with the folding portion in the covering portion 42 of the column exterior member 40.
[0089] [Waterproof means installation step] Next, as shown in FIG. 16(b), waterproof means 70 is installed between the column exterior member 40 and the wall panel 20. In the column exterior material 40 of this embodiment, the thickness dimension of the base portion 41 is set to be longer than the depth dimension of the groove portion 1a. Therefore, a gap is provided between the folded portion of the covering portion 42 of the column exterior material 40 and the wall panel 20 (in this embodiment, the exterior wall material 31 covering the wall panel 20). In this step, the gap is filled with waterproofing means 70 such as a sealing material or a caulking material.
[0090] [Interior material installation steps] Finally, as shown in FIG. 16(b), the pillar interior material 50 for covering the pillars 11 and 12 is installed. The interior materials covering the wall 1 in this embodiment include at least an inner wall material 32 covering the wall panel 20 and a pillar interior material 50 covering the pillars 11, 12. In this embodiment, the wall panel 20 with the interior wall material 32 attached is transported from the factory to the construction site. That is, in this embodiment, the interior wall material 32 is attached to the wall panel 20 at the factory, but this is not limited to this, and the interior wall material 32 may be attached to the wall panel 20 at the construction site. When the interior wall material 32 is attached to the wall panel 20 at the construction site, the timing of attaching the interior wall material 32 may be before or after the wall panel 20 is installed. Therefore, it is also possible to install the interior wall material 32 that covers the wall panel 20 in this step. This step may also be performed prior to the "exterior material installation step" described above.
[0091] Furthermore, in the example shown in Figures 4 to 13, four first pillars 11 are installed in the "pillar installation step (see Figure 4)", but the number of first pillars 11 installed in the "pillar installation step" is not limited to this. Furthermore, nine second pillars 12 are installed in the "pillar installation step (see FIG. 4)", but the number of second pillars 12 installed in the "pillar installation step" is not limited to this.
[0092] In addition, in the example shown in Figures 4 to 13, three wall panels 20 are installed in "wall panel installation step A (see Figure 5)", but the number of wall panels 20 installed in "wall panel installation step A" is not limited to this. Further, in "ceiling beam installation step A (see FIG. 6)", one ceiling beam 13 is installed, but the number of ceiling beams 13 installed in "ceiling beam installation step A" is not limited to this.
[0093] Further, in the "wall panel installation step B (see FIG. 7)", one wall panel 20 is installed, but the number of wall panels 20 installed in the "wall panel installation step B" is not limited to this. Further, in "ceiling beam installation step B (see FIG. 7)", one ceiling beam 13 is installed, but the number of ceiling beams 13 installed in "ceiling beam installation step B" is not limited to this.
[0094] Further, although one wall panel 20 is installed in the "wall panel installation step C (see FIG. 8)", the number of wall panels 20 installed in the "wall panel installation step C" is not limited to this. Further, in the "ceiling beam installation step C (see FIG. 8)", one ceiling beam 13 is installed, but the number of ceiling beams 13 installed in the "ceiling beam installation step C" is not limited to this.
[0095] Further, although one ceiling beam 13 is installed in "ceiling beam installation step Z1 (see FIG. 9)", the number of ceiling beams 13 installed in "ceiling beam installation step Z1" is not limited to this. Further, although two ceiling beams 13 are installed in "ceiling beam installation step Z2 (see FIG. 10)", the number of ceiling beams 13 installed in "ceiling beam installation step Z2" is not limited to this.
[0096] Furthermore, although three wall panels 20 are installed in "wall panel installation step D (see FIG. 11)", the number of wall panels 20 installed in "wall panel installation step D" is not limited to this. Further, in "ceiling beam installation step D (see FIG. 12)", six ceiling beams 13 are installed, but the number of ceiling beams 13 installed in "ceiling beam installation step D" is not limited to this.
[0097] "effect" According to the above embodiment, the following excellent effects are obtained. The construction method in the above embodiment is a construction method for a wall 1 in a building, and the wall 1 comprises a frame 10 consisting of pillars 11, 12 and beams 13, 14, and a wall panel 20 attached to the frame 10. After a pillar installation step in which a plurality of pillars 11, 12 are installed, a wall panel installation step (wall panel installation steps A to D) is performed in which the wall panel 20 is lifted and installed between the pillars (between the first pillar 11 and the second pillar 12, and between the second pillars 12), and after the wall panel installation step, a ceiling beam installation step (ceiling beam installation steps A to D) is performed in which a ceiling beam 13 among the beams is lifted and installed between the upper ends of the pillars (between the upper ends of the first pillars 11).
[0098] In other words, since the wall panel installation step is performed before the ceiling beam installation step, even if a hanger is attached to the upper end surface of the wall panel 20, the ceiling beam 13 does not get in the way while the wall panel 20 is being installed. Therefore, there is no need to remove the hanging rods to change the hanging position while installing the wall panel 20, which eliminates problems such as bother and danger. Also, by attaching the hanging device to the upper end surface of the wall panel 20, it is easier to hang the wall panel 20 vertically than when the hanging device is attached to the surface (e.g., the surface facing the outdoors) of the wall panel 20, so there is no problem such as difficulty in installing the wall panel 20. Furthermore, by attaching the hanging device to the upper end surface of the wall panel 20, even if an exterior material (exterior wall material 31, etc.) is attached to the wall panel 20 in advance, there is no need to set the installation position of the hanging device in a position that takes into consideration the exterior material. Therefore, a construction method for a wall 1 comprising a frame 10 consisting of columns 11, 12 and beams 13, 14, and a wall panel 20 attached to the frame 10, with improved workability, can be provided.
[0099] For example, if the construction site is to assemble in the order of floor beam 14 → columns 11, 12 → ceiling beam 13 → wall panel 20, the wall panel 20 will be hoisted by a crane at the construction site and fitted into the spaces between the columns and beams in the frame 10. If a hanging device is attached to the upper end surface of the wall panel 20, as shown in Figure 17(a), the ceiling beam 13 will get in the way halfway through fitting the wall panel 20 into the spaces between the columns and beams, so it will be necessary to remove the hanging device halfway through to change the hanging position, which is troublesome, dangerous, etc.
[0100] On the other hand, as shown in Fig. 17(b), if a hanger is attached to the surface of the wall panel 20 (e.g., the surface facing the outdoors), there is no need to change the hanging position midway. However, if a hanger is attached to the surface of the wall panel 20, it is difficult to hang the wall panel 20 vertically, which can cause problems such as making it difficult to fit the wall panel 20 between beams. Furthermore, in the case where an exterior material such as the exterior wall material 31 is attached to the wall panel 20 in advance as in the above embodiment, attaching a hanger to the surface of the wall panel 20 can also cause problems such as the need to set the installation position of the hanger in a position that takes into consideration the exterior material. In contrast, these problems can be solved by using the construction method in the above embodiment, that is, by assembling the floor beams 14 → columns 11, 12 → wall panel 20 → ceiling beam 13 in that order at the construction site.
[0101] In addition, the construction method in the above embodiment includes a temporary fixing step (temporary fixing steps A to D) of attaching temporary braces 100 that support the wall panel 20 to the wall panel 20, and a final fixing step (final fixing steps A to D) of fixing the wall panel 20 to the ceiling beam 13, and after the final fixing step, the temporary braces 100 are removed.
[0102] That is, a temporary fixing step of attaching the temporary cross member 100 to the installed wall panel 20 is performed. Therefore, after the wall panel 20 is installed and before the wall panel 20 is fixed to the ceiling beam 13, the wall panel 20 can be supported by the temporary cross member 100. Accordingly, even if the ceiling beam installation step is performed after the wall panel installation step, the wall panel 20 will not fall before the ceiling beam 13 is installed (specifically, before the ceiling beam 13 is installed and the wall panel 20 is fixed to the ceiling beam 13), so safety can be ensured. Also, when there is a possibility that the wall panel 20 may fall, it is necessary to work while taking measures to prevent the wall panel 20 from falling. Therefore, it is more laborious than performing the temporary fixing step (including removing the temporary cross member 100). On the other hand, in the above embodiment, by performing the temporary fixing step, the possibility of the wall panel 20 falling is eliminated. Therefore, even if the temporary fixing step (including removing the temporary cross member 100) is performed, the workability is improved.
[0103] Also, in the above embodiment, the interval dimensions L11, L12, L31, L32 between the columns are set to be longer than the width dimensions L21, L22, L41, L42 of the wall panel 20 installed between the columns (L11 > L21, L12 > L22, L31 > L41, L32 > L42). Accordingly, since the interval dimensions L11, L12, L31, L32 between the columns are longer than the width dimensions L21, L22, L41, L42 of the wall panel installed between the columns, that is, a clearance (clearance for the wall panel 20) is provided between the columns, the wall panel installation step can be easily performed, and the workability is improved.
[0104] Also, the construction method in the above embodiment includes an exterior material installation step of installing the column exterior material 40 that covers the columns 11, 12. The width dimension L52 of the indoor side portion of the column exterior material 40 is set to be shorter than the interval dimension L61 between the wall panels 20 (L52 < L61), and the width dimension L51 of the outdoor side portion of the column exterior material 40 is set to be longer than the interval dimension L61 between the wall panels 20 (L51 > L61).
[0105] Therefore, the width dimension L52 of the indoor side portion of the exterior material 40 for columns is shorter than the interval dimension L61 between the wall panels 20, that is, a clearance (clearance for the exterior material 40 for columns) is provided between the wall panels 20. Thus, the exterior material installation step can be easily performed, and the workability is improved. On the other hand, since the width dimension L51 of the outdoor side portion of the exterior material 40 for columns is longer than the interval dimension L61 between the wall panels 20, both ends (folding portions) of the outdoor side portion of the exterior material 40 for columns can cover the boundary between the columns 11, 12 and the wall panels 20. Therefore, compared with the case where a member for covering the boundary between the columns 11, 12 and the wall panels 20 is separately provided, the workability is improved and the number of parts can be reduced.
[0106] Here, in the above embodiment, since the interval dimensions L11, L12, L31, L32 between the columns are longer than the width dimensions L21, L22, L41, L42 of the wall panels installed between the columns, a gap is formed between the columns 11, 12 and the wall panels 20. Therefore, the interval dimension L61 between the wall panels 20 is not uniform and has a width. Thus, in the above embodiment, the width dimension L52 is set shorter than the minimum value of the interval dimension L61 (L52 < minimum value of L61), and the width dimension L51 is set longer than the maximum value of the interval dimension L61 (L51 > maximum value of L61).
[0107] In this way, by making the width dimension L52 shorter than the minimum value of the interval dimension L61, even when a gap is formed between the columns 11, 12 and the wall panels 20, and even when the dimensions of the gaps formed between the columns 11, 12 and the wall panels 20 are uneven, a clearance (clearance for the exterior material 40 for columns) can be provided between the wall panels 20. Thus, the exterior material installation step can be easily performed, and the workability is improved. Furthermore, by making the width dimension L51 longer than the maximum value of the interval dimension L61 between the wall panels 20, even if gaps are formed between the columns 11, 12 and the wall panel 20, and even if the dimensions of the gaps formed between the columns 11, 12 and the wall panel 20 are not uniform, these gaps can be covered by both ends (folded parts) of the outdoor side part of the column exterior material 40. Therefore, since it is not necessary to make the dimensions of the gaps formed between the columns 11, 12 and the wall panel 20 uniform, the wall panel installation step can be easily performed, improving workability.
[0108] Moreover, the construction method in the above embodiment includes a waterproofing means installation step of installing waterproofing means 70 between the pillar exterior material 40 and the wall panel 20. Therefore, a waterproofing means installation step is performed in which waterproofing means 70 is installed between the pillar exterior material 40 and the wall panel 20, thereby improving the watertightness and airtightness between the pillar exterior material 40 and the wall panel 20, and further between the pillars 11, 12 and the wall panel 20.
[0109] In recent years, there has been a demand for the realization of a decarbonized society through the promotion of carbon neutrality, which reduces carbon dioxide emissions to virtually zero, and for the achievement of the SDGs (Sustainable Development Goals), and the construction industry is also working to build buildings using wood, which produces less carbon dioxide emissions. The wall 1 of the embodiment has a frame 10 and wall panel 20 made of wood, and therefore can contribute to the realization of a decarbonized society through the promotion of carbon neutrality and the achievement of the SDGs. [Explanation of symbols]
[0110] 1. Wall 10 Frames 11 Pillar 1 12 Pillar 2 13 Ceiling beams 14 Floor beam 20 Wall Panels 40 Exterior material for columns 100 Temporary brace L11, L12, L31, L32 Column spacing dimensions L21, L22, L41, L42 Width dimensions of wall panels L51 Width of exterior part of pillar exterior material L52 Width of the indoor part of exterior material for pillars L61 Distance between wall panels
Claims
1. A method for constructing a wall in a building, comprising the steps of: The wall comprises a frame of columns and beams and a wall panel attached to the frame; After the pillar installation step of installing the plurality of pillars, a wall panel installation step of lifting the wall panel and installing it between the pillars is performed; A construction method characterized in that after the wall panel installation step, a ceiling beam installation step is performed in which a ceiling beam among the beams is lifted and installed between the upper ends of the columns.
2. In the construction method according to claim 1, A temporary fixing step of attaching a temporary brace to the wall panel to support the wall panel; and a final fixing step of fixing the wall panel to the ceiling beam, A construction method characterized in that the temporary brace is removed after the final fixing step.
3. In the construction method according to claim 1, A construction method characterized in that the spacing between the pillars is set longer than the width of the wall panel to be installed between the pillars.
4. In the construction method according to claim 1, The method includes a step of installing an exterior material for a column that covers the column, The width dimension of the indoor side portion of the column exterior material is set shorter than the interval dimension between the wall panels, A construction method characterized in that the width dimension of the outdoor portion of the pillar exterior material is set longer than the spacing dimension between the wall panels.
5. In the construction method according to claim 4, A construction method comprising a waterproofing means installation step of installing a waterproofing means between the pillar exterior material and the wall panel.
Citation Information
Patent Citations
Attachment of wall panel
JP1983120942A
Assembling of wall panel
JP1994049931A
Server room
JP2007285082A
Bulkhead panel for LP gas cylinder or the like
JP2010175069A
External wall heat insulation structure of unit type building
JP2012154063A